HomeMy WebLinkAbout025602 - Construction-Related - Contract - Infinity Contractors, Inc.�
�
l�l
0
0
. +._
�,.ti . � r
� � ClYY ���t��' �,-ARY ,.
-„ c�rv�rR,�� � a t� .� 5l� ��
� ��
�� is
THE CITY� OF FOl�T WORT�-`, TEXAS
�I ee
1�
REPLACEMENT OF�I590 T�N CENT FUGAL CHILLER
FORT WORTH CO�NVENTIO�v CENTER
� � �asco�rro�
d�
/ �crot
�
° � � �� oa�nuc�sa�oco.
�
� � �1�T �. O1ZT .�...����
n�y
� t)2' � � � - /���u�Y� t
' ' u J�_ L ,�1��i AMi�M�� O�
_� `�
`� --r �`si�Li��/ i/iTi
D � CbNVENT��ON CENTE t/►w-�c;ay �;;.
, .
�� ,
��
KENNET-H BARR `� M B�n 1�i�Ll. �
MAYOR '�� CITY 1VIANAGER
. ,:
D - n� n ,
�
�
�
�
- - ,� �a
� �� _ � I�UGO M ANGA, P. }
DIRECTOR, TRANSPORT TION AND UBLIC WORKS
� �,
KIRI�'°SLAUGI�TER, DIRE TOR
PUBLI� EVENTS .
� �, ��
.M ii
L�
�
�
� ,�, �
�.
u
Architectural Se�'vices Secti " TPW
Romine� Romine and Burgess, ineers
s� N g
�
OCTO�ER, 1 "�9
�. �
�
� �, �
s�
�, ��
,
, �, -
OC�f�BC
�, ii Ca�l
�� (�o �
�o (�
,_ �.
y �e
�j�C��G�D
���e
�
�
�
�
,�
'�
l�
�
�
�'
�
�
L*'
�
�I
C'
��
Ci�'y of Fort� Worth, Te.�as
Ma or �nd. �ouncrl �ommU�.ication
y
DATE REFERENCE NUMBER LOG'NAME PAGE
1/11 /00 **C-17818 20-590 1 of 2
SUBJECT AWARD OF CONSTRUCTIO CONTRACT TO I; FINITY ONTRACTORS, INC. FOR
� THE REPLACEMENT OF 590 TON CHILLER A�THE FORT WORTH CONVENTION
CENTER �
RECOMMENDATIpN:
It is recommended that the City Cour�cil authorize the City Mana�er to execute a construction contract
with Infinity Contractors, Inc. for the p'urchase and,installation of a� 590 ton Centrifugal Chiller to replace
the existing chiller at the Fort Worth �3onvention Cwenter in the am aunt of $213,922 and for a duration of
120 calendar days.
DISCUSSION:
The existing chiller failed in April, 1998. Romine, Romine and Burgess, consulting mechanical and
electrical engineers, prepared construction documents to procure �and install the replacement unit.
The project was advertised in the Commercial Recorder October 21 and 28, 1999. On November 18,
1999, the following proposals were received:
Bidders
Infinitv Contractors, Inc.
GES, Inc.
Systems Integration
Gulf Energy Systems, Inc.
DMI Corporation, Decker Mechanical
Techstar General Contracting, Inc.
Federal Mechanical Systems, Inc.
Weldon Contractors
Burden Brothers, Inc.
Bid
$213.922
$224,960
$228,985
$235,000
$256,885
$259,565�
$262,400
$280,288
$283,092 �
Calendar Days
120
120
115
110
120�
84
126
140
120
The low bidder, Infinity Contractors, Inc., is in compliance with the City's M/WBE Ordinance by
committing to 5% M/WBE participation. The City's goal on this pr�ect is 5%.
The engineer's estimate was $275,000.
The budget for this p'roject will be:
Construction Contract
Contingencies (5%)
Inspection and Management
Tota1
$213,922
10,700
2.000
$226,622
�
�r
� s, !
City of Fort Wortli, T, as
Q 1VLGi�'OY Gin� COUYiCil CO�i'[�f'i � ICG��rOYt
DATE REFERENCE NUMBER LOG NAME PAGE
1/11 /00 **C-'i 7��i 8 I ' ?0-590 2 of 2
� SUBJECT AWARD OF CONSTRUCTION �ONTRACT TO IP FINiTY QNTRACTORS INC. FOR
. THE REPL4CEMENT OF 590 TO�I CHILLER AT 7HE FORT WORTH CONVENTION
aCENTER .
FiSCAL INFORMATION/CERTIFICATION:
� The Finance Director certifes that funds are available in the curre �t o eratin - bud et, as a ro ria#ed
p 9 5 pP p ,
of the Culture and Tourism Fund.
a � �.
MG:j '
f
� �
�
� � � ,
� 6
.�
� � i
� . .
� •
� �w
�
Submitted for City Manager's I FiIND I ACCOUNT I CENTER . I AMOUNT I, CITY SECRETARY
� Office by: � (to) '
Mike Groomer 6140 �
Q Originating Department Head: ' �
�
Hugo Malanga 7801 �(from) ' APPROVED 1/11/00 �
� . + GG04 541200 0242000 $213,922.00
Additional Information Contact: I
Hugo Malanga 7801 � • � ,
� :�
�
� '
�
�
r
�.
C
r
THE CITY OF FORT WORTH, TEXAS
REPLACEMENT OF 590 TON CENTRIFUGAL CHILLER
FORT WORTH CONVENTION CENTER
O1ZT OI�TH
J a
� `
�� _-�
CONVENTION CENTER
KENNETH BARR
MAYOR
�
�
KI SLAUGHTER, DIRECTOR
PUBLIC EVENTS
BOB TERRELL
CITY MANAGER
�o�i�/� �
DATE
� �
/�/� �? � - �� �� � /S �
� MIKE MATHEWS, P.E. DATE
CHIEF, ARCHITECT'URAL SERVICES SECTION
HUGO MALANGA, P. E.
`-� DIRECTOR, TRANSPORTATION AND PUBLIC WORKS
�
KIRK SLAUGHTER, DIRECTOR
PUBLIC EVENTS
,, ,. ._. .-_ � G,�r���Lp1
��� �J�'���� u�:S �-
�` ,,��� �����G����aG�°�
� �� }���,�; ���`�o.
U J,: , i` .. '
..'rt'
-.{,.. - - ..Yw ,.
i;�!
y
.�
Architectural Services Section, TPW -� ::�;�'�, � .
Romine, Romine and Burgess, Engineers ,,'�;�,.�. ;�:
OCTOBER, 1999
��
�
,., .�. : r�%'
_ ,' •
; �.; x'' ' .
�1��. �������
�q�����
NOTICE TO BIDDERS
�`'� Sealed bids for Replacement of 590 ton Centrifugal Chiller, Fort Worth Convention Center, 1111 Houston
Street, Fort Worth, will be received at the Purchasing Office, City of Fort Worth, 1000 Throckmorton, Fort
Worth, 76107, until 1:30 P.M., Thursday, November 18, 1999, and will be opened and publicly read
. aloud approximately thirty minutes later in the Council Chambers.
A Pre-Bid Conference will be held at 10:00 AM, Tuesday, November 2, 1999, at the Power House
Mechanical Room, located on Commerce Street directly east of the Arena at the Fort Worth Convention
Center.
The Project consists of the replacement of a Water chilling Unit No. 3 with a Trane Model CVHF, including
supporting piping, electrical, instrumentation and equipment pad.
� The MWBE Goal for this project is 5%. Contact the MWBE office (871-6104) to obtain lists of certified
subcontractors and suppliers.
Contractors will be required to post Payment and Performance Bonds and provide Contractors General
� Liability and Statutory Workers Compensation Coverage.
Copies of the Project Manual and plans for this project may be obtained at the Department of Engineering
� Plans Desk, City Hall, 1000 Throckmorton Street (817.871.7910) in return for a$50 deposit for each set.
For additional information contact the design engineer, Tom Romine, of Romine, Romine and Burgess at
336-4633.
Advertisement: October 21, 1999
October 28, 1999
�
,
'
,
'
'
�
�
�
�
�
� ���'GOG�� �`:'��'� °��
����' ����G�%�'aG�,�
�lo �U �'��o ����o �
r
�
�._
�
L..
�
�.
�
�
�
,
'
'
'
�
�
1
FORT WORTH CONVENTION CENTER
1111 Houston Street, Fort Worth. Texas 76102
Ganersl
Wort(.
Sauare
/ �\1 ^
N �'�
-«--.�---
��o��\
�:< <a�
� ��\\
�TCCC Puking
re Gora c
, � ���
�����
c'+s"`
��
cL�.�— -'v��,F
o� �
o J,
a�
��
�
���[����GU�� �'[��C�G�D
� ��� ����� Gt[���G?°�
�l�o ����r'l�ly ���o
0
TABLE OF CONTENTS
'�� NOTICE TO BIDDERS
TABLE OF CONTENTS
�:, INSTRUCTIONS TO BIDDERS
SPECIAL INSTRUCTION FOR BIDDERS (M/WBE)
� PROPOSAL
GENERAL CONDITIONS
� WEATHER TABLE
WAGE RATES
"" TECHNICAL SPECIFICATIONS
' 15010 MECHANICAL SPECIAL PROVISIONS
15060 PIPING
�, 15100 VALVES, STRAINERS AND UNIONS
15180 INSULATION FOR MECHANICAL TRADES
� 15600 CHILLER REPLACEMENT
16000 ELECTRICAL WORK
r
CONTRACT
PERFORMANCEBOND
PAYMENTBOND
�"' CERTIFICATE OF INSURANCE
�° CONTRACTOR COMPLIANCE WITH WORKERS' COMPENSATION LAW
�
'
,
,
'
,
�
�
�
�� f�����1�� �'�C���G� ��
�: 0�� ��C�''� `?��G� ��
�o '� ��'���9 ��l?o
INSTRUCTIONS TO BIDDERS
�
�..
�
�
�
1. PROPOSAL REQUIREMENTS: The following requirements are considered in judging the
responsiveness of a Proposal:
• Use the Proposal Form provided in the Project Manual.
• Entries on the Proposal Form may be handwritten or typed
• Write in contract duration if not specified
• Acknowledge all addenda on the Proposal Form
• Have a Principal sign the Proposal
• Enclose a bid deposit of 5%. This can be in the form of a cashiers check or standard
bid bond. Personal checks are not acceptable. Note Project Name on the check or bid
bond
2. MINORITY/WOMENS BUSINESS ENTERPRISE (M/WBE)
1f your bid is in excess of $25,000, the MWBE Program applies, and you have five City business days
following the bid date to prepare and submit your M/WBE Plan. Early submittal is encouraged. Be aware
that if you elect to provide documentation of a Good Faith Effort you will have to accomplish each and
every action in the Soecial Instructions to Bidders, Minority and Women Business Enterprises
Specifications, included in this Project Manual. In order to meet all the requirements for a Good Faith
Effort you will have to start at least two weeks before the Bid date.
The lowest responsive, responsible, bidder meeting the M/WBE requirements will be recommended for
award. Information concerning participation of Minority and Women's Business Enterprises is not required
for Projects less than $25,000. All purchases from M/WBE suppliers, second tier subcontractors and
second tier suppliers may be included in M/WBE contribution toward meeting the goal.
The Bidder shall submit the M/WBE UTILIZATION FORM, PRIME CONTRACTOR WAIVER FORM and/or
� the GOOD FAITH EFFORT FORM ("Documentation") as appropriate. The Documentation must be
received no later than 5:00 P.M. five (5) City business days after the bid opening date. The Bidder shall
obtain a receipt from the appropriate employee of the managing department to whom delivery was made.
� Such receipt shall be evidence that the City received the documentation.
Successful Bidder will be required to submit co-signed letters of intent or executed agreements with all
M/VVBE subcontractors and suppliers prior to receiving a Notice to Proceed.
�
3. BID SECURITY: Cashier's check or an acceptable bidder's bond payable to the City of Fort
� Worth, in an amount of five (5) per cent of the bid submitted. The Bid Security must accompany the bid
and is subject to forfeit fin the event the successful bidder fails to execute the contract documents within
ten (10) days after the contract has been awarded. The Bid Security shall be included in the envelope
containing the bid proposal. Failure to submit the Bid Security will result in the proposal not being consid-
� ered for this project. Bidder's bond will be returned if the City fails to award the contract within 49 calendar
days of receipt of bids, unless the Bidder agrees to an extension.
� 4. PAYMENT BOND AND PERFORMANCE BOND: For projects in excess of $25,000, the
successful bidder entering into a contract for the work will be required to give the City surety in a sum
equal to the amount of the contract awarded. The form of the bond shall be as herein provided and the
r,,, surety shall be acceptable to the City. All bonds furnished hereunder shall meet the requirements of
Article 5160 of the Revised Civil Statutes of Texas, as amended.
�
'
In order for a surety to be acceptable to the City, (1) the name of the surety shall be included on the
current U. S. Treasury List of Acceptable Sureties (Circular 870), or (2) the surety must have capital and
'��U��9��V�:��, ��'�,���;•��:��3�11
L':
��; J � V N���� U`_�� �1 e,?�
� i �-�G,�
I�1� I�t�ii; �S�P�� i?f��'Z
surplus equal to ten times the amount of the bond. The surety must be licensed to do business in the
� state of Texas. The amount of the bond shall not exceed the amount shown on the Treasury list or one-
tenth of the total capital and surplus. If reinsurance is required, the company writing the reinsurance must
_ be authorized, accredited or trusteed to do business in Texas.
� No sureties will be accepted by the City which are at the time in default or delinquent on any bonds or
which are interested in any litigation against the City. Should any surety on the contract be determined
�"' unsatisfactory at any time by the City, notice will be given to the Contractor to that effect and the
contractor shall immediately provide a new surety to the City.
If the total contract price is $25,000 or less, payment to the contractor shall be made in one lump sum.
Payment shall not be made for a period of 45 calendar days from the date the work has been competed
�"' and accepted by the City.
� If the contract is in excess of $25,000, a Payment Bond shall be executed, in the amount of the contract,
solely for the protection of all claimants supplying labor and materials in the prosecution of the work.
� lf the contract amount is in excess of $100,000, a PerFormance Bond shall also be provided, in the amount
of the contract, conditioned on the faithful performance of the work in accordance with the plans,
specification, and contract documents. Said bond shall be solely for the protection of the City of Fort
�... Worth.
`" 5. PRE-BID SITE INVESTIGATION: Prior to filing a bid, the bidder shall examine the site(s) of the
work and the details of the requirements set out in these specifications to satisfy himself as to the
"� conditions which will be encountered relating to the character, quality, and quantity of the work to be
performed and materials and equipment required. The filing of a bid by the bidder shall be considered
evidence that he has complied with these requirements.
L�
�
�
6. AMBIGUITY: In case of ambiguity or lack of clearness in stating prices in the proposal, the City
reserves the right to adopt the most advantageous construction thereof to the City or to reject the propos-
al.
7. WAGE RATES.: Not less than the prevailing wage rates set forth in Contract Documents, must be
paid on this project.
8. POST BID - PREAWARD SUBMITTALS: Bidders are required to submit the following information
to the Architectural Services Section, Building Services Division, 3409 Harley Avenue, 817-871-8274,
� within five business days subsequent to bid opening (Normally Thursday following a Thursday bid
� opening) in order to assist City staff in determining the Contractor's capability of performing the work and
in meeting City contract requirements:
� Minority/Women's Business Documentation (for bids in excess of $25,000)
Contractors Qualification Statement (AIA Form A305)
Proposed Subcontractors and Suppliers
Proof of insurability for Statutory Workers Compensation Insurance
9. PROPOSED SUBCONTRACTORS: Acceptance of the bid in no way requires the City to accept
� the qualifications of the subcontractors. The Subcontractor lists are for use by the City in preparing
recommendations for award of the contract. The Contractor must provide and use subcontractors listed
unless the City agrees to allow a substitute.
� 10. DISCREPANCIES AND ADDENDA:
�
,
�� ����GUG�:� �?����G�D
C ��i � ��� �G°?C�G�1�
�e �'VSI111U9 Il�a—
Should a bidder find any discrepancies in the drawings and specifications, or should he be in doubt as to
their meaning, he shall notify the City at once. If required, the City will then prepare a written addendum
`°� that will be available to all Bidders at the Plans Desk or place designated for distribution of Bid Documents
by the Notice to Bidders. The Contractor is responsible for determining if addenda are available and for
� securing copies prior to submitting a proposal. Oral instructions or decisions unless confirmed by
addenda will not be considered valid, legal or binding. No extras will be authorized because of failure of
the contractor to include work called for in the addenda.
Bidder must acknowledge addenda in the Proposal. Failure to acknowledge addenda may cause the
Proposal to be ruled non-responsive. It is the Contractor's responsibility to obtain Addenda and include its
information in the Proposal.
� 11. WORKERS COMPENSATION INSURANCE: Bidders will be required to demonstrate that
coverage is in effect at time of Award of Contract. Sample Certificate of Insurance, or other proof that
Workers Compensation Insurance will be obtained, must be submitted within five working days of bid
opening
12. TAXES: Equipment and materials not consumed by or incorporated into the work are subject to
State sales taxes under House Bill 11, enacted August 15, 1991.
13. PERMITS: Contr�ictor shall apply for all City of Fort Worth Permits and for any other permits
required by this project. City of Fort Worth Building and Trade Permit fees are waived. Separate permits
may be required for each w�ork location.
� 14. CONTRACT DURATION: Time is of the essence. City will evaluate the bids based upon
construction cost and stated bid period of time for construction. Where the Bidder proposes time, the City
will evaluate the City's program needs in determining the acceptability of the proposed contract duration.
The City reserves the right to award the contract upon those terms considered by the City to be in its best
� interests.
15. PLAN DEPOSIT: The City will deposit plan deposit checks to its account two weeks following
receipt of bids. Plans must be returned by all except the apparent low bidder prior to that time.
Contractors forFeit their plan deposit after that time.
� 16. ADJUSTMENT OF QUANTITIES: Where unit prices and estimated quantities are used to
compute the contract amount, the Owner may increase the quantities by an amount that is 20% of the
total cost for that section. Unit prices for adjustments to unit quantities in excess to 20% may be
negotiated at the request of either party.
17. MANUFACTURER'S REFERENCE: Catalog, brand names, and manufacturer's references are
� descriptive, not restrictive. Bids on brands of like nature and quality will be considered. Within 14 days
after bid opening and upon request of the architect or contractor, the contractor will submit a full sized
sample and/or detailed information as required to allow the architect to determine the acceptability of
proposed substitutions. Where equipment has been listed as "no substitute accepted", the City will accept
� no alternates to the specified equipment.
..�.•
'
'
�
�
�
� �����rOG��� ��rr��Gl� �.
�:;��'ti' ��!:;V`���;� e,��
C� �� � ���J � ����'
r •: �: a SU,.o
PROPOSAL
T0: MR. BOB TERRELL
CITY MANAGER
CITY OF FORT WORTH, TEXAS
FOR: REPLACEMENT OF 590 TON CENTRIFUGAL CHILLER
FORT WORTH CONVENT(ON CENTER,
1111 HOUSTON STREET, FORT WORTH
Pursuant to the foregoing "Notice to Bidders," the undersigned has thoroughly examined the plans,
specifications and the site, understands the amount of work to be done, and hereby proposes to do all the
work and furnish all labor, equipment and materials necessary to fully complete all the work as provided in
the plans and specifications, and subject to the inspection and approval of the Director of Transportation
and Public Works of the City of Fort Worth.
� Upon acceptance of this Proposai by the City Council, the bidder is bound to execute a contract and, if the
contract amount exceeds $25,000.00, furnish Performance and/or Payment Bonds approved by the City of
Fort Worth for perForming and completing the Work within the time stated and for the following sum, to wit:
DESCRIPTION OF ITEMS
n 1 .�-- �.
Replace 590 Ton Chiller, including all labor and material $ G(�7 � 2-� 7� )( �' ��`""
�
The undersigned agrees to complete the Work within I 2� calendar days after the date of Notice io
Proceed.
The City reserves the right to accept or reject any and all bids or any combination thereof proposed for the
above work.
The undersigned assures that its employees and applicants for employment and those of any labor
organization, subcontractors or employment agency in either furnishing or referring employee applicants
to the undersigned are nof discriminated against as prohibifed by the terms of City Ordinance 7278 as
amended by City Ordinance 7400 (Fort Worth City Code Section 13A-21 through 13A-29).
Residency of Bidders: The 1985 Session of the Texas Legislature passed house Bill 620 relative to the
award of contracts to non-resident bidders. The law provides that, in order to be awarded a contract as
low bidder, non-resident bidders (out of state contractors whose corporate offices or principal place of
business are outside of the State of Texas) that bid projects for construction, improvements, supplies or
services in Texas at an amount lower than the lowest Texas resident bidder by the same amount that
Texas resident bidder would be required to underbid a non-resident bidder in order to obtain a comparable
contract in the state in which the non-resident's principai place of business is located. The appropriate
blanks in Section A must be filled out by all non-resident bidders in order for your bid to meet
specifications. The failure of out of state or non-resident bidders Failure to complete the forms may
disqualify that bidder. Resident bidders must check the box in Section B.
��
�Y �
� �
A• �_� Non-resident vendors in (give state), our principal place of
business, are required to be percent lower than resident bidders by state
law.
�_� Non-resident vendors in (give state), are not required to
underbid resident bidders.
B• �Our principal place of business or corporate offices are in the State of
exas.
;a'f��r�b�i=,`��t, ����!G�U�c�IU� '
. !�u b' `L''�U,:��UGaUSI'i
���:v �
��� ,�,�,�� ���o �(l��o ;
�
,from: Mike Mathews 817-871-8488 To: Jim Salter Date: 11H7199 Time: 1320:56 Page 2 af 2
�f 9 .
�
,,
,
�
�
�.
�
�
�
...
�
�
�
Within ten (10) days of receipt of notice of acceptance of this bid, the successful bidder
will execute the formal contract and will deliver approved Surety Bonds for the faithful
performance of this contact. The attached deposit check in the sum of
Dollars ($ •,,� is to become the property of the City of Fort Worth, Texas, or the
attached Bidder's Bond is to be forfeited in the event the contract and bonds are not
executed within the time set forth, as liquidated damages for delay and additional work
caused thereby.
MINORITYNVOMENS BUSINESS ENTERPRISE (MMIBE}: {For bids in excess of
$25,000)
• I am aware that I must submit information the Director, Transportation and Public
Works, concerning the M/WBE participation within FIVE BUSINESS DAYS of
submittal of this Proposal in order to be RESPONSIVE.
Respectfully submitted,
:
Address:
Infinity Contractors, Inc.
Company N e
Signatur 1"
Jim Salter
Printed Name of Principal
P.O. Box 163316
Street
Fort Worth, TX
City
Phone: 817/431-6424
Fax: 817/431-7054
Receipt is acknowledged of the following addenda:
Addendum No. 1:
Addendum No. 2:
President
Title
76161
Zip
^i������G�� �'�C�u�D
(rv,�'-g�1( ��'v� ° °�
C�a ��� ����lo ��o
�
ATTACHME�IT S
Pa9� 2 of ;
City of Fort Worth
r". Minority and Women Business Enterprise Specifications
I,
� . MBElWBE UTILiZATION
� Company Name, ConWct N�me, CerUfied Specify Ail Contncting Speci(y AI( Items to be Dollar Amount
Address, and Tclephonc No. .�. Scopc o( Work (') Supplicd(') 2.--.
t{.� �- 2 . - �
� g� g�
Z
{ _ - _
I_ ---... ._.. _.- --
I_.._...--
I'� - ----. ... .. _
he bidder further agrees to provide, directly to the City upon request, complete and accurate information regardinc -
actual work pertormed by al! subcontractors, including MBE(s) andlor WBE(s) arrangements submitted with this bid
The bidder also agrees to allow an audit and/or examination o( any books, records and tites held by their company thai
ill substantiate the actual work performed by the MBE(s) and/or WBE(s) on this contract, by an authorized of(icer or
�mployee o( thc City. Any intentional and/or knowing mis�epresentalion o( facts will be grounds for terminating thc
contract or debarment trom City work for a period ot not less than three (3) years and for initiating action under Federal,
-tate o� Local laws concerning talse statements. Any failure to comply with this ordinance and creates a material
�each o( contract may result in a determination o( an irresponsible offeror and barred from participating i� City wo�k
tora period of lime not Iess than onc (1) year.
L and WBEs MUST BE CERTIFIED BY THE CITY BEFORE CONTRACT AWARQ
Jim Salter
Authoriz Signaturc Printed Signaturc
?resident
tle Contact Name and Title (if di(ferent�
Infinity Contractors, Inc. 817/431-6424
"' �mpany Namc Tcicphonc Numbcr (s)
?.O. Box 163316 817/431-7054
Address Fax Numbcr
,ort Worth, TX 76161 11-26-99
tylStatc/Zip Codc Datc
TH1S FORM MUST BE RECEIVED �Y THE MANAGING DEPARTMENT �Y 5:00 p.m., FIVE (S) CITY BUSINESS 7�AXS-A,�T.EQ��
OPENING. EXCLUSIVE OF THE E310 OPENING OATE ^ � � '��(^!'r�
�` ���I��'��/�����'� U.0
Pages 1 and 2 of Attachment 1A must be received by the Managing Oepartment �?1 �� (Nti�ji^ Ie1�`���j°;�
;r u � .; u�;L
��� �,��ct���9 ���.
� M W 8 E- 3 ._. ...._... -
�,; City of Fort Worth
Minority and Women gusiness Enterprise Specifications
� MBE/WBE UTILIZATION
Infinity Contractors, Inc. 11-18-99
�, PRIME COMPANY NAME EiID DATE
� Replacement of 590 ton chiller at Convesition
PROJECT NAME Center PROJECT NUMBER
I C1Tl"S 61/�YBE PROJECT COAI,: �j a � I �I/�YBE PERCENTAGE �CIIIEveD:
Speci(y A�I Contracting Specify AII Items to be
Scope of Woric (') Supplied(')
�`" Failure to complete thls form, In its entirety with supporting documentation, and received by the Managing Departmenf
on or before 5:00 p.m. five (S) City business days after bid opening, excluslve o( bid opening date, will result in the bid
" being consldered non-responslve to b(d specl�cations.
�
The undersigned bidder agrces to enter into a foRnal agrcement with the MBE andlor WBE fiRns for work listed In this
�,,, schedule, conditioned upon execution of a contract with the City of Fo�t Worth. The intentional and/or knowing
misreprese�tation of faets is grounds for eons(deration of disquali�cation and will result In the bid being consldered
non-responslve to speclfications.
�� Company Namc, Contact Name, � CerUfied
� Address, and Telepho�e No. � _
u '" '
� o0
F � �
/m H
M =
�- E.O. Wood Co.
Robert Haskins
�712� N. Beach St.
F'ort�Worth, TX 76111
817%�83�-�$.� �
�All-Tex Supply
Tom Dixon
9745 Brockbank
r- Dallas, TX 75220 �
214 j'35����� �
� ---
�
X
��
��.
� MlWpE.s must be located In the 9(ni�e) county marketplace or currently doing buslness In lhe marketplace at the time o( bld. �
� O Spccl(y all areas In which MWEiE's are to be utitized andlor Items lo bc supplied: I
"�(') A comn�ete listing of Items to be supplied is required in order to receive credil toward the M/WBE goal.
' ('j Identi(y each Tier level. Tier. Means the level o( subcontracling below the prime contractorlconsultant, I.e., a direct payment '
� �' (rom the prfine con[nctor to a subcontraclor Is consldered 1� tler, a payment by a subcontractor to
its supplier Is consldorad 2n° tior.
�
�
THIS FORM MUST BE RECEIVED BY THE MANAGING DEPARTMENT BY 5:00 p.m., FIVE (5) CITY BUSINESS DAYS AFTER BID
OPENING, EXC�USIVE OF THE BID OPENING OATE
Rev 612198
Pages 1 and 2 of Attachment 1A must be received by the Managing Department
Pipe insulation
for all new pipe
�r
N F"
ATTACHMENT 1<
Pagc 1 of �
Dollar Amount
'�T 1,528.00
Weld fittings, �sj 9,170.00
weld pipe, valve�,
gage & thermomet�s
� MWE3E-2
'� �^�D'� OG�� �'�Cu"�
�� � U U C����� d� U
f�R �n����iM 5�f2M
�
�
� INFINITY C4NTRACTORS, INC.
P.O. Box 163316 Fort Worth, Texas 76161
C Phone: (817) 431-6424 Fax: (817) 431-7054
INFINI7Y
CONflACTORf�,N�. �TR.ANSMITTAL LETTER �
TO:
ATTN:
PROJECT:
(name & address)
NUMBER OF
COPIES
1
� City of Fort Worth
3409 Harley Avenue
Fort Worth, TX
L Mike Matthews
Chiller Replacement at
Fort Worth Convention Center
� DATE:
�
IICI Job#
� 11 /26/99
REVISION
NUMBER DESCRIPTION DATE
Minority and Women Business Enterprise Specifications 11 /26/99
WE TRANSMIT:
0 Herewith
❑ Under separate cover via
THE FOLLOWING:
❑ Drawings
❑ Change Order
� Specifications
❑ In accordance with your request
❑ Contracts ❑ Product Literature
❑ Payment & Pertormance Bond
❑
FOR YOUR:
� Use ❑ Review & Comment ❑ Distribution
❑ Approval ❑ Information
❑ Record ❑
REMARKS If you have any questions, please call Jim Salter at 817/431-6424.
COPIES TO: (with enclosures) �
❑ ,�
File ❑� � ^ � v �
❑ SIGNED: ���/� . '�:, a 1. /q � �� i r �-�
*NOTE* If enclosures are not as noted, please ` ' '� ' Rachel �. Sal�zar =' � '
inform this office. INFINITY CONTRRCTORS, �1VC,
Please:
�✓ Acknowledge receipt of enclosures. il` � � �� � � �
❑. -� ��,, ,
Return enclosures to us. ° �[����
� �t
, � �� U _ � , _ . ,., �; ¢Ua Il
U Uu U`J�J�� ��II11� �15�a
FAXF
.,.�.�.D
�"' C
INFINITY
, CONTRACTORi, INC.
WHERE TRUST IS BUILT WITH
, QUALITY, VALUE AND SERVICE
�
MECHANICAL/ PLUMBING/ PROCESS
� AND INDUSTRIAL PIPING AND
HVAG COMMER CIAL/ IND USTRIAL
�
,
�
Jim Salter
President
Post Office Box 163316
Fort Worth, Texas 76161
Office: (817) 431-6424
Fax: (817) 431-7054
FAX MESSAGE TO: (817) 871-8488
Company: C� of Fort Worth
Attention: Mike Matthews
Reference: Chiller Replacement at FW Convention Center
Date: November 26, 1999 No. of Pages: 3
(Including Cover Page)
ADDITIONAL COMMENTS:
If you ha�e any questions, please call our office at the above
number.
�
�
'
�
Message From
INFINITY CONTRACTORS, INC.
Thank You,
�ivn �a�ter
�:;����������:� �'1�����'D
�� ��`�r �,���°?� ° °�
` �i; �:���G'i�� ��` o
0
�
�'"
�
DATE:
TO:
�z o �
FoRT oRTH }� _____ ___ .�
_. �
�_ . .
__:�
TRANSPORTATION AND PUBLIC WORKS DEPARTMENT
CITY OF FORT WORTH, TEXAS
BUILDING SERVICES DIVISION
ARCHITECTURAL SERVICES SECTION
3409 HARLEY AVENUE, 76107
(817)871-8274
FAX (817) 871-8488
FAX NOTE
�Z/ � �� � NO PAGES: (
�
'1L�c,+�. � F� 86q v
�I�li✓
FROM: Mike Mathews
SUBJECT: I�Gt%�� L�����
�'
�
�:
�
�
�
1
�
e
,
ORIGINAL WILL NOT FOLLOW:
MESSAGE:
� f�� 1�,�� � �, � �
����G� �OG�d G'�C���D
�� u U c���'� G°� b e��
!r!b 1�11���:�uWo �o
City of Fort Worth, Texas
Transportation/Public Works DeparUnent
Building Services Division/Architectural Services Section
GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION
�..
!
�
rr
�,
SECTION A
DEFINITIONS, PROCEDURES AND INTERPRETATIONS
A-1 CONTRACT DOCUMENTS. By the term Contract
Documents is meant all of the written and drawn documents
setting forth or affecting the rights of the parties, including
but not necessarily limited to, the Contract, Notice to
Bidders, Proposal, General Conditions, Special Conditions,
Specifications, Plans, Bonds and all Addenda, Amendments
signed by all parties, Change Orders, written Interpretations
and any written Field Order for a minor change in the Work.
A-2 ENTIRE AGREEMENT. The Contract Documents
represent the entire agreement between the Parties, and no
prior or contemporaneous, oral or written agreements,
instruments or negotiations shall be construed as altering the
terms and effects of the Contract Documents. After being
executed, the Contract Documents can be changed only by
a written Amendment signed by the Contractor and the
Owner, or Change Order, or by a written Field Order for a
minor change.
A3 WORK. By the term Work is meant all labor,
supervision, materials and equipment necessary to be used
or incorporated in order to produce the construction required
by Contract Documents.
A-4 EXECUTION OF THE CONTRACT
DOCUMENTS. The Contract Documents shall be executed
in six originals by the Contractor and the Owner in such form
as may be prescribed by law.
A-5 FAMILIARITY WITH PROPOSED WORK. Before
filing a bid, the bidder shall examine carefully the proposal,
plans, specifications, special provisions, and the form of
contract to be entered into for the work contemplated. He
shall examine the site of work and satisfy himself as to the
conditions that will be encountered relating to the character,
quality and quantity of work to be performed and materials to
be furnished. The filing of a bid by the bidder shall be
considered evidence that he has complied with these
requirements and has accepted the site as suitable for the
work.
Claims for additional compensation due to variations
between conditions actually encountered in construction and
as indicated by the plans will not be allowed.
