Change Order Request
Project Namel Water and Sanitary Sewer Replacement Contract 2021 WSM-C City Sec No. 61352 _
Project No.(s) 06004301070043010200431-103500 1 MEN/A City Pro. No. 103500
Water and Sanitary Sewer Main replacements on Westridge Avenue.
Contractor William J. Schultz Inc. dba Circle C Construction Company Change Order # ® Date: 7/612026
City Project Mgr.1 Dena Johnson, P.E. City Inspector Donald Watson
Phone Number, 817-392-7866 Phone Number. 817-20M911
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C. Process)
Contract Cost to Date
Unit I - Water
Unit II A -
Sewer
$7,801,094,00
$1,507,159.1
$1,759,164.25
$214,000.0
bEEEJ$1,721,159,i
Unit II B - Unit III - Pavin Totals cono-utTime
Sewer 9 (Comd tr Dtyr)
10
ON. Funds Available for Change Orders I $234,033.OU 1�Yo,a�o•w ��� ��� ��
Remaining Funds Available for this CO 0.00 $0.00 $52,460.00 $52,450.03
Additional Funding (if necessary) 94,166.00 $32,808.09 a 1 461,357.91
CHANGE ORDERS to DATE {INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT r 23.27%
$12,946,822.50
FOR
Change Order No. 1 will provide for the following pay items that are necessary on the project:
Additional 12-inch water main by other than open cut
12 addiditonal 12-inch gate valves
Additional temporary pavement repair
Additonal permanent asphalt pavement repair with asphalt base due to existing of 8-inchs of concrete base
- 6" to 8" sewer pipe enlargement,
The replacement of existing cast -iron -water main on Milburn Street.
The deletion of pay items that are no longer needed on this project,
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
__.1 ......._..\ 0....,II ..,.�r� ;.; , „Id of nr incidental to. the above Change Order.
In rUll tWUI 11111Il any uwucYr wi a„ •�
Co lU6 tafs ' ; un Nan e
Wham J. SdaA2lnc. dba Cilde C Canskuctim Cortpany
� •�•^y _-• _•,-...._.__-_-...
uantractor Name
Teri Skelly
_ _
Contractor Sfginalure
Dote
Date
�`Y�'•-
Ins r
`,� Gd
Pt 'ect Man er _.
T�Q.IZCL Ili
Directa water I -
Cons ion Sol' ter —
Dale
christo her ffirdor
(//��� -
+' � .'.+rli Cit a _ __ _._
WA
--
07/28/202
--
Srnlar Assistant City Atiame
pfy
Dianna Giordano Jul 28 2026 09 .T-----
Douglas Black
(,oi)r)dl Action (d fequired) -
—_
M&C Number N/A
M&C Date Approved
G'
F_ o R-r Wo "['ri City of Fort worth
Change Order Additions
Project Name Water and Sanitary Sewer Replacement, Contract 2021 WSM-C CitySec No. 6 5
Project No.(s) 0600430/070043010200431-103500 DOENo.= CityPro. No. 1 3
Project Water and Sanitary Sewer Main replacements on Westridge Avenue.
Description _
Contractor William J. Schultz, Inc. dba Circle C Construction Company �� Change Order # C4] Date: 7/612026
City Project Mgr. I Dena Johnson, P.E. CityInspector 1 Donald Watson
ADDITIONS
Unit
Unit oat
Total
8
121 DIP BOTOC
UnitWater
0.
F
6 .0
26,000.
10
8" PVC Waledine
Unit I -Water
80.0
LF
$115.00
$9,200.00
11
6' PVC Waterline
Unit I -Water
90.0
LF
$115.00
$10,350.00
18
12' Gate Valve
Unit I -Water
5.0
EA
$4,000.00
$20,000.00
2
8' Gate Valve
Unit I - Water
1.0
EA
$2,200.00
$2,900.00
21
6" Gate Valve
Unit I - Water
2.0
EA
1 $1,800.00
$3,6W.00
23
Fire Hydrant
Unit I - Water
1.0
EA
$5,500.00
$5,500.00
30
24' Casing BOTOC
Unit I -Water
20.0
LF
$1,500.00
$30,000.00
35
2' Water Service, Meter Reconnection
Unit I - Water
1.0
EA
$1,000.00
$1,000.00
39
Remove Concrete Drive
Unit 1- Water
314.0
SF
$6.00
$1,884.05
53
Salvage 1' Water Meter
Unit I - Water
1400
EA
$200.00
$2,800.00
54
Salvage 1 1/2" Water Meter
Unit I - Water
1.0
EA
$200.00
$200.00
57
4' Wide Asphalt Pvmt Repair
Unit I - Water
8.0
LF
$65.00
$520.00
59
Temporary Asphalt Paving Repa
2' HMAC on 6" Flexbase) 4' Wlde
Unit I - Water
1,0 .0
LF
--JF2-0
$32,000.00
Temporary Asphalt Paving Repair(2'
HMAC on 6" Flexbase) T Wide
Unit I - Water
500.0
LF
1 $35.00
17,500.00
61
Temporary Asphalt Paving Repalr(2'
HMAC on " F exbase Extra Width
Unit I - Water
1,000.00
BY
$35.00
35,000.0
67
"Concrete Driveway
Unit 1- Water
513.
