HomeMy WebLinkAbout064503-A1 - Construction-Related - Contract - Driven Brands, Inc.Date Received: 07/28/2026 City Secretary
Time Received:
9:38 a.m.
Contract No.: 64503-A1
FIRST AMENDMENT TO CITY SECRETARY CONTRACT NUMBER 64503
A COMMUNITY FACILITIES AGREEMENT BETWEEN
THE CITY OF FORT WORTH AND Driven Brands, Inc.
This FIRST AMENDMENT TO CITY SECRETARY CONTRACT NUMBER 64503
("First Amendment") is made and entered into by and between the City of Fort Worth ("City"),
a home -rule municipal corporation of the state of Texas, and Driven Brands, Inc. ("Developer").
WHEREAS, the City and Developer entered into a Community Facilities Agreement for
the construction of public infrastructure Improvements for a Project known as Take 5 - E. Bonds
Ranch Rd, City Project Number 106194, City Secretary Contract Number 64503 ("CFA"); and
WHEREAS, Developer provided the City with a development bond as the financial
guarantee for the Improvements in the CFA; and
WHEREAS, Developer has hired a new contractor to construct the Improvements
pursuant to the CFA and the construction costs have increased; and
WHEREAS, City and Developer desire to amend the CFA to reflect the revised Cost
Estimates and Cost Summary Table, Cost Estimates and increase the financial guarantee; and
WHEREAS, Developer has provided the City with a rider to the development bond to
increase the penal sum of the development bond to correspond with the new construction costs;
NOW THEREFORE, City and Developer, acting herein by and through their duly
authorized representatives, enter into the following agreement, which amends City Secretary
Contract Number 64503:
1.
Section 36 of the CFA is amended in its entirety to be and read as set forth in Exhibit A of
this First Amendment, which is attached hereto and incorporated herein by reference.
2.
The Cost Estimates in the CFA are amended in their entirety to be and read as set forth in
Exhibit B of this First Amendment, which is attached hereto and incorporated herein by reference.
3.
a. All other provisions of City Secretary Contract Number 64503 which are not expressly
amended herein shall remain in full force and effect.
OFFICIAL RECORD
CITY SECRETARY
City of Fort Worth, Texas FT. WORTH, TX
First Amendment to City Secretary Contract No. 64503
Page 1 of 4
b. All terms in this First Amendment that are capitalized, but not defined, shall have the
meanings ascribed to those terms in City Secretary Contract Number 64503.
[SIGNATURES ON FOLLOWING PAGE]
City of Fort Worth, Texas
First Amendment to City Secretary Contract No. 64503
Page 2 of 4
IN TESTIMONY WHEREOF, the City and Developer have executed this First
Amendment to be effective on the date signed by the City's Assistant City Manager.
CITY OF FORT WORTH
AM%-M&—
Dianna Giordano (Jul 28, 2026 09:28:02 CDT)
Jesica McEachern
Assistant City Manager
Date: 07/28/2026
Recommended by:
)0AI4gw, W-
Dwayne Hollars/Leonel Rios
Sr. Contract Compliance Specialist
Development Services
Approved as to Form & Legality:
Qom Grl)lwlah-1
JOOessika Williams
Assistant City Attorney
Date: 07/17/2026
gQg4OAnnIla
a�. � F o0o rlla�0
ATTEST: p"°
Pvo o=4 * oo *�a
d
da�� nEXA?o4p
Jannette S. Goodall
City Secretary
City of Fort Worth, Texas
First Amendment to City Secretary Contract No. 64503
Page 3 of 4
DEVELOPER:
Driven Brands, Inc.
Anthony WinchesMr (Jul 17, 2026 09:14:28 EDT)
Anthony Winchester
Vice President - Legal, Real Estate
Date: 07/17/2026
Contract Compliance Manager:
By signing, I acknowledge that I am the
person responsible for the monitoring and
administration of this contract, including
ensuring all performance and reporting
requirements.
jzu�)
Kandice Merrick
Contract Compliance Manager
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
EXHIBIT A
36.