A-6 ONE UNIFIED CONTRACT. Insofar as possible,
the Contract Documents will be bound together and
executed as a single unified Contract, the intention of the
Contract Documents being to provide for all labor,
supervision, materials, equipment and other items necessary
for the proper execution and completion of the Work. Words
that have well recognized technical or trade meanings are
used herein in accordance with such recognized meanings.
A-7 DIVISION OF WORK. The arrangement of
Drawings and/or Specifications into Divisions, Sections,
Articles, or other Subdivisions shall not be binding upon the
contractor in dividing the work among Subcontractors or
Trades.
A-8 INTERPRETATIONS. The Architect will furnish
such Interpretations of the Plans and Specifications as may
� GC - 1 of
10/11/99
�
be necessary for the proper execution or progress of the
work. Such Interpretations shall be furnished at the instance
of the Architect or at the request of the Contractor, or Owner,
and will be issued with reasonable promptness and at such
times and in accordance with such schedule as may be
agreed upon. Such Interpretations shall be consistent with
the purposes and intent of the Plans and Specifications and
may be effected by Field Order. In the event of any dispute
between any of the parties to the Contract and the Architect
or each other involving the interpretation of the Contract
Documents, the evaluation of work or materials performed or
furnished by the Architect Contractor, or any subcontractor
or materialsman, or involving any question of fault or liability
of any party, the decision of the Owner shall be final and
binding.
In the event of inconsistency in the contract documents, the
following sequence for interpretation shall be used in order
of precedence: Change Orders and/or Field Orders (by date
of issuance); Addenda (by date of issuance); Drawings;
Notes and dimensions on Drawings; Technical
Specifications; Special Provisions; Supplementary General
Conditions; General Conditions; and, Construction Contract.
A-9 COPIES OF WORKING DRAWINGS AND
SPECIFICATIONS. The Architect will furnish to Contractor
free of charge 15 sets of working Drawings and 15 sets of
Specifications. Contractor shall pay the cost of reproduction
for ail other copies of Drawings and Specifications furnished
to him.
All Drawings, Specifications and copies thereof furnished by
the Owner of the Architect are and shall remain the property
of the Owner. They are not to be used on any other project
and, with the exception of one Contract set for each Party to
the Contract, are to be returned to the Owner on request at
the completion of the work.
A-10 MINORITY AND WOMENS BUSINESS
ENTERPRISE POLICY. The City of Fort Worth has goals
for the participation of disadvantaged business enterprises in
City contracts. Compliance with the policies designed to
meet these goals is mandatory in order to be considered a
responsive bidder. The City policy and procedures to be
followed in submitting bids is included.
The City of Fort Worth MWBE Program will take precedence
over other subcontractor utilization programs on Block Grant
and other Federally funded Projects.
A-11 CORRELATION AND INTENT.. In general, the
drawings indicate dimension, locations, positions, quantities,
and kinds of construction; the specifications indicate the
quality and construction procedures required. Work
indicated on the drawings and not specified of vice-versa,
shall be furnished as though set forth in both. Work not
detailed, marked or specified shall be the same as similar
parts that are detailed, marked or specified. If the drawings
are in conflict or conflict with the specifications the better
quality or greater quantity or work or materials shall be
estimated and shall be furnished or included. Dimensions
on drawings shall take precedence over small-scale
drawings. Drawings showing locations of equipment, piping,
ductwork, electrical apparatus, etc., are diagrammatic and
job conditions may not alla•,�r 1..Ilu����� ��� u�C exact ioca ion
� ��
� � il ' ���� � �� �
. . ,.>�. .._. ._�.. . .._,
1�c ^�� Q�����''
�' � �l � �I�� �, S �';; �
23 �� ; ����� c��� � G:� 1�-aUL 1�
1 5��;v
���, �,'�')i;'�; �''la U •.SGr�
�.,
F
�
4.
�
P
t�
�_
shown. Relocation shall not occur without the Architects
approval.
SECTION B
IDENTITY OF ARCHITECT
the progress of the Work and will endeavor to guard the
Owner against defects and deficiencies in the Work of the
Contractor. Based upon such observations and the
Contractor's applications for payments, the Architect will
make determinations and recommendations concerning the
amounts owing to the Contractor and will issue certificates
for payment amounts.
B-1 CONTRACT ADMINISTRATION. Where the term
"Architect" is used in the "General Conditions of the Contract
for Construction", it shall refer to the Director, Transportation
and Public Works or his designated Project Manager. The
Director, Transportation will designate a Project Manager
and Construction Manager to administer this contract and
perform the functions of the "ArchitecP' as indicated in the
General Conditions. The design architect or engineer may
also be designated to perForm the duties of "Architect".
B-2 TERMINATION AND SUSPENSION OF WARK:
The Owner has the right to terminate the Project for any
reason. if the project is terminated, the Contractor shall:
a) Stop work under the Contract on the date and to
the extent specified on the notice of termination.
b) Place no further orders or subcontracts except as
may be necessary for the completion of the work not
terminated.
c) Terminate all orders and subcontracts to the
extent that they relate to the perFormance of the work
terminated by the notice of termination.
After termination as above, the City will pay the contractor a
proportionate part of the contract price based on the work
completed; provided, however, that the amount of payment
on termination shall not exceed the total contract price as
reduced by the portion thereof allocatable to the work not
completed and further reduced by the amount of payments,
if, any otherwise made. Contractor shall submit its claim for
amounts due after termination as provided in this paragraph
within 30 days after receipt of such claim. In the event of
any dispute or controversy as to the propriety or allowability
of all or any portion of such claim under this paragraph, such
dispute or controversy shall be resolved and be decided by
the City Council of the City of Fort Worth, and the decision
by the City Council of the City of Fort Worth shall be final
and binding upon all parties to this contract
B-3 DUTIES OF THE ARCHITECT As used herein,
the term Architect means the Architect or his authorized
representative. Nothing contained in these Contract
Documents shall create any privity of Contract between the
Architect and the Contractor.
B-4 ARCHITECT AS REPRESENTATIVE OF THE
OWNER The Architect will provide general administration of
the Contract on behalf of the Owner and will have authority
to act as the representative of the Owner to the extent
provided in the Contract Documents unless changed in
writing by the Owner. The Architect will be available for
conferences and consultations with the Owner or the
Contractor at all reasonable times.
B-5 ACCESS TO JOB SITES. The Architect shall at
all times have access to the Work whenever it is in
preparation and progress. The Contractor shall provide
facilities for such access so the Architect may perform its
assigned functions under the Contract Documents.
The Architect will make periodic visits to the Site to
familiarize himself with the progress and qualiry of the work
and to determine if the work is proceeding in accordance
with the Contract documents. On the basis of on-site
observations, the Architect will keep the Owner informed of
10/ 11 /99
B-6 INTERPRETATIONS. The Architect will be, in the
first instance, the interpreter of the requirements of the Plans
and Specifications and the judge of the perFormance
thereunder by the Contractor, subject to the final decision of
the Owner.
The ArchitecPs decisions in matters relating to artistic effect
will be final if consistent with the intent of the Contract
Documents.
B-7 AUTHORITY TO STOP WORK. The Architect will
have authority to reject work that does not conform to the
Plans and Specifications. In addition, whenever, in its
reasonable opinion, the Architect considers it necessary or
advisable in order to insure the proper realization of the
intent of the Plans and Specifications, the Architect will have
authority to require the Contractor to stop the Work or any
portion thereof, or to require special inspection or testing of
the Work whether or not such Work be then fabricated,
installed or completed.
B-8 MISCELLANEOUS DUTIES OF ARCHITECT.
Shoo Drawinas. The Architect will review Shop Drawings
and Samples as provided in Section D. Two copies of each
approved Shop Drawing and submittal wiil be provided to the
Owner by the Architect.
Chanae Orders. Change Orders and Field Orders for Minor
Changes in the Work will be issued by the Owner through
the Architect in accordance with the provisions of Section L.
Guarantees,. The Architect will receive on behalf of the
Owner all written guarantees and related documents
required of the Contractor. Upon completion of the project
the Contractor shall provide the Architect five copies of each
guarantee. The Architect will provide three copies of each
guarantee to the Owner.
Insoections The Architect will conduct inspections for the
purpose of determining and making his recommendations
concerning the dates of substantial completion and final
completion.
Ooeration and Maintenance Manuals The Architect will
receive on behalf of the Owner, six copies of all applicable
equipment installation, operation, and maintenance
brochures and manuals required of the Contractor. The
Architect will provide three copies of this information to the
Owner.
B-9 TERMINATION OF THE ARCHITECT. In case of
the termination of the employment of the Architect by the
Owner, the Owner shall either assume the duties of the
Architect through the Director of the Department of
Transportation and Public Works, or shall appoint a
successor Architect against whom the Contractor makes no
reasonable objection.
SECTION C
OWNER
C-1 IDENTIFICATION. By the term Owner is meant
the City of Fort Worth acting herein by its duly authorized
representatives in the manner provided by law. Authrri��
`j� j;�,-�i ��il
� "-.')Ef�lj�u���" � 1��:�. ��:��./
GC - 2 of 23 6=: �7f,' ��j{�7 u,,,GJ� �°:�'�
� �r��, � ,�j C' IJ � �
� �o �U�'�rPi�.!�'S��p ti���o
�
�
�
k
L�
L'�
�
�
�,
representatives include the City Manager, Assistant City
Manager, the Director and of Transportation and Public
Works Department and members of the Building Services
Division. Generally speaking a designated representative
will be identified from within the Building Services Division to
act as a point of contact for day to day contract
administration.
C-2 DUTIES OF THE OWNER. The Owner shall
furnish surveys describing the physical characteristics, legal
limits and utility locations for the site of the Work; provided,
however, that the Contractor hereby covenants that he has
inspected the premises and familiarized himself therewith
and that the locations of utilities and other obstacles to the
prosecution of the Work as shown on the Owner's survey
are for inforrnation only, are not binding upon the Owner,
and the Owner shall not incur any liability for loss or damage
by virtue of any inaccuracies or deficiencies in such surveys.
The Owner shall secure and pay for tide to the site and all
necessary permanent or construction easements. The
Owner will cooperate with the Contractor in the prosecution
of the Work in such manner and to such. extent as may be
reasonable and shall furnish information under its control
with reasonable promptness at the request of the Contractor.
C-3 INSTRUCTIONS. The Owner shall issue all
instructions to the Contractor through the Architect.
C-4 ACCESS TO JOB SITE. The Owner shall at all
times have access to the Work whenever it is in preparation
and progress. The Contractor shall provide facilities for such
access so the Owner may perform its assigned functions
under the Contract Documents.
C-5 PROGRESS INSPECTIONS. The Owner and the
Architect will make visits to the Site to familiarize themselves
with the progress and quality of the Work and to determine if
the work is proceeding in accordance with the Contract
documents. On the basis of on-site observations and
�eports provided by the Architect concerning the progress
and quality of the work, the Owner will approve and
authorize the Contractor's applications for payments.
C-6 AUTHORITY TO STOP WORK. The Owner will
have authority to reflect work that does not conform to the
Plans and Specifications. Whenever, in its reasonable
opinion, the Owner considers it necessary or advisable in
order to insure the proper realization of the intent of the
Plans and Specifications, the Owner will have authority to
require the Contractor to stop the work or any portion
thereof, or to require the Contractor to stop the Work or any
portion thereof, or to require special inspection or testing of
the Work whether or not such Work be then fabricated,
instailed or completed.
C-7 SUBSTANTIAL COMPLETION INSPECTION,.
Upon agreement of the Contractor and Architect that the
Work is substantially complete, the Owner will schedule a
Substantial CompleUon Inspection to be conducted by the
Architect and attended by representatives of the Architect,
Owner and Contractor. Items identified during this inspection
as being incomplete, defective or deficient shall be
incorporated into a punch list to be prepared by the Architect
and attached to the AIA document G704, which is to be
prepared and signed by the Contractor, and accepted,
approved and signed by the Owner.
C-8 RIGHT TO AUDIT:
Contractor agrees that the City shall, until the expiration of
three years after final payment under this contract, have
access to and the right to examine any directly pertinent
� 10/11/99
books, documents, papers and records of the contractor
involving transactions relating to this contract.
Contractor further agrees to include in all his subcontracts
hereunder a provision to the effect that the subcontractor
agrees that the City shall, until the expiration of three years
after final payment under the subcontract, have access to
and the right to examine any directly pertinent books,
documents, papers and records of such subcontractor,
involving transactions to the subcontract. The term
"subcontract" as used herein includes purchase orders.
Contractor agrees to photocopy such documents as may be
requested by the city. The city agrees to reimburse
Contractor for the costs of copies at the rate published in the
Texas Administrative Code.
SECTION D
CONTRACTOR
D-1 IDENTIFICATION. The Contractor is the person
or organization identified as such in the Contract. The term
Contractor means the Contractor or his authorized
representative.
D-2 INDEPENDENT CONTRACTOR Contractor shall
perform all work and services hereunder as an independent
contractor, not as an officer, agent, or employee of the City.
Contractor shall have exclusive control of and the exclusive
right to control the details of the work and services
performed hereunder, and all persons performing same, and
Contractor shall be solely responsible for the acts and
omissions of its officers, agents, and employees. Nothing
herein shall be construed as creating a partnership or joint
enterprise between City and the Contractor, its officers,
agents and employees, and the doctrine of respondeat
superior shall not apply.
D-3 SUBLETTING It is further agreed that the
performance of this Contract, either in whole or in part, shall
not be sublet or assigned to anyone else by said Contractor
without the written consent of the Director of Transportation
and Public Works of the City of Fort Worth.
D-4 REVIEW OF CONTRACT DOCUMENTS. The
Contractor shall carefully study and compare the Agreement,
Conditions of the Contract, Drawings, Specifications,
Addenda and modifications and shall at once report to the
Owner and to the Architect any error, inconsistency or
omission he may discover. The Contractor shall do no work
without Drawings, Specifications and Interpretations.
D-5 SUPERVISION. The Contractor shall supervise
and direct the Work, using his best skill and attention. He
shall be solely responsible for ail construction means,
methods, techniques, sequences and procedures and for
coordinating all portions of the Work under the Contract
Documents.
D-6 LABOR AND MATERIALS. Unless othervvise
specifically noted, the Contractor shall provide and pay for all
labor, materials, equipment, tools, construction equipment
and machinery, water, heat, utilities, transportation and other
facilities and services necessary for the proper execution
and completion of the Work.
The successful low bidder will use its reasonable best efforts
to hire local laborers, workmen and materialmen. The
general condition is not to be constructed as limiting the right
of any bidder to employee laborers, workmen or materialmen
from outside local area.
� ;. �, ^ ; � ;; ,�'=� ='i��� �(;
'..��'�'If'';��i�`,:15 �j.'aL��;�VPc�
GC - 3 of 23 '^, �, ���u� ���::��Utn1U��
�i�����, �,���C���le ��
r.;. �� ,
. __....._�� _
�.,.<
�
�
�
r�'
�
�
r
�,
�
�
�.
f'"
The Contractor shall at all times enforce strict discipline and
good order among his employees, and shall not employ on
the Work any unfit person or anyone not skilled in the task
assigned to him.
D-7 PREVAILING WAGE RATE. The Contractor
agrees to pay not less than the general prevailing rate of per
diem wages for Work of a similar character in the locality in
which the Work is performed, and not less than the general
prevailing wage of per diem wages for a legal holiday and
overtime work to all laborers, workmen and mechanics
employed on the Work under this Contract. The Contractor
agrees to pay at least the minimum wage per hour for all
labor as the same is classified and set out by the City of Fort
Worth, Texas, a copy of which is attached hereto and made
a part hereof the same as if it were copies verbatim herein.
D-8 WARRANTY. The Contractor warrants to the
Owner and the Architect that all materials and equipment
furnished under this Contract will be new unless othervvise
specified, and that all work will be of good quality, free from
faults and defects, and in conformance with the Contract
Documents. All work not so conforming to these standards
may be considered defective. If required by the Architect or
the Owner, the Contractor shall furnish satisfactory evidence
as to the kind and quality of materials and equipment.
The warranty provided in this Section shall be in addition to
and not in limitation of any other warranry or remedy
provided by law or the Contract Documents.
D-9 TAXES. The Contractor is exempt from State
Sales Tax on material incorporated into the finished
construction, Excise and Use Tax.
D-10 LICENSES. NOTICES AND FEES. The
Contractor shall obtain all Permits, Licenses, Certificates,
and Inspections, whether permanent or temporary, required
by law or these Contract Documents.
The Contractor shall give all Notices and comply with all
Laws, Ordinances, Rules, Regulations and Orders of any
public authority bearing on the performance of the Work. If
the Contractor observes or becomes aware that bearing on
the performance of the Work. If the Contractor observes or
becomes aware that any of the Contract Documents are at
variance therewith in any respect, he shall promptly notify
the Architect in writing and any necessary changes will be
made. If the Contractor performs any Work knowing that it is
in violation of, or contrary to, any of such Laws, Statutes,
Charter, Ordinances, Orders or Directives, or Regulations
without furnishing Notice to the Architect, the Contractor will
assume full responsibility therefor and bear all costs
attributable thereto.
D-11 CASH ALLOWANCES. The Contractor shall
include in the Contract Sum all allowances stated in the
Contract Documents. These allowances shall cover the net
cost of the materials and equipment delivered and unloaded
at the site, and all applicable taxes. The Contractor's
handling costs on the site, labor, installation costs, overhead,
profit and other expenses contemplated for the original
allowance shall be included in the Contractor Sum and not in
the allowance. The Contractor shall cause the Work covered
by these allowances to be performed for such amounts and
by such persons as the Architect may direct, but he will not
be required to employ persons against whom he makes a
reasonable objection. If the cost, when determined, is more
than or less than the allowance, the Contract Sum shall be
adjusted accordingly by Change Order which will include
additional handling costs on the site, labor, installation costs,
field overhead, profit and other direct expenses resulting to
the Contractor from any increase over the original allowance.
10/11/99
D-12 SUPERINTENDENT. The Contractor shall
employ a competent superintendent and necessary
assistants who shall be in attendance at the Project site
during the progress of the Work. The superintendent shall be
satisfactory to the Contractor and the Owner. The
superintendent shall represent the Contractor and all
communications given to the superintendent shall be binding
as if given to the Contractor. Important communications will
be confirmed in writing. Other communications will be so
confirmed on written request in each case.
D-13 RESPONSIBILITIES FOR EMPLOYEES AND
SUB-CONTRACTQRS. The Contractor shall be responsible
to the Owner for the acts and omissions of all his employees
and all Sub-contractors, their agents and empioyees, and all
other persons performing any of the Work under a contract
with the Contractor.
D-14 FAILURE TO COMMENCE WQRK: Should the
Contractor fail to begin the work herein provided for within
the time herein fixed or to carry on and complete the same
according to the true meaning of the intent and terms of said
Plans, Specifications and Contract Documents, then the
Owner shall have the right to either demand the surety to
take over the work and complete same in accordance with
the Contract Documents or to take charge of and complete
the work in such a manner as it may deem proper, and if, in
the completion thereof, the cost to the said Ciry shall
exceed the contract price or prices set forth in the said plans
and specifications made a part hereof, the Contractor and/or
its Surety shall pay said City on demand in writing, setting
forth and specifying an itemized statement of the total cost
thereof, said excess cost.
D-15 PROGRESS SCHEDULE. The Contractor,
immediately after being awarded the contract, shall prepare
and submit for the ArchitecYs approval, an estimated
progress schedule for the Work. The progress schedule shall
be related to the entire Project. This schedule shail indicate
the dates for the starting and completion of the various
states of construction and shall be revised as required by the
conditions of the Work, subject to the ArchitecYs approval. It
shall also indicate the dates for submission and approval of
shop drawings and submittals as well as the delivery
schedule for major pieces of equipment and/or materials.
The progress schedule shall be updated at least monthly by
the contractor and submitted to the Architect for approval
with the Contractor's monthly progress payment requests.
D-16 DRAWINGS AND SPECIFICATIONS AT THE
SITE. The Contractor shall maintain at the site for the
Owner one copy of all Drawings, Specifications, Addenda,
approved Shop Drawings, Change Orders, and other
Changes and Amendments in good order and marked to
record all changes made during construction. These shall
also be available to the Architect. The Drawings, marked to
record all changes made during construction, shall be
delivered to the Architect upon completion of the Work, and
the Architect will prepare, and provide to the Owner, one
complete set of reproducible record drawings of the work.
D-17 SHOP DRAWINGS AND SAMPLES. Shop
Drawings are drawings, diagrams, illustrations, schedules,
performance charts, brochures and other data which are
prepared by the Contractor or any Subcontractor,
manufacturer, supplier or distributor, and which illustrate
some portion of the Work.
Samples are physical examples furnished by the Contractor
to iliustrate materials, equipment or workmanship, and to
establish standards by which the Work will be judged.
GC-4of23
,;iif'';�;� fU�:'!, U;;��I�•�UU`_lJ
I ' " ��i�� I�l)I a
� �
r j" n�7
I r ��i7�1,
�. f,1V�� � t�� •� U�:7 UIiYW �
�f
�'; i�!��i;�i`�;'L`LIIE �'�Wo
� �:�
L
�
!
��
�'
�
The Contractor shall review, stamp with his approval and
submit, with reasonable promptness and in orderly sequence
so as to cause no delay in the Work or in the work of any
other contractor, normally within the first 90 days of the work,
six copies of all shop Drawings and Samples required by the
Contract Documents or subsequently by the Architect as
covered by changes or amendments. Shop Drawings and
Samples shall be properly identified as specified, or as the
Architect may require. At the time of submission the
Contractor shal� inform the Architect in writing of any
deviation in the Shop Drawings or Samples from the
requirements of the Contract Documents.
By approving and submitting Shop Drawings and Samples,
the Contractor thereby represents that he has determined
and verified all field measurements, field construction
criteria, materials, catalog numbers and similar data, and
that he has checked and coordinated each shop drawing
given in the Contract Documents. The ArchitecYs approval of
a separate item shall not indicate approval of an assembly in
which the item functions.
The Architect will review and approve Shop Drawings and
Samples with reasonable promptness so as to cause no
delay, but only for conformance with the design concept of
the Project and with the information given in the Contract
Documents. The ArchitecYs approval of a separate item shall
not indicate approval of an assembly in which the item
functions.
The Contractor shall make any corrections required by the
Architect and shall resubmit the required number of
corrected copies of Shop Drawings or new Samples until
approved. The Contractor shall direct specific attention in
writing or on resubmitted Shop Drawings to revisions other
than the corrections requested by the Architect on previous
submissions.
The ArchitecYs approval of Shop Drawings or Samples shall
not relieve the Contractor of responsibility for any deviation
from the requirements of the Contract Documents unless the
Contractor has informed the Architect in writing of such
deviation at the time of submission and the Architect has
given written approval to the specific deviation. ArchitecYs
approval shall not relieve the Contractor from responsibility
for errors or omissions in the Shop Drawings or Samples.
No portion of the Work requiring a Shop Drawing or Sample
submission shall be commenced until the Architect has
approved the submittal. All such portions of the Work shall
be in accordance with approved Shop Drawings and
Samples.
D-18 SITE USE. The Contractor shall confine
operations at the site to areas permitted by law, ordinances,
permits and the Contract Documents and shall not
unreasonably encumber the site with any materials or
equipment. Until acceptance of the work by the City Council
of the City of Fort Worth, the entire site of the Woric shall be
under the exclusive control, care and responsibility of the
Contractor. Contractor shall take every precaution against
injury or damage to persons or property by the action of the
elements or from any other cause whatsoever. The
Contractor shall rebuild, repair, restore and make good at his
own expenses all injuries or damages to any portions of the
Work occasioned by any of the above, caused before
acceptance.
D-19 SAFE WORK PRACTICES. The Contractor shall
empioy safe practices in handling materials and equipment
used in performing required work so as to insure the safety
of his workmen, City employees and the public. The
10/11/99
Contractor shall keep the premise free at all times from
accumulation of waste materials or rubbish. At the
completion of the work, the Contractor shall remove all his
wastes and rubbish from and about the work area, as well as
his tools, equipment and surplus materiais and shall leave
the area as clean and free of spot, stains, etc., as before the
work was undertaken.
D-20 FIELD OFFICES AND SHEDS The Contractor is
not required to provide a temporary field office or telephone
for projects under $500,000. Contractor shall equip the
Project Superintendent with a pager and provide 24-hour
contacts to the City.
D-21 TRENCH SAFEIY The Contractor shall be
responsible for all design and implementation of trench
shoring and stabilization to meet regulatory requirements. If
the Proposal requires, the Contractor shall include a per unit
cost for trench safety measures in .his bid. If not included in
the Proposal, the Contractor shall include a cost for trench
safety measures for all trenches over 5 feet in depth in his
Schedule of Values.
D-22 CUTTING AND PATCHING QF WQRK. The
Contractor shall do all cutting, fitting or patching of his Work
that may required to make its several parts fit together
properly, and shall not endanger any Work by cutting,
excavating or otherwise altering the Work or any part of it.
D-23 CLEAN UP. The Contractor at all times shall keep
the premises free from accumulation of waste materials or
rubbish. At the completion of the Work he shall remove all
his waste materials and rubbish from and about the Project
as well as all his tools, construction equipment, machinery
and surplus materials, and shall clean all glass surfaces and
leave the Work "Broom-clean" or its equivalent, except at
otherwise specified. In addition to removal of rubbish and
leaving the buildings "broom-clean", Contractor shall clean
all glass, replace any broken glass, remove stains, spots,
marks and dirt from decorated work, clean hardware,
remove paint spots and smears from all surfaces, clean
fixtures and wash all concrete, tile and terrauo floors.
If the Contractor fails to clean up, the Owner may do so, and
the cost thereof shall be charged to the Contractor.
D-24 COMMUNICATIONS. As a general rule, the
Contractor shall forward all communications to the Owner
through the Architect, and in all other instances the
Contractor shall furnish the Architect a copy of any
communication sent directly to the Owner.
SECTION E
SUBCONTRACTORS
E-1 DEFINITION. A Subcontractor is a person or
organization who has a direct contract with the Contractor to
perform any of the Work at the site. The term Subcontractor
is referred to throughout the Contract Documents as if
singular in number and masculine in gender and means a
Subcontractor or his authorized representative.
Nothing contained in the Contract, Documents shall create
any contractual relation between the Owner and the
Architect and any subcontractor or any of his sub-
subcontractors or materialmen.
E-2 AWARD OF SUBCONTRACTS. The bidder shall
furnish a list of the names of the subcontractors or other
persons or organizations (including those who are to furnish
materials or equipment fabricated to a special design)
proposed for such portions of the Work as may be
designated in the bidding requirements, or if none is so
GC-Sof23
- P:1���,'� J�`;,� �
`,.: C�%"'.L
� ��
, �-� � �� ;�^ ey�`� � ;� ,
.. ��} � '���Y ��o
�
L..
�.
�
�
w
rr
eri
�
�4
r�-
��
designated in the bidding requirements, the names of the
Subcontractors proposed for the principal portions of the
Work. Prior to the award of the Contract, the Architect shall
notify the successful bidder in writing if either the Owner or
Architect, after due investigation, has reasonable objection
to any person or organization on such list. Failure of the
Owner and Architect to make an objection to any person or
organization on the list prior to the award of this Contract
shall not constitute acceptance of such person or
organization.
If, prior to the award of the Contract, the Owner or Architect
has an objective to any person or organization on such list,
and refuses to accept such person or organization, the
apparent low bidder may, prior to the award, withdraw his bid
without forfeiture of bid security. If such bidder submits an
acceptable substitute, the Owner may, at its discretion,
accept the bid or he may disqualify the bid. If, after the
award, the Owner or Architect objects in writing to any
person or organization on such list, the Contractor shall
provide an acceptable substitute.
The Contractor shall not make any substitution for any
Subcontractor or person or organization that has been
accepted by the Owner and the Architect, unless the
substitution is also acceptable to the Owner and the
Architect.
E-3 TERMS OF SUBCONTRACTS. All work
perFormed for the Contractor by a Subcontractor shall be
pursuant to an appropriate agreement between the
Contractor and the Subcontractor (and where appropriate
between Subcontractors and Sub-subcontractors) which
shall contain provisions that:
1. preserve and protect the rights of the Owner and the
Architect under the Contract with respect to the Work to
be performed under the subcontract so that the
subcontracting thereof will not prejudice such rights;
2. require that such Work be performed in accordance
with the requirements of the Contract Documents;
3. require submission to the Contractor of applications for
payment under each subcontract to which the
Contractor is a party, in reasonable time to enable the
Contractor to apply for payment;
4. require that all claims for additional costs, extensions of
time, damages for delays or otherwise with respect to
subcontracted portions of the Work shall be submitted
to the Contractor (via any Subcontractor or Sub-
subcontractor where appropriate) in the manner
provided in the Contract Documents for like claims by
the Contractor upon the Owner;
5. waive all rights the contracting parties may have
against one another for damages caused by fire or
other perils covered by the property insurance, except
such rights, if any, as they may have to proceeds of
such insurance held by the Owner, and,
6. obligate each Subcontractor specifically to consent to
the provisions of this Section
All of the provisions set out in this section shall be deemed
to have been included in every subcontract, and every
subcontract shall be so construed and applied as to the
Owner and the Architect, whether or not such provisions are
physically included in the sub-contract.
E-4 MINORITY AND WOMENS BUSINESS
ENTERPRISE (M/WBEI. Should the base bid be less than
$25,000, the requirements of this section do not apply.
10/11/99
In accordance with City of Fort Worth Ordinance No 11923,
the Ciry of Fort Worth sets goals for the participation of
minority business enterprises and women business
enterprises in City contracts. Ordinance No 11923 is
incorporated in these Specifications by reference. A copy of
the Ordinance may be obtained from the Office of the City
Secretary. Failure to comply with the Ordinance shall be a
material breach of contract.
The M/WBE UTILIZATION FORM, M/WBE GOALS WAIVER
FORM and GOOD FAITH EFFORT FORM, as applicable,
must be submitted within five city business days after bid
opening. Failure to submit the post bid information shall
render the bid non-responsive.
The City will consider the contractor's performance on other
City Projects regarding its M/WBE program in the evaluation
of bids. Failure to comply with the City's M/WBE program, or
to demonstrate a"good faith effort", shall result in a bid
being considered irresponsible.
Upon request, Contractor must provide the City with
complete and accurate information regarding actual work
performed by a Minority or Women Business Enterprise
(M/WBE) on the contract and proof of payment thereof.
Contractor further agrees to permit an audit and/or
examination of any books, records or files in iYs possession
that will substantiate the actual work performed by an M/
WBE. The misrepresentation of acts (other than a negligent
misrepresentation) and/or the commission of fraud by the
Contractor will be grounds for termination of the contract
and/or initiating acfion under appropriate federal, state, or
local laws or ordinances relating to false statement. Further
any such misrepresentation (other than a negtigent
misrepresentation) and/or commission of fraud will result on
the Contractor being determined to be irresponsible and
barred from participating in City work for a period of time of
not less than three years.
Contractor shall provide copies of subcontracts or cosigned
letters of intent with approved M/WBE subcontractors prior to
issuance of the Notice to Proceed. Contractor shall also
provide monthly reports on utilization of the subcontractors
to the Construction Manager.
The Contractor may count first and second tier
subcontractors and/or suppliers toward meeting the goals.
The Contractor may count toward its goal a portion of the
total dollar amount of the contract with a joint venture equal
to the percentage of the M/WBE participation in the joint
venture for a clearly defined portion of the work to be
perFormed. All subcontractors used in meeting the goals
must be certified prior to the award of the Contract.
Whenever a change order affects the work of an M/WBE
subcontractor or supplier, the M/VNBE shall be given an
opportunity to perForm the work. Whenever a change order
is in excess of 10% of the original contract, the M/WBE
coordinator shall determine the goals applicable to the work
to be performed under the change order.
During the term of the contract the contractor shall:
1. Make no unjustified changes of deletions in it's M/WBE
participaUon commitments submitted with or
subsequent to the bid, and,
2. If substantial subcontracting and/or substantial supplier
opportunities arise during the term of the contract which
the contractor had represented he would perform with
his forces, the contractor shall notify the City before
subcontracts or purchase orders are let, and shall be
�� u��:,'�r�i���ln�.l� 6 L�:,`v�-J
� �
GC - 6 of 23 i,~-1;1 II ���GU�� S�1�
�� ���e1���4 ����a
�,
�
�
�
Lc.
�. .
required to comply with modifications to goals as
determined by the City, and,
3. Submit a REQUEST FOR APPROVAL OF CHANGE
FORM, if the contractor desires to change or delete any
of the M/WBE subcontractors or suppliers.
Justification for change may be granted for the following:
1. Failure of subcontractor to provide evidence of
coverage by Workers' Compensation Insurance
2. Failure of subcontractor to provide required general
liability or other insurance.
3. Failure of subcontractor to execute a standard
subcontract form in the amount of the proposal used by
the Contractor in preparing his M/WBE Participation
plan
4. Default by the M/WBE subcontractor or supplier in the
performance of the subcontract.
Other reasons at the discretion of the M/WBE Coordinator
Within ten days after final payment from the City the
contractor shall provide the M/WBE O�ce with
documentation to reflect final participation of each M/WBE
subcontractor and supplier used on the project.
E-5 PAYMENTS TO SUBCQNTRACTORS. The
Contractor shall pay each Subcontractor, upon receipt of
payment from the Owner, an amount equal to the
percentage of completion allowed to the Contractor on
account of such Subcontractor's Work. The Contractor shall
also require each Subcontractor to make similar payments to
his subcontractors.
If the Architect refuses to issue a Certificate for Payment for
any cause which is the fault of the Contractor and not the
fault of a particular subcontractor, the Contractor shall pay
that Subcontractor on demand, made at any time after the
Certificate for Payment would otherwise have been issued,
for his Work to the extent completed, less the retained
percentage.
The Contractor shall pay each Subcontractor a just share of
any insurance monies received by the Contractor, and he
shall require each Subcontractor to make similar payments
to his Subcontractors.
The Architect may, on request and at its discretion, furnish to
any Subcontractor, if practicable, information regarding
percentages of completion certified to the Contractor on
account of Work done by such Subcontractors.
