HomeMy WebLinkAbout064158-A3 - Construction-Related - Contract - SpawGlass Contractors, Inc.AMENDMENT NO.3 TO AGREEMENT
Meacham Airport Field Maintenance Facility Project— Design Build
STATE OF TEXAS 64158-A3
CITY SECRETARY CONTRACT NO.
COUNTY OF TARRANT
WHEREAS, the City of Fort Worth and SpawGlass Contractors, Inc. of the City of Fort
Worth County of Tarrant, State of Texas (Contractor) made and entered into City
Secretary Contract No. 64158 (The Contract), which was authorized by the City Council
by M&C 25-0229 in the amount of 5,500,000.00 on the 11th day of March 2025, for
Meacham Airport Design Build Contract; and
WHEREAS, the initial contract price for design services was $545,055.00; and
subsequently revised by Amendment Number 1 for $36,438.00, which was approved on
the 10th Day of February 2026 and Amendment #2 was approved 15th Day of June
2026 in the amount of $605,544.00; a further amendment is necessary to support
contractors' ability to deliver the scope of work for the Meacham Airport Design Build
Contract and related costs referred to in Attachment A; and
NOW THEREFORE, City and Contractor, acting herein by and through their duly
authorized representatives, enter into the following agreement, which amends the
Contract:
In accordance with Paragraph 5.2.1 of the contract, it is amended as follows:
"The GMP shall be the cost of the Design & Construction Services, in the amount of
$5,495,729.00 Five Million Four Hundred Ninety -Five Thousand Seven Hundred
Twenty -Nine Dollars. The increase in the amount of $4,308,692.00, Four Million Three
Hundred Eight Thousand Six Hundred Ninety -Two Dollars to include: Remaining
construction work to complete the 14,076 SF Meacham Maintenance Facility and site
work without the add alternates, as defined in Article 1.4.7, plus the Design -Builders fee
of 5%, which shall not exceed the Guaranteed Maximum Price set forth in the GMP
FAIT, MirPT-is Y
This addition will cover, at a minimum, the areas of scope listed in Attachment A:
1. SpawGlass Guaranteed Maximum Price - Owner Change Order #3 Dated 2026-
07-10/Rev 02 2026-07-14
OFFICIAL RECORD
City of Fort Worth, Texas
Meacham Airport Field Maintenance Project Amendment 3 CITY SECRETARY
Page 1 of 3
FT. WORTH, TX
Executed and effective as of the date signed by the Assistant City Manager below.
FORT WORTH:
City of Fort Worth
V41
BY: Valerie Washington (Aug 14, 2026 16:09:35 CDT)
Name: Valerie Washington
Title: Assistant City Manager
Date:
Approval Recommended:
By:
Name: Marilyn Marvin
Title: Director, Property Management
Attest:
By:
Name
Title:
o�n
Fonr° &
PVo o=O
ll }Q°a t e44'
Jannette Goodall
City Secretary
CONTRACTOR:
LlbyCILraver (JUI 3U. 1UZb U9:4J:Zb UU
By:
Name: Lloyd Faver
Title: President, North Texas Region
Date:
City of Fort Worth, Texas
Meacham Airport Field Maintenance Project Amendment 3
Page 2 of 3
Contract Compliance Manager:
By signing I acknowledge that I am the person
responsible for the monitoring and
administration of this contract, including
ensuring all performance and reporting
requirements.
By:
Name: Nikita Watts
Title: Sr. Capital Project Officer
Approved as to Form and Legality:
A
Stephen Hines (J�ul 31'M26- 15:48:01 CDT)
By:
Name: Stephen M. Hines
Title: Sr. Assistant City Attorney
Contract Authorization:
M&C:
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FUNDING BREAKDOWN SHEET
City Secretary Contract No. 64158 -A3
Amendment No. 3
Fund
Dept ID
Account
Project ID
CF1-
Activity
Amount
53002
0550435
5330500
105655
008130
545,055.00
53002
0550435
5330500
105655
008130
36,438.00
53002
0550435
5330500
105655
008130
605,544.00
53002
0550435
5330500
105655
008130
4,308,692.00
Total:
$5,495,729.00
City of Fort Worth, Texas
Meacham Airport Field Maintenance Project Amendment 3
Page 3 of 3
Ailk
low
SpawGlass
Providing the Absolute Best
Construction Experience
Y
-` -"MMEL..
t OL
i
r� 'ti ��,• - _ ,ram r � ) j
TABLE OF CONTENTS
TAB 1 TAB 6
DETAILED COST REPORT PROJECT SCHEDULE
TAB 2 TAB 1
GENERAL CONDITIONS PROJECT TEAM
TAB 3 TAB 8
ALTERNATES SITE LOGISTICS
TAB 4 TAB 9
ASSUMPTIONS & CLARIFICATIONS N/A
TAB 5 TAB 10
LIST OF DOCUMENTS
Best
ice
Recap Report
Rev 02 7/14/26
Meacham Airport Maintenance Facility
Owner Change Order #003
Estimate Date:
Project Size (SF):
Project Location:
07/10/2026
14,076
Fort Worth, TX
ITEM
Documents Date
Project #:
Lead Estimator:
COST
04/28/2026
3024100
Justin Hyder
COST I SF % OF TOTAL
Direct Costs
Div. 01 - General Requirements
1 3,166,822 1
134,005
224.98
9.52
I 73.50
3.11 %
Div. 03 - Concrete
696,779
49.50
16.17 %
Div. 04 - Masonry
Div. 05 - Metals
0
0.00
1.62
0.00 0/0
0.53
22,825
27,738
Div. 06 - Wood, Plastics & Composites
1.97
0.64 %
Div. 07 - Thermal & Moisture Protection
17,714
1.26
0.41 0/6
Div. 08 - Openings
174,005
12.36
4.04 0/6
Div. 09 - Finishes
Div. 10 - Specialties
214,391
22,872
15.23
4.98 0/6
1.62
0.53
Div. 22 - Plumbing
220,100
1.5.64
5.11 %
Div. 23 - Heating, Ventilating & Air Conditioning
166,255
11.81
3.86 %
Div. 26 - Electrical
Div. 27 - Communications
511,401
0
36.33
11.87
0.00 %
0.00
Div. 28 - Electronic Safety & Security
33,572
2.39
0.78 %
Div. 31 - Earthwork
537,871
38.21
12.48 %
4.45
4.54
Div. 32 - Exterior Improvements
Div. 33 - Utilities
191,798
195,496
13.63
13.89
Meacham Airport Maintenance Facility Estimate Date: 0711012026
Owner Change Order #003 Page 1 of 2 Documents Date: 0412812026
ITEM I COST
COST I SF % OF TOTAL
General Conditions
367,413
Builder's Risk Insurance
12,500
General Liability Insurance
47,325
Payment and Performance Bonds
63,782
Subcontractor Bonds
0
12,225
Warranty
97,804
Contractor's Contingency
Owner's Contingency
296,246
26.10 8.53 %
0.89 0.29 %
3.36 1.10 %
4.53 1.48 %
0.00 0.00
0.87 0.28 %
6.95 2.27 %
21.05 6.88 %
Overhead and Profit 244,575 17.38 5.68 %
Total Cost $ 4,308,692 $ 306.10 100.000/0
Meacham Airport Maintenance Facility
Owner Change Order #003 Page 2 of 2
Estimate Date: 0711012026
Documents Date: 0412812026
Detail Report
Rev 02 7/14/26
Meacham Airport Maintenance Facility
Owner Change Order #003
Estimate Date:
07/10/2026
Documents Date:
04/28/2026
Project Size (SF):
14,076
Project #:
3024100
Project Location:
Fort Worth, TX
Lead Estimator:
Justin Hyder
ITEM QUANTITY l UM UNIT COST TOTAL COST
11 - General Requirements
General Requirements
134,005
14,076.0 SF 0.81 11,428
8.0 Mos 650.00 5,200
1.0 LS 5,000.00 5,000
8.0 Mos 1,623.75 12,990
Final Clean
Safety Supplies
Small Tools
Temp Power
Temp Water
Connex
Connex Delivery & Pickup
Water, Ice, Cups
8.0 Mos
1,082.50 8,660
757.75 6,062
1,624.00 3,248
250.00 2,000
8.0 Mos
2.0 Each
8.0 Mos
Temp. Protection
14,076.0 SF
1.00 14,076
2,000.00 2,000
20,000.00 20,000
3,897.00 31,176
Safety Signage
Layout / Survey
1.0 LS
1.0 LS
Site Maintenance/Street Cleaning
8.0 Mos
Potholing/Hydrovac Utilities
1.0 LS
10,000.00
10,000
Temporary Fire Extinguishers Bldg.