Cost Summary Sheet
Project Name: Take 5 - E. Bonds Ranch Rd
CFA No.: 25-0177 City Project No.: 106194
Items Developer's Cost
A. Water and Sewer Construction
1. Water Construction $ 134,250.00
2. Sewer Construction $ 268,512.00
Water and Sewer Construction Total $ 402,762.00
B. TPW Construction
1. Street $ 104,865.00
2. Storm Drain $ 18,899.00
3. Street Lights Installed by Developer
4. Signals
TPW Construction Cost Total $ 123,764.00
Total Construction Cost (excluding the fees): $ 526,526.00
Estimated Construction Fees:
C. Construction Inspection Service Fee $36,112.50
D. Administrative Material Testing Service Fee $1,378.00
E. Water Testing Lab Fee $270.00
Total Estimated Construction Fees: $ 37,760.50
IPRC No.: 25-0056
Financial Guarantee Amount
Bond = 100% $ 526,526.00 x
City of Fort Worth, Texas
First Amendment to City Secretary Contract No. 64503
Page 4 of 4
EXHIBIT B
Cost Estimates
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID
00 42 43
DAP - BID PROPOSAL
Page I of 7
Bidder's Application
Project Item Information
Bidder's Proposal
Bidlist Item
No.
Description
Specification
Section No.
I Unit of
Measure
Bid
Quantity
Unit Price
Bid Value
UNIT I: WATER
IMPROVEMENTS
1
0241.1118 - 8" Plug
3305.0003 - 8" Water Line Lowering
3305.0109 - Trench Safety
0241 14
33 05 12
EA
1
$1,000.00
$1,000.00
2
EA
1
$9,250.00
$9,250.00
3
33 05 10
LF
216
$10.00
$2,160.00
4
3311.0001 - Ductile Iron Water Fittings w/ Restraing
3311 11
TON
1
$750.00
$750.00
5
3311.0241 - 8" Water Line
3311 12
LF
216
$415.00
$89,640.00
6
3312.0001 - Fire Hydrant Assembly
33 12 40
EA
1
$5,750.00
$5,750.00
7
3312.0117 - Connect to Existing - Cut In Tee
33 12 25
EA
1
$1,500.00
$1,500.00
8
3312.2003 - 1" Irrigation Water Service Line
33 12 20
EA
1
$7,550.00
$7,550.00
9
3312.2003 - 1" Domestic Service Line
33 12 20
EA
1
$7,550.00
$7,550.00
10
3312.3003 - 8" Gate Valve
33 12 20
EA
2
2
$4,250.00
$300.00
_
$8,500.00
11
3110.0103 - 12"-18" Tree Removal - 1 Tree & 1 Stump
31 1000
EA
$600.00
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
_
40
41
42
TOTAL
UNIT I: WATER IMPROVEMENTS
$134,250.00
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
Form Version May 22, 2019
00 42 43_Bid Proposal_ DAP._ REV TO MATCH PROPOSAL
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID
00 42 43
DAP -BID PROPOSAL
Page 2 of 7
Bidder's Application
Project Item Information
Bidder's Proposal
Bidlist Item
No.
Description
Specification
Section No.
I Unit of
Measure
Bid
Quantity
Unit Price
Bid Value
UNIT II: SANITARY SEWER IMPROVEMENTS
1
3301.0001 Pre -CCTV Inspection
3301 31
LF
136
$ 1.00
$136.00
2
3301.0002 Post CCTV Inspection
3301 31
LF
136
$ 1.00
$136.00
3
3305.1103 - 20" Steel Encasement
33 05 22
LF
136
$ 1,250.00
$170,000.00
$400.00
4
3305.0109 - Trench Safety
33 05 10
LF
40
$ 10.00
5
3331.4119 - 8" Ductile Iron Pipe
3311 10
LF
336
$ 505.00
$68,680.00
6
3339.1001 - 4' Diameter Sanitary w/ Hydraulic Slide
3339.0001 - Epoxy Manhole Liner
3339.1102 - External Drop on Existing Manhole
3301.0004 - Final MH-CCTV Inspection
33 39 10,
33 39 20
33 39 60
EA
1
$ 16,350.00
$16,350.00
7
VF
16
$ 285.00
$4,560.00
8
03 80 00,
33 39 10
EA
1
$ 7,500.00
$7,500.00
9
3301 31
3301 30
EA
EA
2
2
$ 125.00
$ 250.00
$250.00
$500.00
10
3301.0101 -Manhole Vacuum Testing
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
TOTAL UNIT II: SANITARY SEWER IMPROVEMENTS
$268,512.00
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
Form Version May 22, 2019 00 42 43_Bid Proposal_DAP._REV TO MATCH PROPOSAL
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID
00 42 43
DAP -BID PROPOSAL
Page 3 of 7
Bidder's Application
Project Item Information
Bidder's Proposal
Bidlist Item
No.