Neither the Owner nor the Architect shall have any obligation
to pay or to see to the payment of any monies to any
Subcontractor.
SECTION F
SEPARATE CONTRACTS
F-1 OWNER'S RIGHT. The Owner reserves the right
to award separate contracts in connection with other portions
of the Work. When separate contract are awarded for other
portions of the Work, "the Contractor" in the Contract
Documents in each case shall be the contractor who signs
each separate contract.
F-2 MUTUAL RESPONSIBILITY OF
CONTRACTORS. The Contractor shall afford other
contractors reasonable opportunity for the introduction and
10/I 1/99
storage of their materials and equipment and the execution
of their work, and shall properly connect and coordinate his
work with theirs.
If any part of the Contractor's Work depends for proper
execution or results upon the work of any other separate
contractor, the Contractor shall inspect and promptly report
to the Architect any apparent discrepancies or defects in
such work that render it unsuitable for such proper execution
and results. Failure of the Contractor to inspect and report
shall constitute an acceptance of the other contractor's work
as fit and proper to receive his Work, except as to defects
which may develop in the other separate contractor's work
after the execution of the Contractor's Work.
Should the Contractor cause damage to the work or property
of any separate contractor on the site, the Contractor shall,
upon due notice, settle with such other contractor by
agreement, if he will so settle. If such separate contractor
sues the Owner on account of any damage alleged to have
been so sustained, the Owner shall notify the Contractor
who shall defend against such suit at the Contractor's
expense, and if any judgment against the Owner arises
therefrom, the Contractor shall pay or satisfy such judgment
and shall reimburse the Owner for all attorney's fees, court
costs and expenses which the Owner has incurred in
connection with such suit.
F-3 CUTTING AND PATCHING UNDER SEPARATE
CONTRACTS. The Contractor shall do all cutting, fitting or
patching of his Work that may be required to fit it to receive
or be received by the work of other contractors shown in the
Contract Documents. The Contractor shall not endanger any
work or any other contractors by cutting, excavating or
otherwise altering any work and shall not cut or alter the
work of any other contractor except with the written consent
of the Architect.
Any costs caused by defective or ill-timed work shall be
borne by the party responsible therefor.
F-4 OWNER'S RIGHT TO CLEAN UP. If a dispute
arises between the separate contractors as to their
responsibility for cleaning up, the Owner may clean up and
charge the cost thereof to the several contractors as the
Director of the Department of Transportation and Public
Works shall determine to be just.
SECTION G
MISCELLANEOUS PROVISIONS
G-1 CONFLICT OF LAWS. The law of the place
where the site is located shall govern the Contract. The
Contractor must familiarize himself and strictly comply with
all Federal, State, and County and City Laws, Statutes,
Charter, Ordinances, Regulations, or Directives controlling
the action or operation of those engaged upon the work
affecting the materials used. He shall indemnify and save
harmless the City and all of its officers and agents against
any claim or liability arising from or based on the violation of
any such Laws, Statutes, Charter, Ordinances, Regulations,
or Directives, whether by himself, his employees, agents or
subcontractors.
G-2 GOVERNING LAWS. it is mutually agreed and
understood that this agreement is made and entered into by
the parties hereto with reference to the existing Charter and
Ordinances of the City of Fort Worth and the laws of the
State of Texas with reference to and governing all matters
affecting this Contract, and the Contractor agrees to fully
comply with all the provisions of the same.
GC-7of23
��� ��C��O�OC:� ����c��G� ��
��-�� ^ � ����
'�-; iT V �L�'GG?C�If�? u
���3 ��CNUVUp lSJ`�u
�..
�
�
L.,
�`
�
�..
�
i.,,.
�
�
W�,
�
L.
f
�
G-3 PERSONAL LIABILITY OF PUBLIC OFFICIALS.
In performing their duties under the Statutes of the State of
Texas and the Charter and Ordinances of the City of Fort
Worth in connection with this Contract, or in exercising any
of the powers granted the Owner herein, the officers, agents
and employees of the City of Fort Worth are engaged in the
performance of a governmental func6on and shall not incur
any personal liabiliry by virtue of such performance
hereunder, except for gross negligence or willful wrong.
G� COMPLIANCE WITH LAWS. Contractor agrees
the comply with all laws, Federal, state and local, including
all ordinances, rules and regulations of the City of Fort
Worth, Texas. Materials incorporated into the finished
Project are not subject to State Sales Tax.
Contractors are responsible for obtaining construction
permits from the governing agencies. Contractor shall
schedule all code inspections with the Code Inspection
Division in accordance with the permit requirements and
submit a copy of updated schedule to the Construction
manager weekly. Building, plumbing, electrical and
mechanical building permits are issued without charge.
Water and sewer access fees will be paid by the City. Any
other permit fees are the responsibility of the Contractor.
G-5 INDEMNIFICATION: Contractor covenants and
agrees to indemnify City's engineer and architect, and their
personnel at the project site for Contractor's sole negligence.
In addition, Contractor covenants and agrees to indemnify,
hold harmless and defend, at its own expense, the Owner,
its o�cers, servants and employees, from and against any
and all claims or suits for property loss, property damage,
personal injury, including death, arising out of, or alleged to
arise out of, the work and services to be performed
hereunder by Contractor, its officers, agents, employees,
subcontractors, licensees or invitees, whether or not anv
such iniurv. damaae or death is caused. in whole or in
part, bv the nealiaence or alleaed nealiaence of Owner.
its o�cers. servants. or emnlovees. Contractor likewise
covenants and agrees to indemnify and hold harmless the
Owner from and against any and all injuries to Owner's
o�cers, servants and employees and any damage, loss or
destruction to property of the Owner arising from the
performance of any of the terms and conditions of this
Contract, whether or not anv such iniury or damaae is
caused in whole or in nart 6v the nealipence or alleaed
nealiaence of Owner. its o�cers. servants or
employees.
In the event Owner receives a written claim for damages
against the Contractor or its subcontractors prior to final
payment, final payment shall not be made until Contractor
either (a) submits to Owner satisfactory evidence that the
claim has been settled and/or a release from the claimant
involved, or (b) provides Owner with a letter from
Contractor's liability insurance carrier that the claim has
been referred to the insurance carrier.
The Director may, if he deems it appropriate, refuse to
accept bids on other City of Fort Worth public work from a
Contractor against whom a claim for damages is oufstanding
as a result of work performed under a City Contract.
G-6 SUCCESSORS AND ASSIGNS. Except as
provided in Paragraph E-2, this contract shall be binding
upon and insure to the benefit of the parties hereto, their
Successors or Assigns. Contractor shall not assign or sublet
all or any part of this Contract or his rights or duties
hereunder without the prior written consent of the Owner.
Any such purported assignment or subletting without the
prior written consent of Owner shall be void.
� 10/11/99
G-7 WRITTEN NOTICE. Written Notice shall be
deemed to have been duly served if delivered in person to
the individual or member of the firm or to an officer of the
corporation for whom it was intended, or if delivered at or
sent by registered or certified mail to the last business
address known to him who gives the notice.
G-8 SURETY BONDS: Surety Bonds are required on
all City contracLs in excess of $25,000. The Contractor
agrees, on the execution of this Contract, and before
beginning work, to make, execute and deliver to said Ciry of
Fort Worth good and su�cient surety bonds for the faithful
performance of the terms and stipulations of the Contract
and for the payment to all claimants for labor and/or
materials furnished in the prosecution of the work, such
bonds being as provided and required in Article 5160 of the
Revised Civil Statutes of Texas, as amended, in the form
included in the Contract Documents, and such bonds shall
be 100 percent of the total contract price, and the said surety
shall be a surety company duly and legally authorized to do
business in the State of Texas, and acceptable to the City
Council of the City of Fort Worth.
Bonds shall be made on the forms furnished by or otherwise
acceptable to the City. Each bond shall be properly
executed by both the Contractor and the Surety Company.
Bonds required by the City shall be in compliance with all
relevant local, state and federal statutes.
To be an acceptable surery on the bond the name of the
surety should be included on the current U. S. Treasury List
of Acceptable Securities [Circular 570], and must be
authorized to do business in Texas. Sureties not listed in
Circular 570 may write performance and payment bonds on
a project without reinsurance to the limit of 10 percent of its
capital and surplus. Such a surety must reinsure any
obligation over 10 percent. The amount in excess of 10
percent must be reinsured by reinsurers who are duly
authorized, accredited, or trusteed to do business in the
State of Texas.
Should any surety for the contracted project be determined
unsatisfactory at any time during same, the Contractor shall
immediately provide a new surety bond satisfactory to the
City.
G-9 OWNER'S RIGHT TO CARRY OUT THE WORK.
If the Contractor defaults or neglects to carry out the Work in
accordance with the Contract Documents or fails to perform
any provision of the Contract, the Owner may, without
prejudice to any other remedy he may have, enter the site
and make good such deficiencies. In such case an
appropriate Change Order shall be issued deducting from
the payments then or thereafter due the Contractor the cost
of correcting such deficiencies, including the cost of the
ArchitecYs additional services made necessary by such
default, neglect or failure. If the payments then or thereafter
due the Contractor are not sufficient to cover such amount,
the Contract shall pay the difference to the Owner.
G-10 ROYALTIES AND PATENTS. The Contractor
shall pay all royalties and license fees. He shall defend all
suits or claims for infringement of any patent rights and shall
save the Owner harmless from loss on account thereof and
shall be responsible for all such loss when a particular
design, process or the product of a particular manufacturer
or manufacturers is specified; however, if the Contractor has
reason to believe that the design, process or product
specified is an infringement of a patent, he shall be
responsible for such loss unless he promptly gives such
information to Architect.
i����(;��Ui�O�;�, �;!��C�v��;_�Gl
GC - 8 of 23 '�`. G lI� �����U��Ut�,,U
U Uo VVV�IIIIIUQ ��Wo--
�
�
�
�
�
�..
�
G-11 TESTS. If the Contract Documents, Laws,
Ordinances, Rules, Regulations or Orders of any public
authority having jurisdiction require any Work to be
inspected, tested or approved, the Contractor shall give the
Architect timely notice of its readiness and the date arranged
so the Architect may observe such inspection, testing or
approval. The Owner shail bear all costs of such inspection,
tests and approvals unless otherwise provided.
!f after the commencement of the Work, the Owner or
Architect determine that any Work requires special
inspection, testing or approval not included above, the
Owner or the Architect, upon written authorization from the
Owner, will instruct the Contractor to order such special
inspection, testing or approval, and the Contractor shall give
notice as required in the preceding paragraph. If such
special inspection or testing reveals a failure of the Work to
comply (1) with the requirements of the Contract Documents
or (2) with respect to the performance of the work, with
Laws, Statutes, Charter, Ordinances, Regulations or Orders
of any public authority having jurisdiction, the Contractor
shall bear all costs thereof, including the ArchitecPs
additional services made necessary by such costs;
otherwise the Owner shall bear such costs, and an
appropriate Change Order shall be issued.
The Contractor shall secure certificate of inspection, testing
or approval, and three copies will be promptly delivered by
him to the Architect. The Architect will review the certificates
and forward one copy of each with his recommendation(s) to
the Owner.
If the Architect or Owner wish to observe the inspections,
tests or approvals required by this Section, they will do so
promptly and, where practicable, at the source of supply.
Neither the observations of the Architect or the Owner in
their administration of the Construction Contract, nor
inspections, tests or approva�s by persons other than the
Contractor shall relieve the Contractor from his obligations to
perform the Work in accordance with the Contract
Documents.
G-12 INTERRUPTION OF EXISTING UTILITIES
SERVICES. The Contractor shall perform the work under
this Contract with a minimum of outage time for all utilities.
Interruption shall be by approved sections of the utility. In
some cases, the Contractor may be required to perform the
work whiie the existing utility is in service. The existing utility
service may be interrupted only when approved by the
Owner. When it is necessary to interrupt the exis6ng utilities,
the Contractor shall notify the Owner in writing at least ten
days in advance of the time that he desires the existing
service to be interrupted. The interruption time shall be kept
to a minimum. Depending upon the activities at an existing
facility that requires continuous service from the existing
utility, an interruption may not be subject to schedule at the
time desired by the Contractor. In such cases, the
interruption may have to be scheduled at a time of minimum
requirements of demand for the utility. The amount of 6me
requested by the Contractor of existing utility services shall
be as approved by the Owner.
G-13 LAYING OUT WORK. The Contractor shall verify
dimensions and elevations indicated in layout of existing
work. Discrepancies between Drawings, Specifications, and
existing conditions shall be referred to Architect for
adjustment before work affected is performed. Failure to
make such no6fication shall place responsibility upon
Contractor to carry out work in satisfactory workmanlike
manner at the Contractor's sole expense.
� 10/11/99
�
The Contractor shall be held responsible for the location and
elevation of all the construction contemplated by the
Construction Documents.
Prior to commencing work, the Contractor shall carefully
compare and check all Architectural, Structural, Mechanical
an Electrical drawings; each with the other that in any affects
the locations or eleva6on of the work to be executed by him,
and should any discrepancy be found, he shai; immediately
report the same to the Architect for verification and
adjustment. Any duplication of work made necessary by
failure or neglect on his part to comply with this function shall
be done at the contractors sole expense.
G-14 MEASUREMENTS: Before ordering any material
or doing any work, the Contractor shall verify all
measurements at the site or at the building and shall be
wholly responsible for the correctness of same. No extra
charge or compensation will be allowed on account of any
difference between actual dimensions and dimensions
indicated on the drawings. Any difference which may be
found shall be submitted to the Architect for consideration
and adjusUnent before proceeding with the project.
G-15 EXISTING OVERHEAD OR UNDERGROUND
WORK. The Contractor shall carefully check the site where
the project is to be erected and observe any existing
overhead wires and equipment. Any such work shall be
moved, replaced or protected, as required, whether or no
shown or specified at the contractor's sole expense.
Attention is directed to the possible existence of pipe and.
other underground improvements that may or may not be
shown on the Drawings. All reasonable precautions shall be
taken to preserve and protect any such improvements
whether or not shown on the Drawings.
Location of existing underground lines, shown the Drawings
are based on the best available sources, but are to be
regarded as approximate only. Exercise extreme care in
locating and identifying these lines before excavation in
adjacent areas.
G-16 ALIGNMENT OF JOINTS IN FINISH
MATERIALS. It shall be the responsibility of the Contractor
to make certain in the installation of jointed floor, wall and
ceiling materials that:
1. preserve and protect the rights of the Owner and the
Architect under the Contract with respect to the Work to
be performed under the subcontract so that the
subcontracting thereof will not prejudice such rights;
2. Place joints to reiate to all opening and breaks in the
structure and be symmetrically placed wherever
possible. This includes heating registers, light fixtures,
equipment, etc.
If because of the non-related sizes of the various materials
and locations of openings, etc., it is not possible to
accomplish the above, the Contractor shall request the
Architect to determine the most satisfactory arrangement.
The Contractor shall establish centerlines for all trades.
G-17 INTEGRATING EXISTING WORK. The
Contractor shall protect all existing street and other
improvements from damages.
Contractor's operations shall be confined to the immediate
vicinity of the new work and shall not in any interfere with or
obstruct the ingress or egress to an from existing adjacent
facilities.
�;������ �Oi�:� ��[���G�D
GC - 9 of 23 � p, r -� �
��`;,���'�( ���':�G?�I�Q� .
Y �o r v �C•1��� Il �\� +
Where new site work is to be connected to existing work,
special care shall be exercised by the Contractor not to
disturb or damage the existing work more than necessary.
All damaged work shall be replaced, repaired and restored
to its original condition at no cost to the Owner.
e..,
f.
�
�
�,
r
�..-
�
�
w�
�
�.,
�
G-18. HAZARDOUS MATERIAL CERTIFICATION: It is
the intent of the contract documents, whether expressly
stated or not, that nothing containing hazardous materials,
such as asbestos, shall be incorporated in to the project.
The contractor shall exercise every reasonable precaution to
ensure that asbestos-containing materiais are not
incorporated into any portion of the project, including
advising all materials suppliers and subcontractors of this
requirement. The contractor shall verify that components
containing lead do not contact the potable water supply.
G-19 LOCATION OF EQUIPMENT AND PIPING.
Drawing showing location of equipment, piping, ductwork,
etc. are diagrammatic and job conditions may not always
permit their installation in the location shown. When this
situation occurs, it shall be brought to the ArchitecPs
attention immediately and the relocation determined in a joint
conference. The Contractor will be held responsible for the
relocating of any items without first obtaining the Architect's
approval. He shall remove and relocate such items at his
own expense if so directed by the Architect. Where possible
uniform margins are to be maintained between parallei lines
and or adjacent wall, floor or ceiling surfaces.
G-20 OVERLOADING. The Contractor shall be
responsible for loading of any part or parts of structures
beyond their safe carrying capacities by placing of materials,
equipment, tools, machinery or any other item thereon. No
loads shall be placed on floors or roofs before they have
attained their permanent and safe strength.
G-21 MANUFACTURER'S INSTRUCTIONS. Where it
is required in the Specifications that materials, products,
processes, equipment, or the like be installed or applied in
accordance with manufacturer's instructions, direction or
specifications, or words to this effect, it shall be construed to
mean that said application or installation shall be in strict
accordance with printed instructions furnished by the
manufacturer of the material concemed for use under
conditions similar or those at the job site. Six copies of such
instructions shall be furnished to the Architect and his
approval thereof obtained before work is begun.
G-22 CLEANING UP. The Contractor shall keep the
premises free from accumulation of waste material or
rubbish caused by employees or as a result of the work.
At completion of worlc, the General Contractor shall,
immediately prior to final inspecUon of complete building,
execute the following final cleaning work with trained
janitorial personnel and with material methods
recommended by the manufactures of installed materials.
1. Sweep and buff resilient floors and base, and vacuum
carpeting.
2. Dust all metal and wood trim and similar finished
materials.
3_ Clean all cabinets and casework.
4. Dust all ceilings and walis.
5. Dust, and if necessary wash, all plumbing and electrical
fixtures.
6. Wash all glass and similar non-resilient materials.
� 10/11/99
7. All hardware and other unpainted metals shall be
cleaned and polished and all equipment and paint or
decorated work shall be cleaned and touched-up if
necessary, and all temporary labels, tags, and paper
coverings removed throughout the buildings. Surfaces
that are waxed shall be polished.
8. The exterior of the building, the grounds, approaches,
equipment, sidewalks, streets, etc. shall be cleaned
similar to interior of buildings and left in good order at
the time of final acceptance. All paint surfaces shall be
clean and unbroken, hardware shall be clean and
polished, all required repair work shall be completed
and dirt areas shall be scraped and cleared of weed
growth.
9. Clean all glass surfaces and mirrors of putty, paint
materials, etc., without scratching or injuring the glass
and leave the work bright, clean and polished. Cost of
this cleaning work shall be borne by Contractor.
10. Cleaning, polishing, scaling, waxing and all other finish
operations indicated on the Drawings or required in the
Specifications shall be taken to indicate the required
condition at the time of acceptance of all work under the
Contract.
11. Burning: Burning of rubbish on the premises will not be
permitted.
G-23 DUST CONTROL. Precaution shall be exercised
at all times to control dust created as a result of any
operations during the construction period. If serious
problems or complaints arise due to air-borne dust, or when
directed by the Architect, operations causing such problems
shall be temporarily discontinued and necessary steps taken
to control the dust.
G-24 FIRE PROTECTION. The contractor shall at all
times maintain good housekeeping practices to reduce the
risk of fire damage or injury to workmen. All scrap materials,
rubbish and trash shall be removed daily from in and about
the building and shall not be permitted to be scattered on
adjacent property.
Suitable storage space shall be provided outside the
immediate building area for storing flammable materials and
paints; no storage will be permitted in the building. Excess
flammable liquids being used inside the building shall be
kept in closed metal container and removed from the
buiiding during unused periods.
A fire extinguisher shall be available at each location where
cutting or welding is being performed. Where electric or gas
welding or cutting work is done, interposed shields of
incombustible material shall be used to protect against fire
damage due to sparks and hot metal. When temporary
heating devices are used, a watchman shall be present to
cover periods when other workmen are not on the premises.
The Contractor shall provide fire extinguishers in accordance
with the recommendations and NFPA Bulletins Nos. 10 and
241. However, in all cases a minimum of two fire
extinguishers shall be available for each floor of
construction.
G-25 CUTTING AND PATCHING Wherever cutting and
removal of portions of the existing work is indicated, such
work shall be neatly sawed or cut by contractor in a manner
that will produce a neat straight line, parallel to adjacent
surfaces or plumb for vertical surfaces. Care should be
exercised not to damage any work that is to remain.
GC - 10 of 23
�:'�'��:;UG�:�� ��ISL�vI�`L7 ,
':: D�U cr���; U�.� ���;'�1°1s� ;
;
���, �+�!��`�'�(I�� �:��?� �
�_
�.
r.
�
r
�
�
�
��
�.. .
At no time shall any structural members be cut without
written consent from the Architect.
G-26 PROJECT CLOSEOUT.
Final Insoection. Record Drawinas: Attention is called to
General Conditions SecGon � entitled, "Payments and
Completion."
Maintenance Manual: Sheets sha�l be 8'/:" x 11", except pu�l
out sheets may be neatly folded to 8 Yz " x 11 ". Manuals shall
be bound in plastic covered, 3 ring, loose leaf binder with
title of project lettered on front and shall contain:
1) Name, address and trade of all sub-contractors.
2) Complete maintenance instructions; name, address,
and telephone number of installing Contractor,
manufacturer's local representative, for each piece of
operative equipment.
3) Catalog data on plumbing fixtures, valves, water
heaters, heating and cooling equipment, temperature
control, fan, electrical panels, service entrance
equipment and light fixtures.
4) Manufacturer's name, type, color designation for
resilient floors, windows, doors, concrete block, paint,
roofing, other materials.
Submit six copies of Maintenance Manual, prior to request
for final payment.
Ooerational Insoection and Maintenance Instruction: The
Contractor shall provide at his expense, competent
manufacturer's representatives to completely check out all
mechanical and electrical systems and items covered by the
Drawings and Specifications. This requirement shall be
scheduled just prior to and during the initial start up. After all
systems are functioning properly the representatives shall
instruct maintenance personnel of the Owner in the proper
operation and maintenance of each item.
G-27 GUARANTEE AND EXTENDED GUARANTEE.
Upon completion of the Project, prior to final payment,
guarantees required by technical divisions of Specifications
shall be properly executed in quadruplicate by
subcontractors and submitted through the Contractor to
Architect. Delivery of guarantees shall not relieve Contractor
from any obligation assumed under Contract.
The Contractor shall guarantee the entire Project for one
year. In addition, where separate guarantees, for certain
portions of work, are for longer periods, General Contractor's
guarantee shall be extended to cover such longer periods.
Manufacturer's extended warrantees shall be included in this
contract.
Guarantees shall become valid and operative and
commence upon issuance of Certificate of Inspection and
Acceptance by Owner. Guarantees shall not apply to work
where damage is result of abuse, neglect by Owner or his
successor(s) in interest.
The Contractor agrees to warrant his work and materials
provided in accordance with this contract and the terms of
the Technical Specifications contained herein. Unless
supplemented by the Technical Specifications or the
manufacturers normal extended warrantees, the Contractor
shall warrant all work materials, and equipment against
defects for a period of one year from the date of final
acceptance. The Contractor further agrees to bear all costs
10/11/99
of making good all work that is found to be defective or not
provided in accordance with the Contract Documents.
Additionally if the facility or contents are damaged due to
defective materials or workmanship of the Contractor, the
Contractor further agrees to bear all cost of repairing and/or
replacing damaged items and components to bring such
items back to at least their original condition.
G-28 Y2K COMPLIANCE REQUIREMENTS The
Contractor warrants that each hardware, software and
firmware product delivered for incorporation into the Work be
able to accurately process date/time data between the years
1999 and 2000, including leap year calculations and as
described below:
1. Date/time data between the information
technology incorporated into the Work shall transfer
accurately to and from information technology purchased
separately from the Work but intended to be used in
associaUon with warranted products or systems.
2. Where the contract documents require that
products must perform as a system with respect to date/time
data transfer, the warranry described herein applies to the
performance of the system rather than to individual products.
3. The duration of this warranty and the remedies
available to the Owner for the breach of this warranty shall
be as defined in and subject to, the terms and limitations of
the Contractor's standard commercial warranty or
warranties.
4. The remedies available to the Owner under this
warranty shall include repair or replacement of any product
or system whose noncompliance is discovered and made
known to the Contractor, in writing, within one year following
the date of substantial completion.
5. Nothing in the provisions of this warranty shall be
construed to limit any rights or remedies the Owner may
have with respect to defects discovered in the Work not
related to compliance requirements of this section.
The contractor agrees to correct defective Work within a one
year period after Date of Substan6al Completion, and
provide one year warranty for accurate transfer of date/time
data between the years 1999 and 2000 as described within
this secGon.
G-29 RECORD DRAWINGS. Upon completion of the
Work and prior to application for final payment, one print of
each of the drawings accompanying this specification shall
be neatly and clearly marked in red by the Contractor to
show variations between the construction actually provided
and that indicated or specified in the Contract Documents.
The annotated documents shall be delivered to Architect.
Where a choice of materials and/or methods is permitted
herein and where variations in the scope or character of the
work from the entire work indicated or specified are
permitted either by award of bidding items specified for that
purpose, or by subsequent change to the drawings, the
record drawings shall define the construction actually
provided. The representation of such variations shall
conform to standard drafting practice and shall include
supplementary notes, legends and details which may be
necessary for legibility and clear portrayal of the actual
construction. The record drawings shall indicate, in addition,
the actual location of all sub-surFace utility lines, average
depth below the surface and other appurtenances.
G-30 CONSTRUCTION FENCE. At the Contractor's
option, he may provide a substantial chain-link construction
fence around all or a part of the site. The fences and gates
must be maintained throughout the construction period.
Remove the fences and gates upon completion of the
Project and restore the site to the required original or
contract condition.
GC - 11 of 23
Ir '���' i
�� ,.,� s iJ�:; �,r�,:�� ;����_���':,':, : __�;�
�• � u I�, �\'�!I� Lr�� W'` ,`��� �
�c�' �I�^ I[v5?j�� �'�1�1
�'ll, r'J�\ �i�:��l!',o •!�/r�a
�
�
�
�
�
�
G-31 PRODUCT DELIVERY. STORAGE_ HANDLING.
The Contractor shall handle, store and protect materials and
products, including fabricated components, by methods and
means which will prevent damage, deterioration and loss,
including theft (and resulting delays), thereby ensuring
highest quality results as the work progresses. Control
delivery schedules so as to minimize unnecessary long-term
storage at project site prior to installation.
G-32 AGE In accordance with the policy ("Policy") of
the Executive Branch of the federal govemment, Contractor
covenants that neither it nor any of its officers, members,
agents, employees, program participants or subcontractors,
while engaged in performing this contract, shall, in
connec6on with the employment, advancement or discharge
of employees or in connection with the terms, conditions or
privileges of their employment, discriminate against persons
because of their age except o� the basis of a bona fide
occupational qualification, retirement plan or statutory
requirement.
Contractor further covenants that neither it nor its officers,
members, agents, employees, subcontractors, program
participants, or persons acting on their behalf, shall specify,
in solicitations or advertisements for employees to work on
this contract, a maximum age limit for such employment
unless the specified maximum age limit is based upon a
bona fide occupational qualification, retirement plan or
statutory equipment.
Contractor warrants it will fully comply with the Policy and
will defend, indemnify and hold City harmless against any
claims or allegations asserted by third parties or subcontrac-
tor against City arising out of Contractor's and/or its
subcontractors' alleged failure to comply with the above
referenced Policy concerning age discrimination in the
performance of this agreement.
G-33 DISABILITY: In accordance with the provisions of
the Americans With Disabilities Act of 1990 ("ADA"),
Contractor warrants that it and any and all of its
subcontractors will not unlawfully discriminate on the basis of
disability in the provision of services to the general public,
nor in the availability, teRns and/or conditions of employment
for applicants for employment with, or employees of
Contractor or any of its subcontractors. Contractor warrants
it will fully comply with ADA provisions and any other
applicable federal, state and local laws concerning disability
and will defend, indemnify and hold City harmless against
any claims or allegations asserted by third parties or
subcontractors against Ciry arising out of Contractor's and/or
its subcontractors' alleged failure to comply with the
above-referenced laws concerning disability discrimination in
the performance of this agreement.
SECTION H
CONTRACT TIME
r,.
�
�
�
H-1 DEFINITIONS. The Contract Time is the period of
time allotted in the Contract Documents for comple6on of the
Work.
The date of commencement of the Work is the date
established in the Notice to Proceed. If there is no notice to
proceed, it shall be the date of the Agreement or such other
date as may be established therein.
The Date of Substantial Completion of the Work or
designated portion thereof is the Date certified by the
Architect with the approval of the Owner that construction is
sufficiently complete, in accordance with the Contract
Documents, so the Owner may occupy the Work or
designated portion thereof for the use for which it is
� 10/11/99
�,
intended. Final acceptance of the completed work or any
portion thereof can be made only by the City Council of the
City of Fort Worth or iYs designated Assistant City Manager,
and no other form of acceptance will be binding upon the
Owner.
A calendar day constitutes 24 hours of time and is any one
of the seven days of a week, including Sunday, regardless of
whether a"Working Day" or not, and regardless of weather
conditions or any situation which might delay construction.
An extension of contract time shall be in accordance with
this Section. Extensions of time will be as recommended by
the Architect with final approval by City of Fort Worth.
A working day is defined as a calendar day, not including
Saturdays, Sundays, and legal holidays, in which weather or
other conditions not under the control of the Contractor
permit the performance of work for a continuous period of
not less than seven hours between 7:00 a.m. and 6:00 p.m.
However, nothing in these Contract Documents shati be
construed as prohibiting the Contractor from working on
Saturdays if he so desires. Should the Contractor choose to
work on Saturdays, one day will be charged as contract-
working time when weather or other conditions permit seven
hours of work as delineated above. Legal holidays are
defined as being New Year's Day, Independence Day, Labor
Day, Thanksgiving Day, Christmas Day, Memorial Day, and
Veteran's Day.
H-2 PROGRESS AND COMPLETION. All the time
limits stated in the Contract Documents are of essence to
the Contract.
The Contractor shall begin the Work on the date of
commencement as defined in this Section. He shall carry the
Work forward expeditiously with adequate forces and shall
complete it within the Contact Time.
H-3 DELAYS AND EXTENSIONS OF TIME. If the
Contractor is delayed at any time in the progress of the Work
by any act or neglect of the Owner or the Architect, or by any
employee of the Owner, or by any separate contractor
employed by the Owner, or by any separate contractor
employed by the Owner, or by changes ordered in the Work,
or by labor disputes, fire, unusual delay in transportation,
unavoidable casualties or any causes beyond the
Contractor's control, or by any cause which the Architect
determines may justify the delay, then the contract time may
be extended by Change Order for such reasonable time as
recommended by the Architect and approved by the Owner.
When the Contractor is delayed due to abnormal weather
conditions, the weather table provided as WT-1 in these
Contract Documents shall be used as the basis for providing
a fair and equitable adjustment of the contract time.
All claims for extension of time shall be made in writing to
the Architect no more than fifteen days after the occurrence
of the delay; otherwise they shall be waived.
If no schedule or agreement is made stating the dates upon
which written interpretations shall be furnished, then no
ciaim for delay shall be allowed on account of failure to
furnish such interpretation until fifteen days after demand is
made for them, and not then unless such a claim is
reasonable.
H� NO DAMAGE FOR DELAY. No payment,
compensation or adjustment or any kind (other than the
extensions of time provided for) shall be made to the
contractor for damages because of hindrances or delays
from an cause in the progress of the work, whether such
hindrances or delays be avoidable or unavoidable, and the
contractor agrees that he will make no claim for
GC - 12 of 23
I--_.� �..-;j. .� �� '� J ^�I��I�.���
;_: �'� u'��UG�� ��C��GU:�:��
1ti'�` �"[��V °��,��I�'�
�;`:i;y �,J�'�i�la �'�U��
�
�.
r
�
Ir~
�,
�
�,
��
i..,
�,
r
�..
compensation, damages or miGgation of liquidated damages
for any such delays, and will accept in full satisfaction for
such delays said extension of time.
SECTION I
PAYMENTS AND COMPLETION
I-1 CONTRACT SUM. The Contract Sum is stated in
the proposal as accepted and is the total amount payable by
the Owner to the Contractor for the performance of the Work
under the Contract Documents.
I-2 SCHEDULE OF VALUES. Before the first
Applicable for Payment, the Contractor shall submit to the
Architect a Schedule of Values of the various portions of the
Work, including quantities if required by the Architect,
aggregating the total Contract Sum, divided so as to facilitate
payments to Sub-contractors, prepared in such form as
specified or as the Architect and the Contractor may agree
upon, and supported by such data to substantiate its
correctness as the Architect may require. Each item in the
Schedule of Values shall include its . proper share of
overhead and profit. This Schedule, when approved by the
Architect and the Owner, shall be used as a basis for the
Contractor's Applications for Payment.
I-3 ADJUSTMENT OF QUANTITIES. Where unit
prices and estimated quantities are used to compute the
contract amount, the Owner may increase the quantities by
an amount that is 20% of the total cost for that section. Unit
prices for adjustments to unit quantities in excess to 20%
may be negotiated at the request of either party.
I-4 PROGRESS PAYMENTS. On the first day of
each month after the first month's work has been completed,
the Contractor will make current es6mates in writing for
review by the Architect of materials in place complete and
the amount of work performed during the preceding month or
period and the value thereof at the prices contracted for as
shown on the approved Schedule of Vaiues and Progress
Schedule.
If payments are to be made on account of materials or
equipment not incorporated in the Work but delivered and
suitably stored at the site or in an independent, bonded
warehouse such payments shall be conditioned upon
submission by the Contractor of bills of sa�e or such other
procedures satisfactory to the Owner to establish the
Owner's titie to such materials or equipment or otherwise
protect the Owner's interest including applicable insurance
and transportation to the site.