1
Cast -In -Place Concrete (Building)
4.0 Each
541.25
2,165
298,460
Slab on Grade (Includes Piers & GB's)
14,076.0 SF
21.20
298,460
Cast -In -Place Concrete (Site)
Concrete Site Paving
398,319
27,818.0 SF
11.84
329,240
5" Concrete Paving ILO of Asphalt Millings
1
Masonry / Stone
7,986.0 SF
8.65
69,079
0
8" CMU at Int. Walls at Elec Workstation (Add Alt.)
381.1 SF
0.00
0
Meacham Airport Maintenance Facility Estimate Date: 0711012026
Owner Change Order #003 Page 1 of 6 Documents Date: 0412812026
ITEM QUANTITY I UM UNIT COST TOTAL COST
► I
Structural/Miscellaneous Steel - Fabrication
Steel Pipe Bollards - Fab. 55.0 Each
Div. 0.Wood, Plastics & Composites
Architectural Woodwork
22,825
415.00
22,825
27,738
Architectural Woodwork - Breakroom Millwork
37.1 LF
298.60
11,078
Architectural Woodwork - Breakroom Solid Surface
Countertops
Architectural Woodwork - Mudroom Bench
Div. 07 - Thermal & Moisture Protection
Waterproofing / Dampproofing / Joint Sealants
Building Sealants/HM Doors
Site Sealants
Div. 0: Openings
Doors / Frames / Hardware
18.0 LF
314.88
5,668
10,992
17,714
17,714
4,881
1.0 Each
10,991.89
1.0 LS
4,881.00
1.0 LS
12,833.00
12,833
174,005
31,904
Hollow Metal Doors - Supply
8.0 Each
619.62
4,957
Hollow Metal Frames - Supply
15.0 Each
375.00
5,625
Wood Doors - Supply
7.0 Each
476.29
999.20
3,334
Door Hardware - Supply
15.0 Sets
14,988
Installation of Doors/Frames/Hardware
15.0 Each
200.00
3,000
OH/Coiling Doors / Grilles
111,700
8,291.67 99,500
6,100.00 12,200
30,401
10,500.00 10,500
3,110.20 15,551
1,450.00 1,450
Coiling Doors (Motorized)
12.0 Each
Fire Shutters for Type W04
2.0 Each
Storefronts / Glass / Curtain Walls
Type W01 Entrance w/ Hardware
Type W02 Exterior Openings
1.0 Each
5.0 Each
Type W03 Interior Glass
1.0 Each
Type W04 at Firewall
Div. ►•
Drywall / Acoustical
2.0 Each
1,450.00
2,900
105,598
3 5/8" Mtl. Stud Office Walls 9.5'
391.0 LF
100.16
39,162
6" Mtl. Stud Rated WH Separation Wall
77.0 LF
239.27
18,424
6" Mtl. Stud Office Exterior Wall
135.0 LF
122.42
16,526
Framing & Plywood at Elec. Workstation ILO CMU
Masonry
1.0 LS
6,098.00
6,098
Meacham Airport Maintenance Facility Estimate Date: 0711012026
Owner Change Order #003 Page 2 of 6 Documents Date: 0412812026
ITEM QUANTITY I UM UNIT COST TOTAL COST
Int. Gypsum Board Ceilings
2' x 2' Acoustical Ceiling Tile & Grid
FRP Wall Panels at RR's, Janitor & Storage (8' Tall)
Blocking
Misc. Equipment/Project Management
187.4 SF
1,810.4 SF
752.0 SF
4.45 834
5.56 10,074
6.68 5,021
1.0 LS
1,112.87
1,113
1.0 LS
8,346.50
8,346
Tile
15,094
Floor Tile - Restrooms
65.0 SF
62.46
4,060
Shower Walls
6.0 Each
1,839.00
11,034
Carpet/Resilient Flooring
28,562
Resilient Flooring (LVT)
Sealed Concrete
6" Rubber Base
Painting / Wall Coverings
Painting Ceilings
1,538.0 SF
10.09
15,511
11,665
1,386
65,137
570
12,320.0 SF
0.95
474.0 LF
2.92
188.0 SF
3.03
Painting HM Doors/Frames
22.0 Each
90.91
2,000
Painting Interior PEMB
11,773.0 SF
3.33
39,245
Painting Interior Walls
Signage / Identification Devices
11,840.0 SF
1.97
23,322
4,047
Interior Signage
Toilet Compartments/Accessories
Toilet Accessories
Wall/Corner Guards
13.0 Each
311.31
4,047
10,606
2.0 LS
5,303.00
10,606
2,917
224.38 2,917
5,302
760.40 3,802
1,500.00 1,500
ii
220,100
Corner Guards
13.0 Each
Fire Protection Specialties
Fire Extinguishers & Cabinets
5.0 Each
Knox Box
Div. 22 - Plumbing
Plumbing
1.0 Each
14,076.0 SF
Plumbing
Div. 23 - Heating, Ventilating & Air Conditioning
HVAC
15.64
220,100
.. ,255
166,255
HVAC
Div. 26 - Electrical
14,076.0 SF
11.81
166,255
40
Meacham Airport Maintenance Facility Estimate Date: 0711012026
Owner Change Order #003 Page 3 of 6 Documents Date: 0412812026
ITEM QUANTITY I UM UNIT COST TOTAL COST
Electrical
Site Electrical
48,365.60
511,401
1.0 LS
48,366
Switchgear/Feeders
Lighting
Equipment Connections
Power/Raceways
Misc
Communications Cabling and Equipment
Communications (By Owner)
Div. 28 - Electronic Safety & Security
Security / Access Control / Surveillance
Security, Access Control, and Surveillance Systems
(By Owner)
Fire Alarm Systems
Fire Alarm System
Earthwork
14,076.0 SF
5.25
73,899
14,076.0 SF
9.00
126,684
14,076.0 SF
14,076.0 SF
14,076.0 SF
3.40
47,858
94,948
119,646
0
6.75
8.50
0.0 LS
0.00
0
33,572
O
0.0 LS
0.00
0
33,572
33,572
517,020
14,076.0 SF
2.39
Bldg. Pad Prep (Per Geotech)
14,076.0 SF
11.77
165,691
Site Grading
108,840.0 SF
2.57
279,404
Lime Stabilization
Site Demo
36,109.0 SF
1.34
48,250
1.0 LS
23,675.00
3.25
23,675
Erosion Control
18,853
Silt Fence (Non -Reinforced)
Erosion Control Log
Rock Check Dams
1,487.0 LF
4,833
120
8,400
12.0 LF
10.00
80.0 LF
105.00
Stabilized Construction Entrances (Includes
Removal)
Inlet Protection
1.0 Each
3,500.00 3,500
500.00 2,000
1,998
4.0 Each
Termite Control
Termite Control
Exterior- nts
Traffic Markings/Signage
14,076.0 SF
0.14
1,998
191,798
2,845
Traffic Markings/Signage 1.0 LS 2,845.00 2,845
Fences / Gates 42,250
Meacham Airport Maintenance Facility Estimate Date: 0711012026
Owner Change Order #003 Page 4 of 6 Documents Date: 0412812026
ITEM QUANTITY I UM UNIT COST TOTAL COST
8' h Chain Link Fence Interior Warehouse
Double Sided Cedar Wood Plank Fence on
Galvanized Posts
Mechanical Unit Screening
Retaining Walls
38.0 LF
128.0 LF
182.11 6,920
140.23 17,950
790.00 17,380
60,109
22.0 LF
Stacked Stone Retaining Walls at Plan East & Pond
265.0 LF
226.83
60,109
Landscaping / Irrigation
71,042.0 SF
71,042.0 SF
12.0 Each
86,594
Temp Irrigation
SOD/Hydromulch
Stone Vehicle Barricades
0.30
21,313
0.75
53,282
1,000.00
12,000
Site Utilities
195,496
Private Water
1.0 LS
9,404.00
9,404
Private Sanitary
1.0 LS
19,033.00
19,033
Public Storm
1.0 LS
45,211.00
45,211
Private Storm
Misc.
