HomeMy WebLinkAbout064425-R1CO5 - Construction-Related - Contract - Woody Contractors, Inc.CSC No. 64425-R1CO5
FORT WORTH,
Project Name Citywide Storm Drain Rehabilitation Open -Cut
City of Fort Worth
Change Order Request
City Sec # 64425-R1
Client Project #(s) 100092
Project Description Replacement and/or Improvement of Existing City Drainage Infrastructure
Contractor Woody Contractors,inc Change Order # 5 Date 7/21/2026
City Project Mgr. Ahana Basnet City Inspector IN/A
Dept. I TPW I I I Totals I ContractttTime
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 0.00%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) $2,500,000.00
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Additional bid items are required but were not included in the original unit price contract. These items are being added for the construction of the storm drain improvements at
Rogers Avenue (CPN 104067). The additional scope of work includes constructing curb and gutter to contain stormwater within the roadway limits and installing three 10-foot
curb inlets to collect runoff and convey it to the existing storm drainage system along University Drive. The proposed unit costs have been compared to the recent drainage
improvement Reactive Contract Unit Price, bid tabulations, and other pricing for similar items and were found to be reasonable.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements.
Contractor's Company Name
Contractor Name
Contract Signature
Date
Woody Contractors, Inc
Troy Wood
Inspector/Inspection Supery Date
Project and Contract Compliance Manager
Date
Program Manager Date
Senior Capital Project Officer
Date
Assistant Director (Dep:' Date
Director, Contracting Department (Dept)
Date
Assistant City Attorney Date
Assistant City Manager
Date
Council Action if required)
ATTEST:
Jannette Goodall, City Secretary
M&C Number I N/A M&C Date Approved N/A
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FOaRT WORTH City of Fort Worth
�,I-- Change Order Additions
Project Name Citywide Storm Drain Rehabilitation Open -Cut City Sec # 64425-R1
Client Project# 100092
Contractor Woody Contractors, Inc PM Ahana Basnet Inspector N/A
Change Order Submittal # 0 Date 7/21/2026
ADDITIONS
ITEM
DESCRIPTION
DEPT
Qty
Unit
Unit Cost
Total
449
TEMP SHORING/ PROTECT EX. WATER
TPW
0.00000000
LS
$5,250.00
$0.00
450
REM/ RESET WOOD BOLLARDS
TPW
0.00000000
LS
$2,500.00
$0.00
451
PVTM MARKINGS (CPN 104067)
TPW
0.00000000
LS
$5,000.001
$0.00
452
1 REM & RESET SIGN
TPW
0.00000000
EA
$500.001
$0.00
TPW $0.00
Sub Total Additions 0.00
Change Order Additions Page 1 of 1
FORTWORTH City of Fort Worth
Change Order Deletions
Project Name I Citywide Storm Drain Rehabilitation Open -Cut City Sec # 64425
Client Project # 1 100092
Contractor Woody Contractors,lnc PM Mohanad Habib Inspector N A
Change Order Submittal # ® Date 7I612026
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
TPW $0.00
Sub Total Deletions $0.00
Change Order Deletions Page 3 of 4
MISBE for this Change Order
Previous Change Orders
CO # DATE AMOUNT
Total $0.00
Signature:
Tr (Jul 23, 2026 15:04:19 CDT)
Email: twoody202O@aot.com
Signature:��
Email: Michael.Glover@fortworthtexas.gov
Signature:
Email: Ahana.Basnet@fortworthtexas.gov
Signature: Q
Email: Lissette.Acevedo@fortworthtexas.gov
Signature:
Lauren Prieur (Jul 28, 2026 13:43:48 CDT)
Email: Lauren.Prieur@fortworthtexas.gov
Signature:
Email: jesica.mceachern@fortworthtexas.gov
Signature:
Email: Thanaa.Maksimos@fortworthtexas.gov
Signature: TatyklJ L. kyw(sack
Patricia L. Wadsack (Jul 28, 2026 13:28:02 CDT)
Email: patricia.wadsack@fortworthtexas.gov
Signature:
Douglas Black (Aug 3, 2026 12:32:00 CDT)
Email:
Douglas.Black@fortworthtexas.gov
oano
gy��FONi`ne0p�
Signature:
�- �� l
R /J �p -7
�/I� �,,�
Email:
jannette.goodall@fortworthtexas.gov
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
2/11/26, 1:56 PM M&C Review
Official site of the City of Fort Worth, Texas
CITY COUNCIL AGENDA FORT ORTH
Create New From This M&C
REFERENCE **M&C 25- 20SWM CITYWIDE
DATE: 11/11/2025 NO.: 1042 LOG NAME: STORMDRAIN
IMPROVEMENTS 2025
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: (ALL) Authorize Execution of a Contract with Woody Contractors, Inc. in the Amount of
$2,000,000.00 for the Citywide Storm Drain Improvements Project, with a One Year
Renewal Option
RECOMMENDATION:
It is recommended that the City Council authorize execution of a contract with Woody Contractors, Inc.
in the amount of $2,000,000.00 for the Citywide Storm Drain Improvements project (City Project No.
100092), with one renewal option.
DISCUSSION:
This Mayor and Council Communication (M&C) will authorize execution of a construction contract with
Woody Contractors, Inc. in the amount of $2,000,000.00 for the extension, replacement, and/or
improvement of existing City drainage infrastructure on an on -call basis. Work on individual locations
will be authorized by work orders. The cost of each work order will be based on the unit prices bid by
the contractor for the work items in the solicitation. The maximum cumulative amount for all work
orders under this contract is $2,000,000.00. While the total bid amount is $24,199,785.00, the actual
contract amount will be $2,000,000.00, which represents the budgeted limit for the on -call services.