The Contractor warrants and guarantees that title to all
Work, materials and equipment covered by an Application
for Payment, whether incorporated in the Project or not, will
pass to the Owner upon the receipt of such payment by the
Contractor, free and clear of all liens, claims, security
interests or encumbrances hereinafter referred to as "Iiens";
and that no Work, materiais or equipment covered by an
Application for Payment will have been acquired by the
Contractor, or by any other persons performing the Work at
the site or furnishing materials and equipment for the Work,
subject to an agreement under which an interest therein or
an encumbrance thereon is retained by the seller or
otherwise imposed by the Contractor or such other person.
The Contractor shall prepare each application for payment
on AIA Document G702, "Application and Certificate for
Payment", and attached thereto AIA Document G703,
"Continuation SheeY', to indicate the progress made to date
and the period or month for which payment is requested for
each Item listed in the Schedule of Values. A copy of the
10/11/99
revised monthly work progress schedule must be attached
before the pay request can be accepted.
I-5 CERTIFICATES FOR PAYMENT. If the
Contractor has made Application for Payment as above, the
above, the Architect will, with reasonable promptness but not
more than seven days after the receipt of the Applicatio�,
prepare a Certificate of Payment, with a copy to the
Contractor, for such amount determined to be properly due,
or state in writing reasons for withholding a Certificate.
The issuance of a Certificate for Payment will constitute a
representation by the Architect to the Owner, based on the
ArchitecYs observations at the site and the data comprising
the Application for Payment, that the Work has progressed
to the point indicated; that the quality of the Work is in
accordance with the Contract Documents (subject to an
evaluation of the Work as a functioning whole upon
Substantial Completion, to the results of any subsequent
tests required by the Contract Documents, to minor
deviations from the Contract Documents correctable prior to
comp�etion, and to any specific qualifications stated in the
Certificate); and recommendations to the Owner that the
Contractor be paid in the amount certified. In addition, the
ArchitecYs approval of final payment assures the Owner that
the conditions precedent to the Contractor's being entitled to
final payment as set forth in this Section have been fulfilled.
After the Architect has issued a Certificate for Payment, the
Owner shall approve or disapprove same within ten days
after it has been delivered to the Director of the Department
of Transportation and Public Works. For contracts less than
$400,000, Owner shall pay 90% of the approved estimate to
the Contractor within seven days after its approval, and the
remaining 10% of each such estimate will be retained by the
Owner until the final estimate is approved and the Work is
accepted by the City Council of the City of Fort Worth. For
contracts in excess of $400,000, the Owner will retain only
5% of each estimate until the fina� estimate is approved and
work accepted by the City Council of the City of Fort Worth.
No Certificate for a progress payment, nor any progress
payment, nor any partial or entire use or occupancy of the
Project by the Owner, shall constitute an acceptance of any
Work not in accordance with the Contract Documents, or
relieve the Contractor of liability in respect to any warranties
or responsibility for faulty materials or workmanship. The
Contractor shall promptly remedy any defects in the Work
and pay for any damage to other work resulting therefrom
that shall appear within a period of one year from the date of
final acceptance of the Work unless a longer period is
specified.
I-6 PAYMENTS WITHHELD. The Architect may
decline to approve an Application for Payment and may
withhold his Certificate in whole or in part if in his opinion he
is unable to make the representations to the Owner as
provided in this Section. The Architect may also decline to
approve any Applications for Payment or, because of
subsequently discovered evidence or subsequent
inspections, may nullify the whole or any part of any
Certificate for Payment previously issued to such extent as
may be necessary in his opinion to protect the Owner from
loss because of:
1) defective work not remedied;
2) claims filed or reasonable evidence indicating probable
filing of claims;
3) failure of the Contractor to make payments properly to
Subcontractors, or for labor, materials or equipment;
4)
GC - 13 of 23
reasonable doubt that the Work can be completed for
the unpaid balance of .; �
r;� 'J��:'���i':'�; l':�a���-±�;il�'_uI i
r�r�r � ran�
':� u � �� �����:: G}�4���;�,�1u
'.�''� ���:'u�� ��o '
�
�
�.
�
ir.w
�,
r
L,.
�
�.e.
5) damage to another contractor;
6) reasonable indication that the Work will not be
completed within the Contract Time; or
7) Unsatisfactory prosecution of the Work by the
Contractor.
When such grounds for the refusal of payment are removed,
payment shall be made for amounts withheld because of
them. The Owner reserves the right to withhold the payment
of any month�y estimate, without payment of interest, if the
Contractor fails to perform the Work in accordance with the
specifications or instructions of the Architect.
I-7 UNRESOLVED CLAIMS: In the event a written
claim for damages against the Contractor or its subcon-
tractors remains unsettled at the time all work on the project
has been completed to the satisfaction of the Director of the
Transportation and Public Works Department, as evidenced
by a final inspection, final payment to the Contractor shall
not be recommended by the Director of the Transportation
and Public Works Department for a period of 30 days after
the date of such final inspection, unless the Contractor shall
submit written evidence satisfactory to the Director that the
claim has been settled and a release has been obtained
from the claimant involved.
Although the claim concerned remains unsettled at the
expiration of the above 30-day period, the Contractor may be
deemed to be entitled to a semi-final payment for work
completed, such semi-final payment to be in an amount
equal to the total dollar amount then due less the dollar
value of any written claims pending against the Contractor
arising out of the performance of such work, and such
semi-final payment may then be recommended by the
Director.
The Director shall not recommend final payment to a
Contractor against whom such a claim for damages is
outstanding for a period of six months following the date of
the acceptance of the work performed unless the Contractor
submits evidence in writing satisfactory to the Director that:
1) The claim has been settled and a release has been
obtained from the claimant involved, or
2) Good faith efforts have been made to settle such out-
standing claims, and such good faith efforts have failed.
If condition (1) above is met at any time within the six month
period, the Director shall recommend that the final payment
to the Contractor be made. If condition (2) above is met at
any time within the six-month period, the Director may
recommend that the final payment to the Contractor be
made. At the expiration of the six- month period the Director
may recommend that final payment be made if all other work
has been performed and all other obligations of the
Contractor have been met to the satisfaction of the Director.
The Director may, if he deems it appropriate, refuse to
accept bids on other Transportation and Public Works
Department contract work from a Contractor against whom a
claim for damages is outstanding as a result of work
performed under a City contract.
1-8 LIQUIDATED DAMAGES: The deduction for
liquidated damages shall be as follows:
Amount of Contract Liquidated Damages Per Day
$15,000 or less $45
$15,001 to $25,000 $ 63
$25,001 to $50,000 $105
10/ 11 /99
1) Contractor's A�davit of Payment of Debts and Claims
(G706) stating that all payrolls, bills for materials and
equipment, and other indebtedness connected with the
Work for which the Owner or his property might in any
way be responsible, have been paid or otherwise
satisfied,
2) Consent of Surety to Final Payment (G707), if anv, ta
final payment, �
u�'�'�!I��� Ui.1:% �i,� ���'llvl'J' C)
�U�
GC - 14 of 23 ;;V j`��i ��i� ° � ^ �
�Gt�. ��., �_?�
i��: �� �!�����a ���o
$50,001 to $100,000 $154
$100,OOOto $500,000 $210
$500,001 to $1,000,000 $315
$1,000,001 to $2,000,000 $420
$2,000,001 to $5,000,000 $630
$5,000,001 to $10,000,000 $840
over$10,000,000 $980
I-9 FAILURE OF PAYMENT If, without fault on the
part of the Contractor, the Architect should fail to issue any
Certificate for Payment within seven days after receipt of the
Contractor's Application for Payment, if the Contractor's
Application for Payment, or if, without fault on the part of the
Contractor, the Owner should fail to approve such estimate
or to pay to the Contractor 90% or 95% (as applicable) of the
amount thereof within the penod of time specified, then the
Contractor may, upon seven (7) days additional written
notice to the Owner and to the Architect, stop the Work until
payment of the amount owing has been received.
I-10 SUBSTANTIAL COMPLETION AND FINAL
PAYMENT Prior to the request for final payment, the
Contractor must meet � provisions for Project Closeout.
When the Contractor determines that the Work or a
designated portion thereof acceptable to the Owner is
substantially complete, the Contractor shall prepare the
submission to the Architect a list of items to be completed or
corrected. The failure to include any items on such list does
not alter the responsibility of the Contractor to complete all
Work in accordance with the Contract Documents. When the
Architect, on the basis of an inspection, determines that the
Work is substantially complete, he then will prepare a
Certificate of Substantial Completion (G704) which, when
approved by the Owner, shail establish the Date of
Substantial Completion, shall state the responsibilities of the
Owner and the Contractor for maintenance, heat, utilities,
and insurance, and shall fix the time within which the
Contractor shall complete the items listed therein, said time
to be within the Contract time unless extended.
Upon receipt of written notice that the Work is ready for final
inspection and acceptance and upon receipt of a final
Application for Payment and upon receipt of a final
application for payment, providing the record drawings have
been received by the Architect, the Architect will conduct
such test and/or inspections as he deems necessary, and if
in his opinion the Work has been completed in accordance
with the Contract Documents, the Architect will promptly
issue a final Certificate of Substantial Completion stating that
to the best of his knowledge, information and belief, and on
the basis of his observations and inspections, the Work has
been completed in accordance with the terms and conditions
of the Contract Documents and that the entire balance found
to be due the Contractor is due and payable. Fina�
acceptance can be made by the City Council of the City of
Fort Worth or it's designated representative, and no other
form of acceptance will be binding upon the Owner. Final
payment and release of the retainage amount will become
due within fifteen days following approval of the City Council
of the City of Fort Worth in accepting the work as complete.
Neither the final payment nor the remaining retained
percentage shall become due until the Contractor submits to
the Architect:
�.,
�
�'
�,
�r-�
k.,
l�
r
r
a
!
�.,
F
�
3) Contractor's Affidavit of Release of Liens (G706A), and,
4) Other data establishing payment or satisfaction of all
such obligations, such as receipts, releases and
waivers of liens arising out of the Contract, to the extent
and in such form as may be designated by the Owner.
If any Subcontractor, materialman or laborer refuses to
furnish a release or waiver required by the Owner, the
Contractor may, at the election of the Owner, furnish a bond
satisfactory to the Owner to indemnity him against any right,
claim or lien which might be asserted by such Subcontractor,
materialman or laborer. If any such right, claim or �ien
remains unsatisfied after all payments are made. The
Contractor shall refund to the Owner all monies that the
latter may be compelled to pay to discharging such right,
claim or lien, including all costs and reasonable attorney's
fees.
The acceptance of final payment shall constitute a waiver of
all claims by the Contractor except those previously made in
writing and still unsettled.
SECTION J
PROTECTION OF PERSONS AND PROPERTY
J-1 SAFETY PRECAUTIONS AND PROGRAMS The
Contractor shall be responsible for initiating, maintaining and
supervising all safety precautions and programs in
connection with the Work. The Contractor shall designate a
responsible member of his organization at the site whose
duty shall be the prevention of accidents. This person shall
be the Contractor's superintendent unless otherwise
designated in writing by the Contractor to the Architect.
J-2 SAFETY OF PERSONS AND PROPERTY. The
Contractor shall take all reasonable precautions for the
safety of, and shall provide all reasonable protection to
prevent damage, injury or loss to:
(1) all employees on the Work and all other persons who
may be affected thereby;
(2) all the Work and all materials and equipment to be
incorporated therein, whether in storage on or-off the
site, under the care, custody or control of the Contractor
or any of his Subcontractors or Sub-contractors; and
(3j other property at the site or adjacent thereto, including
trees, shrubs, Iawns, walks, pavements, roadways,
structures and u6lities not designated for removal,
relocation or replacement in the course of construction.
Until acceptance of the Work, it shall be under the charge
and care of the Contractor, and he shall take every
precaution against injury or damage to the Work by the
action of the elements or from any other cause whatsoever,
whether arising from the execution or from the non-execution
of the Work. The Contractor shall rebuild, repair, restore and
make good, at his own expense, all injuries or damages to
any portion of the Work occasioned by any of the above,
caused before its completion and acceptance.
The Contractor shall comply with all applicable Laws,
Ordinances, Rules, Regulations and Orders of any public
authority having jurisdiction for the safety of persons or
property or to protect them from damage, injury or loss. He
shall erect and maintain, as required by existing conditions
and progress of the Work, all reasonable safeguards for
safety and protection, including posting danger signs and
other warnings against hazards, promulgating safety
regulations and notifying owners and use�s of adjacent
utilities.
When the use or storage of explosives or other hazardous
materials or equipment is necessary for the execution of the
Work, the Contractor shall exercise the utmost care and
shall carry on such activities under the supervision of
properly qualified personnel.
All damage or loss to any property referred to in the
preceding paragraphs caused in whole or in part by the
Contractor, any Subcontractor, or anyone directly or
indirectly employed by any of them, or by anyone for whose
acts any of them may be liable, shall be remedied by the
Contractor, including damage or loss attributable to faulty
Drawings or Specifications and acts or omissions of the
Architect or anyone employed by him or for whose acts he
may be liable, and not attributable to the fault or negligence
of the Contractor or anyone claiming through the Contractor
for such damage or loss.
The Contractor shall not load or permit any part of the Woric
to be loaded so as to endanger its safety.
J-3 HARD HATS. Hard Hats will be required at all
construction sites included in this Contract from start to
completion of work. Each Contractor, employee and visitor
at any construction site inGuded in the Contract will be
required to wear a hard hat. The Contractor shall enforce the
wearing of hard hats by Contractor, employees and visitors.
These requirements are in addition to the Accident
Prevention Clause in the General Conditions of the Contract.
Contractor shall provide ten hard hats for use by the
consulting Architects and Engineers and visitors.
J-4 EMERGENCIES. In any emergency affecting the
safety of persons or property, the Contractor shall act at his
discretion to prevent threatened damage, injury or loss. Any
additional compensation or extension of time claimed by the
Contractor on account of emergency work shall be
determined as provided in Changes in the Work.
SECTION K - INSURANCE
K-1 Insurance Reauired. The Contractor shall not
commence work under this Contract until he has obtained all
insurance required under this Section and such insurance
has been approved by the City of Fort Worth, nor shall the
Contractor allow any Subcontractor to commence work to be
performed under this Contract until all similar insurance of
the Subcontractor has been so obtained and approved.
K-1 Insurance Reauired. The Contractor shall not
commence work under this Contract until he has obtained all
insurance required under this Section and such insurance
has been approved by the City of Fort Worth, nor shall the
Contractor allow any Subcontractor to commence work to be
performed under this Contract until all similar insurance of
the Subcontractor has been so obtained and approved.
K-2 Workers' Comoensation Insurance:
1) General
� GC - 15 of 23
10/11/99
v�
a) Contractor's Worker's Compensation Insurance.
Contractor agrees to provide to the Owner (City) a
certificate showing that it has obtained a policy of
workers compensation insurance covering each of
its employees employed on the project in
compliance with state law. No Notice to Proceed
will be issued until the Contractor has complied
with this section.
b) Subcontractor's Worker's Compensation
Insurance. Contractor agrees to require each and
every subcontractor who will perform work on the
project to provide to it a certificate from such
subcontractor stating t iah1 ... ....:...... /..,:.;�er�e�e-
- �
��� � �I' ��"-ii f! �'i��l
�� � �",-L�- i G i�c; .: �u`_L� �
p�] G�;�;��� �,���/r
u' i, ,tii rLl;^f 'tSl':E, ` U
C: � U C'1 �: Jd
��� '�IYn'J�`�'��� ��u�o
�,
�r
�
policy of workers compensation insurance
covering each employee employed on the project.
Contractor will not permit any subcontractor to
perform work on the project until such certificate
has been acquired. Contractor shall provide a
copy of all such certificates to the Owner (City).
c) By signing this contract or providing or causing to
be provided a certificate of coverage, the
contractor is representing to the City that all
employees of the contractor who will provide
services on the project wili be covered by worker's
compensation coverage for the duration of the
project, that the coverage will be based on proper
reporting of classification codes and payroll
amounts, and that ail coverage agreements will be
filed with the appropriate insurance carrier or, in
the case of a self-insured, with the Texas Worker's
Compensation Commission's Division of Self-
Insurance Regulation. Providing false or
misleading info�rnation may subject the contractor
to administrative penalties, criminal penalties, civil
penalties or other civil actions.
d) The contractor's failure to comply with any of these
provisions is a breach of contract by the contractor
which entitles the City to declare the contract void
if the contractor does not remedy the breach within
ten days after receipt of notice of breach from the
City.
2) Definitions:
a) Certificate of coverage ("certificate"). A copy of a
certificate of insura�ce, a certificate of authoriry to
self-insure issued by the Texas Workers'
Compensation Commission, or a coverage
agreement (TWCC-81, TWCC-82, TWCC-83, or
TWCC-84), showing statutory workers'
compensation insurance coverage for the person's
or entity's employees providing services on a
project, for the duration of the project.
b) Duration of the Project. Includes the time from the
beginning of the work on the project until the
contractor'slperson's work on the project has been
completed and accepted by the City.
c) Persons providing services on the project
("subcontractor" in section 406.096)-includes all
persons or entities performing ali or part of the
services the contractor has undertaken to perform
on the project, regardless of whether that person
contracted directly with the contractor and
regardless of whether that person has employees.
This includes, without limitation, independent
contractors, subcontractors, ieasing companies,
motor carriers, owner-operators, employees of any
such entiry, or employees of any entity which
furnishes persons to provide services on the
project. "Services" include, without limitation,
providing, hauling, or delivering equipment or
materials, or providing labor, transportation, or
other services related to a project. "Services"
does not include activities unreiated to the project,
such as foodJbeverage vendors, office supply
deliveries, and delivery of portable toilets.
3) Requirements
a) The contractor shall provide coverage, based on
�"' proper reporting of classification codes and payroll
amounts and filing of any coverage agreements,
which meets the statutory requirements of 7exas
Labor Code, Section 401.011(44) for all
�
� 10/11/99
GC - 16 of 23
employees of the contractor providing services of
the project, for the duration of the project.
b) The Contractor must provide a certificate of
coverage to the governmental entity prior to being
awarded the contract.
c) If the coverage period shown on the contractor's
current certificate of coverage ends during the
duration of the project, the contractor must, prior to
the end of the coverage period, file a new
certificate of coverage with the City showing that
coverage has been extended.
d) The contractor shall obtain from each person
providing services on a project, and provide to the
City:
i) a certificate of coverage, prior to that person
beginning work on the project, so the
governmental entity will have on file
certificates of coverage showing coverage for
all persons providing services on the project;
and
ii) no later than seven days after receipt by the
contractor, a new certificate of coverage
showing extension of coverage, if the
coverage period shown on the current
certificate of coverage ends during the
duration of the project.
e) The contractor sfiall retain afl required certificates
of coverage for the duration of the project and for
one year thereafter.
f) The contractor shall notify the City in writing by
certified maii or personal delivery, within ten (10)
days after the contractor knew or should have
known, of any change that materially affects the
provision of coverage of any person providing
services on the Qroject.
g) The contractor shall post on each project site a
notice, in the text, form and manner prescribed by
the Texas Worker's Compensation Commission,
informing all persons providing services on the
project that they are required to be covered, and
stating how a person may verify coverage and
report lack of coverage.
h) The contractor sfiall contractually require each
person with whom it contracts to provide services
on a project, to:
i) provide coverage, based on proper reporting
on the classification codes and payroll
amounts and filing of any coverage
agreements, which meets the statutory
requirements of Texas labor Code, Section
4�1.011(44) for all of its employees providing
services on the project, for the duration of the
project;
ii) provide to the contractor, prior to that person
beginning work on the project, a certificate of
coverage showing that coverage is being
provided for all employees of the person
providing services on the project, for the
duration of the project;
iii) provide the contractor, prior to the end of the
coverage period, a new certificate of
coverage showing extension of coverage, if
the coverage period shown on the current
certificate of coverage ends during the
duration of the project;
. . . '�i�v U�''' :,,�C�,L.�l�� ��,�,�
�.�� V'_s L
; ,7,,, {� �
: U �1���:; U:�L,��E � �7 ,
���`'' C�;;: ��i:'l� G�o �(� �o _
, �`
r.
iv) obtain from each other person with whom it
contracts, and provide to the contractor:
(1) a certificate of coverage, prior to the
other person beginning work on the
project; and
, (2) a new certificate of coverage showing
extension of coverage, prior to the end
,�; of the coverage period, if the coverage
period shown on the current certificate
of coverage ends during the duration of
' the project;
v) retain all required certificates of coverage on
file for the duration of the project and for one
year thereafter.
vi) notify the City in wriGng by certified maii or
personal delivery, within ten (10) days after
the person knew or should have known, of
any change that materialfy affects the
provision of coverage of any person providing
services on the project; and
vii) contractually require each person with whom
it contracts, to perform as required by
paragraphs h-i) - vii), with the certificates of
coverage to be provided to the person for
whom they are providing services.
4) Posting of Required Worker's Compensation Coverage.
a) The contractor shall post a notice on each project
site informing all persons providing services on the
project that they are required to be covered, and
stating how a person may verify current coverage
and report failure to provide wverage. This notice
does not satisfy other posting requirements
imposed by the Texas Worker's Compensation Act
or other Texas Worker's Compensation
Commission rules. This notice must be printed
with a tiUe in at least 30 point bold type and text in
at least 19-point normal 1ype, and shall be in both
English and Spanish and any other language
common to the worker population. The text for the
notices shall be the foHowing text, wiihout any
additional words or changes:
operations under this Contract, including blasGng, when
blasting is done on, or in connection with the Work of the
Project, whether such operations be by himself or by any
Subcontractor or by anyone direcUy or indirectly employed
by either of them and the limits of such insurance shall be
not less than the foflowing:
1) Automobile Liability: $1,000,000 each accident, or
reasonably equivalent split limits for bodily injury and
property damage. Coverage shall be on "any auto"
including leased, hired, owned, non-owned and
borrowed vehicles used in connection with this
Contract.
2) Commercial General Liability: $1,000,000 each
occurrence. Coverage under the policy shall be as
comprehensive as that provided in a current insurance
Services Office (ISO) policy form approved for use in
Texas and the policy shall have no exclusions by
endorsement unfess such are approved by the City.
3) Asbestos Abatement Liability Insurance: When the
Project specifically requires the removal of Asbestos
Containing Materials, the Contractor shall be required
to maintain Asbestos Abatement Liability Insurance as
follows: $1,000,000 per occurrence; $2,000,000
aggregate limit. The coverage shall include any
pollution exposure, including environmental impairment
liability, associated with the services and operations
performed under this contract in addition to sudden and
accidental contamination or pollution liability for gradual
emissions and clean-up costs.
K-4 BUILDER'S RISK INSURANCE.
Unless stated otherwise in the Proposal or Invitation, the
Contractor shall procure, pay for and maintain at all times
during the term of this Contract, Builder's Risk Insurance
against the perils of fire, Iightning, windstorm, hurricane, hail,
riot, explosion, civic commotion, smoke, aircraft, land
vehicles, vandalism, and malicious mischief, at a limit equal
to 100% of the Contract Sum.
The policy shall include coverage for materials and supplies
while in transit and while being stored on or off site. If
specifically required in the Instructions to Bidders, the policy
shall include coverage for flood and earthquake. Different
sub-limits for these coverages must be approved by the City.
"REQUIRED WORKER'S
COMPENSATION COVERAGE
The law requires that each person
working on this site or providing services
related to this construction project must
be covered by worker's compensation
insurance. This includes persons
providing, hauling, or delivering
equipment or materials, or providing
labor or transportation or other service
related to the project, regardless of the
identity of their employer or status as an
employee".
Call the Texas Worker's Compensation
Commission at 512-440-3789 to receive
information on the legal requirement for
coverage, to verify whether your
employer has provided the required
coverage, or to report an employer's
failure to provide coverage."
�
��
Consequential damage due to faulty workmanship andJor
design performed by the Contractor or his agents shall be
covered.
Upon completion of the Work, the Contractor shall notify the
City of Fort Worth in writing before terminating this
insurance.
K-5 PROOF QF CARRIAGE OF INSURANCE. The
Contractor shall provide a certificate of insurance
documenting the Transportation and Public Works
Department, City of Fort Worth as a"Certificate Hoider", and
noting the specific project(s) covered by the Contractor's
insurance as documented on the certificate of insurance.
More than one certificate may be required of the Contractor
depending upon the agents an/or insurers for the
Contractor's insurance coverages specified for the project(s�.
K-6 QTHER INSURANCE RELATED
REQUIREMENTS.
K-3 LIABILI7'Y INSURANCE. The Contractor shall
procure and maintain during the term of this Contract such 1) The City of Fort Worth shall be an additional insured, by
Liability Insurance as shall protect him, the City of Fort Worth endorsement, on all applicable i�surance policies.
and any Subcontractor perForming work covered by this
Contract, from claims of damage which may arise from
�-.
��u�'! �;-'����G?D
GC - 17 of 23 ;�::�,!�u c��''�G'�I��� ��i"�
10/11/99 ` �
` ��; '��i `' ���� �
. �r . :'.�� p �b�i o i
��.
�
F`
1�„
2) Applicable insurance policies shall each be endorsed
with a waiver of subrogation in favor of the City of Fort
Worth.
3) Insurers of policies maintained by Contractor and its
subcontractor(s), if applicable, shall be authorized to do
business in the State of Texas, or otherwise approved
by the City of Fort Worth, and such shall be acceptable
to the City of Fort Worth insofar as their financial
strength and solvency are concerned. Any company
through which the insurance is placed must have a
rating of at least A:VII, as stated in current edition of A.
M. BesPs Key Rating Guide. At the City's sole
discretion, a less favorable rate may be accepted by the
City.
4) Deductible limits on insurance policies and/or self
insured retentions exceeding $10,000 require approval
of the City of Fort Worth as respects this Contract.
5) The City of Fort Worth shall be notified in writing a
minimum of thirty days prior to an insurer's action in the
event of cancellation, non-renewal or material change
in coverage regarding any policy providing insurance
coverage required in this Contract.
6) Full limits of insurance shall be available for claims
arising out of this Contract with the City of Fort Worth.
7) The Contractor shall provide certificates of insurance to
the City prior to commencement of operaGons pursuant
to this Contract. Any failure on part of the City of Fort
Worth to request such documentation shall not be
construed as a waiver of insurance requirements
specified herein.
8) The City of Fort Worth shall be entitled, upon request
�r and without incurring expense, to review the insurance
I policies including endorsements thereto and, at its
`, discretion, to require proof of payment for policy
premiums.
�,
�
�
�,
�"'
L
L
9) The City of FoR Worth shall not be responsible for
paying the cost of insurance coverages required herein.
10) Notice of any actual or potential claim and/or litigation
that would affect insurance coverages required herein
shall be provided to the City in a timely manner.
11) "Other insurance" as referenced in any po�icy of
insurance providing coverages required herein shall not
apply to any insurance po�icy or program maintained by
the City of Fort Worth.
12) Contractor shall agree to either require its
subcontractors to maintain the same insurance
coverages and limits thereof as specified herein or the
Contractor shall provide such coverage on the
Contractor's subcontractors.
SECTION L
CHANGES IN THE WORK
execution of the Contract, authorizing a Change in the Work
or adjustment in the Contract Sum or the Contract Time. The
Contract Sum and the Contract Time may be changed only
by Change Order.
Any changes in work required due to changed or unforeseen
conditions, or by request of either the Contractor or the City,
shall be coordinated with the Director, Department of
Transportation and Public Works. A change order must be
written and duly negotiated and executed prior to performing
changed work.
The cost or credit to the Owner resulting from a Change in
the Fort Worth shall be determined in one or more of the
following ways:
1) by mutual acceptance of a lump sum property itemized,
including the allowance to Contractor for overhead and
profit stipulated in the original contract proposal;
2) by unit prices stated in the Contract Documents or
subsequently agreed upon; or
3) by cost and a mutually acceptable fixed or percentage
fee.
If none of the methods set forth herein above is agreed
upon, the Contractor, provided he receives a Change Order,
shall promptly proceed with the Work involved. The cost of
such work shall then be determined on the basis of the
Contractor's reasonable expenditures and savings, including
a reasonable allowance for overhead and profit as indicted in
the original contract proposal. In such cases, the Contractor
shall keep and present, in such form as the Architect shall
prescribe, an itemized accounting together with appropriate
supporting data. Pending final determination of cost to the
Owner, payments on account shall be made on the
ArchitecYs Certificate of Payment as approved by the
Owner.
If after the contract has been executed, the Architect,
requests a price proposai from the Contractor for a proposed
change in scope of the work, Contractor shall process such
proposal within seven days of receipt and return the price
quote to the Architect in writing. The Architect shall review
the price quotation an� if approval is recommended, forward
the proposed change order request and price proposal to the
Owner for approval. If the Architect will attempt to negotiate
with Contractor to revise the proposal to a figure which is fair
and reasonable and forward it on to the Owner for approval.
If the negotiations do not result in an equitable solution, the
Architect shall prepare a cost-plus type Change Order with a
price-not-to-exceed figure for approval by the City and
require specific documentation to be provided by Contractor
in accordance with the paragraph above.
Contractor is advised that according to City of Fort Worth
Charter, that when the cumulative effect of Change Orders
results in an increase in cost of the contract amount by over
$3,000, the Ciry Council must approve all such Change
Orders which will exceed this limit. Normal processing time
for the Ciry Staff to obtain City Council approval, once the
recommended change order has been received at the City,
is approximately thirty (30) days . Owner, Architect and
Contractor shall endeavor to idenGfy Change Order items as
early in the Construction process as possible to minimize
their impact on the construction schedule.
L-1 CHANGE ORDER. The Owner, without
invalidating the Contract, may order Changes in the Work
within the general scope of the Contract consisting of
additions, deletions or other revisions, the Contract Sum
and the Contract Time being adjusted accordingly. All Such
Changes in the Work shall be authorized by Change Order,
and shall be executed under the applicable conditions of the
Contract Documents.
A Change Order is a written order to the Contractor signed
by the Contractor, Owner and the Architect, issued after the
I 10/ 11 /99
If unit prices are stated in the Contract Documents or
subsequently agreed upon, and if the quantities originally
contemplated are so changed in a proposed Change Order
that application of the agreed unit prices to the quantities of
Work proposed will create a hardship on the Owner or the
�
GC - 18 of 23
.=f j�'�=U��:L '^��'v � � C
�I U�:��vJ���
�: �u'u' CrlS��U'�� �;1 e1\7
u
L�uo �'��� ���5?�� ���.
�
r
�
'�_.
�
��
P-
Contractor, the applicable unit prices shall be equitably
adjusted to prevent such hardship.
If the Contractor claims that additional cost or time is
invo�ved because of (1) any written interpretation issued
pursuant to Section A, (2) any order by the Architect or
Owner to stop the Work pursuant to Section B, where the
Contract was not at fault, or (3) any written order for a minor
change in the Work, the Contrar,tor shall make such claim.
L-2 CLAIMS FOR ADDITIONAL COST OR TIME. If
the Contractor wishes to make a claim for an increase in the
Contract Sum or an extension in the Contract Time, he shall
give the Architect written notice thereof within a reasonable
time after the occurrence of the event that gave rise to such
claim. This notice shall be given by the Contractor before
proceeding to execute the Work, except in an emergency
endangering life or property in which case the Contractor
shall proceed in accordance with Section J. No such Gaim
shall be valid unless so made. Any change in the Contract
Sum or Contract Time resulting from such claim, if approved
by the Owner, shall be authorized by Charlge Order.
L-3 OVERHEAD ALLOWANCES FOR CHANGES:
Should any change in the work or extra work be ordered,
the following applicable percentage shall be added to
Material and Labor costs to cover overhead and profit:
1. Allowance to the Contractor for overhead and profit for
extra work performed by the Contractor's own forces shall
not exceed fifteen percent (15%).
2. Allowance to the Contractor for overhead and profit for
extra work performed by a Subcontractor and supervised by
the Contractor shall not exceed ten percent 1j 0°(��.
L-4 MINOR CHANGES IN THE WORK. The Architect
shall have authority to order minor changes in the Work not
involving an adjustment in the Contract Sum or an extension
of the Contact Time and not inconsistent with the intent of
the Contract Documents. Such changes may be effected by
Field Order or by other written order. Such changes shall be
confirmed in writing by the Architect and shall be binding on
the Owner and the Contractor.
L-5 FIELD ORDERS. The Architect may issue written
Field Orders which interpret the Contract Documents in
accordance with Section A, or which order minor changes in
the Work in accordance with Section L without change in
Contract Sum or Contract Time. The Contractor shall carry
out such Field Orders promptly.
SECTION M
UNCOVERING AND CORRECTION OF WORK
M-1 UNCOVERING OF WORK. If any Work should be
covered contrary to the request of the Owner or Architect, it
must be uncovered for observa6on and replaced, at the
Contractor's expense.
If any other work has been covered which the Owner or
Architect have not specifically requested to observe prior to
being covered, the Architect or the Owner may request to
see such work and it shall be uncovered by the Contractor. If
such Work be found in accordance with the Plans and
Specifications, the cost of uncovering and replacement shall,
by appropriate Change Order, be charged to the Owner. If
such work be found not in accordance with the Plans and
Specifications, the Contractor shall pay such costs unless it
be found that this condition was caused by a separate
contractor employed by the Owner.
M-2 CORRECTION OF WORK. The Contractor shall
promptly correct all work rejected by the Owner or Architect
as defective or as failing to conform to the Plans and
Specifications whether observed before or after Substantial
Completion and whether or not fabricated, installed or
completed. The Contractor shall bear all costs of correcting
such rejected Work, including the cost of the ArchitecYs
additional service thereby made necessary.
If, within one year after the Date of Substantial Completion
or within such longer period of time as may be prescribed by
law or by the terms of any applicable special guarantee
required by the Contract Documents, any of the work is
found to be defective or not in accordance with the Contract
Documents, the Contractor shall correct it prompUy after
receipt of a written notice from the Owner to do so, unless
the Owner has previously given the Contractor a written
acceptance of such condition, describing same specifically
and not generally. The Owner shall give such notice
promptly after discovery of the condition.
All such defective or non-conforming work under the
preceding paragraphs shall be removed from the site where
necessary, and the work shall be corrected to comply with
the Contract Documents without cost to the Owner.