1.0 LS
87,055.00 87,055
34,793.00 34,793
1.0 LS
Meacham Airport Maintenance Facility Estimate Date: 0711012026
Owner Change Order #003 Page 5 of 6 Documents Date: 0412812026
Total - Direct Costs
$ 3,166,822
General Conditions
367,413
26.10
8.53 %
Builder's Risk Insurance
General Liability Insurance
12,500
47,325
0.89
0.29 %
3.36
1.10 %
Payment and Performance Bonds
63,782
4.53
1.48 %
Subcontractor Bonds
0
0.00
0.00 %
Warranty
12,225
0.87
0.28 %
Contractor's Contingency
Owner's Contingency
Overhead and Profit
97,804
6.95
2.27 %
296,246
21.05
6.88 %
5.68 %
244,575
17.38
Total Cost $ 4,308,692 $ 306.10 100.000/0
Meacham Airport Maintenance Facility Estimate Date: 0711012026
Owner Change Order #003 Page 6 of 6 Documents Date: 0412812026
Recap Report
Rev 02 7/14/26
Meacham Airport Maintenance Facility
GMP
Estimate Date: 07/02/2026 Documents Date: 04/28/2026
Project Size (SF): 14,076 Project #: 3024100
Project Location: Fort Worth, TX Lead Estimator: Justin Hyder
ITEM COST COST I SF % OF TOTAL
Direct Costs
Div. 01 - General Requirements
Div. 03 - Concrete
Div. 04 - Masonry
Div. 05 - Metals
Div. 06 - Wood, Plastics & Composites
I 4,245,109 I
749,898
301.58
53.27
I 77.24
13.65 %
696,779
49.50
12.68 %
0.00 0/0
0
22,825
0.00
1.62
1.97
0.42 %
0.50 %
27,738
Div. 07 - Thermal & Moisture Protection
17,714
1.26
0.32 %
Div. 08 - Openings
174,005
12.36
3.17 %
Div. 09 - Finishes
214,391
15.23
3.90 %
Div. 10 - Specialties
22,872
1.62
0.42 %
Div. 13 - Special Construction
Div. 22 - Plumbing
Div. 23 - Heating, Ventilating & Air Conditioning
Div. 26 - Electrical
Div. 27 - Communications
Div. 28 - Electronic Safety & Security
Div. 31 - Earthwork
Div. 32 - Exterior Improvements
Div. 33 - Utilities
455,694
32.37
8.29 %
220,100
166,255
511,401
15.64
4.00 %
11.81
3.03 %
36.33
0.00
9.31 %
0
0.00 %
0.61 %
9.91 %
3.49 %
33,572
2.39
544,571
191,798
38.69
13.63
195,496
13.89
3.56 %
Meacham Airport Maintenance Facility Estimate Date: 0710212026
GMP Page 1 of 2 Documents Date: 0412812026
ITEM
COST COST l SF No OF TOTAL
General Conditions
Builder's Risk Insurance
General Liability Insurance
Payment and Performance Bonds
Subcontractor Bonds
..-.-.,r
Contractor's Contingency
Owner's Contingency
Overhead and Profit
367,413
I 26.10
6.69 %
13,953
0.99
0.25 %
53,199
3.78
0.97 %
75,953
5.40
0.00
1.38 %
0.00
0.25 %
0
13,739
0.98
109,915
341,662
274,786
7.81
2.00 %
24.27
6.22 %
19.52
5.00
Total Cost $ 5,495,729 $ 390.43 100.00 %
Meacham Airport Maintenance Facility Estimate Date: 0710212026
GMP Page 2 of 2 Documents Date: 0412812026
Detail Report
Rev 02 7/14/26
Meacham Airport Maintenance Facility
GMP
Estimate Date:
07/02/2026
Documents Date:
04/28/2026
Project Size (SF):
14,076
Project #:
3024100
Project Location:
Fort Worth, TX
Lead Estimator:
Justin Hyder
ITEM QUANTITY I UM UNIT COST TOTAL COST
General-. -
Preconstruction Services
1.0 LS
75,955.00
469,100.00
615,893
Preconstruction Services
Design Services
75,955
469,100
1.0 LS
Owner Change Order #001
1.0 LS
36,438.00
36,438
Owner Change Order #002 - Additional Design
Services
General Requirements
Final Clean
Safety Supplies
Small Tools
Temp Power
Temp Water
Connex
Connex Delivery & Pickup
Water, Ice, Cups
Temp. Protection
Safety Signage
1.0 LS
34,400.00
34,400
134,005
14,076.0 SF
0.81
11,428
8.0 Mos
650.00
5,200
5,000
12,990
1.0 LS
5,000.00
1,623.75
8.0 Mos
8.0 Mos
1,082.50
8,660
8.0 Mos
757.75
1,624.00
250.00
6,062
3,248
2,000
14,076
2.0 Each
8.0 Mos
14,076.0 SF
1.00
1.0 LS
2,000.00
2,000
Layout / Survey
1.0 LS
20,000.00
20,000
Site Maintenance/Street Cleaning
Potholing/Hydrovac Utilities
8.0 Mos
3,897.00
10,000.00
31,176
1.0 LS
10,000
Temporary Fire Extinguishers Bldg.
Concrete•.
