Change Order Request
CSC No. 59846-CO5
Project Name: Backup Power and Electrical Improvements at Four Pump Stations City Sec No.: 1 59846
Project No.(s):l 103410 DOE No, N/A CityProj. No.: 103410-2
Project Description:
Installation of Backup Generators, Electric Motor and Switchgear Replacement and Other Improvements at Four Pump
Stations (Altamesa, Edwards Ranch Eastside and Como Pump Stations
Contractor: Winston Electric, Inc (d.b.a ACME Electric Co.) Change Order # 0 Date: 1 5/13/2026
City Project Mgr.1 Jose Andrade
City Inspector: I Ronnie Cardenas
Phone Number: (817) 392-8404
Phone Number: 692-309-3761
Dept. Water Unit I
Sewer Unit 2 TPW Unit 3 Totals
Contract Time
(Calender days)
Original Contract Amount $23,119,632.00
$23,119,632.00
1,090
Extras to Date $358,413.57
$358,413.57
010
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $23,478,045.57
$23,478,045.57
1,100
Amount of Proposed Change Order
$198,741.76
$198,741.76
055
Revised Contract Amount $23,676,787.33
$23,676,787.33
1,155
Original Funds Available for Change Orders $346,794.00
$346,794.00
$247,065.99
Remaining Funds Available for this CO
Additional Funding (if necessary)
2.41 %
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAXALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 2591o)
$28,899,540.00
JUSTIFICATION (REASONS)
FOR CHANGE ORDER
Change Order No. 5 will provide for the replacement of the existing bridge crane system of Alta Mesa Pump Station with a
new mono -rail hoist system as requested by water product staff to facilitate the safe removal and reinstallation of pumps at
the facility.
Staff concurs with the contractor's request for 55 additional calendar days on the change order.
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
CorlWel Wo' Cam Nam
Cordm*r Nwe
CoifttorSipaVe Date
WnslonElecirk, Inc (d,b.aACME ErWrIcCo.)
Brent lVlCDaniel
z 11F✓ 415 �' y
1
Inspector
Date
Prgect anager
Date
Ronnie Cardenas II
- -
6/3/26
Director Water Dept
Date
Qmstruction Supervisor Water Dept
Date
_
07/02/2026 7 1"
06/30/2026
A)4"ty Attorney
Date r z-,si °t'mCNC , Manager
I Date
Douglas Black (Jul 9, 2026 10:43:50 CDT)
07/09/2026
07/10/2026
Council Action If Required
M&C Number 26-0348 M&C Date Approved 5/17/202
FORT WORTH City of Fort Worth
Change Order Additions
Project Name Backup Power and Electrical Improvements at Four Pump Stations City Sec No.: 59846
Project No.(s): 103410 DOE No. N/A City Proj. No.: 103410 2
Project
Description
Installation of Backup Generators, Electric Motor and Switchgear Replacement and Other Improvements at Four Pump
Stations (Altamesa, Edwards Ranch Eastside and Como Pump Stations
Contractor Winston Electric, Inc (d.b.a ACME Electric Co.) Change Order:= Date: 5/13/2026
City Project Mgr. David R. Townsend, P.E. City Inspector F Ronnie Cardenas
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
ep ace Bridge Urane at Alta Mesa with Mono -Hail ois ys em
as Existing Bridge Crane System is not rated to lift/move new replacement Water Unit 1 1.00 LS $198,741.76 $198,741.76
5.1 motors
Water Unit 1 $198,741.76
Sewer Unit 2
TPW Unit 3
Page 2 of 4 Additions Sub Total $198,741.76
F" a-F Wo!z-Y,H City of Fort Worth
Change Order Deletions
Project Name Backup Power and Electrical Improvements at Four Pump Stations City Sec No.: 59846
Project No.(s): 103410 DOE No. N/A City Proj. No.: 103410 2
Project Description
Installation of Backup Generators, Electric Motor and Switchgear Replacement and Other Improvements at Four
Pump Stations (Altamesa, Edwards Ranch Eastside and Como Pump Stations
Contractor
Winston Electric, Inc (d.b.a ACME Electric Co.)
Change Order: FTI
Date 5/13/2026
City Project Mgr.
David R. Townsend, P.E.
City Inspector:
Ronnie Cardenas
DELETIONS
ITEM IDESCRIPTION I DEPT I Qty JUnit I Unit Cost ITotal
Water Unit I
Sewer Unit 2
TPW Unit 3
Page 3 of 4 Deletions Sub Total
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Jose Andrade
Name of Employee
Project Manager
Title
ATTEST:
Jannette S. Goodall
City Secretary
oA� FOR 0
,U' O o°°°0000°
%
/► ° o0�0
O�
0
Vo o=�
0
0
�o o4c41
0
`C ° 0000000 °°° �
Kati nEXASa�p
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth
PENDING CHANGE REQUEST COST ANALYSIS
To be completed by General Contractor or Subcontractor
as outlined in the Uniform General Conditions Section 6.6.1
PROJECT
Work performed by:
JOB NO.