The Contractor shall bear the cost of making good all work of
separate contractors destroyed or damaged by such removal
or correction.
If the Contractor does not remove such defective or non-
conforming work within a reasonable time fixed by written
notice from the Architect or the Owner, the Owner may
remove it and may store the materials or equipment at the
expense of the Contractor. If the Contractor does not pay the
cost of such removal and storage within ten days thereafter,
the Owner may upon ten additional days' written notice sell
such work at auction or at private saie and shall account for
the net proceeds thereof, after deducting all the costs that
should have been borne by the Contractor including
compensation for additional architectural services. If such
proceeds of sale do not cover all costs that the Contractor
should have borne, the difference shall be charged to the
Contractor and an appropriate Change Order shall be
issued. If the payments then or thereafter due the Contractor
are not sufficient to cover such amount, the Contractor shall
pay the difference to the Owner.
If the Contractor fails to correct such defective or non-
conforming work, the Owner may correct it in accordance
with Section G.
The obligation of the Contractor under this Section shall be
in addition to and not in limitation of any obligations imposed
upon him by special guarantees required by the Contract
Documents or otherwise prescribed by law.
M-3 ACCEPTANCE OF DEFECTIVE OR NON-
CONFORMING WORK. If the Owner prefers to accept
defec6ve or non-conforming work, he may do so instead of
requiring its removal and correction, in which case a Change
Order will be issued to reflect an appropriate reduction in the
Contract Sum, or, if the amount is determined after final
payment, it shall be paid by the Contractor.
SECTION N
TERMINATION OF THE CONTRACT
N-1 TERMINATION BY THE CONTRACTOR. If the
work is stopped for a period of 30 days under an order or
any court or other public authority having jurisdiction,
through no act or fault of the Contractor or a Subcontractor
or their agents or employees or an,y other persons
� GC - 19 of 23
10/11/99
. 6'� I�� � 1i��5'�,'� j����'
�r ���� Cr�s���G��i�u�?�1
� ��ti�C���:��C� ���o i
o _�. P i
�
�
�
L,.
�
�
C
r..
�,
F
performing any of the work under a contract with the
Contractor, or if the work should be stopped for a period of
30 days by the Contractor for the Owner's failure to make
payment thereon as provided in Section I, then the
Contractor may after the end of such period of 30 days and
upon seven additional days' written notice to the Owner and
the Architect, terminate the Contract.
N-2 TERMINATION BY THE OWNER. If the
contractor is adjudged as bankrupt, or if he makes a general
assignment for the benefit of his creditors, or if a receiver is
appointed on account of his insolvency, of if the Contractor
refuses, except in cases for which extension of time is
provided, to supply enough proper�y skilled workmen or
proper materials, or if he fails to make prompt payment to
Subcontractors or for materials or labor, or fails to comply
with al Laws, Statutes, Charter, Ordinances, Regulations or
Orders of any public authoriry having jurisdiction, or
otherwise is guilty of a substantial violation of a provision of
the Contract Documents, then the Owner, on its own
initiative or upon certification by the Architect that sufficient
cause exists to justify such action, may, without prejudice to
any rights or remedy and after giving the Contractor and his
surety, if any, seven (7) days' written notice, terminate the
employment of the Contractor and take possession of the
site and of all materials, equipment, tools, construction
equipment and machinery thereon owned by the Contractor
and may finish the work by whatever method he may deem
expedient. �n such case the Contractor shall not be entitled
to receive any further payment until the Work is finished.
If the costs of finishing the Work, including compensation for
the ArchitecYs additional services., exceed the unpaid
balance of the Contract, the Contractor shall pay the
difference to the Owner.
The City of Fort Worth may terminate this contract in whole,
or from time to time, in part, whenever such termination is in
the best interest of the City. Termination will be effected by
delivering to the Contractor a notice of termination specifying
to what extent performance of the work of the contract is
being terminated and the effective date of termination. After
receipt of termination the contractor shall:
a) Stop work under the Contract on the date and to the
extent specified on the notice of termination.
b) Place no further orders or subcontracts except as may
be necessary for the completion of the work not
terminated.
c) Terminate all orders and subcontracts to the extent that
they relate to the performance of the work terminated
by the notice of termination.
After termination as above, the City will pay the contractor a
proportionate part of the contract price based on the work
completed; provided, however, that the amount of payment
on termination shall not exceed the total contract price as
reduced by the portion thereof allocatable to the work not
completed and further reduced by the amount of payments,
if, any otherwise made. Contractor shall submit its claim for
amounts due after termination as provided in this paragraph
within 30 days after receipt of such claim. In the event of
any dispute or controversy as to the propriety or allowability
of all or any portion of such claim under this paragraph, such
dispute or controversy shall be resolved and be decided by
the City Council of the City of Fort Worth, and the decision
by the City Council of the City of Fort Worth shall be final
and binding upon all parties to this contract
SECTION O
SIGNS
� ' 10/11/99
i._
The Contractor shall construct and install the project
designation sign as requi�ed in the Contract Documents and
in strict accordance with the Specifications for "Project
Designation Signs." This sign shall be a part of this Contract
and shall be included in the Contractor's Base Bid for the
Project.
SECTION P
TEMPORARY FACILITIES
P-1 OPE. The Contractor shall furnish, erect, and
maintain facilities and perform temporary work required in
the perFormance of this Contract, inGuding those shown and
specified.
P-2 USE OF TEMPORARY FACILITIES. All
temporary facilities shall be made available for use by all
workmen and subcontractors employed on the project,
subject to reasonable directions by the Contractor as to their
proper and most efficient utilization.
P-3 MAINTENANCE AND REMOVAL. The
Contractor shall maintain temporary facilities in a proper,
safe operating and sanitary condition for the duration of the
Contract. Upon completion of the Contract, all such
temporary work and facilities shall be removed from the
premises and disposed of unless otherwise directed or
specified hereunder.
P-4 FIELD OFFICES AND SHED. The Contractor
shall provide a temporary field office building for himself, his
subcontractors and use by the Architect. For construction
contracts with a bid price in excess of $1,000,000.00, the
Contractor shall provide a separate field office for the City's
field representative (but the separate office may be in the
same structure). The buildings shall afford protection against
the weather, and each office shall have a lockable door, at
least one window, adequate electrical outlets and lighting,
and a shelf large enough to accommodate perusal of the
project drawings. Openings shall have suitable locks. Field
offices shall be maintained for the full time during the
operation of the work of the Contract. During cold weather
months, the field offices shall be suitably insulated and
equipped with a heating device to maintain 70 degree
Fahrenheit temperature during the workday. During warm
weather the o�ces shall be equipped with an air conditioning
device to maintain temperature below 75 degrees F. Upon
completion of the work of the Contract, the Contractor shall
remove the building from the premises. In addition to the
drawing shelf, provide for the City field representatives
office: one deck, four chairs, plan rack and a four drawer
filing cabinet (with lock). Each office shall contain not less
than 120 square feet of floor space.
The Contractor shall provide and maintain storage sheds,
other temporary buildings or trailers on the project site as
required for his use. Location of sheds and trailers shall be
as approved by the Architect. Remove sheds when work is
completed, or as directed.
P-5 TELEPHONE. The Contractor shall provide and
pay for telephone installation and service to the field offices
described above. Service shall be maintained for the
duration of opera6ons under this contract. The Contractor
shall provide for and pay for an automatic telephone-
answering device at the site office for the duration of the
project. The contractor shall provide a separate telephone
line, and instrument for use by the City's field
representatives.
P-6 TOILET FACILITIES. The Contractor shall
provide proper, sanitary and adequ�te toilet facilitec for th,�,
GC - 20 of 23
� I� li�, �; �;'� j `Ir�n�'�'�����
'��-� ! .. �w,_ �.!S 1�.�, x:'v
�_ ���:;�,,; crrl!'�, , ���
�: L C �. cs 1: � ,
�. `r�� Ut7��✓�J'�Ullp U�i11a �
i.._
i..,
�
�
i..
��.,
�
�
use of all workmen and subcontractors employed on the
project.
P-7 UTILITIES. Contractor shall make all necessary
arrangements and provide for temporary water and
electricity required during the construction. Contractor shall
provide and install temporary utility meters during the
contract construction period. These meters will be read and
the Contractor will be billed on this actual use. The
Contractor shal� provide all labor and materials required to
tap into the utilities. The Contractor shail make the
connec6ons and extend the service lines to the construction
area for use of all trades. Upon completion of the work all
utility lines shall be removed and repairs made to the
existing lines. Only utilities at existing voltages, pressures,
frequencies, etc. will be available to the Contractor.
Water. Provide an ample supply of potable water for all
purposes of construction at a point convenient to the project
or as shown on the Drawings. Pipe water from the source of
supply to all points where water will be required. Provide
sufficient hose to carry water to every required part of the
construction and allow the use of water facilities to
subcontractors engaged on the work. Provide pumps, tanks
and compressors as may be required to produce required
pressures.
Electric Service. Provide adequate electric service for power
and lighting to all points where required. Temporary, electric
service shall be of sufficient capacity and characteristics to
supply proper current for various types of construction tools,
motors, welding machines, lights, heating plant, air
conditioning system, pumps, and other work required.
Provide sufficient number of electric outlets so that 50 foot
long extension cords will reach all work requiring light or
power.
Li htin . Supply and maintain temporary lighting so that
work of all trades may be properly and safely performed, in
such areas and at such time that day-lighting is inadequate.
Provide at least 0.75 watts of incandescent lighting per
squqr4e foot and maintain a socket voltage of at least 110
volts. Use at least 100 watt lamps. In any event, the lighting
intensity shall not be less than 5 foot candles in the viciniry of
work and traffic areas.
P-8 HEATING. Heating devices required under this
paragraph shall not be electric. The Contractor shall provide
heat, ventilation, fuel and services as required to protect all
work and materials and to keep the humidity down to the
extent required to prevent corrosion of any metal and to
prevent dampness or mildew which is potentially damaging
to materials and finishes. All such heating, ventilation and
services shall be provided and maintained until final
acceptance of all work. In addition, the Contractor shall
provide heat ventilation prior and during the following work
operations as follows:
a) At all times during the placing, setting and curing of
concrete provide su�cient heat to insure the heating of
the spaces involved to not less than 40 F.
b) From the beginning of the application of drywall and
during the setting and curing period, provide sufficient
heat to produce a temperature in the spaces involved of
not less than 55 F.
c) For a period of seven (7) days previous to the placing of
interior finish materials and throughout the placing of
finish painting, decorating and laying of resilient flooring
materials, provide sufficient heat to produce a
temperature of not less than 60 F.
10/ 11 /99
P-9 TEMPORARY CONSTRUCTION. EQUIPMENT
AND PROTECTIQN
The Contractor shall provide, maintain, and remove upon
completion of the work all temporary rigging, scaffolding,
hoisting equipment, rubbish chutes, ladders to roof,
barricades around openings, and all other temporary work as
required to complete all work of the Contract. Contractor
sha�l coordinate the use and furnishing of scaffolds with his
sub-contractors.
The Contractor shall provide, maintain, and remove upon
completion of the work, or sooner, if authorized by the
Architect, all fences, barricades, lights, shoring, pedestrian
walkways, temporary fire escapes, and other protective
structures or devices necessary for the safety of workmen,
City employees, equipment, the public and property.
All temporary construction and equipment shall conform to
all regulations, ordinances, laws and other requirements of
the authorities having jurisdiction, inGuding insurance
companies, with regards to safety precautions, operation
and fire hazard.
The Contractor shall provide and maintain pumping facilities,
including power, for keeping the site, all times, whether from
underground seepage, rainfall, drainage of broken lines.
The Contractor shall maintain provision for closing and
locking the building at such time as possible to do so. If this
is not feasible, maintain a night
The Contractor shall provide and maintain all barricades or
enclosures, required to protect the work in progress from
outside elements, dusts, and other disturbances as a result
of work under this Contract. Such protection shall be
positive, shall meet the approval of the Architect and shall be
maintained for the duration of the construction period or as
required to provide for the protection as specified.
P-10 PROJECT BULLETIN BOARD. The Contractor
shall furnish, install and maintain during the life of the project
a weather-tight bulletin board approximately 3 feet high by 5
feet wide having not less than two hinged or sliding glass
doors with provisions for locking. The bulletin board shall be
mounted where and as approved by the Architect, in a
prominent place accessible to employees of the Contractor
and sub-contractors, and to applicants for employment. The
bulletin board shall remain the property of the Contractor and
shall be removed by him upon completion of the Contract
work. The following information which will be furnished by
the City to the Contractor, shall be posted on the bulletin
board and shall be maintained by the Contractor in easily
readable condition at all times for the duration of the
Contract.
a. The Equal Opportunity Poster and Notice
Nondiscrimination of Employment (Standard Form
38).
b. Wage Rate Information Poster (Form SOL 155),
with the Contract Schedule of minimum wage
rates as required by the Davis-Bacon Act.
c. Safety Posters.
SECTION Q
VENUE
Should any action arise out of the terms and conditions of
this contract, venue for said action shall lie in Tarrant
County, Texas.
GC - 21 of 23
''>�-''L�����OG�� ����'0'U"�
�� G�' � [���G� d � ��
V� o IN'vi��l�:�l�'Wp �lSWo
�
f
��.
�.
�"
�.
�
�
�,
i`
A
A-1
A-2
A-3
A-4
A-5
A-6
A-7
A-8
A-9
A-10
A-11
DEFINITIONS PROCEDURES AND
INTERPRETATIONS
GENERAL CONDITIONS
INDEX
SUBCONTRACTORS
Contract Documents
Entire Agreement
Work
Execution of the Contract Documents
Familiarity with Proposed Work
One Unified contract
Division of Work
Interpretations
Copies of Working Drawings and
Specifications
Minority and Women's Business Enterprise
Policy
Correlation and Intent
IDENTITY OF ARCHITECT
B-1 Contract Administration
B-2 Termination and Suspension of Work
B-3 Duties of Architect
B-4 Architect as Representative of the Owner
B-5 Access to Job Site
B-6 Interpretations
B-7 Authority to Stop Work
B-8 Miscellaneous Duties of Architect
B-9 Termination of Architect
C OWNER
C-1 Identification
C-2 Duties of the Owner
C-3 Instructions
C-4 Access to Job Site
C-5 Progress Inspections
C-6 Authority to Stop Work
C-7 Substantial Completion Inspection
C-8 Right to Audit
D CONTRACTOR
D-1 Identification
D-2 Independent contractor
D-3 Subletting
D-4 Review of contract Documents
D-5 Supervision
D-6 Labor and Materials
D-7 Prevailing Wage Rate
D-8 Warranry
D-9 Taxes
D-10 Licenses, Notices and Fees
D-11 Cash Allowances
D-12 Superintendent
D-13 Responsibility for Employees and Sub-
contractors
D-14 Failure to Commence work
D-15 Progress Schedule
D-16 Drawings and Specifications at the Site
D-17 Shop Drawings and Samples
D-18 Site Use
D-19 Safe Work Practices
D-20 Field Offices and Sheds
D-21 Trench Safety
D-22 Cutting and Patching of Work
D-23 Cleaning Up
D-24 Communications
10/11/99
E-1 Definition
E-2 Award of Subcontracts
E-3 Terms of Subcontracts
E-4 Minority and Women's Business Enterprise
(M/WBE)
E-5 Payments to Sub-Contractors
SEPARATE CONTRACTS
F-1 Owner's Right
F-2 Mutual Responsibility of Contractors
F-3 Cutting and Patching Under Separate
Contracts
F-4 Owner's Right to Clean Up
L
G-1
G-2
G-3
G-4
G-5
G-6
G-7
G-8
G-9
G-10
G-11
G-12
G-13
G-14
G-15
G-16
G-17
G-18
G-19
G-20
G-21
G-22
G-23
G-24
G-25
G-26
G-27
G-28
G-29
G-30
G-31
G-32
G-33
W
MISCELLANEOUS PROVISIONS
Conflict of Laws
Governing Laws
Personal �iability of Public Officials
Compliance with Laws
Indemnification
Successors and Assigns
Written Notice
Surety Bonds
Owner's Right to Carry Out the Work
Royalties and Patents
Test�
Interruption of Existing Utilities Services
Laying Out Work
Measurements
Existing Overhead or Underground Work
Alignment of Joints in Finish Materials
Integrating Existing Work
Hazardous Material Certifica6on
Location of Equipment and Piping
Overloading
Manufacturer's Instruction
Cleaning Up
Dust Control
Fire Protection
Cutting and Patching
Project Closeout
Guarantee and Extended Guarantee
Y2K Compliance Requirements
Record Drawings
Construction Fence
Product Deliver, Storage, Handling
Age
Disability
CONTRACT TIME
H-1 Definitions
H-2 Progress and Completion
H-3 �elays and Extension of Time
H-4 No Damage for Delay
I PAYMENTS AND COMPLETION
I-1
I-2
I-3
I-4
I-5
GC - 22 of 23
Contract Sum
Schedule of Values
Adjustment of Quantities
Progress Payments
Certificates for Payment
. ,^;;;,��:��� �_'C�G!J���'��
<sl��l� c��L;��U� ° �l�
� uo U I1C_I�q Ile ��!/1\e .
�
�
�`
�
�
�
�
�
�
�
�
�
�
I-6 Payments Withheld
I-7 Unresolved Claims
I-8 Liquidated Damages
I-9 Failure of Payment
I-10 Substantial Completion and Final Payment
J PROTECTION OF PERSONS AND
PROPERTY
J-1 Safety Precautions and Programs
J-2 Safety of Persons and Property
J-3 Hard Hats
J-4 Emergencies
K INSURANCE
K-1 Insurance Required
K-2 Workers' Compensation Insurance
K-3 Liability Insurance
K-4 Builder's Risk Insurance
K-5 Proof of Insurance
K-6 Other Insurance Related Requirements
L CHANGES IN THE WORK
L-1 Change Order
L-2 Claims for Additional Cost or Time
L-3 Overhead Allowance for Changes
L-4 Minor Changes in the Work
L-5 Field Orders
10/11/99
..�..
M
M-1
M-2
M-3
N
N-1
N-2
O
P
P-1
P-2
P-3
P-4
P-5
P-6
P-7
P-8
P-9
P-10
Q
GC - 23 of 23
UNCOVERING AND CORRECTION OF
WORK
Uncovering of Work
Correction of Work
Acceptance of Defective or Non-Conforming
Work
TERMINATION OF THE CONTRACT
Termination by the Contractor
Termination by the Owner
SIGNS
TEMPORARY FACILITIES
Scope
Use of Temporary Facilities
Maintenance and Removal
Field Offices and Sheds
Telephone
Toilet Facili6es
Utilities
Heating
Temporary Construction, Equipment and
Protection
Project Bulletin Board
VENUE
.�,,/. / ^
�;:����'�����D��� �'��u��D
I;�,`� ��i., ��� ° � U
",;;a^�Ii�i�� ULK/n10
:�%;�,.�! U+.lg
Within ten (10) days of receipt of notice of acceptance of this bid, the successful bidder will execute the
formai contract and will deliver an approved Surety Bond for the faithful performance of this contact. The
'^� attached deposit check in the sum of Doliars ($� is to become the property of the City
of Fort Worth, Texas, or the attached Bidder's Bond is to be forfeited in the event the contract and bond
� are not executed within the time set forth, as liquidated damages for delay and additional work caused
�. thereby.
�- MINORITY/WOMENS BUSINESS ENTERPRISE (M/WBE): (For bids in excess of $25,000)
• I am aware that I must submit information the Director, Transportation and Public Works, concerning
the M/WBE participation within FIVE BUSINESS DAYS of submittal of this Proposal in order to be
RESPONSIVE.
�
Respectfully submitted,
Company Name
By:
` Signature
Printed Name of Principal
Address:
Street
I�.,
�
�
�
�
�
r
City
Phone:
Fax:
Receipt is acknowledged of the following addenda:
Addendum No. 1:
Addendum No. 2:
Title
Zip
�,,(j , r�.-, �
ii:iU-U ll��� ��i%:L �t-1�51C OJ DI� �
L5
'�: �'�1 c"��: G�[� � ,��
IYII �hV���'�''1 �` 8 �L�U�
i. �•��..;�i:J o
WEATHER TABLE
Month Average Inches of Snow/Ice
Days of Rainfall Pellets
Rain
January 7 1.80 1
February 7 2.36 *
March 7 2.54 *
April 8 4.30 0
May 8 4.47 0
June I 6 I 3.05 I 0
July I 5 I 1.84 I 0
August I 5 I 2.26 I 0
September I 7 I 3.15 I 0
October I 5 I 2.68 I 0
November I 6 I 2.03 I *
December I 6 I 1.82 I `
I ANNUALLY I 77 I 32.30 I 1
(1) Mean number of days rainfall, 0.01" or more I
(2) Average normal precipitation, in inches i
(3) Mean number of days 1.0 inch or more
; Less than 0.5 inches
This table is based on information reported from Dallas-Fort Worth Regional Airport, Texas. Latitude 32
deg 54 min north, longitude 97 deg 02 min West, elevation (ground) 551 ft.
Average number of days of rain, snow, and ice are based on records covering 27 years. Precipitation is
based on record of 1941-1970 period.
This table is to be used as a basis for calculation of excess rain or weather days for projects with duration
in calendar days. If the site records indicate that the Contractor was un!able to carry out operations due to
? weather, it is counted as a weather day. If the number of weather days exceeds the number of average
rain days plus the snow/ice-pellet days for a given month, the contract period will be adjusted by Change
Order.
.�
�
�
�
:,
u��9C 81�� �'��� �°� �► '.
� rB� ���<<�C�,,��,�
,�
II�o ODUVf�UUp �u1No ,
�.,.
�
`.,
�
�.,
L,,
�.
r
�
�
�
�
�
�
1999
CLASSIFICATION
BUILDING & CONSTRUCTION TRADES
STANDARD WAGE RATE
FOR TARRANT COUNTY
HOURLY RATE CLASSIFICATION
AIR CONDITIONING MECHANIC
AIR CONDITIONING MECHANIC HELPER
ACOUSTIC CEILING INSTALLER
ACOUSTIC CEILING INSTALLER HELPER
BRICKLAYER/STONE MASON
BRICKLAYER/STONE MASON HELPER
CARPENTER
CARPENTER HELPER
CONCRETE FINISHER
CONCRETE FINISHER HELPER
CONCRETE FORM BUILDER
CONCRETE FORM BUILDER HELPER
DRYWALL TAPER
DRYWALL TAPER HELPER
ELECTRICIAN JOURNEYMAN
ELECTRICIAN HELPER
ELECTRONIC TECHNICIAN
ELECTRONIC TECHNICIAN HELPER
FLOOR LAYER (CARPET)
FLOOR LAYER (RESILIENT)
FLOOR LAYER HELPER
GLAZIER
GLAZIER HELPER
INSULATOR
INSULATOR HELPER
LABORER COMMON
LABORER SKILLED
LATHER
LATHER HELPER
METAL BUILDING ASSEMBLER
METAL BUILDING ASSEMBLER HELPER
PAINTER
PAINTER HELPER
PIPEFIT"fER
PIPEFITTER HELPER
$15.96
8.81
13.82
9.79
13.25
9.86
13.00
934
12.00
9.44
11.59
8.87
11.87
8.25
16.29
10.20
12.86
12.67
13.58
14.48
8.56
13.66
9.26
15.89
9.46
7.82
9.66
15.80
11.75
13.34
7.85
11.93
8.30
14.33
10.93
HOURLY RATE
PLASTERER
PLASTERER HELPER
PLUMBER
PLUMBER HELPER
REINFORCING STEEL SETTER
RE[NFORCING STEEL HELPER
ROOFER
ROOFER HELPER
SHEET METAL WORKER
SHEET METAL WORKER HELPER
SHEETROCK HANUER
SHEETROCK HANGER HELPER
SPRINKLER SYSTEM 1NSTALLER
SPRINKLER SYSTEM INSTALLER HELPER
STEEL WORKER STRUCTURAL
STEEL WORKER STRUCTURAL HELPER
WELDER
WELDER HELPER
HEAVY EQUIPMENT OPERATORS
EQUIPMENT OPERATORS
CONCRETE PUMP OPERATORS
CRANE, CLAMSHELL, BACKHOE,
DERRICK, D'LINE SHO
FORKL[FT OPERATOR
FOUNDATION DRILL OPERATOR
FRONT END LOADER OPERATOR
TRUCK DRIVER
13.29
8.63
16.26
9.39
11.88
9.18
13.17
7.82
15.87
9.29
12.70
9.71
16.93
7.81
14.66
7.91
14.87
9.67
14.66
13.30
13.03
10.34
1 1.66
11.60
�.so
' ������� �'�r'Q'1<'� �
�� `� ��'��� �' i�,�
��� ��',�; �'„` _'�?'M„ 7?�'�;,(�,
�
�
�
�
�"
SECTION 15010
MECHANICAL SPECIAL PROVISIONS
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
�
�
1.02
Drawings and general provisions of Contract, including General and Supplementary Conditions
and Division 1 Specification Sections, apply to this Section.
The above provisions shall take precedence over this section where discrepancy may exist.
DEFINITIONS
in addition to the Supplementary General Conditions, the following definitions shall apply to this
DIVISION.
A. "Contractor" - Refers to the Contractor or Contractors for Mechanical Contract Work.
B. "Subcontractor" - Refers to a Subcontractor to whom the Contractor has awarded a defined
portion of the Mechanical Contract Work.
1.03 CONTRACTOR QUALIFICATIONS
Contractor shall be able to prove considerable experience on jobs of similar nature and size that
�� were completed to the satisfaction of the respective Owners and Engineers, and that he is in
� position at present, both financially and in terms of qualified personnel, to complete this project to
the full satisfaction of the Owner and Engineer. Failure to qualify will be considered adequate
cause of rejection of bid.
�
1.04 BIDS AND ALLOWANCES
A.
�J
�
L:l
1.05
The Mechanical Contractor shall include an allowance of $8,000.00 in his bid for special testing
and project enhancement as required. All expenditures from the allowance shall be approved by
the Engineer prior to performing the work. Unused amounts will be returned to the Owner at
project completion.
Submission of a bid guarantees complete understanding of the extent and character of the work
involved, including site conditions, working conditions and the material and labor required as
described on the plans and/or specifications or which may be fairly implied as essential for a
complete installation.
INSPECTION OF SITE
Contractor submitting proposals for this work shall first make an on-the-spot examination of the
site, and all conditions thereon and/or therein. All proposals shall take into consideration such
conditions as may affect the work under the respective contract. Submission of a bid will be taken
as evidence that this inspection has been made.
��;'��i�V��O�� G;:�I�iG��)��L ,
�;�' !� v' ��C��:; G' ° ���
MECHANICAL SP�E�CIA1 PROVISIOrIS ,;�� �� J�I��MD ����
I'"��_ W
�,
i+i
r
L
Contractor shall comply with local customs as to which particular trade shall install any part or
parts of any work or equipment shown or specified, and shall plan and execute his work in this
regard so as not to interfere with other Contractors on this project.
1.07 DRAWINGS
A.
i,...
r.,
�.
1.
��
2.
��
:
Drawings numbered with the prefix "ME" show the extent of the work contemplated.
Exceptions and inconsistencies in plans and specifications shall be brought to the attention of the
Engineer before contract is signed. Otherwise, the Contractor shall be responsible for any and all
changes and additions that may be necessary to accommodate his particular circumstance.
C. The plans are intended to show the general arrangement and the extent of the work
contemplated. The exact location and arrangement of all parts shall be determined after
equipment has been approved by the Engineer as the work progresses, to conform in the best
possible manner with the surroundings and as directed by the Engineer.
D. Figured dimensions shail be followed without regard to scale - where no figures or notations are
given, the plans shall be followed.
9.08 SYMBOLS
Symbols for the various outlets, piping, and related systems are noted on the plans, and shall be
strictly adhered to in connection with all work. Should the Contractor be in doubt regarding the
real meaning and intent of the various symbols used, he shall confer with the Engineer for
interpretation, whose decision shall be final.
9.09 SUBSTITUTIONS
A. Contractor, if desirous of using equipment and/or materials other than that specifically cailed for in
the specifications, shall adhere to the following procedure in obtaining approval of such
substitutions.
Within ten (10) days of the award of the respective contract, each Contractor shall furnish
to the Engineer, in triplicate, a list of proposed manufacturers for the various items of
equipment being substituted for preliminary approval.
Such items as are considered by the Engineer to be generally acceptable shall then be
submitted for finai review according to the procedure outlined for all equipment under
SHOP DRAWINGS AND SUBMITTAL DATA.
r' 3. Such items as are considered by the Engineer to be generally not acceptable and for which
, the Contractor wishes to propose some other substitution, may be resubmitted for
preliminary review within the following ten (10) days or a total of twenty (20) days from
award of contract.
�'`"" 9.10 SHOP DRAWINGS AND SUBMITTAL DATA
� A_ Contractor shall furnish detailed shop drawings and catalogue data in quantity required to allow
three copies to remain with the Engineer, to the Engineer for review before fabrication or
�"
installation and within a total of thirty (30) days from the date of award of contract.
�
1.06 LOCAL CUSTOMS
MECHANICAL SPECIAL PROVISIONS
15010 - 2
-,, ��• r,�. ., � �, �.
��'�� '�� i i 'u �l'' r 1
�-% � �J�.lif'�L'� u����. �:.i�:��i
i� J: (f� c���v U°�i5 UG�IUS U
��o �'G'��9 ���4
�
�
r
�
Upon completion of the job, Contractor shall bind one copy of reviewed shop drawings and
catalogue data on all items of equipment actually installed in the job, into two neat volumes, and
present them to the Engineer for the Owner.
�
Shop drawing and/or catalogue data shall be submitted on the items listed in each Mechanical
Section, but shall not necessarily be limited to these items.
C
D. Ali shop drawings, product data and samples submitted by the Contractor shall illustrate details of
work, equipment, materials, products, systems, designs or workmanship that the Contractor
intends to use in order to comply with the design concept established in the contract documents.
The Engineer's review of these submittals is only for the limited purpose of checking the same for
conformity with the design concept of the work as established in the contract documents, and is
not intended to be for the purpose of determining the accuracy of other matters that may be
contained in such submittals, including but not limited to such matters as dimensions, quantities,
performance of equipment and systems designed by the Contractor, Contractor-furnished
engineering and design, construction means, methods, techniques, sequences, procedures or
safety precautions. the correctness of which as set forth in the contract documents or submittal
shall be the sole responsibility of the Contractor. The Engineer shall undertake its review with
reasonable promptness so as to cause no delay. The Engineer's review of a specific item shall
not indicate approval of an assembly of which the item is a component or in which it functions.
1.11 EQUIPMENT LIST, PROGR�SS SCHEDULES, ESTIMATES
A. Contractor shall prepare and furnish to the Engineer an equipment list tabulating each item of
�, materiai and equipment required and giving the date upon which the order is placed, the date of
submittal of shop drawings, and the anticipated date of delivery of the item.
�
�,
.
�...,
Contractor shall prepare and furnish to the Engineer a"Construction Progress Schedule". This
schedule shall indicate in form satisfactory to the Engineer the proposed dates of commencement
and completion of the entire work.
�
ORDINANCES, PERMITS, AND CERTIFICATES
1.12
`' A. All labor and materials shall be in strict conformance with the rules and recommendations of the
National Fire Protection Association, municipal and state codes and regulations, local electric,
telephone, and gas companies, American Gas Association, National Electricai Code, or any other
authorities that may have lawful jurisdiction pertaining to the work.
�
r
��
�'
B. Each Contractor shall procure all necessary permits, licenses, or inspections to carry out his work
and shail pay the lawful fees therefor. Each Contractor shall procure and pay for all necessary
certificates of approval, which must be delivered to the Engineer before final acceptance of the
work.
C. Work shall be installed as indicated on the drawings, unless drawings and/or materials conflict
with Code requirements governing, in which case, the Code shall be followed without additional
charge to the Owner.
MECHANICAL SPECIAL PROVISIONS
15010 - 3
�f��6�QQ� �������D
���V ��'r��� ° °�i
�,','� �%i ��r''�ti1. ��M
� u �'�,:.� �� . In N � ��;�-�a�,
�-, 9.13 UTILITIES AND EXISTING WORK
"° The locations, sizes, types, depths, pressures, and direction of flow of various existing or
� proposed new piping and/or utility mains, and the locations, sizes, types, and characteristics of
� various existing or proposed new electric and telephone service feeders and facilities are shown
+�� in accordance with the best information available and with data secured from the various
departments of the City and the utility companies involved. Data shown is offered as an
'" estimating guide without guarantee of accuracy. Each bidder shall make complete investigations
of the site, and shall check and verify all data given before entering a bid. Full responsibility for all
complications arising from unverified data shall rest with the Contractor or Contractors involved.
�� 1.14 LARGE EQUIPMENT
Large pieces of equipment, which are to be installed in the building, and which are too large to
rpermit access through doorways, stairways, or shafts, shall be brought to the job by this
� Contractor and placed in spaces before the enclosing structure is completed. Where existing
walls, etc., must be removed to permit installation of large equipment, removal work shall be
� handled in the same manner as specified for CUTTING AND PATCHING. Equipment shall be
cribbed up from the floor by the Contractor and covered with tarpaulins or other protective
covering where necessary or directed.
�: .
1.15 PROTECTION OF WORK AND MATERIALS
� A. All work, materials, and equipment, whether incorporated in the building or not, shall be protected
at all times against the weather (rain, windstorms, frost, ice, or heat) so as to maintain them free
from injury or damage. At the end of each day's work, all work likely to be damaged shall be
covered.
� B. Building openings shall be covered to protect the building from the weather.
C. Finished floors, step treads, Owner's equipment, and all finished surfaces, exterior or interior,
_ shall be protected against damage by workmen or equipment during the work. Wherever
materials are hoisted to the roof or carried into the building, surfaces must be covered with a layer
�= of heavy building paper.
D. Equipment shall be kept out of the weather, and shall be kept covered. Where work is to be done
above equipment, the Contractor shall provide full and solid wood platforms above such
equipment, to prevent its being damaged or soiled.