Cast -In -Place Concrete (Building)
4.0 Each
541.25
2,165
,779
298,460
Slab on Grade (Includes Piers & GB's)
14,076.0 SF
21.20
298,460
Cast -In -Place Concrete (Site)
398,319
Meacham Airport Maintenance Facility Estimate Date: 0710212026
GMP Page 1 of 6 Documents Date: 0412812026
ITEM QUANTITY I UM UNIT COST TOTAL COST
Concrete Site Paving
5" Concrete Paving ILO of Asphalt Millings
Div. 04 - Masonry
Masonry / Stone
8" CMU at Int. Walls at Elec Workstation (Add Alt.)
Div. 05 - Metals
Structural/Miscellaneous Steel - Fabrication
27,818.0 SF
7,986.0 SF
381.1 SF
11.84
8.65
329,240
69,079
0
0.00
0
22,825
22,825
Steel Pipe Bollards - Fab.
•.Wood, Plastics & Composites
Architectural Woodwork
55.0 Each
415.00
22,825
27,738
Architectural Woodwork - Breakroom Millwork
Architectural Woodwork - Breakroom Solid Surface
Countertops
Architectural Woodwork - Mudroom Bench
Div. 07 - Thermal & Moisture Protection
Waterproofing / Dampproofing / Joint Seal
37.1 LF
298.60
11,078
18.0 LF
314.88
5,668
1.0 Each
nts
10,991.89 10,992
17,714
17,714
4,881.00 4,881
12,833.00 12,833
174,005
31,904
619.62 4,957
Building Sealants/HM Doors
1.0 LS
Site Sealants
0: Openings
Doors / Frames / Hardware
1.0 LS
Hollow Metal Doors - Supply
Hollow Metal Frames - Supply
8.0 Each
15.0 Each
375.00
5,625
Wood Doors - Supply
Door Hardware - Supply
Installation of Doors/Frames/Hardware
OH/Coiling Doors / Grilles
Coiling Doors (Motorized)
Fire Shutters for Type W04
Storefronts / Glass / Curtain Walls
Type W01 Entrance w/ Hardware
Type W02 Exterior Openings
Type W03 Interior Glass
Type W04 at Firewall
••
7.0 Each
476.29
3,334
15.0 Sets
999.20
14,988
15.0 Each
200.00
3,000
111,700
12.0 Each
8,291.67
99,500
2.0 Each
6,100.00
12,200
30,401
10,500
1.0 Each
10,500.00
5.0 Each
3,110.20
15,551
1.0 Each
1,450.00
1,450
2,900
2.0 Each
1,450.00
Meacham Airport Maintenance Facility Estimate Date: 0710212026
GMP Page 2 of 6 Documents Date: 0412812026
ITEM QUANTITY I UM UNIT COST TOTAL COST
Drywall / Acoustical
3 5/8" Mtl. Stud Office Walls 9.5'
6" Mtl. Stud Rated WH Separation Wall
391.0 LF
100.16
239.27
105,598
39,162
77.0 LF
18,424
6" Mtl. Stud Office Exterior Wall
Framing & Plywood at Elec. Workstation ILO CMU
Masonry
Int. Gypsum Board Ceilings
2' x 2' Acoustical Ceiling Tile & Grid
FRP Wall Panels at RR's, Janitor & Storage (8' Tall)
Blocking
135.0 LF
122.42
16,526
1.0 LS
6,098.00
6,098
187.4 SF
4.45
834
1,810.4 SF
5.56
10,074
5,021
1,113
752.0 SF
1.0 LS
6.68
1,112.87
Misc. Equipment/Project Management
1.0 LS
8,346.50
8,346
Tile
15,094
Floor Tile - Restrooms
Shower Walls
65.0 SF
62.46
4,060
11,034
6.0 Each
1,839.00
Carpet/Resilient Flooring
1,538.0 SF
12,320.0 SF
28,562
Resilient Flooring (LVT)
10.09
15,511
Sealed. Concrete
0.95
11,665
6" Rubber Base
474.0 LF
2.92
1,386
Painting / Wall Coverings
65,137
Painting Ceilings
188.0 SF
3.03
570
Painting HM Doors/Frames
22.0 Each
90.91
2,000
Painting Interior PEMB
11,773.0 SF
3.33
39,245
Painting Interior Walls
Specialties
Signage / Identification Devices
11,840.0 SF
1.97
23,322
4,047
Interior Signage
Toilet Compartments/Accessories
Toilet Accessories
Wall/Corner Guards
Corner Guards
Fire Protection Specialties
Fire Extinguishers & Cabinets
13.0 Each
311.31
4,047
10,606
10,606
2.0 LS
5,303.00
2,917
13.0 Each
224.38
2,917
5,302
3,802
5.0 Each
760.40
Knox Box
Special. .
1.0 Each
1,500.00
1,500
•,
Meacham Airport Maintenance Facility Estimate Date: 0710212026
GMP Page 3 of 6 Documents Date: 0412812026
ITEM QUANTITY i UM UNIT COST TOTAL COST
Pre -Engineered Metal Buildings
455,694
1.0 LS
14,076.0 SF
Engineering Design Peer Review (OCO #2)
12,300.00 12,300
31.50 443,394
Pre-engineered Metal Building (OCO #2)
Div. 22 - Plumbing
220,100
Plumbing
220,100
Plumbing
14,076.0 SF
15.64
220,100
Heating,-ntilating & Air Conditioning
1.. ,255
HVAC
166,255
HVAC
14,076.0 SF
11.81
166,255
Div. 26 - Electrical
40
Electrical
511,401
Site Electrical
1.0 LS
48,365.60
48,366
Switchgear/Feeders
14,076.0 SF
5..25
73,899
14,076.0 SF
9.00
126,684
Lighting
Equipment Connections
14,076.0 SF
3.40
47,858
14,076.0 SF
6.75
94,948
Power/Raceways
14,076.0 SF
8.50
119,646
Misc
Communications Cabling and Equipment
0
0.0 LS
0.00
0
Communications (By Owner)
Div. 28 - Electronic Safety & Security
33,572
Security / Access Control / Surveillance
0
Security, Access Control, and Surveillance Systems
(By Owner)
0.0 LS
0.00
0
Fire Alarm Systems
33,572
Fire Alarm System
14,076.0 SF
2.39
33,572
Div. 31 - Earthwork
., ,571
Earthwork
517,020
Bldg. Pad Prep (Per Geotech)
14,076.0 SF
11.77
165,691
Site Grading
108,840.0 SF
2.57
279,404
Lime Stabilization
36,109.0 SF
1.34
48,250
Site Demo
1.0 LS
23,675.00
23,675
Erosion Control
25,553
Silt Fence (Non -Reinforced)
1,487.0 LF
3.25
4,833
Meacham Airport Maintenance Facility Estimate Date: 0710212026
GMP Page 4 of 6 Documents Date: 0412812026
ITEM QUANTITY I UM UNIT COST TOTAL COST
Erosion Control Log
Rock Check Dams
Stabilized Construction Entrances (Includes
Removal)
Inlet Protection
12.0 LF
10.00 120
105.00 8,400
3,500.00 3,500
500.00 2,000
3,500.00 3,500
400.00 3,200
80.0 LF
1.0 Each
4.0 Each
1.0 Each
8.0 Mos
SWPPP Narrative (OCO #2)
SWPPP Inspections (OCO #2)
Termite Control
14,076.0 SF
1,998
Termite Control
Traffic Markings/Signage
0.14
2,845.00
1,998
2,845
Traffic Markings/Signage
Fences / Gates
1.0 LS
2,845
42,250
8' h Chain Link Fence Interior Warehouse
Double Sided Cedar Wood Plank Fence on
Galvanized Posts
Mechanical Unit Screening
Retaining Walls
Stacked Stone Retaining Walls at Plan East & Pond
Landscaping / Irrigation
Temp Irrigation
SOD/Hydromulch
Stone Vehicle Barricades
i
Site Utilities
Private Water
38.0 LF
128.0 LF
182.11
6,920
17,950
17,380
140.23
790.00
22.0 LF
226.83
60,109
265.0 LF
71,042.0 SF
60,109
86,594
0.30
0.75
1,000.00
9,404.00
21,313
71,042.0 SF
12.0 Each
53,282
12,000
4•.