( X ) General Conb ( ) Subcontractor CONTRACTOR:
If subcontractor, give Co. name: ACME ELECTRIC COMPANY
Time Extension (if any): _55
Description of Change: Altamea bridge crane
Four PS Edwards
2699
Acme Electric
PCM#:
CPR#: 13
RFI#:
ASI#:
0
AU1J1IIU1NJ ANINUK IC."0115J
EXTENSION
A
B
C
D
Description
Quantity
Unit
Cost/Unit
Material
Labor
Equip.
Trans.
Archer Western
1
EA
$173,912.87
$173,912.87
$0.00
Site Supervision
1
EA
$3,500.00
$0.00
$3,500.00
FSG
1
EA
$10,150.00
$ 10,150.00
$0.00
Subtotals
$184,062.87
$3,500.00
$0.00
$0.00
Line I: Enter total of Columns A+B+C+D+E
Line II: Enter 49% of Col B for Workman's
Comp. Social Security, and like taxes
$187,562.87
$1,715.00
Line III: Enter total Col E (Storage) $0
City of Fort Worth, Texas
Mayor and Council Communication
DATE: Tuesday, May 12, 2026 REFERENCE NO.: **M&C 26-0348
LOG NAME: 60WSGEN&EMERPLAN GENC05-ACMEELECTRIC
SUBJECT.
(CD 9) Authorize Execution of Change Order No. 5 in the Amount of $198,741.76 to a Contract with
Winston Electric, Inc. dba ACME Electric Company, for the Westside Water Treatment Plant Generators
and Emergency Preparation Plan Project: Part 2 for a Revised Contract Amount of $23,676,787.33 and
Add 55 Calendar Days, and Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution to
the Fiscal Years 2026-2030 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of Change Order No. 5 in the additional amount of $198,741.76 and an
additional 55 calendar days, to City Secretary Contract No. 59846 a contract with Winston Electric,
Inc. dba ACME Electric Company, for the Westside Water Treatment Plant Generators and
Emergency Preparation Plan Project: Part 2 for the Alta Mesa Pump Station for a revised Contract
Amount of $23,676,787.33; and
2. Adopt the attached appropriation ordinance adjusting estimated receipts and appropriations in the
Water & Sewer Revenue Bonds Series 2023 Fund by increasing estimated receipts and
appropriations in the Westside Water Treatment Plant Generators and Emergency Preparation Plan
project (City Project No. 103410) in the amount of $198,742.00 and decreasing estimated receipts
and appropriations in the Commercial Paper project (City Project No. UCMLPR) by the same
amount to effect a portion of Water's Contribution to the Fiscal Years 2026-2030 Capital
Improvement Program.
DISCUSSION:
The purpose of this Mayor and Council Communication (M&C) is to authorize execution of Change Order
No. 5 in the amount of $198,741.76 and add 55 calendar days to City Secretary Contract No. 59846 with
Winston Electric, Inc. dba ACME Electric Company.
On June 13, 2023 M&C 23-0500, the City Council authorized a construction contract with Winston Electric,
Inc. dba ACME Electric Company, in the amount of $23,119,632.00 for Westside Water Treatment Plant
Generators and Emergency Preparation Plan for Power Generation at the North and South Holly Water
Treatment Plants Part 2 Back-up Power and Electrical Improvements at Four Pump Stations (Altamesa,
Edwards Ranch, Como & Eastside). The contract was subsequently revised by four change orders as
follows:
Change Order No. 1 in the amount of $39,177.34 administratively authorized September 16, 2024,
provided for two inches of encapsulated insulation for the proposed electrical building pre -cast walls at the
Altamesa and Edwards Ranch Pumps Stations.
Change Order No. 2 in the amount of $60,550.67 administratively authorized on September 24, 2024,
primarily provided for the relocation of Generator at that provided for replacement of the bulk of the
existing fence which was in poor condition at the Edwards Ranch Pump Station (ERPS).
Change Order No. 3 in the amount of $221,671.33 authorized by the City Council (M&C 25-0902) in
September 16, 2025, provide for the relocation of the proposed Generator at ERPS, remove/prune
existing trees at ERPS, install irrigation for proposed landscaping in front of ERPS, will mill and overlay
exiting asphalt at Eastside Pump Station (ESPS);
Change Order No. 4 in the amount of $37,014.23 administratively authorized on March 25, 2026 provided
for planting of addition crepe myrtles at the north and rear sides of the ERPS to provide privacy in lieu of
screening fence.