SF
20.00
$10,260.00
88
Remove Old Meter Boxes
Unit I -Water
20.0
EA
$50.00
$1,000.00
135
8" Concrete beneath asphalt paving 6"
Unit I -Water
600.0
BY
$175. 0
139
Full Width 2' Surface Mill
Unit I - Water
2,500.0
SY
$8.50
140
Butt Mill
Unit I - Water
1.0
EA
$1,850.00
141
2" uper Pave Type D
Unit I - Water
2,500.0
SY
$37.00
M22101.*000
154
Additonal Fire Line Emergency Repair for R dglaa Country Club
Unit I -Water
1.0
EA
$5,500.00
15
Remove 1V Inlet Top
Unit I - Water
5.0
EA
$1,500.00
156
Remove 19 Inlet
Unit I - Water
5.0
EA
$2,000.00
$10,000.00
157
Remove 10' Recessed Inlet
Unit I - Water
5.
EA
$2,00.00
$10,000,00
158
Adjust Concrete Collar
Unit I - Water
15.0
EA
$1,850.00
$27,750.00
1
6' to 8" Pipe Enlargement
Unit II A - Sewer
1800.00
LF
$40.00
$72,000.00
4.b
Epoxy Manhole Liner
Unit II A - Sewer
67.00
VF
$125.00
,375.00
10
Service Reinstatement, Pipe Enlargement, including 4' 2-Way Clean Outs
Unit II A - Sewer
3.00
EA
$1,650.00
$4,950.00
17
Remove 6" Sewer Line
Unit II A - Sewer
39.00
LF
$15.00
$585.00
25
Pre -CCTV Inspection
Unit II A - Sewer
234.00
LF
$8.00
$1,872.05
27
Trench Safety
Unit II A - Sewer
192.00
LF
$1.00
192. 0
114
6" HDPE Installation for Ridglea CC Under Edgehill Rd.
Unit II A - Sewer
1.00
LS
$8,500.00
$8,500.00
115
Colony Hill Sod Landscaping Additions
Unit II A - Sewer
1.00
LS
$8,584.09
$8,584.09
116
Additonal MOL Mobilization
Unit II A - Sewer
1.00
LS
$7,500.00
$7,500.00
Milburn Street Improvements
7
1 ' PVC Water Pipe
Unit I - Water
686.00
LF
$145,00
$99,470.00
6
2' DIP Water
Unit I - Water
20.00
LF
160.00
$3,200.00
10
8' PVC Water Pipe
Unit I - Water
10.00
LF
$115.00
$1,150.00
18
_
12' Gate Valve
Unit I -Water
2.00
EA
$4,000.00
$8,0D0.0
20
' Gata aloe
Unit I - Water
1.00
EA
$2,2D0.00
$2,200.00
16
Connection to Existing C-12" Water Main
Unit I - Water
3.00
EA
$2,600.00
$7,500,00
5
Ductile Iron Fittings wl Restaints
Unit I - Water
1.00
TN
$10,000.00
$10,000.00
59
Temporary Asphalt Paving Repair 2' HMAC on 6" exbase) 4' Wide
Unit I - Water
750.00
LF
$32.00
$24,000.00
159
Temporary Water Services (for Milburn Installation)
Unit I - Water
1.00
LS
$35,000.00
$35,000.00
65
3 Asphalt Pvmt Type D -Ridgeway Street, Edgehill Road
Unit I - Water
2400.00
BY
$30.00
$72,000.00
64
11" Pavement Pulverization- Ridgeway Street, Edgehill Road
Unit I - Water
2400.00
BY
$12.50
$30,000.00
66
Cem Lime (@ 32 Ib/sy) -Ridgeway Street, Edgehill Road
Unit I - Water
50.00
TN
$525.00
$26,250.00
0
Traffic Control
Unit I - Water
2.00
EA
$8,500.00
$17,000.00
16
Survey Pre and Post
Unit I - Water
1.00
EA
$5,500.00
$5,500.00
6
Permanent Road -Repair in Bryant Irvin
Unit I - Water
80.00
LF
200.00
16,000.00
Page 2 of 4
Unit I - Water
$847,634.00
Unit II A - Sewer
$112,558.09
Unit II 8 - Sewer
Unit III- Paving
Additions Sub Total
$960,192,09
1FG1RT WC31SX14 City of Fort Worth
Change Order Deletions
Project Name Water and Sanitary Sewer Replacement, Contract 2021 WSM-C �J City Sec No 61352
Project No.(s) 0600430/0700430/0200431-103500 DOE No, — N/A City Pro, No. J ( 1035 00
Project Description Water and Sanitary Sewer Main replacements on Westridge Avenue.