195,496
9,404
1.0 LS
Private Sanitary
1.0 LS
19,033.00
19,033
Public Storm
1.0 LS
45,211.00
45,211
Private Storm 1.0 LS 87,055.00 87,055
Misc. 1.0 LS 34,793.00 34,793
Meacham Airport Maintenance Facility Estimate Date: 0710212026
GMP Page 5 of 6 Documents Date: 0412812026
Total - Direct Costs
$ 4,245,109
General Conditions
367,413
26.10
6.69 %
Builder's Risk Insurance
General Liability Insurance
13,953
0.99
0.25 %
0.97 %
53,199
3.78
Payment and Performance Bonds
75,953
5.40
1.38 %
Subcontractor Bonds
Warranty
Contractor's Contingency
0
0.00
0.98
0.00 %
0.25 %
2.00 %
13,739
109,915
7.81
Owner's Contingency
Overhead and Profit
341,662
274,786
24.27
6.22 %
19.52
5.00 %
Total Cost $ 5,495,729 $ 390.43 100.00 %
Meacham Airport Maintenance Facility Estimate Date: 0710212026
GMP Page 6 of 6 Documents Date: 0412812026
Providing the Absolute Best
Construction Experience
GENERAL CONDITIONS
DESCRIPTION QUANTITY UNIT UNIT COST EXTENDED COST
ON SITE PROJECT MANAGEMENT
Supervision 1 8 1 Monthsl $ 31.6201 $ 252,961
CONSULTANTS
Safety Consultant (ESC) 81 Monthsl $ 550.001 $ 4,400
TEMPORARY PROJECT CONSTRUCTION AND UTILITIES FOR CM STAFF
Computers
8
Months
$ 520.00
$ 4160
Cell Phones
8
Months
$ 200.00
$ 1,732
P6 Schedule
8
Months
$ 195.00
$ 1,689
Jobsite Photos
8
Months
$ 75.00
$ 650
Documents / Reprographics / (Plangrid)
8
Months
$ 270.00
$ 2,338
As Built Documents
1
Sets
$ 500.00
$ 541
CM Project Specific Signage
1
LS
S 2,977.00
$ 3,719
Postage and Deliveries
8
Months
$ 50.00
$ 433
Office Trailer - Mobilization & Demobilization
2
Ea
S 1,175.00
$ 2,544
Office Trailer - Set Up & Take Down
1
LS
$ 3,860.00
$ 4,178
Office Trailer - Rental
8
Months
S 1,412.00
$ 12,228
Printer, Copier, Scanner
1
LS
$ 1,050.00
$ 1,137
Job Office Supplies
8
Months
S 125.00
$ 1,083
Internet Set Up
1
LS
S 2,500.00
$ 2,706
Internet Service Charges
8
Months
$ 550.00
$ 4,763
Temp Electricity (Job Trailer)
8
Months
$ 300.00
$ 2,598
Temp Water (Job Trailer)
8
Months
$ 100.00
$ 866
Water Meter
1
LS
S 2,500.00
$ 2,706
Sewage Holding Tank (Job Trailer)
8
Months
$ 715.00
$ 6,192
First Aid Kit
1
Ea
$ 300.00
$ 325
First Aid Supplies
8
Months
$ 50.00
$ 433
Temp Fire Extinguisher (Job Trailer)
1
Ea
$ 150.00
$ 162
Portable Toilets - Rental
8
Months
$ 765.00
$ 6,625
Portable Handwash - Rental
8
Months
$ 365.00
$ 3,161
Temporary Fencing w/ Windscreen
0
LS
$ 11,908.00
$ -
Construction Clean -Up
17
Wks
$ 1,400.00
$ 25,764
Dumpsters
32
Pulls
S 500.00
$ 17,320
TOTAL GENERAL CONDITIONS
8
Months
$ 45,927
$ 367,413
n
�
�
0
A
L
�
y
O
m
C
r
h
O
y
r
o
o
�
�
o
e
o
o
e
o
W
OTC W
O
O
O
O
O
IV
AWp
O
O
O
O
W
O
N
N�
D
O
O
O
O
O
IJ
o
o N
O
co
a
i�a
N
N
O
O
m
O
NA
A .p
o CJ1
O
O
O
O
O
o
O
e
O
a
IV
�
N
N
O
L
a
J
W
O
O
O
O
J
?+D
c J
O
e
o
O
Jo
o
o
N
V
A
e J
e
e
o
e
e
N
v
N
N
W
N
m
N�
tC
<
a
o
o
z y
o N g N
CnMCDD
N N 0
T * n
3
rn y co r
y D D
CD
y
O
z
n
-{
O
M
3roviding the Absolute Best
Construction Experience
Recap of GMP for Meacham Airport Maintenance Facility
Project #:
3024100
Name:
Meacham Airport Maintenance Facility
Location:
Fort Worth, TX
Bid Date:
July 2, 2026
Lead Estimator:
Chris Schwertner
Base Bid
$ 5,495,729.00
A01
A02
Generator
$ 137,745
New Air Compressor
$ 36,942
A03
HLVS Fans
$ 59,504
A04
Concrete Stacked Block Walls For Spoils
$ 106,256
A05
6" Flex Base & Asphalt ILO Concrete Paving
$ 59,973
A06
Covered Parking
$ 204,223
A07
Lighting Protection System
$ 44,918
A08
Network Lighting Controls
$ 48,385
A09
CMU ILO Framing & Plywood at Elec. Workstation
$ 33,333
A10
Window Shades
$ 6,008
A11
Appliances
$ 9,035
Al2
Bollard Covers $ 9,681
Downspout Boots $ _ 5,632
Lockers & Bench i $ 22,183
FF&E $ 18,108
A13
A14
A15
Total for All Alternates: $ 801,926
Total Base Bid + All Alternates $ 6,297,655
Recap Report
Meacham Airport Maintenance Facility - Alternates
GMP
Estimate Date:
07/02/2026
Documents Date:
04/28/2026
Project Size (SF):
14,076
Project #:
3024100
Project Location:
Fort Worth, TX
Lead Estimator:
Justin Hyder
ITEM COST COST l SF % OF TOTAL
Direct Costs
Alternate 01 - Generator
Alternate 02 - New Air Compressor
Alternate 03 - HLVS Fans
Alternate 04 - Concrete Stacked Block Walls For Spoils
Alternate 05 - 6" Flex Base & Asphalt ILO Concrete
Paving
Alternate 06 - Covered Parking
I 801,926 I
137,745
56.97
9.79
2.62
84.37
14.49 %
3.89 %
36,942
59,504
4.23
6.26 %
106,256
7.55
11.18 %
59,973
4.26
14.51
6.31 %
21.49 %
204,223
Alternate 07 - Lighting Protection System
44,918
3.19
4.73 %
Alternate 08 - Network Lighting Controls
Alternate 09 - CMU ILO Framing & Plywood at Elec.