�
E. Any and all equipment, piping, motors, insulation, etc., which in the opinion of the Engineer
becomes damaged, abused, inundated, or otherwise harmed beyond normal and minor repair,
shall be replaced with new equipment or material at no additional cost to the Owner. At the
completion of the work, all equipment shall be thoroughly cleaned and the entire system delivered
� in a perfect, unblemished condition.
F. The Contractor shall be proportionately and respectively responsible for all damage done to the
Owner's property or adjacent properties during the construction. The above protection shall be
maintained while work is being done, and in no case shall dirt or grit be ground into floor finishes
'`' or floor coverings.
� G
�...
Contractor shall furnish and install adequate barriers and safety devices to protect his and his
subcontractor's workmen as well as the general public from hazardous conditions.
MECHANICAL SPECIAL PROVISIONS
15010-4
�
������,��rU��G°t� ����;!U'S���
; ` ii��� C��liu � � `� U
� �� � M �r
�' ��o l7`����'V:��Wp U o
�
Contractor shall comply with the applicable provision of all Texas and U.S. Department of labor
safety and health standards and amendments.
�
I. Welding or torch cutting operations may be done only in approved incombustible areas if possible,
or shall include adequate precautions as approved to prevent sparks dropping on combustible
material. Protection shall be provided over persons working underneath or nearby.
�
L�J
�
J. Contractor shall properly flame-proof and securely tie all tarpaulins and provide vertical shoring to
form a rigid frame wherever they are used. Temporary coverings shall be removed as soon as
they have served their purpose or when permanent closures have been installed.
K. Gasoline, oils and other volatile liquids shall be stored outside the building and brought into the
building in small quantities when needed. Such materials shall be stored in a well ventilated
location, spaced not less than twenty (20) feet away from all open heating devices or other
hazardous devices. Contractor shall take particular care in all storage space to eliminate spilling
or the accumulation of oily wastes, and shall provide approved waste and safety cans and
dispensing pumps.
1.16 STORAGE OF MATERIALS
A. The Contractor shall be responsible for the transportation of his materials to and on the job, and
shall provide space for storage of his materials and equipment at ground level. Roof surfaces
shall not be used for storage of materials or equipment. Any storage within the building shall be
approved by the Engineer prior to use of the space, with due consideration to fire hazards
involved.
Pipe, fittings, or other material stored outside of buildings shall be set on wood or steel racks or
platforms at least 12" above grade. All necessary provisions shall be made to keep water and
debris away from such stored materials. Ends of pipes and valves shall be kept sealed until used.
f:
Equipment subject to rusting shall be kept warehoused until just prior to setting.
C.
D. Each Contractor shall remove from time to time all equipment, unused material, rubbish and
.� debris of any kind which may accumulate during the execution of the work. All premises,
including the outside area, shall be kept clean and free from unnecessary impediments, rubbish
and debris at all times.
�
l�Y,
�..�
�
1.17 LOCATION OF OUTLETS
A. The locations of all pipes, outlets, appliances, etc. shown on the plans, if not specifically
dimensioned are approximate only, and understood to be subject to minor revisions as may be
found necessary or desirable at the time work is installed.
6. Generally, all outlets shall be properly centered in rooms, panels, and other finished work, shall
not intertere with outlets or equipment of other Contractors, and shall meet the dimensioned or
large scale architectural drawings.
1.18 CLEANING, TESTING, AND ADJUSTING, GENERALLY
A. The Contractor shall at his own expense, during the progress of the work, or upon its completion,
make such tests of his work as hereinafter specified under the various sections, as required by
the Engineer and under his supervision. -,
MECHANICAL SPECIAL PROVISIONS
15010 - 5
������� OG�� ��C�C�u�D
� o�' ���''�� ° c li
I(�a ��L`��Wy U15W.
�_
�
� B. The Contractor shall furnish all necessary labor, fuel, electricity, apparatus, piping, etc., as
� required for tests. The Contractor shall take all precautions necessary to prevent damage to the
building during tests, and he shall be liable and pay for all damage incurred during the tests.
• C. All leaks and defects discovered by the tests shall be immediately repaired or replaced and tests
�� conducted over until tests prove the systems are satisfactory. No �aulking of threaded piping or
.R
any accelerated rusting of any piping will be permitted to stop leaks.
1.19 IDENTIFICATION OF PIPING AND EQUIPMENT
F A. All items of major mechanical equipment, such as boilers, chillers, pumps (all types), air handling
� units, A/C units, fans, etc., shall be provided with plastic laminated nameplates, engraved with
same designation as appears on the drawings.
� B. Each motor starter, contactor, pushbutton station, control relay, disconnect switch (where not
immediately adjacent to and/or obviously related to any of the foregoing), and all similar electrical
and/or other control devices shall be provided with an approved metallic or plastic laminated
� nameplate, engraved with the name, horsepower, voltage, phase, and/or other special
characteristic of the equipment served. Nameplate names shall correspond to those used on the
drawings.
� C. All piping (both insulated and bare) shall be banded as to service and characteristic on 20 foot
centers and/or as directed. Directional arrows, not less than 1/2" wide and not less than 6" long
shall be permanently stenciled or affixed to each line at each code band. Arrows and stenciling
�, shall be so located as to be clearly visible by a person standing on the floor or adjacent service
platform.
� D. Valves shall be identified as specified under SECTION 15100 - VALVES, STRAINERS &
UNIONS.
1.20 ROOF PENETRATIONS
All roof penetrations shall be provided with base and counterflashings arranged to provide a
� weathertight installation, which shall include, where required, -ventilating collars to give proper
clearance from combustible roofs, floors, ceilings, etc.
�,
r
�.-:
1.21 ELECTRIC MOTORS AND CONNECTIONS, GENERALLY
A. All motor horsepower ratings :called for on the plans or in these specifications are minimum
acceptable ratings based on the original design and on the use of the equipment exactly as
detailed or specified. Any change in motor size brought on directly or indirectly by substitution of
equipment having characteristics peculiar to itself requiring such change shall be the responsibility
of the Contractor furnishing the motor, unless the substitution was initiated by the Owner.
r
B. The responsibility of the Contractor as mentioned above shall include the furnishing and installing
of the proper size motor and drive, subject to the approval of the Engineer and free of any
additional cost. It shall also include responsibility for any increase in electrical equipment and
�
installation costs; over and above that required to comply with the original design.
C. The Contractor furnishing the motor shall install it, and shall furnish all starting and control
� equipment, except that specifically noted to be furnished as an integral part of electrical
switchgear or motor control centers. Each and every motor shall have a starter with overload and
undervoltage protection. Except as otherwise specifically indicated, each starter shall be provided
�� with a heavy-duty pushbutton station. ___,
L��I��J'� ��`�_� u�<��'''�`�;'��,:�'
MECHANICAL SPECIAL PROVISIONS r,��,y� �j��rG���,�1`^,y9
15010-6 j GU Il lf
'- -. U Ua VVG,GIII U�JF li �il3o
�
1.22 OPERATING INSTRUCTIONS
A. At the completion of the work, the Contractor shall deliver to the Owner complete operating
instructions and maintenance brochures as hereinafter described.
B. The operating instructions and maintenance brochures shall consist of a typewritten description of
'' system operation, including necessary diagrams, keyed to the valve and piping identification
systems, and shall include the various operating instructions as received with each piece of
equipment.
L.
C
�
Operating instructions shall be bound in pressboard covers secured with "Acco" fasteners.
The project will not receive final acceptance until the operating instructions and maintenance
brochures have been received by the Owner.
E. The Contractor shall instruct the Owner's operating personnel in the proper operating and
~ maintenance of the equipment and systems for a period of not less than two (2) day of not less
than eight (8) hours. One (1) day of instruction shall be timed to include a normal seasonal
changeover.
��
�
�
r
1.-.
.�
r�,
r
�
�
1.23 RECORD DRAWINGS
A. The Contractor shall secure and pay for a complete set of prints of the drawings of his part of the
work. As the work progresses, the Contractor shall mark any and all corrections on the prints,
clearly indicating actual changes from the original drawings. Alternatively, the Contractor may
request and pay for electronic drawing files (unsealed) for record drawing purposes.
B. The Contractor shall deliver neatly corrected prints or electronic drawing files to the Engineer
upon completion of the work. Final approval of the installations will not be given until these sepias
or files and prints have been received and accepted by the Engineer.
C. Drawings shall indicate clearly the actual location of piping, valves, ductwork, and equipment.
1.24 INSPECTIONS
A. The purpose of the inspection is to determine whether the Contractor is performing the work in a
proper and workmanlike manner, that he is apparently installing the work in accordance with the
intent of the drawings and specifications and that in the Engineer's opinion, the work is
satisfactory.
B. It shall be the duty of each Contractor to personally make a special inspection trip of the whole
project and assuring himself that the work on the project is ready for final inspection before calling
upon the Engineer to make a final inspection.
C. In order not to delay finai acceptance of the work, each Contractor shall have all necessary
bonds, guarantees, receipts, affidavits, etc., called for in the various articles of this specification,
prepared and signed in advance, and together with a letter of transmittal, listing each paper
included, shall deliver same to the Engineer at or before the time of said final inspection. The
Contractor is cautioned to check over each bond, receipt, etc., before preparing same for
submission to see that the terms check with the requirements of the specification.
MECHANICAL SPECIAL PROVISIONS
15010 - 7
z
����[�0'���� ����,� c� �, �
,
II`; �' U Ur C'�����; �1��,'bil�`U I
c�� �-��.��:�ao ��1�0
1.25 SUBCONTRACT AND LABOR
�..
�
�
A. All provisions of these "General Provisions" shall apply to all subcontracts to the extent that they
are applicable.
B. Engineer's written approval shall be obtained for each subcontractor awarded any major
subcontract. The Contractor will be held fully responsible for any acts or omissions of any
subcontractors or suppliers.
1.26 WARRANTY
�..
�
A. In addition to the warranties on the individual items of new equipment, this Contractor shall
warranty all new equipment and workmanship for a period of twelve (12) months from the date of
acceptance as defined in the Supplementary Conditions.
B. If within the warranty period, such equipment or work performed under this contract is found to be
defective in material or workmanship, it shall be replaced or repaired free of any additional
charges.
1.27 INTENT
� It is intended that this speciflcation provide a complete installation. All accessory construction and
apparatus necessary and/or pertinent to the operation and testing of the work shall be included.
� The omission of specific reference to any part of the work necessary for such complete installation
shall not be interpreted as relieving this Contractor from furnishing and installing such parts.
�..
�
I�
F,
..
�
�
�
PART2-PRODUCTS
2.01 STANDARDS FOR MATERIALS AND EQUIPMENT
A. It is the intention of these specifications to indicate a standard of quality for all materials and
equipment incorporated in this work. Manufacturer's names and catalogue numbers are used to
designate the item of equipment or material as a means of establishing grade and quality. Where
several manufacturers are named, only those named will be considered and the Contractor's bid
shall be based on their products. Named manufacturers, although acceptable as manufacturers,
must prove their product will perform satisfactorily and will meet all requirements, etc.
B. Where the "or approved equal" clause is used in these specifications, the name, or names,
mentioned are to be used as :a basis of quality. Other manufacturers may be used if, in the
opinion of the Engineer, the quality of the proposed material is equal to that of materials named.
Such unnamed manufacturer's products will, however, be considered as substitutions and shall
not be used as basis for bidding. Requests for such substitutions shall be made in writing, and
require written approval of the Engineer.
C. The term "no equal" in the specifications or on the drawings indicates that material and equipment
shall be furnished exactly as specified.
D. The term "match existing" in the specifications or on the drawings indicates that material and
equipment shall be exactly the same as existing, if available. If no longer manufactured, then it
shall be similar in design and operation.
E. Basis of quality shall be interpreted to include material, workmanship, size,
gauges of material, appearance, pertormance, etc.
weight, finishes,
r�. I} I{��,�I�, .-� ^ ,lC,���
��!I�;�I�I��,�.�II�:!� U'_LS��:,f���llcL�i�
MECHANICAL SPECIAL PROVISIONS ,_�� rN���� � eM
15010 - 8 ',.� � y e� �rU1 U
� ?� U u'��p ��o
�
�
Manufacturer representation as to availability of equipment, parts and replacement and service
personnel in the area will be a factor in consideration of submittal. .
F
All materials shall be new, unless otherwise shown or specified, and of quality grade, standard
manufacture and first class in every respect. Material shall bear the label of the NFPA, NEMA,
U.L., etc. where such standard has been established for the particular item of equipment used.
G
� H. Naming a manufacturer, brand,or model number as part or all of the description of manufactured
items shall be deemed to include any description or specifications of such items in that
manufacturer's catalogues, advertisements or other representatives. Should there be
contradictions or variations in that manufacturer's literature currently available, the better quality of
, material or workmanship shall be furnished under this contract.
�.
2.02 ELECTRIC MOTORS, GENERALLY
A. Electric motors shall be "high efficiency" design, and of the size, speed, phase, and voltage
specified and of the type recommended by the motor manufacturer for the service intended.
� B. Unless otherwise specified, all motors 1/4 horsepower and larger shall be designed for 50°C. rise
in 40°C. ambient, provided with an open drip-proof frame, and shall have a guaranteed continuous
�� capacity of 115% of rating. No motor shall be installed where the actual or projected imposed
� load exceeds 100% of rating. Motors provided for use with variable-frequency drives shall be
specifically rated as suitable for that application.
C. Unless otherwise specified, all motors smaller than 1/4 horsepower shall be constructed to NEMA
standards for service intended, the standard catalogued product of an approved motor
manufacturer, and the type normally furnished by the equipment manufacturer as an integral part
of his equipment.
D. Bearings for motors 1/2 horsepower and larger shall be 200,000 hour grease-lubricated ball
bearings, conservatively rated for long life at maximum load conditions, and provided with alemite
fittings. Motors in inaccessible locations shall have grease fittings extended to provide easy
service.
E. Bearings for motors smaller than 1/2 horsepower shall be 10 year grease-lubricated, sealed ball
bearings unless otherwise specified. (This requirement is not intended to prohibit a manufacturer
from furnishing an approved different type of bearing that is standard with his equipment, subject
to approval.)
F. Motors 1/2 horsepower and larger shall be NEMA Design B, with Class B insulation, and unless
otherwise specified shall be 1750 RPM.
�
G. Motors smaller than 1/2 horsepower shall be provided with automatic reset thermal overload
protection, and unless otherwise specified shall be 1750 RPM. Motor starting shall be capacitor
type, except that split-phase starting may be provided for motors smaller than 1/6 horsepower.
..�, H. Motors located in hazardous areas or driving equipment handling hazardous materials shall be
explosion-proof. Motors exposed to the elements shall be raintight. Motors subject to potential
`° water damage (such as at pumps) shall be splashproof.
�"�
The nameplate horsepower of the driving motor shall be not less than the brake horsepower
requirement of the driven machine. Motors over 40 horsepower shall be 6-lead type, suitable for
wye-delta reduced voltage starters.
MECHANICAL SPECIAL PROVISIONS
15010 - 9
,
�;���i�i'� 0�� i� ����GuG, U
, � J _ �.
�-�� ���''�°?i�1�6 ���
Ur�o ➢U�:/�,�!!�UUp �ISUU. .
�
J.
�
� K.
r�
�
�
�"'
L.
�.
�
�
�
�
�
�"
�
�
�
F
It is preferred that all motors be of the same manufacturer. All motors of the same horsepower
rating, except those furnished as integral parts of factory assembled equipment, shall be of the
same manufacture.
Except as otherwise specifically noted, all motors shall conform to the following:
1
�
Larqer than 1/2 Horsepower:
(a) 480 Volt
(b) Three Phase
(C) 60 Hertz
1/2 Horseqower and Smaller:
(a) 120 Volt
(b) Single Phase
(c) 60 Hertz
Minimum acceptable efficiency and power factor ratings under full load conditions shall be as
follows:
HP
1
1.5
3
5
7.5
10
15
20
25
Larger
2.03 MOTOR STARTERS
% Efficiencv
82
83
84
85.5
87
88
89
89.5
90
91
91
°/o Power Factor
84
85
85
86
87
87
88
88
88
88
88
A. Starters for singie phase non-electrically interlocked motors within fifty (50) feet developed length
of the switching point shall be flush-mounted single or double pole switches as required, with red
filament type pilot lights and stainless steel face plates, equal to "Allen Bradley" #500-TQX216, or
"Square D" #FS-1 P.
B. Starters for single phase electrically interlocked motors, single phase non-electrically interlocked
motors more than fifty (50) feet developed length from the switching point and/or three phase 480
volt motors up through 40 horsepower, shall be one, two, or three pole, 60 Heriz, 600 volts,
across the line magnetic contactors, with thermal overioad protection on each qhase when used
with momentary contact pilot devices or undervoltage release when used with maintained contact
pilot devices.
C. Starters for 480 volt, 3 phase motors larger than 40 horsepower, shall unless othenNise noted, be
60 Hertz, part-windina reduced inrush increment magnetic contactors, with general purpose
enclosure, thermal overload protection on each phase, and undervoltage protection when used
with momentary contact pilot devices or undervoltage release when used with maintained contact
pilot devices. Starters shall contain a definite adjustable time-delay relay to transfer from start to
run connection.
MECHANICAL SPECIAL PROVI510NS
15010 - 10
���
��I1 �.r1I . �,,
��-;!I��- N '' �'�' i�;ii��l��,'����
�d �fu'�;UG��� J�I��,�In_Lr
��� � V li c����r U� s e h�
'��o �IuG'��IP ��o
�
�
�
�
�
�
�
�
�
�
�
�
D
E
F.
G
H
I .
J.
Starters for voltages other than 120 or 480 shall be as separately specified hereinafter.
All magnetic contactors shall have 120 volt holding coils, and those operating at voltages above
120 shall be furnished with individual control transformers.
All electrically interlocked starters shall be furnished with "hand-off-automatic" switches in the
enclosure cover.
Starters installed outside the building, or otherwise exposed to the weather, shall be furnished with
weather-resistant NEMA Type 3 enclosures, in lieu of general purpose type.
Starters installed in hazardous locations or as otherwise indicated, shall be provided with Class 1,
Groups C or D, NEMA Type 7 enclosures, in lieu of general purpose type.
All starters of any one type shall be of the same manufacture.
Starters furnished as integral parts of factory-assembled pre-wired equipment, or special starters
for large equipment such as water chilling units, shall conform in general to the above
requirements, as they may be applicable in the opinion of the Engineer.
K. Variable speed motor controller starters shall be fully compatible with the motor(s) served so as to
prevent frequency noise. Variable speed motor controller starters shall each be solid-state pulse-
width-modulated type, factory-assembled and tested, UL labeled device, arranged to provide
infinite controi of alternating current frequency from at least as low as 6 Hertz to at least as high
as 60 Hertr, in response to either an external signal (electrical or pneumatic, as appropriate) or a
manually adjustable setpoint device in the event automatic control is not called for. Construction
shall be similar and equal to "Reliance Electric" Model A-C V-S, and shall include but not be
limited to the following:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
Output contactor with overload protectors on each phase leg
115 volt control transformer
Adjustable current limiter
Automatic shutoff devices
Line transient protection
Voltage, current, and frequency meters
Relay contacts as necessary for interlock and signal functions
Acceleration and deceleration at approximately 20 seconds
Starting torque at 100% full load torque
NEMA enclosure suitable to the installation location
Ground fault protection
Output short circuit protection
Output line filters
Manual bypass with magnetic contactors
2.04 PUSHBUTTON STATIONS
A.
c�
Except as otherwise specifically indicated, each pushbutton station shall be rated for 10 amperes
continuous load at 600 volts or less.
Enclosures shall be general purpose NEMA Type 1, except that pushbutton stations installed
outside the building or otherwise exposed to the weather shall be duct and weathertight, NEMA
Type 7. Enclosures shall be provided for surface mounting, except as otherwise indicated.
MECHANICAL SPECIAL PROVISIONS
15010 - 11
'�����'GO�:� ���C�'�'�'
r0�1 ��'GG� ' °�l
�o �'��'��o ���.
C. Pushbutton stations for non-interlocked contactors shall be momentary-contact type with start
� button, stop button, and red indicator light. Where required for delayed "seal-in", or otherwise
noted, pushbuttons shall be maintained contact type.
� D. Pushbutton stations for electrically interlocked contactors shall be provided with "hand-off-
automatic" selector switches, and both red and green indicator lights.
�"' E. Pushbutton stations requiring other special features shall be provided as required or otherwise
indicated.
2.05 DRIVES
�
E'"�
�
�
A. Except as otherwise noted, motor drives shall be V-belt type, matched and provided with a slide
rail base for mounting the driver.
B. Drives of 10 horsepower and under shall be rated at 1.2 service factor (120% maximum
horsepower at the given drive speed). Drives above 10 horsepower shall be rated at 1.4 service
factor.
C_ Motor sheaves shall be adjustable-pitch for motors 7-1/2 horsepower and smaller, and fixed-pitch
for larger motors.
2.06 SLEEVES
Unless otherwise indicated on the structural drawings, all pipe sleeves installed in the vertical
position shall be constructed of 26 gauge galvanized steel. All pipe sleeves in the horizontal
position shall be constructed of standard weight steel pipe or extra heavy cast iron pipe.
2.07 ESCUTCHEONS
Escutcheon plates shall be chrome-plated, cast-brass, set-screw held type, similar and equal to
"McGuire" #127.
p� 2.08 IDENTIFICATION OF PIPING AND EQUIPMENT
A. Banding shall be 1" wide plastic tape installed with a minimum of 2" overlap.
B. Stenciling shall be paint, as indicated, with letter sizes as appropriate or as directed by the Owner,
� but not less than 1" high. .
�
�
C. Directional arrows shall be same color as stencil cofor.
D. For pipe identification, Contractor shall use "Seton" SETMARK Type SNA snaparound pipe
markers. Adhesive backed, stick-on pipe markers are not acceqtable.
E. One set of inetal interlocking stencil letters and numbers shall be turned over to the Owner at the
completion of the job.
� F. Nameplates for mechanical equipment, motor starters, contactors, etc., shall be 1/8" thick
engraved laminated plastic type, "Setonite" or equal, drilled for boltinq to the face of the respective
� enclosure. Letter sizes and arrangements shall be per details on the plans.
�
MECHANICAL SPECIAL PROVISIONS
� 15010 - 12
,
��� ����a�.a�� ���cc�a�
�I��� ��I�G� 6 e�
� r ����
' �d:ti�p �� �
2.09 YEAR Z000 CONFORMITY
�"° A. The Contractor shall warrant that any system (includinq, its associated hardware, software, and
firmware) and each hardware, software, and firmware product delivered under this contract shall
� provide Year 2000 conformity. Year 2000 conformity shall mean that neither performance nor
functionality is affected by dates prior to, during and after the year 2000. In particular (1) no value
for current date wili cause any interruption in operation; (2) date-based functionality must behave
�� consistently for dates prior to, during and after year 2000; (3) in all interfaces and data storage,
the century in any date must be specified either explicitly or by unambiguous algorithms or
inferencing rules; and (4) Year 2000 must be recognized as a leap year. The Contractor further
shall further warrant that any system, component, hardware, software or firmware product that is
� found not to meet Year 2000 conformity or that fails as a result of not meeting Year 2000
conformity shall be upgraded, repaired, or replaced solelv at the Contractor's expense. Nothing in
� this warranty shall be construed to limit any rights or remedies the Owner may otherwise have
under this contract with respect to defects other than Year 2000 performance.
�
�
�
��
PART 3 - INSTALLATION
3.01 WORKMANSHIP
A. All workmanship shall, in all respects, be of the highest grade, and all construction shall be done
according to the best practice of the trade. Work shall be done by mechanics experienced and
skilled in the trade involved. All work shall be completed to the entire satisfaction of the Engineer,
and only when in a finished, undamaged and clean state.
B. Location of all pipes, ducts, outlets, appliances, etc., as shown on the drawings, are approximate
only and are understood to be subject to such reasonable revisions as may prove necessary or
desirable at the time the work is installed. Contractor will be required to install his work with
relation to building conditions and shall be entirely responsible for the correctness of his work with
reference to finish elevations, etc. Exterior utilities shown on the drawings are diagrammatic only
and their exact locations, depth and invert elevations shall be as required for proper flow and
coordination with other areas.
►' C. The drawings show the arrangement of piping and ductwork. Should project conditions indicate
the piping or ductwork can be installed to better advantage in a different manner, the Contractor
shall before proceeding with the work, prepare and submit five (5) copies of drawings of the
proposed arrangement for the Engineer's review and written approval.
�`'" D. If the Contractor proposes to install equipment, including piping and ductwork, requiring space
conditions other than those shown, or to rearrange the equipment, he shall assume full
� responsibility for the rearrangement of the space and shall have the Engineer review the change
�- before proceeding with the work. The request for such changes shall be accompanied by
drawings of the space in question.
r
E. Contractor is responsible for the proper location and size of all slots, holes or openings in the
building structure pertaining to his work, and for the correct location of pipe sleeves.
F. This Contractor will be held responsible for the timely placing of all materials and equipment in a
�`' thorough, substantial and workmanlike manner.
� G. Except for necessary connections to equipment and fixtures, Contractor shall not install piping of
any kind exposed to view at the building exterior or in occupied spaces without Engineer's
permission. Where exposure is necessary, Contractor shall hold such work to a�+�n�-�um,
� installed with good practice.
�;�;i��������:� �'����G��
MECHANICAL SPECIAL PROVISIONS i;�C�' c��i� eJ e eti�
15010 - 13 �a ��.�,��M� 5��/0
._.., Y�Q��JU' W �15W
�
� 3.02 ELECTRICAL WORK
A. The Mechanical Contractor shall furnish motors, motor starters, firestats, remote switches, pilot
� lights, and control panels as specified elsewhere herein. The Mechanical Contractor shall set
motors in piace and shall furnish the starters, firestats, switches, and pilots to the Electrical
Contractor together with all necessary wiring diagrams and instructions. All power wiring and
�` equipment start-stop switch wiring will be done by the Electrical Contractor under his Contract.
B. The Electrical Contractor shall furnish and install required disconnect switches for equipment.
The Mechanicai Contractor shall coordinate with the Electrical Contractor as to location of the
disconnects so as to avoid damage to the equipment and preserve adequate access to all
removable panels, etc., and shall furnish mounting brackets if and as required for a workmanlike
installation.
�
�
�
�
r^
C. All temperature control wiring shall be included under the Mechanical Contractor's Contract.
Wiring shall be in accordance with applicable portions of DIVISION 16. Where equipment
switching is integral with temperature controls, such wiring shall also be included also under the
Mechanical Contract. Wiring shall be in conduit inside walls or building components, above
ceilings, exposed inside buildings or on roof, or outside buildings.
D. Each applicable trade shall prepare a list of all electrical consuming items being installed in the
project under this contract, which lists amps, volts, phase, etc., of each piece of equipment or
electrical device. Such lists shall be formally transmitted to the Electrical Contractor, who shall
verify electrical service provided to each item and who shall immediately notify the Engineer of
any discrepancies. Reasonable adjustments in branch service sizes, if required, shall be made
without an addition to the contract amount. Coordination shall be completed prior to finalizing all
equipment and material purchases which could be affected for this project.
3.03 PRECAUTION AGAINST NOISE AND VIBRATION
The Contractor shall take the utmost precautions in the installation of his equipment, piping, and
systems to prevent noise and vibration transmission.
A.
Equipment that would tend to cause noise or vibration shall be isolated to prevent noise
transmission to the building or to other equipment.
�
� C. Piping, conduit, etc., connected to equipment shall be isolated. The Contractor shall be
responsible for the prevention�.of noise and vibration transmission through his connections to
equipment.
� 3.04 DRIVES
4► A. All sheaves sha�l be properly aligned.
B. Belts shall be installed with correct take-up allowance, and with equal tension on all belts of a set.
Belts shall be readjusted as required after belts have been fully seated and "run-in".
i`' C. Direct drive e ui ment shall be
q p properly aligned. Flexible couplings shall not be used to
compensate for misalignment. Factory aligned equipment shall be field checked for alignment.
� Alignment adjustments shall be made after grout has set, foundation bolts have been properly
tightened, and all piping, conduit, and wiring have been connected.
�
MECHANICAL SPECIAL PROVISIONS
� 15010 - 14
in..
'�v�,Gl���'�� `',� ��l��U��
�.=;� V% ������ a ��
Il��o V'�tl�.'�Vu9 UlSLVo
�
�
�,
L
�
n
E
Angular alignment shall be determined by inserting a tape gauge feeler at four points between
coupling faces.
Parallel alignment shall be determined by diai indicators.
F. After each unit with drive couplings has been running for not less than one week, coupling halves
shall be given a final check for misalignment caused by pipe or temperature strains. When
alignment is proven correct, both the equipment and its driver shall be doweled to base plate.
3.05 CUTTING AND PATCHING
A. The Contractor shall be responsible for all cutting and patching required for the proper installation
of his work, and shall obtain permission from the Engineer before doing any cutting. Cutting and
patching shall be done in such a manner that the surrounding work will be restored to its original
condition.
B. NO STRUCTURAL MEMBER MAY BE CUT WITHOUT WRITTEN PERMISSION FROM THE
� ENGINEER, and then only where and as directed by the Structural Engineer. If a structural
member is cut, the Contractor will be responsible for reinforcing the member as directed by the
Structural Engineer.
i...
�
r
ti...
�
C
D
When cutting and patching is done in occupied spaces within the building, the Contractor shall
provide a dust-tight enclosure and any other necessary protection around his operation in order to
protect equipment and finishes.
Openings cut through the roof or exterior walls shall be provided with a temporary watertight cover
during construction or until equipment or repair has been made.
3.06 PAINTING
A.
�
Materials and equipment not concealed shall be painted. Painting shall be as specified in
"Painting" Section of these specifications.
Items and materials shall be thoroughly cleaned of dirt and grease by this Contractor before
application of paint.
C. Items with factory applied enamel painting shall be protected during installation and other
construction work. Damaged factory applied finishes shall be repainted by the installing
contractor. Sceatches to factory applied finishes shall be sanded smooth before repainting.
D. All work performed under this contract shall be painted as hereinafter specified.
E. All insulated equipment not canvas covered, and all uncovered piping, hangers, ducts, equipment,
iron work, etc., in finished rooms, including all mechanical equipment areas, or outside building
where exposed to view, shall be painted one (1) coat of an approved metallic primer suitable for
this class of work, and two (2) coats of semi-gloss paint, color as selected by the Engineer.
Ductwork visible in back of Qrilles shall be painted black. All uncovered work in concealed spaces
above floor line, such as pipe chases or attics above ceilings shall not be painted.
F. All exposed canvas covered work, including that in all mechanical rooms or equipment areas shall
be painted one (1) coat of approved size and two (2) coats of paint.
MECHANICAL SPECIAL PROVISIONS
15010 - 15
� ���G�D� 8�:� ��[�C�GG��
���11 b� d'��:;V� ° ° Y
�r ua 1��� `:'�Ip ��.
G. All other concealed canvas covered insulation, including that under floor, in pipe chases or attics
above ceiling, shall be painted one (1) coat of sizing, and two (2) coats of "Talcote" #070, or equal
asphalt emulsion damp-proofing.
�
I'`
�
�
3.07 IDENTIFICATION OF PIPING AND EQUIPMENT
A. Location and color of equipment stenciling shall be appropriate for ready identification, readable
from a normal position standing on the floor, and/or as directed by the Engineer. Letter sizes shall
be as approved by the Engineer, but not less than 1" high.
B. Nameplates shall be bolted to the face of the respective enclosure. Adhesive systems of
attaching nameplates are NOT acceptable.
3.08 COOPERATION
Each Contractor shali cooperate with the General Contractor and all other Contractors to
coordinate the respective work properly, avoid interference and delays, and to arrange all parts of
the work so as to harmonize in service and appearance with all other parts.
3.09 INTERFERENCE
� The plans are generally diagrammatic, and the Contractor must harmonize the work of the
different trades so that interference between their work and the architectural and structural work
� will be avoided. All piping, ductwork, and electrical raceways shall be installed as close as
possibie to walls, floors, columns, ceilings, and beams, and offsets or special fittings shall be
installed as required to accomplish this end whether or not shown on the plans.
L�
�
3.10 PRECEDENCE
The mechanical and electrical work shall have precedence over each other in the following
sequence:
Soil and Waste Piping
Storm Drainage Piping
Ductwork
Chilied & Heating Water Piping
Plumbing Water Piping
Fire Protection Sprinkler Piping
Gas Piping
Electrical
A.
B.
C.
D.
E.
F.
G.
H.
� 3.19
�
HOISTS, SCAFFOLDS, AND TOOLS
Each Contractor shall provide or arrange for his own scaffolds, hoists, derricks, tools, and labor as
necessary for the complete installation of the work under his contract.
3.12 TRADE RESPONSIBILITY
`' Except as otherwise specifically noted, it is not the intent of this specification to establish limits of
responsibility between trades as to work which may or may not be performed under a subcontract
� to the Contractor awarded a contract for this project. The terms "the Contractor", "this
Contractor", etc., shall in all cases be interpreted to mean the Contractor as defined in the
GENERAL CONDITIONS.
�
MECHANICAL SPECIAL PROVISIONS
15010 - 16
�
� ^�����6� �1�� ����'��D
':�: �l�ti'' ���'� �' ° °`�
��a UU�:J�'�Ullp ��JJo
�
C
�
3.13 ASBESTOS CERTIFICATION STATEMENT
It is the intent of all contract documents, whether expressly stated or not, that no material
containing asbestos shall be incorporated into the project. Each Contractor shall exercise every
reasonabte precaution to insure that asbestos-containing materials are not incorporated into any
portion of the project, including advising all materials suppliers and subcontractors of this
requirement. At project close-out, each Contractor shall submit a certification that, to the best of
his ability and knowledge, no asbestos-containing materials have been used.
3.14 LEAD FREE CERTIFICATION STATEMENT
� It is the intent of all contract documents, whether expressly stated or not, that no material
containing lead and having to do with potable water shall be incorporated into the project. Each
Contractor shall exercise every reasonable precaution to insure that lead-containing materials are
� not incorporated into any portion of the project, including advising all materials suppliers and
subcontractors of this requirement. At project close-out, each Contractor shall submit a
certification that, to the best of his ability and knowledge, no lead=containing materials have been
� used.