Description
Specification
Section No.
I Unit of
Measure
Bid
Quantity
Unit Price
Bid Value
UNIT III: DRAINAGE IMPROVEMENTS
1
3341.0205 - 24" RCP, Class III
3349.3003 - Reset 24" Headwall
3341 10
03 80 00,
024114
LF
EA
10
$245.00
$2,450.00
2
1
$1,656.00
$1,656.00
3
3301.0012 - Post -CCTV Inspection of Storm Drain
3301 32
LF
68
$1.00
$68.00
4
3292.0100 - Block Sod Placement
32 92 13
SY
615
$15.00
$9,225.00
5
3123.0101 - Unclassified Excavation by Plan - Import Fill
and Channel Grading
31 2316
CY
220
$25.00
$5,500.00
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
38
40
41
42
_
43
TOTAL UNIT
III: DRAINAGE IMPROVEMENTS
$18,899.00
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
Form Version May 22, 2019 00 42 43 Bid Proposal_DAP._REV TO MATCH PROPOSAL
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID
00 42 43
DAP -BID PROPOSAL
Page 4 of 7
Bidder's Application
Project Item Information
Bidder's Proposal
Bidlist Item
No.
Description
Specification
Section No.
I Unit of
Measure
Bid
Quantity
Unit Price
Bid Value
UNIT IV: PAVING IMPROVEMENTS
1
3211.0502 - 8" Lime Treated Subgrade
3212.0401 - 2' Wide HMAC Pavement Patch
3211 29
32 12 16
SY
168
$40.00
$6,720.00
2
TON
SF
10
1407
$350.00
$65.00
$3,500.00
$91,455.00
3
3213.0402 - 7" Concrete Pavement w/Curb and Gutter
32 13 13„
32 13 20
4
3216.0101 - 6" Conc Curb and Gutter
32 16 13
LF
120
$12.00
$1,440.00
5
3123.0101 - Unclassified Excavation by Plan - Import Fill
and Grading for Driveway
31 2316
CY
70
$25.00
$1,750.00
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
TOTAL UNIT IV: PAVING IMPROVEMENTSI
$104,865.00
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
Form Version May 22, 2019 00 42 43_Bid Proposal_DAP._REV TO MATCH PROPOSAL
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID
00 42 43
DAP - BID PROPOSAL
Page 7 ol'7
Bidder's Application
Project Item Information
Bidder's Proposal
Bidlist Item
Specification
Unit of
Bid
Description
Unit Price
Bid Value
No.
Section No.
Measure
Quantity
Bid Summary
UNIT I: WATER IMPROVEMENTS
UNIT II: SANITARY SEWER IMPROVEMENTS
UNIT III: DRAINAGE IMPROVEMENTS
UNIT IV: PAVING IMPROVEMENTS
This Bid is submitted by the entity named below:
BIDDER:
NORTH TEXAS CONTRACTING, INC.
7368 FM 2449
PONDER, TX 76259
Contractor agrees to complete WORK for FINAL ACCEPTANCE within
CONTRACT commences to run as provided in the General Conditions.
Total Construction Bid
BY: CARSON COLLIER
7 �
TITLE: VP -PM
DATE: 6/29/2026
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
Forni Version May 22, 2019
$134,250.00
$268,512.00
$18,899.00
$104,865.00
90 working days after the date when the
00 42 43_Bid Proposal_ DAP._ REV TO MATCH PROPOSAL
FORT WORTH.
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: Driven Brands, Inc.
Subject of the Agreement: CFA - amendment
M&C Approved by the Council? * Yes ❑ No 8
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes 8 No ❑ 64503
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 8 No ❑
If unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 8 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date:
If different from the approval date.
Expiration Date:
If applicable.
Is a 1295 Form required? * Yes ❑ No 8
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 106194
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 8 No ❑
Contracts need to be routed for CSO processing in the following order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.