Workstation
Alternate 10 - Window Shades
Alternate 11 - Appliances
Alternate 12 - Bollard Covers
Alternate 13 - Downspout Boots
Alternate 14 - Lockers & Bench
Alternate 15 - FF&E
48,385
3.44
5.09 %
33,333
6,008
2.37
o
3.51 /o
0.63 %
0.43
9,035
0.64
0.95 %
1.02 %
0.59
2.33 %
9,681
0.69
0.40
5,632
22,183
1.58
18,108
1.29
1.91 %
Meacham Airport Maintenance Facility - Alternates Estimate Date: 0710212026
GMP Page 1 of 2 Documents Date: 0412812026
Detail Report
Meacham Airport Maintenance Facility - Alternates
GMP
Estimate Date:
07/02/2026
Documents Date:
04/28/2026
Project Size (SF):
14,076
Project #:
3024100
Project Location:
Fort Worth, TX
Lead Estimator:
Justin Hyder
ITEM
Direct Costs
QUANTITY I UM
1.0 LS
UNIT COST TOTAL COST
117,390
99,500.00 99,500
i
2,000.00 2,000
Generator & ATS
Gas Regulator
1.0 Each
Bollards
6.0 Each
415.00
2,490
Bollard Covers
6.0 Each
150.00
900
Generator Pad
1.0 Each
12,500.00
12,500
Indirect Costs
Indirect Costs (17.34%)
AlternateNew
Direct Costs
20,355
20,355
•,
31,483
1.0 LS
20,355.43
Air Compressor
1.0 LS
31,483.00
31,483
Indirect Costs
5,459
Indirect Costs (17.34%)
Direct Costs
1.0 LS
5,459.15
5,459
04
50,711
2,400
PEMB Structure Supports
2.0 Each
1,200.00
HLVS Fans
Electric for Fans
Indirect Costs
Indirect Costs (17.34%)
2.0 Each
17,144.00
7,011.50
' 34,288
2.0 Each
14,023
8,793
1.0 LS
8,793.29
8,793
Alternate 04 - Concrete Stacked Block Walls
Direct Costs
For Spoils
106,256
90,554
30,704
33,600
Concrete Stacked Block Walls for Spoils - Install
Concrete Stacked Block Walls for Spoils - Supply
96.0 Each
96.0 Each
319.83
350.00
Meacham Airport Maintenance Facility - Alternates Estimate Date: 0710212026
GMP Page 1 of 4 Documents Date: 0412812026
ITEM I QUANTITY I UM UNIT COST TOTAL COST
Concrete Foundation
1,050.0 SF
25.00
26,250
15,702
Indirect Costs
Indirect Costs (17.34%)
1.0 LS
15,701.98
15,702
- & Asphalt ILO Concrete
Direct Costs
51,110
6" Flex Base & Asphalt
7,986.0 SF
15.05
120,189
Concrete Paving
7,986.0 SF
-8.65
-69,079
Indirect Costs
Indirect Costs (17.34%)
Alternate0. -. Parking
Direct Costs
8,863
8,862.54 8,863
204,223
174,044
49,044.00 49,044
115,000.00 115,000
1.0 LS
1.0 Each
Covered Parking Foundation
Covered Parking Structure
1.0 Each
Electrical at Covered Parking
1.0 LS
10,000.00
10,000
Indirect Costs
30,179
Indirect Costs (17.34%)
Alternate 07 - Lighting Protection System
Direct Costs
1.0 LS
30,179.23
30,179
44,918
38,280
Lighting Protection
1.0 LS
38,280.00
38,280
Indirect Costs
6,638
Indirect Costs (17.34%)
Alternate 0:Network
Direct Costs
1.0 LS
6,637.75
6,638
41,235
Network Lighting Controls
1.0 LS
41,235.00
41,235
Indirect Costs
7,150
Indirect Costs (18.31%)
1.0 LS
7,150.15
j 7,150
Alternate• Framing & Plywood
Direct Costs
at Elec.
90.54
-6,098.00
28,407
8" CMU at Int. Walls at Elec Workstation (Add Alt.)
381.1 SF
34,505
I� -6,098
Framing & Plywood at Elec. Workstation ILO CMU
Masonry
Indirect Costs
Indirect Costs (17.34%)
Window..-
1.0 LS
4,926
1.0 LS
4,925.77 4,926
00.
Meacham Airport Maintenance Facility - Alternates Estimate Date: 0710212026
GMP Page 2 of 4 Documents Date: 0412812026
ITEM QUANTITY I UM UNIT COST TOTAL COST
Direct Costs
5,120
Manual Operated Window Shades - Exterior
5.0 Each
1,024.00 5,120
Windows
Indirect Costs
888
Indirect Costs (17.34%)
1.0 LS
887.81 888
-AppliancesAlternate 11
Direct Costs
1.0 Each
7,700
2,500.00 2,500
Electric Range (No Spec)
1.0 Each
Built -In Microwave (By Owner)
0.00 0
Refridgerator (No Spec)
1.0 Each
3,000.00
3,000
Ice Machine (By Owner)
1.0 Each
2,200.00
2,200
Indirect Costs
1,335
Indirect Costs (17.34%)
1.0 LS
1,335.18
1,335
Direct Costs
8,250
Bollard Sleeves
55.0 Each
150.00 8,250
1,431
1,430.55 1,431
Indirect Costs
Indirect Costs (17.34%)
1.0 LS
Downspout Boots
Direct Costs
4,800
600.00 4,800
832
Downspout Boots
8.0 Each
Indirect Costs
Indirect Costs (17.34%)
1.0 LS
832.32
832
Direct Costs
18,905
Metal Lockers 18"x 18"
6.0 Each
2,817.48
16,905
Locker Bench
1.0 Each
2,000.00
2,000
Indirect Costs
3,278
Indirect Costs (17.34%)
1.0 LS
3,278.11
3,278
Direct Costs
15,432
FF&E 1.0 LS 15,432.00 15,432
Indirect Costs 2,676
Indirect Costs (17.34%) 1.0 LS 2,675.91 2,676
Meacham Airport Maintenance Facility - Alternates Estimate Date: 0710212026
GMP Page 3 of 4 Documents Date: 0412812026
Total - Direct Costs
$ 801, 926
Meacham Airport Maintenance Facility - Alternates
GMP Page 4 of 4
Estimate Date: 0710212026
Documents Date: 0412812026
m
Providing the Absolute Best
Construction Experience
D/B Meacham Airport Field Maintenance Facility
GMP submission
SPECIFIC QUALIFICATIONS
Division 01 — General Requirements and General Conditions
1. Includes costs for preconstruction and design services.
2. We are assuming that we can use adjacent lot nearby for jobsite trailer and construction laydown
area. Refer to attached Site Logistics Plan.
3. Assume normal working hours M-F, 7:00 a.m. to 5:30 p.m. We are assuming early morning
concrete pours will be acceptable for SOG and site concrete as deemed necessary. We are
assuming we can work on Saturdays as needed to maintain schedule or make-up for weather.
