HomeMy WebLinkAbout064609-CO8 - Construction-Related - Contract - McCarthy Building Companies, Inc.FORT WORTH® City of Fort Worth `r� Change Order Request CSC No. 64609-008 Project Name Bomber Spur Trail Phase 1 City Sec # 64609 Client Project#(s) 104345 Project Construction of a shared use path from Calmont Ave. to US Route 377, including pedestrian crossings over Camp Bowie Blvd. and US Route 377 Description Contractor McCarthy Building Companies, Inc. Change Order # 8 Date 7/15/2026 City Project Mgr. Blaise Grissom City Inspector Sergio Garcia Pedroza Dept. Original Contract Amount Extras to Date Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date PARD Totals Contract Time (CD) $4,901,279.77 $4,901,279.77 215 $41,512.98 $41,512.98 20 $2,058.48 $2,058.48 $4,940,734.27 $4.940,734.27 235 235 Original Funds Available for Change Orders Remaining Funds Available for this CO Additional Funding (if necessary) CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 0.80% MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) $6,126,599.71 Traffic Control Plans for US 377 and Spur 580 have been updated to reflect additional barricades for the Westbound closure of US 377, the removal of unnecessary 1, and the inclusion of barricade and signage thumbnail images, as required for permitting applications. This is a minor change order with zero added costs and zero tional contract time. Original plan sheets 012 through 015 have been updated, and a new plan sheet 012a has been added. This is a TxDOT funded project, and as i TxDOT requires any and all changes to a Traffic Control Plan be processed as an official Change Order. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. offContractor's Company Name Contractor (Name) Contract Signature Date s�^�""� McCarthy Building Companies, Inc. Peter Siggerud Ae � s� eruct (Afl za, zozs 1516 14 cor 07/28/2026 Inspector/Inspection Supervisor Date Project and Contract Compliance Manager Date ��Jj-�•--- 07/30/2026 -- 07/28/2026 Program Manager Date Senior Capital Project Officer Date Assistant Director Date Director, Contracting Department (Dept) Date - :`t- -.. Teresa TYlomason z; rL19:32 CDT) Assistant City Attorney Date Assistant City Manager Date ❑ouyl,, Blank: (A,q 4, 2026 13'31:32 CDT) 08/04/2026 Dana Bur hd (Au . 2026 11:26:33 CDT 08I05/2026 Council Action (if required) ATTEST: A.N...:.s e � & Jannette Goodall, City Secretary 6o4oun C � � FORto4 O9.10 _Fg PVo 0=0 3a n rExAq+oOp 4 �nnaa6'�' M&C Number N/A M&C Date Approved NIA cc cc OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX Foxr Wox'ra City of Fort Worth 11v- - Change Order Additions Project Name Bomber Spur Trail Phase 1 City Sec # 64609 Client Project # 104345 Contractor McCarthy Building Companies, Inc. PM Blaise Grissom Inspector Change Order Submittal # ® Date 7115I2026 Change Order Additions Page 2 of 4 FORTWORTH City of Fort Worth —— Change Order Deletions Project Name Bomber Spur Trail Phase 1 City Sec # 64609 Client Project# 104345 Contracto McCarthy Building Companies, Inc. PIMJ Blaise Grissom Inspector® Change Order Submittal # ® Date 7/15/202fi Change Order Deletions Page 3 of 4 MISBE for this Change Order M/SBE Sub Type of Service Amount for this CO N/A Total $0.00 Previous Change Orders CO # DATE AMOUNT Total $0.00 - - o Rh -No p�.a - oI -<cn aLL< 6� " �$ t5 w �fi w F E x 5 1 �w-,�ds ,aawoq-oaaa �mso\^�oMp°or.H\:a :a Yalu rou�cmH� , cm 14 tl 5 -H ':9, tZ—G —ml 19 'pallor N $ -gp582gam w 462, i E I- um FAN ��- ♦, E wo Rom. r•. pp ♦ 'wa [may, _• �w Q� l _ Y4� !F $ c»a�oid i4,iao� �s,o,i\sia�vs\aao,\�o�sry,-,ids ,avwov-maa�o�so\.(onPoorv.»\:.: �a� (3ansoro ccc snl zs:�e+a� ao-so-szoz _p cos )soi w v —, 'oa ,, roo-so-szoz le 'aaxio. i G$ t` M E jw No RZN ~ o LL z�N a �a _ _ �� - F E s no. soa. BR `1 8 3NnHOIM 0 .oil I F- vi H � JII I I oo �a i, / LLI J O�ec y\ amm DR UM I y 6mpuold loi;uo> >q;o„\sways\ppo�\u6isap—�ntls—�agwoq—Ob461O190\RgnpoormD\;ry :awoualLl f(i) aNn[n Cnl a 14 tl 600H '09'9Z:90 tZ—So-9ZOE Xg 'PaliPld Ho O o Ea o w E s a = I C o4q _ o a I a ® 3 O M m � CIO d W � �a I - I r7 O a I p 1�353Q� �J 1� _ / / If � ` C\ �a o 3)� I i 8 3NIlHO1VW 6mp'-ld piiuoa W.,j\sways\ppw\0-- Inds Iagwoq—Ob4 -11\.fonp—"\:ry w ualj f!>) �NIKT, enl r yso� 'p.ddid 'II:SS 9l 2Z-90-Ml 19 'oa w tpgyn- L w o k p E 0. C. N o av Doi -` - oQ o� cn W o�w - o� W a a ¢ o p e J a � U p N lJ [tJ v: x a f xgt6 I ¢o / b .tl Y _ I Ll i o I o Iz w Haan=w���aa ,gas woa-oraaio�eov.oMaoo, Maws Yalu vla ni nn+eani vlv vzual ,a.rc.ci rz an-amz .aa�os soy FORT WORTH. City Secretary's Office Contract Routing & Transmittal Slip Contractor's Name: McCarthy Building Companies, Inc. Subject of the Agreement: Bomber Spur Trail Phase 1 - Change Order #8 M&C Approved by the Council? * Yes ❑ No M If so, the M&C must be attached to the contract. Is this an Amendment to an Existing contract? Yes 0 No ❑ CSC 64609-CO8 If so, provide the original contract number and the amendment number. Is the Contract "Permanent"? *Yes 0 No ❑ If unsure, see backpage for permanent contract listing. Is this entire contract Confidential? *Yes ❑ No 0 If only specific information is Confidential, please list what information is Confidential and the page it is located. Effective Date: If different from the approval date. Expiration Date: If applicable. Is a 1295 Form required? * Yes ❑ No ED *If so, please ensure it is attached to the approving M&C or attached to the contract. Project Number: If applicable. 104345 *Did you include a Text field on the contract to add the City Secretary Contract (CSC) number? Yes 0 No ❑ Contracts need to be routed for CSO processing in the followingorder: rder: 1. Katherine Cenicola (Approver) 2. Jannette S. Goodall (Signer) 3. Allison Tidwell (Form Filler) *Indicates the information is required and if the information is not provided, the contract will be returned to the department.