HomeMy WebLinkAbout056208-A5 - Construction-Related - Contract - MAS Consultants, LLCCSC No. 56208-A5
AMENDMENT No . 5
TO CITY SECRETARY CONTRACT No. 56208
WHEREAS, the City of Fort Worth (CITY) and MAS Consultants, LLC, (ENGINEER)
made and entered into City Secretary Contract No. 56208, (the CONTRACT) which was
authorized by M&C 21-0586 on the 17th day of August, 2021 in the amount of $
269,495.00; and
WHEREAS, the CONTRACT was subsequently revised by:Amendment No. 1 in the
amount of $38,375.00 which was administratively authorized on Feburary 08, 2022,
Amendment No. 2 in the amount of $75,469.00 which was authorized by M&C 22-0597
on August 09, 2022, Amendment No. 3 in the amount of $67,443.00 administratively
authorized on May 23, 2023, and Amendment No. 4 in the amount of $2,389.00
administraively authorized on February 22, 2024; and
WHEREAS, the CONTRACT involves engineering services for the following
project:
Water and Sanitary Sewer Replacements Contract 2020 WSM-D, CPN 103419;
and
WHEREAS, it has become necessary to execute Amendment No. 5 to the CONTRACT
to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their duly
authorized representatives, enter into the following agreement, which amends the
CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional engineering
services specified in proposal attached hereto and incorporated herein. The cost
to City for the additional design services to be performed by Engineer totals
$15, 745. 00 (Sewer) .
2.
Article II of the CONTRACT is amended to provide for an increase in the fee
to be paid to Engineer for all work and services performed under the Contract, as
amended, so that the total fee paid by the City for all work and services shall
be an amount of $468,916.00.
3.
All other provisions of the Contract, which are not expressly amended herein,
shall remain in full force and effect.
OFFICIAL RECORD
City of Fort Worth, Texas W&SS Replacement Contract 2020, WSM-L
Prof Services Agreement Amendment Template CITY SECRETARY 103419
Revision Date: June 13, 2025
Page 1 of 2 1 FT. WORTH, TX
EXECUTED and EFFECTIVE as of the date subscribed by the City's designated
Assistant City Manager.
APPROVED:
City of Fort Worth
i
Jesica McEachern
Assistant City Manager
DATE: 07/08/2026
q � 4anu
AF FORr °�a
pas °°°�Y09�0
G �`o ° •+10
Pv� o=d
ATTEST: °op�
Jannette Goodall
City Secretary
APPROVAL RECOMMENDED:
chri gopher 1fap-�ler
�y11X-lr .. :FTra�m�:.yr►z�yz:�rwz: y.>t:�
Chris Harder, P.E.
Director, Water Department
Contract Compliance Manager:
ENGINEER
MAS Consultants, LLC.
Angel Sanchez, P.E.
President
DATE: 6/11 /2026
By signing, I acknowledge that I am the person responsible for the monitoring
and administration of this contract, including ensuring all performance and
reporting requirements.
r'1�7 ��
ClayVon M. Torrance, P.E.
Pr ject Manager
APPROVED AS TO FORM AND LEGALITY: M&C No.#: N/A
a�� M&C Date: N/A
Douglas Black (Jun 15, 2026 14:41:46 CDT)
Douglas W. Black
Sr. Assistant City Attorney
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth, Texas W&SS Replacement Contract 2020, WSM-D
Prof Services Agreement Amendment Template 103419
Revision Date: June 13, 2025
Page 2 of 2
A&,- - At
A, CONSULTING ENGINEERS
June 10, 2026
Clayton M. Torrance, P.E.
Professional Engineer
City of Fort Worth - Water Department
311 West 10th Street
Fort Worth, Texas 76102
Reference: Water and Sanitary Sewer Replacements, Contract 2020 WSM-D, City Project
Number 103419 — Contract Amendment No. 5 (Additional Sanitary Sewer Laterals and Service
Reroutes)
Dear Clayton:
MAS Consulting Engineers is pleased to provide additional professional engineering services for
the above -referenced project. These services are requested to include approximately 1,250
linear feet of 8-inch sanitary sewer lateral and the rerouting of 12 sanitary sewer services.
We propose to increase the contract amount by $ 15,745.00 for these additional services,
which include updates to the plans and specifications to incorporate the improvements. All
services will be performed in accordance with the original contract dated August 23, 2021.
Summary of Contract Fee
Original Contract Amount
$ 269,495.00
Contract Amendment No. 1
$ 38,375.00
Proposed Amendment No. 2
$ 75,469.00
Proposed Amendment No. 3
$ 67,443.00
Proposed Amendment No. 4
$ 2,389.00
Proposed Amendment No. 5
$ 15,745.00
Revised Contract Amount
$ 468,916.00
If you have any questions or we may be of further service, please call me at 817-938-8832.
Respectfully Submitted,
MAS Consulting Engineers
'�r A/
Angel Sanchez, PE
Principal
MAS Consulting Engineers
TBPELS Firm Reg. No. 17018
101 Summit Avenue, Suite 1030, Fort Worth Texas 76102 • Office: 817-708-2422 • www.mas-ce.com
N
d
A
3
■i11�111311i1�111�1�
I;Illi
�
��
�III�
il�illl�li
Illl�lilll�l■illlllll
l
■ii�il�ll�li,�1,11111�
dill
FORT WORTH.
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: MAS Consultants, LLC
Subject of the Agreement: Water and Sanitary Sewer Replacements Contract 2020 WSM-D
M&C Approved by the Council? * Yes ❑ No M
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes 0 No ❑ 56208-A5
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 0 No ❑
If unsure, see backpage for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 0 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date: N/A
If different from the approval date.
Expiration Date: N/A
If applicable.
Is a 1295 Form required? * Yes ❑ No 21
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 103419
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 0 No ❑
Contracts need to be routed for CSO processing in the followingorder:
rder:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.