�
'
�
L_�
�
r
�
�
�
END OF SECTION
MECHANICAL SPECIAL PROVISIONS
15010 - 17
! :�:°;�� =�', ,` ,�'�C�'Jf°��
, u ::: i�:���_ 1,:
i��-i,��' ��,�;i�Y�ej � e��
.:�.f J C�:v u
���: ��'�J"�G�, ���.
SECTION 15060
PIPING
�
�
�
�...
�
�
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of Contract, including General and Suppiementary Conditions
and Division 1 Specification Sections, apply to this Section.
1.02 SCOPE
This section of the specifications includes all labor and materials required for the complete and
finished installation of the following piping systems:
A. Chilled Water Cooling
B. Condenser Water Circulation
1.03 RELATED WORK SPECIFIED ELSEWHERE
A. Valves, strainers, & unions
B. Insulation
C. Heating and air conditioning equipment and accessories
D. Material storage and handling
PART 2 - PRODUCTS
2.01 PIPE
Pipe for the various systems shall conform to the following:
A. Condenser Water and Chilled Water Piping: Black steel; Schedule 40 through 10" size, standard
weight for 12" and larger.
2.02 FITTINGS
Fittings for the various systems shall conform to the following:
A. Condenser Water and Chilled Water Piping:
1. Size 2-1/2" and larger - welded black steel, same weight as piping.
2. Under 2-1/2" size - screwed black malleable iron, standard weight.
��C��8�0(�.� �?�C �G�D
�.p� ��cG��° �`�
�o ��?��9 ��c�o �
PIPING
15060 - 1
L.
�
PART 3 - INSTALLATION
�
� 3.01 CONDENSER WATER AND CHILLED WATER PIPING SYSTEMS
` A. This Contractor shall furnish and install complete systems of condenser water and chiiled water
. piping as indicated on the plans, interconnecting new equipment and piping with existing.
B. Mains shall be pitched upward not less than 1/8" per ten (10) feet in the direction of flow, unfess
� specifically noted otherwise on the drawings. Branch connections to mains shall be taken out of
bottoms of mains at an angle of not less than 45° down, and are to pitch up to mains not less than
. '/z" per foot. The high points of each main, and other points indicated on the plans or where
required for remaval o� air from the system, shall be automatical{y vented in an approved manner
" with float operated air vent valves. Vent valve discharge lines shall be run to the nearest floor
„ drain, or as otherwise directed.
3.02 PIPING, HANGERS, SUPPORTS, ETC., GENERALLY
A. All piping shall be installed parallel or perpendicular to the lines of the building, unless distinctly
shown or noted on plans otherwise. Spacing of lines shall be such as to provide not less than 1"
clearance between finished coverings on the various services.
B. This Contractor shali furnish all foundations, hangers, or supports for the work installed.
'1. All suspended drainage piping shall have supports not more than 5' on centers.
2. All suspended piping shall have supports not more than 5' on centers for sizes under 2",
and not more than 10' on centers for sizes 2" and larger.
C. Supports to walls shall be made with "Molly" bolts.
D. Perforated strap hangers shall not be used for any work.
E. lnsulation protection saddles, as specified hereinafter, shall be used at the following locations:
1. At pipe hangers on insulated chilled water lines.
2. At trapeze hangers on any insulated piping.
3. At pipe rollers or othec framed suppo�ts on any insulated piping.
F. Hangers for piping shall be adjustable split ring malleable iron similar and equal to "Fee & Mason"
No. 199, or steel clevis type similar and equal to "Modern" No. 590, with threaded rod and
turnbuckle in rod where hanging height permits. Except as otherwise specified, hangers shall be
sized to fit the pipe.
1. Hangers shall be sized to fit the outside diameter of the pipe insulation on chilled water
piping.
...
G. Trapeze hangers may be used for multipfe parallel runs where specifically indicated on the plans,
�` or elsewhere with permissio� of the Engineer.
H. The openings of all pipe shall be capped during construction. All steel pipe (exc�ui p��r,i�s,ulat �, _���r,Li
before installation, shall be stood on end and pounded to remove dirt and scale, a i«','��N'���I
� shall be properly reamed before joints are made up. ,,� ����i��,:�!� �� �'��
PIPING ',�'4:;��'����u5����` ��1a �
� 15060 - 2 `` .. :�
I. All piping shall be installed so as to allow for expansion and contraction using offsets, swing joints,
� etc., as shown or as may be required to prevent undue strain on piping.
Pipe shall be cut accurately to fit. No bending or springing of pipe will be permitted.
rr
3.03 PIPE JOINTS
A. Except as otherwise noted, joints in threaded piping shall be made only with best linseed oil and
graphite or with "Jointite" applied on the male thread only. The ends of pipes shall be square cut,
reamed, and wiped clean before being made up into fittings.
� B. Joints in welded piping shall be made up with factory fabricated welding fittings as specified above
� which shall include all elbows, tees, laterals, reducers, etc., and shall be "Tube-Tum", 'Taylor
Forge", "Ladish", or "Crane" full radius type, except that tees may be formed for lines 4" and larger
�"' connecting to lines 6" and larger by saddling branch into side and main and connection of lines 1-
1/2" and smaller into lines 2" and larger may be made with "Threadolets". All welding shall be
� done in accordance with standard practice, utilizing only fully qualified welders. All joints shall be
smoothly fitted before welding, and welding rod shall be specifically suited to the pipe material.
Flanges shall be weld-neck type, class to match valve, except #150 minimum.
r..� 3.04 CLEANING, TESTING, AND ADJUSTING
A. It is the intent of this section of the specifications to provide for the thorough cleaning of the
interior and exterior of all piping systems, and for all necessary tests during and at completion of
the job to insure tight piping and correctly balanced systems. This Contractor shall do any and all
work required to accomplish this end.
B. Before installation of pipe covering or final connection of units, all condenser water and chilled
water piping shall be tested under a hydrostatic pressure of 125 psig at the lowest point in the
system, with all air freed from the lines, and made tight at this pressure. Control valve elements,
instruments, or other equipment that may be damaged by this pressure shall be removed from the
system before testing. After completion of this test, the system shall be drained and final
connections made to the units.
C. All new strainers and fitters shall be cleaned after pressure testing and system cleaning
operations, and prior to final filling of systems.
D. All motors, bearings, etc., on all equipment shall be correctly oiled and/or greased with proper
lubricant before the equipment is operated, and again at completion of the job.
E. The Contractor shall conduct operating tests of all equipment and other apparatus installed by him
� to demonstrate to the Owner and the Engineer the satisfactory operation of same and the
fulfillment of the specified requirements. He shall make any additional tests that may be required
by other authorities.
END OF SECTION
�
r
���U�� ���� �?[��C � °�D
����' ��'�� ' °�
;r�� �������=�� ����
PIPING ' �4
15060 - 3 �pY'�
�
r
�
�'
I
ka
r�
SECTION 15100
VALVES, STRAINERS 8� UNIONS
PART 1 - u^ENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of Contract, including General and Supplementary Conditions
and Division 1 Specification Sections, apply to this Section.
1.02 SCOPE
This section of the specifications includes all labor and materials for the complete and finished
installation of the following:
A. Valves
B. Strainers
C. Unions
D. Valve Identification
1.03 RELATED WORK SPECIFIED ELSEWHERE
A. Piping
B. Insulation
C. Material Storage and Handling
D. Heating and Air Conditioning
1.04 SUBMITTALS
Submit manufacturer's certified rating data, descriptive literature, and catalogue cuts for all
proposed:
A. Valves
B. Strainers
C. Unions
PART 2 - PRODUCTS �.
2.01 VALVES, STRAINERS AND UNIONS
A. All valves, strainers and unions shall have the name or trademark of the manufacturer and the
guaranteed working pressure cast or stamped on the body, and all vaives of any one type shall be
of the same manufacture.
B. Unless othenNise specified or shown on the drawings, all valves shall be 125 psig, SWP, with
sizes 2" and smaller screw or solder end, bronze body, and sizes 2-1/2" and larger flange end,
iron body, or bronze trimmed.
� � ���� 0�� ���Cu °�D
�:; �� � ��� °�[�G?°�
VALVES, STRAINERS & UNIONS i�R' �p;����-,4iu1� ���'�o
15100 - 1 lr l 1'I�1 � W
�
�
C.
�
�
s
�,.,
�
Manufacturers' references given in the following table are to indicate a minimum standard of
quality and design only.
1
2
Gate Valves, Interior, General Service
Crane
Walworth
Globe Valves
Crane
Walworth
3. Ball Valves
� Crane
�..
Nibco
� 4. Swing Check Valves, General Service
Crane
Walworth
r�
�
�
D.
�
E.
5. Butterfly Valves`
Crane
Victaulic
Nibco
BRASS BODY IRON BODY
Fig.438 Fig.461
Fig. 4 Fig. 719F
Fig. 1 Fig. 351
Fig.58 Fig.906F
2180 or 2182
S or T-590-Y
Fig.37 Fig.373
Fig.406 Fig.920F
Fig.226-MMB Fig.23N-BRB
700/701
Fig. LD3144 Fig. LD005
*A total of two (2) operating handles for each size and/or type required shall be furnished for this
project.
Ball valves shall be used in all chilled water lines 2" and smaller, and gate valves for 2-1/2" and
larger, for general shut-off service.
The use of lug-wafer butterfiy pattern valves will be permitted at the option of the Contractor, but
shall be limited to chilled water or condenser water lines, for flow balance only, in lieu of globe or
plug pattern valves. Butterfly valves shall in all cases be rated for dead-end shutoff, and where
larger than 3" size shall be provided with wheel-handle gear-drive operators.
F. Strainers shall be iron or brass body with 20 mesh monel screens for water service. Strainers
``'° shall be wye pattern, similar and equal to "Crane" #988-1/2 with screw ends for 2" size and
smaller, and "Crane" #989-1/2 with flanged ends for sizes larger than 2". Each strainer 2" and
[�` larger shall be provided with a blow-off valve piped to a floor drain; 3/4" for up to 3" size; and 1-
��• 1/2" for 4" to 6" size.
�`" G.
�"` 2.02
� A.
�
Unions 2" and smaller shall be 300 psig, S.W.P., malleable iron screw end, with bronze seat ring,
similar and equal to "Crane" Fig. 198E or "Walworth" Fig. 7716. Unions 2-1/2" through 4" shall be
300 psig, S.W.P., three-part flanged unions, with self-seating bronze to iron ball joint, similar and
equal to "Walworth" 8301.
VALVE IDENTIFICATION TAGS
Valve tags shall consist of a bronze or brass disc not under 1-1/2" diameter, stamped with the
prefix "P" or "AC" followed by an identifying number not less than 1/2" high, "Seton" #250-BL, or
equal.
VALVES, STRAINERS & UNIONS
r 15100 - 2
4
�
,n����=�D�B�ud ��C�C��G�D
� : ��fi�' c���: G�� y °,`�
��� V"��_�UW� ����o
PART 3 - INSTALLATION
�
�
�.�
�
�Lr.,
,
�
��.
�
f`
3.01 VALVES AND STRAINERS
A. Valves, strainers, connections, etc., shall be provided wherever shown on the drawings, or
required for controlling the various portions of the work, furnished by other trades or by the
Owner, and including proper rough-in and final connection to such equipment. Each and every
fixture and item of equipment shall have controlling valves easily accessible from rooms or
through access panels.
B. Valves, strainers, etc., shall be installed in such a way as to facilitate operation and maintenance.
When installed in horizontal lines, valve stems, shall be vertically upward. Joints shall be made up
as specified for the corresponding piping. All isolation valves and disconnecting means shall be
located in such a manner that the isolated device (coil, tube bundle, etc.) can be physically
removed and replaced without shutdown or interruption of the piping system to which connected.
C. Each valve installed for balancing purposes shall have adjustable memory stops.
3.02 UNIONS
A.
B.
C.
No unions are to be placed in a location which will be inaccessible after completion of the building
unless specifically shown on plans or specified otherwise.
Unions shall be installed on each side of all special valves, regulators, etc., and one side of all
check valves, thermostatic traps and at all pieces of equipment such as pumps, heating units,
tanks, etc., so that such equipment may be readily disconnected.
Where joints are made up with bolted flanges or grooved mechanical couplings, separate union
fittings as such will not be required.
3.03 VALVE IDENTIFICATION
A. The Contractor shall attach to the handle of each valve installed an identifying valve tag.
Attachment of tag shall be by means of brass jack chain or brass "S" hook as appropriate for
valve size.
B. Valve tags may be omitted when the function of the valve is completely obvious, of secondary
importance, and immediately adjacent to and in plain sight of the equipment served, such as
lavatory supply stops, isolation valves at water coils, etc. Every valve used for flow-control
balancing, for system isolation, or in any other manner not completely self-explanatory, must be
tagged.
C
C
The number, location and purpose corresponding to each valve shall be listed in sequence,
properly typewritten on a schedule sheet and submitted to the Engineer for approval. The
approved schedule shall be framed under glass and mounted on the wall where directed.
All valve tag identification shall be indicated on the as-built drawings and a copy of the typewritten
schedule shall be included in the operation and maintenance manual.
END OF SECTION
VALVES, STRAINERS & UNIONS
15100 - 3
,
^ r �;�,,
�� i� :�'i V�,,t�: �15��.,�:iU��'v
'' -�;� �[�'GG� �° ce�
['i,� Vt���:��Wo ��ln1�
�.
�..
fi
�
SECTION 15180
INSULATION FOR MECHANICAL TRADES
PART1-GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of Contract, including General and Supplementary Conditions
and Division 1 Specification Sections, apply to this Section.
1.02 SCOPE
It is the intent of this specification that all piping and/or mechanical equipment installed shall
(except for obvious functional reasons or where otherwise specifically excepted herein) be
insulated whenever the exterior surfaces are or can be:
A. Above 125°F
B, Below average ambient dew point
1.03 QUALITY ASSURANCE
The Contractor shall cover all piping and apparatus as specified hereinafter or otherwise required
with insulation as manufactured by "Manville", "Armstrong", "Owens Corning", "Schuller", or equal.
1.04 WORK SPECIFIED ELSEWHERE
A. Factory-applied insulation of equipment
1.05 SUBMITTALS
Submit manufacturer's certified rating data and descriptive literature for all proposed:
A. Pipe insulation
B. Pipe insulating fitting covers
C. Equipment insulation
D. Mastic and sealants
1.06 INSULATION NOT REQUIRED
No field-applied insulation will be required for the following:
A. Chillers (factory insulation)
B. Condenser water piping
_ �
��f��CO�� ���C���D
�G� ����rG� ° °�
r�, ���,��!r'�{�! � 1 �`(�
INSULATION FOR MECHANICAL TRADES
15180 - 1
�.�
r PART2-PRODUCTS
�"� 2.01 PIPE INSULATION
� A. All chilled water lines shall be insulated with a molded sectional glass fiber insulation (4 Ib./c.f.
norn. densiry) with an "ASJ" vinyl-coated and embossed vapor-barrier laminated jacket. Fittings,
valves, etc., shall be insulated with wrapped glass fiber material and finished with "Zeston" or
'` equal PVC fitting covers. Insulation thickness shall conform to the following:
Chilled Water
� Service Thickness
� Chilled Water '/" - 1 YZ" 1 YZ"
2�� _ 6,� 2��
� 8"-Larger 2Y2"
�' B. Rigid urethane insulation may not be used in lieu of glass fiber.
� 2.02 FIRE AND SMOKE RATINGS
All insulation and insulation jackets (except foamed plastic and PVC covers) shall have UL Pipe
and Equipment Covering rating RSS83 U8.15, not to exceed:
�
A. Fiame Spread 25
�B. Fuel Contributed 50
C. Smoke Developed 50
�„ PART 3 - INSTALLATION
��� 3.0'1 PIPE INSULATION
A. Glass Fiber Insulation: The sections shall be applied to dry pipe and secured with the self-sealing
, butt and longitudinal lap of the jacket. Fittings, valves etc. shall be wrapped with glass fiber
i:�
C.
r�
�"!
material to an equivalent thickness and density to the pipe insulation, and finished with PVC
covers installed as directed by the manufacturer.
Insulation at strainers for chilled water supply and return lines shall be provided with removable
heads for strainer basket removal without damage to insulation or the strainer body. Exact
method of providing strainer access shall be subject to approval.
Protective metal 180° shields of galvanized steel, in sizes and gauges as listed below, shall be
installed on the lower half of all insulated lines, at each support point, and secured with two (2)
copper or aluminum wires or bands.
PIPE SIZE GAUGE OF METAL LENGTH OF SHIELD
1 /2" - 2-1 /2"
3" - 5"
6�� _ 8.,
10"-Up
18
16
16
16
6"
10"
14"
18"
INSULATION FOR MECHANICAL TRADES
15180 - 2
'^'���uCOQ� ����VG��
�r�r U\u c����:; el ° c� U
� �,, �V�''(�;�'���� u �iLo
�..
�
i.,.
�",
�
�
�
�
�
�
�
r•P
�...
3.02 INSTALLATION, GENERALLY
A. All sectional covering shall finish round and smooth without lumps or depressions, and all ends
and joints shall butt evenly and tightly together and to the covered surface. No damaged or
broken sections shall be used. Blocking shall be provided at pipe supports in all pipe insulation
exposed in occupied spaces, as required to eliminate crimps or depressions. When covering is
formed from blocks, they shall be carefully and evenly applied, securely wired in place, and joints
shall be closed with cement insulation.
0
C
❑�
�
F
All insulated lines or ducts passing through walls or floors shall be provided with metal sleeves
large enough to pass a full thickness of insulation.
After being painted as specified elsewhere, any insulation showing signs of coming loose or
tendencies of the cloth pulling shall be removed and reapplied.
The application of all insulation shall be made strictly in accordance with the manufacturer's
directions and by experienced craftsmen in a neat, careful, and workmanlike manner. All
unsightly or sloppy work will be rejected.
Vapor-barrier and finish shall be continuous at all supports.
All insulated piping exposed in mechanical rooms shall be finished out with an 8 oz. canvas jacket
meeting fire and smoke ratings, prior to painting. Jacketing shall be applied with "Benjamin
Foster" 30-36 or equal mastic, and shall receive one (1) coat of approved sizing by the Insulation
Subcontractor.
END OF SECTION
'� i���� �G'�� ���� �'�@ �
I� (I�li �"��.:; G� ° e °�r �
_ ,�, fV!�i�,.�r��M 5���, !
�---:,
INSULATION FOR MECHANICAL TRADES
15180-3
�
�
.
�,
�
��
r
�
�
�,'.
�
SECTION 15600
CHILLER REPLACEMENT
PART 1 - GENERAL
1.01 SCOPE
�
�:
1.02
p�,.,.�-
This section of the specifications includes all labor and materials required for the finished and
complete replacement installation of Water Chilling Unit No. 3.
Involved in the classification of work above are the following systems:
1. Chilled water cooling
2. Condenser water piping
3. Miscellaneous, as indicated on the plans
RELATED WORK SPECIFIED ELSEWHERE
A. Piping
B. Valves, strainers and unions
C. Insulation
D. Material storage and handling
E. Motor starters
1.03 SUBMITTALS
Submit manufacturer's certified rating data, descriptive literature, and catalogue cuts for all
proposed equipment items as follows:
A. Water chilling units
B. Vibration isolation
C. Hydronic specialties
PART2-PRODUCTS
2.01 WATER CHILLING UNtT
A. Water chilling unit shall be a factory-assembled one-piece, water-cooled, centrifugal type unit,
"Trane" Model CVHF. Unit shall be listed by Underwriters' Laboratories, Inc., or an acceptable
equivalent, and all wiring shall comply with National Electrical Code.
B. The unit shall produce not less than the specified tonnage per the scheduled data in accordance
with ARI 550/590-98. The unit shall bear the ARI certification label as applicable.
2.02 COMPRESSOR AND MOTOR
A. Compressor shall be centrifugal type, and motor shall be hermetic and either suction or liquid
refrigerant cooled. Impellers shall be fully shrouded and made of a high strength aluminum alloy.
Impellers shall be dynamically balanced and over-speed tested at 1.25 times impeller shaft speed.
CHILLER REPLACEMENT �'�')���LQ���- �'��IJU��
15600 - 1 '...'!�i��� ���° ��� `° e�
I i� Ufl�v�!i;.��U ilp lI L�.
�
� 2.03
� A_
B.
EVAPORATOR AND CONDENSER
Evaporator and condenser shall be built in accordance with ANSI/ASHRAE 15-1994 Safety Code
for Mechanical Refrigeration. Water piping connections shall be victaulic.
Evaporator and condenser tubes shall be internally enhanced, with minimum tube wall thickness
of 0.028 inch.
�..
C. Adjustable or float type refrigerant metering devices and therma{ expansion valves sha{I be
, inspected and adjusted by the manufacturer at the end of each year for the first five years of
operation to assure equivalent reliability and maintenance to a fixed orifice system. A written
� report shall be forwarded to the owner each year to confirm compietion.
D. Compressor shall incorporate an interstage flash vessel "economizer".
E. Supply and return head water boxes shall be designed for a working pressure of 150 psig and
factory hydrostatic pressure tested at 150 percent of the design pressure. Drain and vent
connections shall be provided in water boxes.
F. Unit shall have standard water boxes for the evaporator and marine water boxes for the
+ condenser. Marine water boxes shall be configured such that the water piping at both the
entering and leaving sides need not be disconnected for mechanical cleaning. Water piping
connections shall be in a direction perpendicular to the shells to allow full unblocked access to the
° tubes.
G. lnsulation shall be 3!4" foamed plastic insulation and cover all low temperature surfaces to include
the evaporator, water boxes, and suction elbow. Insulation for economizer and motor cooling lines
may be of lesser thicknesses.
2.04 PURGE SYSTEM
A. A'Trane Purifier' purge system shall be provided. The purge must be able to operate when the
chiller is idle in accordance with ASHRAE Guideline 3-1996, paragraph 4.4.1.2., and the purge
must be ARI Standard 580 listed.
B. The purge efficiency shall be not less than called for by ASHRAE Guideline 3-1996 paragraph
4.4.1.1. At standard room operating conditions and with a condensing refrigerant temperature >
80 degrees F, the purge system shall be rated for no more than .0049 Ib. of refrigerant per 1 ib.
non-condensable.
2.05 REFRIGERANT MONITOR
A. The installation shall include a refrigerant monitor, located as directed. Monitor shall be "Trane"
Model RMWC or "Mine Safety Appliances", Model "Chillgard RT".
0
��
'I_ Refrigerant monitor shail have an infrared sensor using either photo acoustic or photo
absorptive sensing method. The minimum refrigerant detection level shaii be no more than
1 ppm and its specified error over its measurement range shall be no more than +f- 3 ppm
for 1- 50 ppm range and +/- 10% for 51 - 1,000 ppm range.
CHILLER REPLACEMENT
15600 - 2
_ _.��`��;C;,�+�� �G�� ���C�� °?D
�:��� ����� � �,�
�� I� �� i I
�r'��tt � ��'i`'LUOy �l�(Ns
�z,�.�.�.. -
�
�
2. Monitor's specified performance for its specified refrigerant shall be confirmed by a factory
or jobsite test. This test shall be done with a NIST (National Institute of Standards and
Technology) traceable mixture of the monitor's scheduled refrigerant(s). If done at the
factory, the manufacturer shall provide a certificate of tesb verification with the unit. If done
at the jobsite, the manufacturer's representative shall use 10 ppm refrigerant mixture to
demonstrate that the refrigerant monitor has an error of no more than +/- 3 ppm at 10 ppm �
concentration.
Three factory-set alarm levels shall be provided, each with a front panel light and a latching
binary contact closure for the control of remote devices.
�
�
�
+.v
4. An analog output corresponding to the unit display is required for connection to a BAS or
other recording equipment.
Ambient temperature operating range shall be 40 to 105 F.
2.06 CONTROLS
/�
�
Chiller shall be controlled by a stand-alone direct Digital Control (DDC) System, including a
dedicated chiller microprocessor control panel mounted on the unit at the factory.
Chiller control panel shall provide control of chiller operation and monitoring of chiller modules,
sensors, actuators, relays and switches and shall include controls to safely and efficiently operate
the chiller.
C. Safeties - chiller control panel shall monitor the following safeties: start and running time between
compressor/motor starts, low chilled water temperature, low evaporator refrigerant temperature or
pressure, high condenser refrigerant pressure, evaporator and condenser water flow status, low
oil pressure, low oil temperature, high oil temperature, high motor winding temperatures, sensor
faults, and proper operation of unit controls.
To monitor bearing temperatures, all of the compressor and motor bearings, (including high
speed, low speed, and thrust bearings) shall have factory installed separate temperature
sensors installed in the bearing or the oil return lines of each bearing. If any oil temperature
reaches or exceeds a set value, the chiller control panel shall shut down the chiller, display
the diagnostic, and light the front panel alarm LED.
2. The chiller control panel shall incorporate advanced motor protection to safeguard the
motor throughout the starting and running cycles from the adverse affects of:
a. Phase loss
b. Phase imbalance
c. Phase reversal
d. Under voltage
e. Motor overload
f. Motor overload protection incorrectly set
g. Momentary power loss protection with auto restart consisting of three-phase current
sensing devices that monitor the status of the current
h. Starter contactor fault protection
i. Starter transition failure
Alternately, the advanced motor protection system can be furnished in the starter.
�"
.�
E. The chiller control panel shall be provided with a starts counter and running time counter.
CHILLER REPLACEMENT
15600 - 3
'�'��B��OG�� ����'G�D
".;�C�� ��'��C�,° °."�
��!a U'�!'�.� ��II�•I�III)e lll�.��a
rr��
� F
r-
�
�..
The front of the chiller control panel shall display the following in clear language, without the use
of codes, look-up tables, or gauges:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23
24
25
Entering and leaving evaporator water temperatures
Entering and leaving condenser water temperatures
Compressor Motor Winding Temperature 1,2,3
Saturated evaporator and condenser refrigerant temperatures
Evaporator and condenser refrigerant pressure
Oil Temperature
Oil Tank pressure
Oil pump discharge pressure
Differential oil pressure
Compressor motor starts and running hours
Compressor motor current,. by phase
Compressor motor percent RLA
Purge compressor suction temperature
Purge pumpout rate
Purge pumpout time last or current cycle
Total Purge pumpout time
Total Purge run time
Chilled water set point and set point source
Electrical current limit set point and set point source
Current chiller operating mode
Equipment room refrigerant monitor ppm levels
Chiller diagnostics including a time and date of occurrence
diagnostics stored in non-volatile chiller panel memory)
Bearing Oil Temperatures (one per bearing)
Discharge Temperature (compressor)
Compressor motor voltage, by phase, KW, power factor
(minimum 20 historical
G. The chiller control panel shall provide evaporator freeze protection and low limit control to avoid
low evaporator refrigerant temperature trip-outs during critical periods of chiller operation. The
control shall take action in response to the actuai value of the evaporator refrigerant temperature.
A diagnostic message shall be automatically displayed at the front panel whenever this control is
in effect, and if the condition exists for more than 20 minutes, a limit warning alarm relay shall
energize.
H. The chiller control panel shall also provide:
Individual relay outputs to start/stop the evaporator and condenser water pumps.
2.
r
3.
4.
�
5.
�
�..
6.
�.
�
i�`
V
Relay output that shall energize whenever the compressor is running.
Alarm relay output that shall energize whenever a fault requiring manual reset is detected
by the panel.
Relay output that shall energize whenever the chiller is operating at maximum capacity.
A head relief request relay output to indicate that the chiller is in condenser limit mode and
thereby requesting condenser water temperature relief.
Analog output signal that shall indicate the Compressor Motor Percent RLA.
CHILLER REPLACEMENT
15600 - 4
�� ���c�p�cpl�� ��[�C�uG�D
�::�u'�u ���rG� ° e�U
IC�� �y�� e���y �'�o
�
�
�
�
L,
2.07
A.
B.
C.
D.
E.
�" a. Each printed output is stamped with the time and date of printing.
b. Print on command from the operator interface keypad.
c. Print based upon each occurrence of a chiller diagnostic.
d. Print a standard summary report based upon an operator specified timed interval.
11. The chiller control panel shall be capable of providing short cycling protection.
�
�
�
�
�
�.,
�
�:,_
7. Analog output signal that shall indicate the condenser refrigerant pressure or
condenser/evaporator differential refrigerant pressure.
8. Condenser limit control to include a pressure transducer and interconnecting piping and
wiring. This control shall be used to avoid high condenser refrigerant pressure tripouts. The
control shall take action in response to the condenser refrigerant pressure. A diagnostic
message shall be automatically displayed at the front panel whenever this controi is in
effect, and if the condition exists for more than 20 minutes, a limit warning alarm relay shall
energize.
�
10.
STARTER - STAR DELTA (LOW VOLTAGE)
Motor starter shall be a Star-Delta Closed Transition and shall have a NEMA 1A gasketed
enclosure.
Motor starters shall include incoming line provisions for the number and size cables shown on the
drawings. Incoming line lugs shall be copper mechanical type.
Contactors shall be sized properly to the chiller full load currents.
Motor starter shall include a 3 KVA control power transformer with fused primary and secondary.
Control relays shall be provided within the motor starter to interface with the control panel.
Starter shall include an advanced motor protection system incorporating electronic three phase
overloads and current transformers. This electronic motor protection system shall monitor and
protect against the following conditions:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10
The leaving chilled water temperature set point in the form of a 4- 20mA or 2-10 vdc signal
from a remote source (i.e. the existing Power Plant automation system).
The chiller control panel shall be capable of supporting a printer. The printer interface shall
provide the.following printing functions:
Phase loss �
Phase imbalance
Phase reversal
Under voltage
Motor overload
Motor overload protection incorrectly set
Momentary power loss protection with auto restart consisting of three-phase current
sensing devices that monitor the status of the current.
Starter contactor fault protection
Starter transition failure
Distribution fault protection.
F. Alternately the advanced motor protection system can be furnished in the chiller control panel.
��::�i;;1�0��G�� �:'��L'Gc_'�
CHILLER 5 OOLA5 EMENT '. fLI U� ���vr��gre en�
It• IIC
ir'�7 �� ri�iJ'Jp ?��o
J' �� �' u 1
. — �......__... �
�
� G.
.. H.
�..
�^
�
The starter shall be able to operate in temperatures up to 120 degrees F.
All fieid supplied wires, bus bars, and fittings shall be copper only.
1. Circuit 6reaker - Starter shall contain a circuit breaker capable of breaking currents up to its
interruption capacity of 65,000 amperes. Operating handle and trip indicator shall be located on
the door. This handle shall be capable of being padlocked. The starter enclosure shall have a
withstand rating of 65,000 amperes. If the starter enclosure does not have this withstand rating,
then a device shall be provided upstream of the starter to limit the fault current at the starter to be
equal or less than the withstand rating of the starter.
2.08 THERMOMETERS AND THERMOMETER WELLS
A. Where indicated on the plans, furnish and install a"Weksler" or equal 9" scale, cast bronze or
aluminum case, socket joint type, .red-reading mercury-filled thermometer, range as indicated on
the drawings.
B. Where thermometers are installed in locations higher than six (6) feet above the working floor line,
they shall also have a totally enclosed hinge assembly with lockscrew, equal to "Weksler" Type
AA "Adjust Angle".
C. All thermometers shall be installed, adjusted and locked in such locations and/or angular positions
that they may be easily and accurately read by a person standing on the floor.
D. At the inlet and outlet of the chiller and condenser, and elsewhere as indicated on the plans
furnish and install a"Weksler" or equal bronze thermometer well with screw cap and chain, sized
to extend through the insulation, for tests with a portable industrial thermometer. Test wells shall
be located that a 12" thermometer may be used in such welis after adjacent piping has been
insulated and other obstructions installed.
2.09 GAUGES, GAUGE COCKS AND METERS
A. At the inlet and outlet of the condenser and chiller, furnish and install a"Weksler" Type AA14 or
r equal 4-1/2" dial, cast aluminum case, +/-1/2% accuracy, pressure gauge with red set hand, '/<"
, brass gauge cock, and pressure "snubber". Range of gauges shall be as selected by the
Engineer. Additional gauges shall be provided as noted.
�� 2.10 VIBRATION ISOLATION
A. Isolation pipe hangers shall consist of a steel housing or retainer with steel spring in compression,
� and shall have a fabric or neoprene isolator washer in series with the spring. Spring static
deflection shall not be less than 1".
*" B. Isolators shall be steel spring type with leveling devices. Springs for base-mounted or suspended
units or fans of less than 2,000 cfm shall have not less than 1" static deflection; and all larger units
shall have a minimum of 2" static deflection. The size, number and location of the isolators shall
be as recommended by the equipment manufacturer.
`" C.
� D.
�
'��
�
Sound pads shall be fabricated of a layer of cork between two layers of grooved neoprene,
bonded together, and 1" thick unless otherwise noted.
Vibration isolation media shall be as manufactured by "Korfund", "Amber Booth", or "Vibration
Mountings, Inc.".
CHILLER REPLACEMENT
15600 - 6
�
;:,;��'��l��Ir�L� ���l�;l�.� e��'
�� ��1( �i�'� ►� ° °��
U 4�n �:'lP.+GUL� �lSUCo
�
�
�
�
��,
PART 3 - INSTALLATION
3.01 EQUIPMENT
A. All new air conditioning equipment shall be installed in accordance with the details on the plans.
3.02 INSTALLATION
A. Installation shall be in strict accordance with manufacturer's instructions.
Furnish and install necessary auxiliary water piping for oil cooling units and purge condensers if
required.
�:3
Arrange piping for easy dismantling to permit tube cleaning. Provide piping from chiller relief
device to outdoors. Size as recommended by manufacturer.
C
3.03 MANUFACTURER'S FIELD SERVICES
A. Manufacturer shall furnish a factory trained service engineer without additional charge to provide
leak testing, evacuation, dehydration, charging of the unit, and startup of the unit. Chiller
manufacturer shall maintain service capabilities no more than 50 miles from the jobsite.