4. We are assuming an 8-month construction schedule.
5. Onsite Supervision will consist of (1) full-time Project Manager, (1) full-time Superintendent, (1)
part-time Safety Professional, and (1) part-time Project Administrator. Refer to Salary Matrix
Attached.
6. The GMP estimate does not include sales tax.
7. The GMP estimate does not include any cost for ONCOR.
8. The GMP estimate does not include Building Permit cost(s).
9. The GMP estimate does not include any alternates.
10. Line items in the GMP Estimate are not guaranteed. Buyout savings from one line item can be
used to cover overruns or estimating errors from other lines. Final buyout gains will be moved to
the Contractor Contingency line item.
11. The GMP estimate contains a Contractor's Contingency of 2% of contract value. Contractor's
Contingency is to be used for the purpose of covering estimating errors, cost which are related to
a subcontractor's failure, scope inadvertently missed in initial approval letters, or otherwise as
needed per the contractual agreement.
12. The GMP estimate contains an Owner's Contingency of $341,662. The Owner's Contingency is
intended to be used to cover items such as scope of work growth, increases due to hidden or
unforeseen conditions, inclusion of items excluded from this GMP, Owner initiated changes, design
errors and omissions, and any losses not covered by insurance.
13. The GMP along with the Assumptions and Clarifications are to be incorporated into the project via
Owner Change Order.
14. Pricing submitted in this GMP will remain in effect for 30-days, after that period pricing may be
subject to change.
15. The GMP estimate includes an SBE of 3.13%.
Page 1 of 4
Division 02 — Existing Conditions
1. Existing 8" and 24" water lines are to be removed and rerouted as part of work taking place
outside of this Agreement. Utilities must be completed in accordance with Schwarz -Hanson
Drawing set dated 6/5/2026. Any unsuitable spoils generated by the Utility scope outside of this
Agreement must be removed from site prior to SpawGlass mobilization.
2. Work performed by Utility contractor outside of this Agreement must be completed prior to
SpawGlass Mobilization as defined by the Project Schedule.
3. Does not include demolition of existing utilities.
4. Does not include demolition of existing maintenance facility.
5. Does not include any costs associated with removing/relocating existing power pole.
6. This GMP estimate does not include any modifications or new security fencing at LOC.
Division 03 — Concrete
1. Piers are bid as dry, no casing.
2. No concrete footings or foundation are included for stacked stone retaining wall.
3. No foundation has been included for concrete bin storage area, see add alternate.
4. Includes Wet Curing of building slab.
5. The GMP estimate does not include the Generator Pad. This is part of Alternate 1.
6. The GMP estimate includes concrete paving in lieu of asphalt or asphalt millings.
Division 04 — Masonry
1. The GMP estimate does not include any Masonry.
2. Does not include any exterior masonry or dumpster enclosure.
Division 05 — Metals
1. The GMP estimate does not include steel downspout boots. These are priced as a separate add
alternate.
2. The GMP estimate does not include (6) exterior bollards around generator. These are included
with Alternate #1.
Division 06 — Wood, Plastics, and Composites
1. N/A
Division 07 — Thermal and Moisture Protection
1. N/A
Page 2 of 4
Division 08 — Oneninas
1. Does not include final keying or final cores.
2. Assumes standard colors on overhead doors.
Division 09 — Finishes
1. GMP estimate includes framing and plywood for wall at electric workstation in lieu of CMU.
2. The GMP estimate does not include any exterior painting per spec section 09 91 13.
Division 10 — Specialties
1. This GMP estimate does not include Metal Lockers and Bench. These are being carried as an add
alternate.
2. The GMP estimate does not include covered parking. See add alternate #6
Division 11 — Equipment
1. The GMP estimate does not include appliances from Spec section 11 30 13. These are being
carried as an add alternate.
Division 12 — Furnishings
1. The GMP estimate does not include any window treatment. These are being carried as an add
alternate.
2. The GMP estimate does not include any FFE costs. The FFE is carried as an add alternate per Uplift
Desks, quote dated 1/27/26.
Division 13 — Special Construction
1. Pre -Engineered metal building cost has been incorporated per Amendment 02.
Division 14 — Conveying Equipment
1. Overhead cranes are not included.
Division 21 — Fire Suppression
1. Fire suppression is not included.
Division 22 — Plumbing
1. N/A
Division 23 — HVAC and Controls
1. The GMP estimate includes standalone thermostats only.
2. The GMP estimate does not include HVLS fans, see add alternate.
Page 3 of 4
Division 26 — Electrical
1. The GMP estimate does not include utility charges.
2. Does not include 100kw natural gas generator with 250A ATS, see add alternate #1.
3. Does not include lightning protection system. See add alternate #7.
Division 27 — Communications
1. Does not include communications scope. Our scope includes raceways stub -ups (ring & string) only.
Cabling and devices are to be furnished and installed by Owner.
2. Does not include audio visual system.
Division 28 — Electronic Safety & Securitx
1. Does not include security scope. Our scope includes raceways stub -ups (ring & string) only.
Assume one drop per exterior door. Cabling and devices are to be furnished and installed by
Owner.
Division 31 — Earthwork
1. For building pad prep: we are assuming excavation to limestone and moisture conditioning
utilizing usable onsite materials and 1' select fill cap; with 5' overbuild around building footprint.
2. For site pavement subgrade prep, we have included 6" lime stabilization.
3. The GMP estimate does not include asphalt millings as we are assuming Ross Ave will be demo'd
by utility contractor outside of this Agreement.
4. The GMP estimate includes removing and haul -off of all onsite excavated materials and importing
suitable fill material for the project.
5. The GMP estimate includes civil revisions per Addendum #1.
Division 32 — Exterior Improvements
1. N/A
Division 33 — Utilities
1. Does not include any costs associated with Atmos or Oncor providing new service.
2. Does not include 8" or 24" water lines or Sanitary Sewer manhole or stub out (by others).
3. The GMP estimate includes civil revisions per Addendum #1.
SPECIFIC EXCLUSIONS
1. Taps, meters and related fees by utility providers not provided.
2. Building permits
3. Material testing services
4. Contaminated soils, asbestos abatement
5. FF&E
6. Sales Tax
Page 4 of 4
0
ding the Absolute Best
struction Experience
Meacham Airport - Maintenance Facility
Fort Worth, Texas
7/2/2026
shoo No.