Contractor Change Order#® Date 716/2026
City Project Mgr. Dena Johnson, P.E. I City Inspector Donald Watson
4
4B
22
27
29
66
3
5
7
8
9
11
89
133
DELETIONS
DEPT
Qty
Unit JUnitCost
Total
DESCRIPTION
30" Concrete AWWA C303 Water Pipe
Unit I - Water
1106.00
LF
$450.00
$497,700.00
48" Casing BOC
Unit I - Water
4.00
LF
$850.00
$3,400.00
174.00
LF
$1,850.00
$321,900.00
30" Concrete AWWA C303 Water Pipe BOTOC (No casing)
Unit I - Water
$1,800.00
$1,800.00
4" Gate Valve
Unit I - Water
1.00
EA
6,00
EA
$8,500.00
$51,000.00
8" Water Line Lowering
Unit I - Water
90.00
LF
$500.00
$45,000.00
24" Casing BOC
Cem Lime (@32 Ib/sy)- Ridgeway Street, Edgehill Road
Unit I - Water
Unit I - Water
40.00
TN
$525.00
$21,000.00
8" Sewer Pipe
Unit II A - Sewer
422.00
LF
$125.00
$52,750.00
Unit II A - Sewer
1.00
EA
$6,500.00
$6,500.00
4' Manhole
4' Extra Depth Manhole
Unit II A - Sewer
8.00
VF
$350.00
$2,800•00
Unit II A - Sewer
3.00
EA
$1,200.00
$3,600.00
Remove 4' Sewer Manhole
Concrete Collart
Unit II A- Sewer
1.00
EA
$650.00
$650.00
2.00
FA
$150.00
$300.00
Manhole Vacuum Testing
Unit II A -Sewer
Unit II A - Sewer
1.00
EA
$1,500.00
$1,500.00
4" Sewer Service (Reconnection)
Unit II A - Sewer
1.00
VF
$650.00
$650.00
Extra Depth Double Drop
Unit II A - Sewer
I 55.00
LF
$200.00
_
$11,000.00
8" Sewer Pipe, Point Repair
_ _
Unit I - Water $941,800.00
Unit II A - Sewer $79,750.00
Unit II B - Sewer _
Unit III - Paving _
Deletions Sub Total $1,021,550.00
Page 3 of 4
Previous Change Orders
.Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Dena 7ohi on
Signature
Dena Johnson
Name of Employee
Project Manager
Title
oovvnnL
O
ATTEST: pro °a9.i°o
o=°a
°oo * ".
xlatt4 urte Cucek- Dann nex 45d4
Jannette Goodall
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT WORTH.
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: William J. Schultz, Inc. dba Circle C Construction Company
Subject of the Agreement: Water and Sanitary Sewer Replacement Contract 2021, WSM-C
M&C Approved by the Council? * Yes ❑ No M
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes 0 No ❑ 61352-CO4
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 0 No ❑
If unsure, see backpage for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 0 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date: N/A
If different from the approval date.
Expiration Date: N/A
If applicable.
Is a 1295 Form required? * Yes ❑ No 21
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 103500
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 0 No ❑
Contracts need to be routed for CSO processing in the followingorder:
rder:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)