B. A start-up log shall be furnished by the manufacturer to document the chiller's start-up date, which
will be signed by the owner or his authorized representative prior to commissioning the chillers.
3.04 EQUIPMENT BASES
A. Provide as indicated on the plans or otherwise required, the various equipment bases. Unless
noted, all floor-mounted equipment shall be furnished with a concrete base in addition to any
required vibration isolation.
B. Equipment bases in general shall be reinforced concrete, having # 3 steel reinforcing bars on 12"
centers both ways, located approximately halfway between the top and bottom of the base.
Outside dimensions shall be such that the concrete base extends approximately 4" beyond the
equipment mounting base, unless otherwise specifically shown on the plans. Base depth shall be
4", or as otherwise specified or noted. All corners shall be chamfered 1".
C. Mounting bolts shall be set in pipe sleeves, with 6" x 6" x 1/4" anchor plates, and shall be grouted-
in after mounting equipment.
3.05 VIBRATION AND NOISE CONTROL
A. Transmission of perceptible vibration, structure-borne noise or objectionable air borne noise by �
�` � and/or from equipment installed to occupied areas will not be permitted. The Contractor shall '
submit for approval data showing disturbing frequency, support weight, static deflection or natural
frequency and efficiency for each isolator and damper he proposes to use.
CJ
�
r�
CHILLER REPLACEMENT
15600 - 7
�:�;�f���� ��:� �'C��cuG°�D
r, �
�`:I;',� ���+GG� � °�
���p �c��:����p ���o
��
�
�
B. All isolation material selections are to be based on laboratory published or factory certified data,
proving that all such materials and usage comply with these specifications. After installation, and
before acceptance by the Owner, the Contractor, in company with the Engineer, shall inspect all
isolation materials. Should any noise or vibration be objectionable to the Engineer, field
instrumentation tests and measurements shall be made by the Contractor to determine the
source, cause, and path of such disturbance. Any variance or non-compliance with the
specification requirements shall be corrected by the Contractor in an approved manner at no
additional cost to the Owner.
C. In general, all piping shall be shimmed or blocked in place until all connections are made and
systems filled, the isolators adjusted to support the weights, and then shims and clocks removed.
The first support point from a piece of isolated equipment shall provide not less than the static
deflection of the equipment isolators. All springs supporting piping shall be capable of an
additional 1" deflection without becoming solid, and springs supporting vertical risers shall have
provisions for limit stops.
1. First three (3) supports for all piping, including drains, from any piece of equipment
specified to be isolated, shall incorporate steel springs with not less than 1" static
deflection.
3.06 CLEANING, TESTING AND ADJUSTING
A. It is the intent of this section of the specifications to provide for all necessary tests during
� construction and at completion of the job to insure tight piping and correctly balanced systems.
This Contractor shall perform such tests and shall do any and all work required to accomplish this
end.
� B. All new chilled and condenser water piping and equipment shall be cleaned as specified under
SECTION 15060 - PIPING.
C
��
�
All strainers and filters shall be cleaned after pressure testing and system cleaning operations,
and prior to final filling of systems.
All motors, bearings, etc., on all equipment shall be correctly oiled and/or greased with the proper
lubricant before the equipment is operated, and again at the completion of the job.
E. This Contractor shall operate the equipment installed by him for one (1) working day of eight (8)
hours, and shall leave the equipment in perfect operating condition. During this period, he shall
aiso instruct the Owner's representatives in the proper operation and maintenance of all
equipment and systems.
F. This Contractor shall furnish the Owner with three typed sets of complete operating instructions
and maintenance schedules for the insta�led systems as a whole. Operating instructions shail first
be submitted for approval. Maintenance schedules shall include, but not be limited to, complete
lubricating instructions designating all oiling and greasing points for all equipment and designating
type of lubricant to be used.
�
END OF SECTION
�
�
CHILLER REPLACEMENT
15600 - 8
'_,''!� i�OC�UC�� �'�C�Je1@
�� ;: i�'u' ��`�G?[�G°�?��
� ��('!I �{'M p/� 7
����'v'a �JC7L��'l'U1fr ��,;o !
i
SECTION 16000
�
�"
�
l�
�
�
�r
�
�
�
�
�
ELECTRICAL WORK
PART 1 - GENERAL
1.01 SCOPE
A.
�
1.02
�
'L�-�
C.
1.03
Electrical work consists of disconnection of existing feeder serving the existing refrigeration
machine and reconnection of the new machine.
Contractor shall visit the site before bidding to observe conditions and verify location of existing
feeder and the amount of relocation and/or extension required for reconnection to new machine.
The existing feeder location is not shown on the drawings.
CODE COMPLIANCE, PERMITS AND GUARANTEES
All labor and materials shall be in strict conformance with the most recently revised editions and
amendments of all applicable laws, rules and recommendations of the National Fire Protection
Association (NFPA), municipal and state codes and regulations.
Contractor shall procure all necessary permits, licenses, or inspections to carry out his work and
shall pay the lawful fees thereof.
Contractor shall guarantee his work for twelve (12) months from date of final acceptance.
PERFORMANCE
A. All labor and materials necessary for a complete functioning reconnection of the existing feeder
shall be furnished and installed by the Contractor at no extra cost to the contract, whether
mentioned in the Contract Documents or not.
PART 2 — PRODUCTS (NOT APPLICABLE)
PART 3 — EXECUTION (NOT APPLICABLE)
8
END OF SECTION
ELECTRICAL WORK
16000 - 1
;���,�f�aC�0/�� �'f�C��G�@ '
'; ��(1 � �'� G°� �°` `_'��
�R��y��p���ir,y��IM ;;;'777'�ti�
Uo UV��i�.�.l:lilly tl,.:��:o
�
L
THE STATE OF TEXAS
PERFORMANCE BOND
:� � � :•:���::��
�
- COUNTY OF TARRANT
KNOW ALL MEN BY THESE PRESENT: That we (1) Intinitv Contractors.
�- Inc. (2)- Comnanv of Texas hereinafter called Principal and (3) VIGILANT INSURANCE
COMPANY AND FEDERAL INSURANCE COMPANY
� , a corporation organized and existing under the laws of the State and fully authorized to transact
business in the State of Texas, as Surety, are held and firmly bound unto the City of Fort Worth, a
municipal corporation organized and existing under the laws of the State of Texas hereinafter called
�' Owner, in the penal sum of:
Two Hundred Thirteen Thousand, Nine Hundred Twentv Two Dollars & No Cents
�., $213,922.00 Dollars in lawful money of the United States, to be paid in Fort Worth, Tarrant County,
Texas, for the payment of which sum well and truly be made, we hereby bind ourselves, our heirs,
� executors, administrators, and successors, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION is such that Whereas, the Principal entered into a
� certain contract with the City of Fort Worth, the Owner, dated the llth day of January , 2000 , a
copy of which is hereto attached and made a part hereof, for the construction of:
REPLACEMENT OF 590 TON CENTRIFUGAL CHILLER
FORT WORTH CONVENTION CENTER
�' designated as Project Number GG04-0242000 , a copy of which contract is hereto
� attached, referred to, and made a part hereof as fully and to the same extent as if copies at length herein,
such project and construction being hereinafter referred to as the "work".
i., NOW THEREFORE, if the Principal shall weli, truly and faithfully perform the work in
accordance with the plans, specification, and contract document during the original term thereof, and any
� extensions thereof which may be granted by the Owner, with or without notice to the Surety, and if he
shall satisfy all claims and demands incurred under such contract, and shall fully indemnify and save
harmless the Owner from all costs and damages which it may suffer by reason of failure to do so, and
� shall reimburse and repay the owner all outlay and expense which the Owner may incur in making good
any default, then this obligation shall be void; otherwise to remain in full force and effect.
�
PROVIDED FURTHER, that if any legal action be filed upon this bond, venue shall lie in
Tarrant County, State of Texas.
AND PROVIDED FURTHER, that the said Surety, for value received, hereby stipulates and
agrees that no change, extension of time, alteration or addition to the terms of the contract or to the work
to be performed thereunder or the specifications accompanying the same shall in any wise affect its
obligation on this bond, and it does hereby waive notice of any such change, extension of time alteration
or addition to the terms of the contract or to the work or to the specifcations.
���OCOI�� ����G�D
�� �� ���:; c115 ° e U
Y Uo 1�17V!'��U�y Ul7U�o `
r A:14PERBOND.FRM
.,
!
�
�
.�
�
�
IN WITNESS WHEREOF, tliis instrument is executed in 6 Counterparts each one of which
shall be deemed an original, this the 14th day of January , 2000.
ATTEST:
,
(Pri cipal) Secretary
(SEAL)
(Address)
INFINITY CONTRACTORS, INC.
Principal (4)
` �7v
By:
!
J 1 r.,SA� �'4'�t./ pR.Es� a�.s,—
(Printed Nar�e/Title)
P.O. Box 163316
ADDRESS
Fort Worth, Texas 76161
CITY/STATE/ZII'
VIGILANT INSURANCE COMPANY
FEDER.AL INSURANCE COMPANY
(Surety)
ATTEST:
(Surety) Secretary
(SEAL)
r�iR�., ��IJ�(` �
Witness � to Surety
A:\4PERBOND.FRM
By: ((��YIC(,� ( • %
(Attorney-in-Fact) (5)
Tamara E. Murray
(Printed Attorney-in-Fact)
Note
(1)
(�)
(3)
(4)
(S)
Date of Bond mus! not be prior to date of
Con[ract
Correcl name ojContractar
A Corporation, a Partnership or and
Indrvidual, as case may be
Correet Name of Surery
I,f Contractor is parinership a!! Partners
should execute bond
A true copy of Power of Atlorney shall be
attached fo bond by Altorney-in-Faet
��[�OCB�� ��[�C���D �
'�.-�� ��� ° ' °�
!''� �l��f yG Yl1 U 15�
—^^---.�»�..,...,,,_ .: •
�
1
IMPORTANT NOTICE
To obtain in�ormation or make a complaint:
You may contact the Texas Department of Insurance to obtain information on
companies, coverages, rights or complaints at:
1-800-252-3439
You may write the Texas Department of Insurance at:
P.O. Box 149104
Austin, Texas 78714-9104
Fax # (512) 475-1771
P
�
PREMIUM OR CLAIM DISPUTES
Should you have a dispute concerning your premium or about a claim, you
should contact the agent or the company first. If the dispute is not resolved, you
may contact the Texas Department of Insurance.
ATTACH THIS NOTICE TO YOUR BOND
This notice is for information only and does not become a part or condition of the
attached document.
��f�BCB�� ��C�C���
� ��i �����G� ° 1�
(�, � `���, �l�.
�
L
�...
L
PAYMENT BOND
THE STATE OF TEXAS
COUNTY OF TARRANT
KNOW ALL MEN BY THESES PRESENTS: That
BOND N0. 89800880
we, Infinity Contractors, Inc. a
corporation of Tarrant County, Texas . hereinafter called Principal
and (3) VIGILANT INSURANCE COMPANY AND FEDERAL INSURANCE COMPANY
(� , a corporation organized and existing under the laws of the State and fully authorized to
L transact business in the State of Texas, as Surety, are held and firmly bound unto the City of Fort Worth,
a municipal corporation organized and existing under the laws of the State of Texas, hereinafter called
� Owner, and unto all persons, firms, and corporations who may furnish materials for, or perform labor
upon, the building or improvements hereinafter referred to in the penal sum of:
�
Two Hundred Thirteen Thousand, Nine Hundred Twentv Two Dollars & No Cents
$213,922.00 lawful money of the United States, to be paid in Fort Worth, Tarrant County, Texas, for the
� payment of which sum well and truly be made, we bind ourselves, our heirs, executors, administrators
, and successors jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION is such that Whereas, the Principal entered into a
� certain contract with the City of Fort Worth, the Owner dated the llth day of January , 2000, a
copy of which is hereto attached and made a part hereof, for the construction of:
REPLACEMENT OF 590 TON CENTRIFUGAL CHILLER
FORT WORTH CONVENTION CENTER
�
designated as Project Number GG04-0242000 copy of which contract is hereto
attached, referred to, and made a part hereof as fully and to the same extent as if copied at length herein,
such project and construction being hereinafter refe:red to as the "works".
�
NOW, THEREFORE, the condition of the obligation is such that, if the Principal shall promptly
� make payment to all claimants as defined in Article S l 60 of the Revised Civil Statutes of Texas,
supplying labor and materials in the prosecution of the work provided for in said Contract, then this
obligation shall be null and void, otherwise it shall remain in full force and effect.
THIS BOND IS MADE AND ENTERED into solely for the protection of all claimants supplying
labor and material in the prosecution of the work provided for in said Contract, as claimants are defined
in said Article 5160, and all such claimants shall have a direct right of action under the bond as provided
in Article 5160 of the Revised Civil Statutes.
r PROVIDED FURTHER, that if any legal action be filed upon this bond, venue shall lie in
Tarrant County, State of Texas, and that the said Surety, for value received, hereby stipulates and agrees
that no change extension of time, alteration or addition to the terms of tlle contract or to the work to be
performed thereunder or the specification accompanying the same shall in any wise affect its ob(igations
on this bond, and it does hereby waive notice of any such change, extension of time, alteration or
�" addition to the terms of the contract or to the work or the specifications.
�
r
PROVIDED FURTHER, that no final settlement between the Owner
A:15PAYBOND.FRM
and the l.(�niron�yy ty�;l��
��V���u�OG�I� �_'��'JG.�D
���� c�[��v °� ' °�
�a ���c��� ��.
abridge the right of any benefciary hereunder whose claim shall be unsatisfied.
IN WIT'NESSETH WHEREOF, this instrument is executed in 6 counterparts, each one of which
sl�all be deemed an original, this the 14th day of January . 2000.
�..
L
�
L
r
ATTEST:
( rincipal) Secretary
(SEAL)
�
(Address)
�
ATTEST:
�
(Surety) Secretary
�
�
�
�
R"'
�
'
�
(SEAL)
,
� � �
itness as to Surety
INFINITY CONTRACTORS, INC.
Principal (4)
BY: �..�i��
�•,r,,, 5 �►lt�,a./ QR�� m�'�-
(Printed I�ame/Title)
P.O. Box 163316
ADDRESS
Fort Worth, Texas 76161
CITY/STATE/ZIP
VIGILANT INSURANCE COMPANY
FEDERAL INSURANCE COMPANY
(Surety)
By: � l .
�
(Attorney-in-Fact) (5) I
.J
Tamara E. Murray
(Printed Attorney-in-Fact)
Note:
(�)
(2)
(3)
�4)
Date of Bond must not be prior to date of
Contract
Correct name ofContractor
A Corporation, a Partnership or and
Individual, as case may be
Correct Name of Surety
I,f Contractor is Partnership all Partners
should execu[e bond
,���(�(�6� Ol�.� ��C�����
(v�j}�,�1�% (; �' 0 l
���., ����
�I/�1� � �
U �1'� V�'::;%� � ��p �
Chubb POWER
� oF
Surety ATTORNEY
�
�„'
Federai Insurance Company Attn.: Surety Department
Vigilant Insurance Company 15 Mountain View Road
Pacific Indemnity Company Warren, NJ 07059
Krww All by These Presents, That FEDERAL INSURANCE COMPANY, an Indiana corporation, VIGILAAff INSURANCE COMPANY, a New York
corporation, ar�d PACIFIC INDEMNITY COMPANY, a Wisconsin corporation, do each hereby constitute and appoirtt Kyle W. Sweeney ,
Charles D. Sweeney, Bobby E. Mayo and Tamara E. Murray of Fort Worth, Texas---------
each as their true and lawfui Attomey-in-Fact to execute under such designation in their names and to affa their corporate seals to and deliver for and
on their behalf as surety thereon or othervvise, bonds and undertakings and other writings obligatory in the nature thereof (other than bail bonds) given
or executed in the course of business, and any instruments amending or aftering the same, and consents to the modification or afteration of any
� instrumeM refeRed to in said bonds or obligations.
In Vlfdness Whereuf, said FEDERAL INSURIWCE COMPANY, VIGIUNf� INSURANCE COMPANIf, and PACIFIC INDEMNITY COMPANY have each
� executed and attested these presents and aftaed their corporate seals on this 1 S th day o f Novem r, 1999
�
�"" � / / � /
nneth C. Wendel, Assistant Secretary � �� Fra E. Robe son, Vice Presu�Ent
STATE OF NEW JERSEY l
%
j �.
County of Somerset
L�
�
r.r
�
On this 15 tYlday of Novemb er , 1999 , before me, a Notary Public of New Jersey, personally came Kenneth C. Wendel, to me knovm to be
Assistant Secretary of FEDERAL INSURANCE COMPANY, VIGILANT INSURANCE COMPANY, and PACIFIC INDEMNITY COMPANY, the companies which
executed the foregoing Power of Ariomey, and the said Kenneth C. Wendel being by me duly swom, did depose and say that he is Assistant Secretary of FEDERAL
INSURANCE COMPANY, VIGILANT INSURANCE COMPANY, and PACIFIC INDEMNITY COMPANY and knows the corporate seals thereot, that the seals affixed to
the foregoing Power of Attomey are such corporate seais and were thereto affaed by authority of the By-Laws ot said Companies; and that he signed said Power of
Attomey as Ascistant Secretary ot said Companies by like authority; and that he is acquainled with Frank E. Robertson, and knows him to be Vice President of said
Companies; and that the signature ot Frank E. Robertson, subscribed to said Power of Attomey is in tha genuine handwriting of Frank E. Robertson, and was thereto
subscribed by authority of said By-Laws and in deponenPs presence.
Nolarial Seal �k ���. t
�TiAR�'; � � JOANhI£ K. RUSSAK ` %�����
� }�p�, SL'sin :� �►aw JeroeY {
LIC; No. z2,i�esu6 �
�,- ���� �P�y June �7. 2�3J / Notary Public
s�' .._. CERTIFICATION
Extract from the By-Laws of FEDERAL INSURANCE COMPANY, VIGILANT INSURANC COMPANY, and PACIFIC INDEMNITY COMPANY:
r„ 'All powers of attomey for and on behalf of the Company may and shall be executed in the name and on behalf of the Company, efther by the
' Chairman or the President or a vice Presider�t or an Assistant Vice President, jointy with the Secretary or an Assistant Secretary, under their
respective designations. The signature of such officers may be engreved, printed or lithographed. The signature of each of the following
officers: Chairman, President, any Vice President, a�y Assistant Vice President, any Secretary, any Assistant Secretary and the seal of the
Company may be affixed by facsimile to any power of attomey or to any certificate relating thereto appointing Assistant 5ecretaries or
Attomeys-in-Fact for purposes only of executing and attesting bonds and undertakings and other mitings obligatory in the nature thereof, and
� any such power of attomey or ceRificate bearing such facsimile signature or facsimile seai shall be valid and binding upon the Company and
any such power so executed and certified by such facsimile signature and facsimile seal shall be valid and binding upon the Company with
respect to any bond or undertaking to which ft is attached "
�
�
�
�. �
i
i:
�,
I, Kenneth C. Wendel, Assistant Secretary of FEDERAL INSURANCE COMPANY, VIGILANT INSURANCE COMPANY, and PACIFIC INDEMNITY
COMPANY (the 'Companies") do hereby certify thffi
(i) the foregoing extract of the By-Laws of the Companies is true and correct,
(ii) the Companies are duly Iicensed and auU�orized to trar�sact surety business in all 50 of the United States of America arxi the �istrid of
Columbia and are author¢ed by the U. S. Tr�sury Departrnefrt; furthef, Federal and VgilaM ate licensed in Puerto Rico and the U. S. Virgin
Islands, and Federal is licc�nnsed in Art�ican Samoa, Guam, and each of the Pmvinces of Canada except Prince Ectward Island; and
(iii) the foregoing Power of Attomey is true, correct and in full force and effect.
Given under my hand and seals of said Companies at Warren, NJ this 14th day of January , 2000 .
SU�C
`� �p `` �atrom <O `a5rRA1y�FC�
O J �a� �G � ��� '+�,�
�
� � j : �o
� 2 * —*— * �� :?
V� 7 ��� 11 �,,y � !*
�DIAt�* � �SCON��' �EW YOR�
�
� Kenneth C. Wendel, ssistant Secretary
IN THE EVENT YOU WISH TO NOTIFY US OF A CLAIM, VERIFY THE AUTHENTICITY OF THIS BOND OR
NOTIFY US OF ANY OTHER MATTER, PLEASE CONTACT US AT ADDRESS LISTED ABOVE, OR BY
�, Telephone (908) 903-3485 Fax (908) 903-3656 e-mail:�-�a�eE�e�te�b�errr—
r o/� �`f
1510-0225 (Ed 4-98) CONSENT �, �i!7i;���i��� � �� ��,� �) 1�„��f il
G;� V U : �!V'.�.. . `�� �
� Ir ��' '����G� ° °�
� ���� � �
UPr V'' ��� o�i�JUp ��
CITY OF FORT WORTH, TEXAS
CONSTRUCTION CONTRACT
�
THE STATE OF TEXAS
COUNTY OF TARRANT
KNOW ALL MEN BY THESE PRESENTS:
�,,, This agreement made and entered into this the 11�' day of January AD, 20 00 , by
� and between the CITY OF FORT WORTH, a municipal corporation of Tarrant County, Texas, organized and
existing under and by virtue of a special charter adopted by the qualified voters within said City on the 11th
day of December, A.D. 1924, under the authority (vested in said voters by the "Home Rule" provision) of the
Constitution of Texas, and in accordance with a resolution duly passed at a regular meeting of the City
�, Council of said city, hereinafter called OWNER, and Infinitv Contractors. Inc. of the City of Fort Worth
County of Tarrant State of Texas hereinafter called CONTRACTOR.
LWITNESSETH: That for and in consideration of the payments and agreements hereinafter mentioned to be
made and performed by the Owner, and under the conditions expressed in the bond bearing even date
herewith, the said Contractor hereby agrees with the said Owner to commence and complete the
� construction of certain improvements described as follows:
REPLACEMENT OF 590 TON CENTRIFUGAL CHILLER
FORT WORTH CONVENTION CENTER
That the work herein contemplated shall consist of furnishing as an independent contractor all labor, tools,
� appliances and materials necessary for the construction and completion of said project in accordance with
the Plans and Specifications and Contract Documents adopted by the City Council of the City of Fort Worth,
which Plans and Specifications and Contract Documents are hereto attached and made a part of this
_ contract the same as if written herein.
The Contractor hereby agrees and binds himself to commence the construction of said work within ten (10)
days after being notified in writing to do so by the Owner.
�,; City agrees and binds itself to pay, and the said Contractor agrees to receive, for all of the aforesaid work,
and for stated additions thereto or deductions therefrom, the price shown on the Proposal submitted by the
� successful bidder hereto attached and made a part hereof. Payment will be made in monthly installments
upon actual work completed by contractor and accepted by the Owner and receipt of invoice from the
Contractor.
The agreed upon total contract amount shall be $213,922.00 and includes the base bid and No Alternates.
� Contractor agrees to complete the project, suitable for occupancy and beneficial use, within 120 calendar
days.
�
�'
The Contractor will provide a Certificate of Insurance listing the Transportation and Public Works Department
as certificate holder, showing the required General Contractors Liability coverage, Auto Liability, Builder's
Risk and Worker's Compensation coverage. If this Contract is in excess of $25,000, the Contractor shall
provide Payment Bond. If the Contractor is in excess of $100,000, the Contractor shall provide both
Payment and Performance Bonds for the full amount of the contract. Contractor shall apply for all City of Fort
Worth Permits and for any other permits required by this project. City of Fort Worth Permit fees are waived.
Separate permits will be required for each facility.
If the Contractor should fail to complete the work as set forth in the Plans and Specifications and Contract
Documents within the time so stipulated, plus any additional time allowed as provided in the General Condi-
tions, there shall be deducted from any monies due or which may thereafter become due him, the liquidated
c - � �����CrO� �G� � ���C����
J'::�1��' ���':;G�� ' °�
�la VV `� 11C:,�U Up �L7(No
damages outlined in the General Conditions, not as a penalty but as liquidated damages, the Contractor and
his Surety shall be liable to the Owner for such deficiency.
IN WITNESS WHEREOF, the City of Fort Worth has caused this instrument to be signed in SIX (61
counterparts in its name and on its behalf by the City Manager and attested by its Secretary, with the
corporate seal of the City of Fort Worth attached. The Contractor has executed this instrument through its
duly authorized officers in SIX (6) counterparts with its corporate seal attached.
Done in Fort Worth, Texas, this the 11`" day of January , AD, 20 00 .
T� N� �+y Ca,w,nQ.,a�za�ar� -y., � -
i��
Contract
�'
By: �', �, � � �'�-��
Name
�'2'�.S � 4 E �"'
Office
APPR V : �
By: � !
Assistant City Manager
APPROVAL RECOMMENDED: RECORDED:
� ,� � ,, /��) '�_
B�"'"!�'+r� �`�� By: �Lt'.r:1%; � �L ��� /
Tf�ar(sportation and Public Works �ity Secretary
APPROVED AS TO FORM AND LEGALITY:
� By• r
Assistant Attorney
��
1
,
'
�
l�J
� �,� - �D
Date
C..� ' � /���
Contract Authorization
/-/�`�D
Date
,
C - 2 ':)������� ������ .
�^ �� e����� US ° � _d
Il Ilo l'�)��'�UOy �LSlNo
�
�
L�
�'~
�
CONTRACTOR COMPLIANCE WITH
WORKER'S COMPENSATION LAW
Pursuant to Article 8308-3.23 of Vernon's Annotated Civil Statutes, Contractor, Infinitv Contractors. Inc.
certifies that it provides worker's compensation insurance coverage for all of its employees employed on
City of Fort Worth project ReAlacement of 590 Ton Chiller — Fort Worth Convention Center project
number, GG04-0242000.
By: ,
�P�.� s; � ��
Title
l•l��a�
Date
STATE OF TEXAS
COUNTY OF TARRANT
3
3
BEFORE ME, the undersigned authority, on this day personally appeared
. J I.CYI ���1� , known to me to be the person
whose name is subscribed to the foregoing instrument, and acknowledged to me that he executed the same as
the act and deed of I Y1� � �,��Tj �, � n L` • , for
the purposes and considerations therein expressed and in the capacity therein stated.
GIVEN LTNDER MY HAND AND SEAL OF OFFICE this ��i �' ` day of
, .�"�.•
�
;r��a��., �aau�� s. s,�w
s*: * MY COMMI561UN �(PIRES
N;r.. . �+ Octobar 22, 2qQ1
�E 5
,4k, _ �
,...,, .. �, � �� ���. __ �..�,�� �������, ���r.�...�..
� � ..�.
Notary Public in and for e State of Texas
(a) Contractor agrees to provide to the City a certificate showing that it has obtained a policy
of workers compensation insurance covering each of its employees on the project in compliance
with state law. No Notice to Proceed will be issued until the Contractor has complied with this
section.
� (b) Contractor agrees to require each and every subcontractor who will perform work on the
project to provide to it a certificate from such subcontractor stating that the subcontractor has a
� policy of workers compensation insurance covering each employee employed on the project.
Contractor will not permit any subcontractor to perform work on the project until such certificate
, I has been acquired. Contractar shall provide a copy of all such certificates to the Citv.
�
�����L����U�:�� �'�CUu?�
A:\3WORKCOM.FRM �v��i �r��v��i �
� '�� �'1��� �
l� o � i� - a �
�
�Certificate Holder:
Date:
Project Name:
�Project Number:
This is to certify that:
Address:
�
CERTIFICATE OF INSURANCE
City of Fort Worth
January 11, 2000
Replacement of 590 Ton Centrifugal Chiller — Fort Worth Convention Center
GG04/0242000
Infinity Contractors, Inc.
P O Box 163316
Fort Worth, Texas 76161 .
is at the date of this certificate, insured by this company with respect to the business operations hereinafter described, for the
�type of insurance and in accordance with the provisions of the standard po(icies used by this Company, and further
hereinafter described. Exceptions to standard policy noted on reverse side thereof.
� Type of Insurance
Por.[cv No.
Workers Compensation H142130
X��msi� Grneral C.�� 0 2 3 8
Liability Insurance
(Public Liability)
Commercial�enLiaFi
Blasting
Collapse of Buildings
or structures adjacent to
excavations
a6ove
_�• -
Damage to underground d�ve
Utilities
Buildet's Risk
N /A
Comprehensive
Automobile Liability
ARAK79351
Contractual Liability
Other
see Gen Liab.
EFFECT[VE EXPIRES
ra�i�
I� ..
7-1-00
7-1-00
��'�%�
LiMITS OF Z,IABILITY
�00,000/500,000/SU0,000
��� Cie�'�� �2, 000, o00
Each Occurrence: 1, 000 , 000
��x��Proc�Ag<� I, 000 , 000
P�rs�on�n&�v;��u�y a1,000,000
Each Occurrence S
Each Occurrence S
Each Occurrence S
Bodily Injury �-�T'
7-1-00 ���
���I�oaa��rr�xae
Properry Damage CSL
��i��k
Bodily Injury
Each Occurrence
Property Damage
Each Occuaence
� 1,000,000
S
S
$
�
Locations covered: �1 of insured's �,�ork sTtes
Description of opecations covered: All ot insured' s operations
The above po(icies either in the body thereof or by appropriate endorsement provide that they may not be changed or canceled by the
insurer in less than five (5) days after the insured has received written notice of such change or cancellations.
� Where applicable local laws or regulations require more than five (5) days actual notice of change or cancellation to be assured, the above
policies contain such special requirements, either in the body thereof or by appropriate endorsement thereto attached.
� ;�i._
Agency Agents Insurance Service, Inc. ' D �
Forc Wo A genc ��ri lianiel, �1�c;u, �IC: gY: '
Address�5U-� rarKv�.ew llr. �luU Title: Vic� Presi ent "
� t�L. '1VOrL11� '1'X /blUL
��;������u�r� �}�cuc��
� A:121NSURAN.FRM ' `�" "f ���+v� ` e�
�����I`�'l�� ����o
�
�i� ,� � �
,.
,, , , ..� , . ,.,.. . ... ,..:.,.r•ua�. .._ . . _ _ . _.._.
City �°of Fort T�'o�th, Tex�s
�.
A ar And n, aun �° ' l a. n�un�cAt�an
�� !1 !� C
DATE REFERENCE NUMBER LOG NAME �� PAGE
1/11 /00 **C-17818 I 0-590 2 of 2
SUBJECT AWARD OF CONSTRUCTION CON�TRACT TO IN INITY CONTRACTORS, INC. FOR
THE REPLACEMENT OF 590 TON�� CHILLER AT �HE FORT WORTH CONVENTION
CENTER � ,
— - _ _ .. �I .
FISCAL INFORMATION/CERTIFICATION: ��
The Finance Director certifies that funds are available in the curre�t operating budget, as appropriated,
of tfie Culture'and 7ou`rism Fund. �
MG:j
Submitted for City Manager's
Office by:
Mike Groomer
Originating Department Head:
Hugo Malanga
' Additional Information Contact:
6140
�soi
Hugo Malanga 7801
�
��
F`�JND I ACCO�JNT I
(to)
LL
(from) „
GG04 541200
r
�
�
CENTEI� , I AMOUNT
024200C� $213,922.00 �
� i
J I
ll
11
.
CITY SECRETARY
APPROVED
C1TY COUNCIL
.1e�+ II 2000
�� ��
City Secretnry of the
ril� Ot FpI� �/,�fif}t, 9rnvna
City of Fort Worth, Texas
�11�A�ar And Caunc�il Ca��rtun�cAt�on
DATE REFERENCE NUMBER LOG NAME PAGE
1/11 /00 **C-17818 20-590 1 of 2
SUBJECT AWARD OF CONSTRUCTION CONTRACT TO INFINITY ONTRA�TORS, INC. FOR
THE REPLACEMENT OF 590 TON CHILLER AT THE FORT WORTH CONVENTION
CENTER
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute a construction contract
with Infinity Contractors, Inc. for the purchase and installation of a 590 ton Centrifugal Chiller to replace
the existing chiller at the Fort Worth Convention Center in the amount of $213,922 and for a duration of
120 calendar days.
DISCUSSION:
The existing chiller failed in April, 1998. Romine, Romine and Burgess, consulting mechanical and
electrical engineers, prepared construction documents to procure and install the replacement unit.
The project was advertised in the Commercial Recorder October 21 and 28, 1999. On November 18,
1999, the following proposals were received:
Bidders
Infinitv Contractors, Inc.
GES, Inc.
Systems Integration
Gulf Energy Systems, Inc.
DMI Corporation, Decker Mechanical
Techstar General Contracting, Inc.
Federal Mechanical Systems, Inc.
Weldon Contractors
Burden Brothers, Inc.
Bid
$213.922
$224,960
$228,985
$235,000
$256,885
$259,565
$262,400
$280,288
$283,092
Calendar Days
120
120
115
110
120
84
126
140
120
The low bidder, Infinity Contractors, Inc., is in compliance with the City's M/WBE Ordinance by
committing to 5°/o M/WBE participation. The City's goal on this project is 5%.
The engineer's estimate was $275,000.
The budget for this project will be:
Construction Contract $213,922
Contingencies (5%) 10,700
Inspection and Management 2,000
Total $226,622
�;:
t.
��i
"��
��r
��
\
�
W�
�k
�
R �*
�
,�' �
ac
�
a
h ."
!�
i.�`�
��
A��
���
l�
v
y ��
rr
��
n�
f
m
�
.o
,'
"�
�
��
T
�
��
e
0
u
e�
i�
a�
G!
ig
q
1
.�
.i
.p
;i
.a
i�
11
wq
�A
M
i�
��
N
�9
� �, �...�:; '.'c.
� �
�
�
N
�'
il
�'
�'
��
�
�'!
f�
11
IY
�
M
�
��
1�
�
�
n
wJ
BS +'
11
�
��
�
�
�
�
��
�
�
�
�
�
�
1'
I4�
'�
M
�
R
��
�
1�
�
W
@
c
�
�
�
�
r
5
„�,..,.,�s
8
f
�
, :�T`
�
�
�
a
,�
ei
�
�
�
Y
�
i
�
�
+w
�
�
:�
�
��