Change Order No. 5 will provide for the replacement of the existing bridge crane system of Alta Mesa
Pump Station with a new mono -rail hoist system as requested by water production staff to facilitate the
safe removal and reinstallation of pumps at the facility.
It is the practice of the Water Department to appropriate its Capital Improvement Program (CIP) plan
throughout the Fiscal Year (FY), instead of within the annual budget ordinance, as projects commence,
additional funding needs are identified, and to comply with bond covenants.
Funding is budgeted in the W&S Rev Bonds Series 2023 Fund within the Commercial Paper project for
the Water Department for the purpose of funding the Westside Water Treatment Plant Generators and
Emergency Preparation Plan project.
Appropriations for the Westside Water Treatment Plant Generators and Emergency Preparation Plan
project are as depicted below:
Fund
Existing
Appropriations
Additional
Appropriations
Project Total*
W&S Capital
Project Fund
$12,814,614.00
$0.00
$12,814,614.00
56002
W&S Rev Bonds
Series 2021 -
$8,614,910.12
$0.00
$8,614,910.12
Fund 56019
W&S Rev Bonds
Series 2022 -
$4,230,228.00
$0.00
$4,230,228.00
Fund 56020
W&S Rev Bonds
Series 2023 -
$26,170,999.00
$198,742.00
$26,369,741.00
Fund 56021
Water/Sewer
Gas Lease Cap
$4,850,000.00
$0.00
$4,850,000.00
Proj — Fund
53004
W&S Rev Bonds
Series 2024 —
$7,773,838.88
$0.00
$7,773,838.88
Fund 56022
Project Total
$64,454,590.00
$198,742.00
$64,653,332.00
*Numbers rounded for presentation purposes.
This project is located in COUNCIL DISTRICT 9.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Commercial Paper project within
the W&S Rev Bonds Series 2023 Fund and upon approval of the above recommendations and adoption of
the attached appropriation ordinance, funds will be available in the W&S Rev Bonds Series 2023 Fund for
the WS Gen & Emer Prep Plan project to support the execution of the change order. Prior to any expense
being incurred, the Water Department has the responsibility to validate the availability of funds.
FUND IDENTIFIERS (FIDs).:
TO
Fund
Department
Accoun
Project
Program
ctivity
Budget
Reference #
mount
ID
I
ID
Year
(Chartfield 2)
FROM
Fund
Department
Accoun
Project
Program
[Activity
Budget
Reference #
mount
ID
ID
Year
(Chartfield 2)
CERTIFICATIONS:
Submitted for City Manager's Office by_ Jesica McEachern (5804)
Originating Department Head: Chris Harder (5020)
Additional Information Contact: David Townsend (8430)
ATTACHMENTS
1. 60WSGEN&EMERPLANC05-ACME ELECTRIC Map 01.pdf (Public)
2. 60WSGENEMERPLAN GENC05-ACME ELECTRIC FID Table (WCF 04.07.26).xlsx (CFW Internal)
3. 60WSGENEMERPLAN GENC05-ACMEELECTRIC funds avail (002).docx (CFW Internal)
4. ACME Electric Form 1295 Certificate of Interested Parties 4.2.2026.pdf (CFW Internal)
5. ORD.APP 60WSGEN&EMERPLAN GENC05-ACMEELECTRIC 56021 A026(R2).docx (Public)
6. PBS CPN 103410.pdf (CFW Internal)
U
c
C
T
'n
a
a
0_
D
n
D
0
0
c
c
c
- y
o•
H
o
0
�v
o
v
rt
v
- -
D
-
D
X
m
G
Z
C
m
co
-7
(D C
c-
m
°1 QQIQ
l a
UQ
(DX
-
m
(o
m
M
p
T
1111'
07Q 0)
d
3
T
io
oco M
v
3
T
_
�v
m
3
m
1
1"-
C
X
0
z
r
m
D
3
cc (D
rt
�.
D
3
0
D
3
0
K
Z
a
-
a
M
c
m
c
m
m
c
m
FORT WORTH.
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: Winston Electric, inc. d.b.a. ACME Electric Co.
Subject of the Agreement: Backup Power and Electrical Improvements at Four Pump Stations
M&C Approved by the Council? * Yes 0 No ❑
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes 0 No ❑ 59846-CO5
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 0 No ❑
If unsure, see backpage for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 0 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date: 5/13/2026
If different from the approval date.
Expiration Date: N/A
If applicable.
Is a 1295 Form required? * Yes 0 No ❑
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 103410-2
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 0 No ❑
Contracts need to be routed for CSO processing in the followingorder:
rder:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.