The bid amounts cited in the solicitation were based on hypothetical quantities for the purpose of
establishing unit prices for each work item. Payment for each work order will be made based on actual
quantities measured at those bid prices. Funding will be verified individually for each work order prior to
its execution.
The project was advertised for bid in the Fort Worth Star -Telegram on August 27, 2025, and September
3, 2025. On September 18, 2025, one bid was received:
Bidder Amount
Woody Contractors, Inc $24,199,785.00
The term of the contract will be until the work is completed or funds are expended, whichever occurs
first. The contract may be renewed one (1) time, with the same terms, conditions, and unit prices, at
the City's discretion.
An additional $292,000.00 is needed for contingencies, construction management, surveying,
inspection, materials testing, and GIS/project controls.
Project Cost Description
Amount
Woody Contractors, Inc.
$2,000,000.00
Contingencies, Construction Management,
Surveying, Inspection, Material Testing
$292,000.00
Total Project Budget
$2,292.000.00
apps.cfwnet.org/council packet/mc_review.asp?ID=33905&councildate=11 /11 /2025 1 /2
2/11/26, 1:56 PM
M&C Review
These projects are not currently defined, and the impacts on Operations Budgets are unknown.
Projects that replace or improve existing infrastructure should not have an impact on the operational
budget, as the City already maintains infrastructure in these locations. However, extensions, such as
additional storm drainpipes or inlets, would increase future maintenance responsibilities.
Funding is budgeted in the Drainage Improvement Projects programmable project (City Project No.
P00043) within the Stormwater Capital Projects Fund for the purpose of funding various work order
projects, as appropriated.
The projects are located in ALL COUNCIL DISTRICTS.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are available in the current capital budget, as previously
appropriated, in the Stormwater Capital Projects Fund for the Drainage Improvements Projects
programmable project to support the approval of the above recommendation and execution of the
contract. Prior to any expenditure being incurred, the Transportation and Public Works Department
has the responsibility to validate the availability of funds.
TO
Fund
Department
Account
Project
Program
Activity
Budget
Reference #
Amount
ID
ID
Year
(Chartfield 2)
FROM
Fund
Department
Account
Project
Program
Activity
Budget
Reference #
Amount
ID
ID
Year
(Chartfield 2)
Submitted for City Manager's Office by-.
Originating Department Head:
Additional Information Contact:
ATTACHMENTS
Jesica McEachern (5804)
Lauren Prieur (6035)
Thanaa Maksimos (2485)
1295 Form.pdf (CFW Internal)
20SWM CITYWIDE STORMDRAIN IMPROVEMENTS 2025 funds avail.docx (CFW Internal)
20SWM CITYWIDE STORM DRAIN PROJECT FID TAB LE.xlsx (CFW Internal)
Citywide Bid Tabulation.pdf (CFW Internal)
SAMS Search 2025.10.7.pdf (CFW Internal)
apps.cfwnet.org/council packet/mc_review.asp?ID=33905&councildate=11 /11 /2025 2/2
FORT WORTH.
Routing and Transmittal Slip
Transportation & Public Works Department
DOCUMENT TITLE: Citvwide Storm Drain Improvements Proiect Construction Contract
M&C: 25-1042 CPN: 100092 CSO: CS64425-R1 DOC#:
Date: 07/22/2026
To:
Name
Department
Initials
Date Out
1
Troy Woody
Contractor
07/23/2026
2.
Mike Glover
TPW - Inspector
07/23/2026
3.
Ahana Basnet
TPW - Project Manager
07/23/2026
4.
Thanaa Maksimos
TPW —Program Manager
07/23/2026
5.
Lissette Acevedo
TPW — Sr. CPO
J
07/24/2026
6.
Patricia Wadsack
TPW — Assistant Director
07/28/2026
7.
Lauren Prieur
TPW - Director
Lauren P-,
07/28/2026
8.
Doug Black
Legal - Assistant City Attorney
08/03/2026
9.
Jesica McEachern
CIVIC) — Assistant City Manager
08/11/2026
10.
Katherine Cenicola
CSO — City Secretary
cc
08/11/2026
11.
Jannette Goodall
CSO — City Secretary
J neli
08/12/2026
12.
Allison Tidwell
CSO — City Secretary
Ar
08/13/2026
13.
Tpw_SW_Contract
TPW Stormwater
NEEDS TO BE NOTARIZED: DYES ❑No
RUSH: ❑YES ®No SAME DAY: ❑ YES ❑No NEXT DAY: ❑YES []No
ROUTING TO CSO: ®YES ❑No
Action Required: ❑ Signature/Routing and or Recording
FORT WORTH.
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: Woody Contractors, Inc.
Subject of the Agreement: Additional bid items are needed but were not included
in the original unit price contract
M&C Approved by the Council? * Yes 0 No ❑
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes 0 No ❑ CS64425-CO5
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 0 No 0
If unsure, see backpage for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 0 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date: 11 /11 /2025
If different from the approval date.
Expiration Date: 11/10/2030
If applicable.
Is a 1295 Form required? * Yes 0 No ED
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 100092
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 0 No ❑
Contracts need to be routed for CSO processing in the followingorder:
rder:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.