TITLE
DRAWINGS
ISSUE DATE
REVISION DATE
GENERAL
G0.0
COVER
04,28.2026
06.19.2026
73.1
SHEET INDEX
04.28.2026
G0.2
TEXAS ACCESSIBILITY STANDARDS
O4.28.2026
G0.3
TEXAS ACCESSIBILITY STANDARDS
O4.28.2026
G0.4
TEXAS ACCESSIBILITY STANDARDS
O4.28.2026
G0.5
FRAMING DETAILS
O4.28.2026
G0.6
MOUNTING HEIGHTS
O4.28.2026
G0.7
FIRE PENETRATION DETAILS
O4.28.2026
CIVIL
C1.1
COVER SHEET
04.28.2026
06.19.2026
C1.2
GENERAL NOTES
O4.28.2026
06.19.2026
C2.1
FINAL PLAT
04.28.2026
C3.1
EXISTING CONDITIONS PLAN
04.28.2026
C3.2
DEMOLITION PLAN
04.28.2026
06.19.2026
74.1
SITE & DIMENSION CONTROL PLAN
04.28,2026
06.19.2026
C5.1
OVERALL UTILITY PLAN
04.28.2026
06.19.2026
77.1
SANITARY SEWER PLAN
04.28.2026
06.19,2026
C7.2
UTILITY DETAILS
O4.28.2026
C8.1
PAVING & STRIPING PLAN
04.28.2026
7.2
PAVING DETAILS
O4.28.2026
C8.3
PAVING DETAILS
O4.28.2026
79.1
GRADING PLAN
04.28.2026
06.19.2026
C10.1
EXISTING DRAINAGE AREA MAP
04.28.2026
C10.2
PROPOSED DRAINAGE AREA MAP
04.28.2026
711.1
DETENTION POND
04.28.2026
06.19.2026
C11.2
DETENTION POND
04.28.2026
06.19.2026
C11.3
DETENTION POND CALCULATIONS
O4.28.2026
06.19.2026
C11.4
STORM DETAILS
06.19.2026
C11.5
STORM DETAILS
06.19.2026
C12.1
EROSION CONTROL PLAN
04.28.2026
06.19.2026
C12.2
EROSION CONTROL DETAILS
O4.28.2026
LANDSCAPE
L1.1
EXISTING CONDITIONS PLAN
04.28.2026
L1.2
LANDSCAPE PLAN
04.28.2026
L1.3
LANDSCAPE SPECIFICATIONS AND DETAILS
O4.28.2026
ARCHITECTURAL
A0.1
LIFE SAFETY PLAN
04.28.2026
A0.2
3-HR FIRE RATED WALL ASSEMBLY
04.28.2026
A1.0
ARCHITECTURAL SITE PLAN
04.28.2026
06.19.2026
A1.1
SITE DETAILS
O4.28.2026
A2.1
DIMENSION PLAN
04.28.2026
A2.2
FLOOR PLAN
04.28.2026
A2.3
FLOOR PLAN - ADD ALTERNATE #06 COVERED PARKING
04.28.2026
72.4
ENLARGED FLOOR PLANS
O4.28.2026
A3.1
EXTERIOR ELEVATIONS
O4.28.2026
A4.0
BUILDING SECTIONS
O4.28.2026
A4.1
WALL SECTIONS
O4.28.2026
A4.2
SECTION DETAILS
O4.28.2026
A5.1
ROOF PLAN
04.28.2026
A6.1
DOOR SCHEDULE AND DETAILS
O4.28.2026
A7.1
REFLECTED CEILING PLAN
04.28.2026
A7.2
REFLECTED CEILING PLAN - ADD ALTERNATE #03 - HVLS FANS
O4.28.2026
78.1
INTERIOR ELEVATIONS
O4.28.2026
A8.2
CASEWORK DETAILS
O4.28.2026
A9.1
FINISH PLAN, SCHEDULE, AND NOTES
O4.28,2026
06.19.2026
STRUCTURAL
S1.1
SPECIAL INSPECTIONS & GENERAL NOTES
O4.28.2026
52.1
FOUNDATION PLAN
04.28.2026
S2.2
SCHEMATIC ROOF FRAMING PLANS
O4.28.2026
S3.1
FOUNDATION DETAILS
O4.28.2026
53.2
FOUNDATION DETAILS
O4.28.2026
MECHANICAL
M0.1
MECHANICAL LEGEND, SCHEDULES & NOTES
O4.28.2026
M0.2
MECHANICAL DETAILS
O4.28.2026
M2.1
FLOOR PLAN - MECHANICAL
04.28.2026
M2.2
FLOOR PLAN - MECHANICAL - ADD ALTERNATE #03
04.28.2026
PLUMBING
P0.1
PLUMBING LEGEND, SCHEDULES & NOTES
O4.28.2026
P0.2
PLUMBING DETAILS
O4.28.2026
P2.1
FLOOR PLAN - PLUMBING WASTE, DRAIN, & VENT
04.28.2026
P2.2
FLOOR PLAN - PLUMBING - DOMESTIC SERVICES
O4.28.2026
P2.3
FLOOR PLAN - PLUMBING DOMESTIC SERVICES - ADD ALTERNATE #02
04.28.2026
ELECTRICAL
E0.1
ELECTRICAL SINGLE LINE & DETAILS
O4.28.2026
E0.2
ELECTRICAL DETAILS
O4.28.2026
E1.1
SITE PLAN - ELECTRICAL
04.28.2026
06.19.2026
E2.1
FLOOR PLAN - ELECTRICAL
04.28.2026
E3.1
FLOOR PLAN - LIGHTING
04.28.2026
E3.2
FLOOR PLAN - LIGHTING DAYLIGHT ZONES
O4.28,2026
E6.1
ELECTRICAL PANEL SCHEDULES
O4.28.2026
E6.2
ELECTRICAL PANEL SCHEDULES
O4.28.2026
ES1.1
FLOOR PLAN - SECURITY
04.28.2026
FA2.1
FLOOR PLAN - FIRE ALARM
04.28.2026
SPECIFICATIONS
DIVISION 00 — PROCUREMENT & CONTRACTING REQUIREMENTS
0001 10
Table of Contents
04.28.2026
6.19.2026
00 72 00
Standard General Conditions of the Construction Contract
6.19.2026
Wage Rates
CFW Horizontal Wage Rate Table
6.19.2026
Wage Rates
CFW Vertical Wage Rate Table
6.19.2026
DIVISION 01 -- GENERAL REQUIREMENTS
01 1000
Summary
04.28.2026
06.19.2026
01 23 00
Alternates
04.28.2026
71 25 00
Substitution Procedures
05.22.2026
06.19.2026
01 31 20
Project Meetings
05.22.2026
06.19.2026
01 33 00
Submittals
05.22.2026
06.19.2026
01 45 23
Testing and Inspection Procedures
05.22.2026
06.19.2026
01 50 00
Temporary Facilities and Control
05.22.2026
06.19.2026
71 57 13
Storm Water Pollution Prevention
05.22.2026
06.19.2026
01 60 00
Product Requirements
05.22.2026
06.19.2026
01 66 00
Product Storage and Handling Requirements
05.22.2026
06.19.2026
01 71 23
Construction Staking and Survey
05.22.2026
06.19.2026
71 7423
Cleaning
05.22.2026
06.19.2026
01 77 19
Closeout Requirements
05.22.2026
06.19.2026
01 78 23
Operation and Maintenance Data
05.22.2026
06.19.2026
01 78 39
Project Record Documents
05.22,2026
06.19.2026
DIVISION 03 -- CONCRETE
03 05 16
Underslab Vapor Barrier
04.28.2026
03 10 00
Concrete Formwork
04.28.2026
03 20 00
Concrete Reinforcement
04.28.2026
03 30 00
Cast -in -Place Concrete
04.28.2026
03 35 it
Concrete Floor Finishes
04.28.2026
DIVISION 04 -- MASONRY
04 20 00
Unit Masonry
04.28.2026
DIVISION 05 -- METALS
05 50 00
Metal Fabrications
04.28.2026
DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES
06 10 00
Rough Carpentry
04.28.2026
06 41 00
Architectural Wood Casework
04.28.2026
06 61 00
Cast Polymer Fabrications
04.28.2026
06 83 16
Fiberglass Reinforced Paneling
04.28.2026
DIVISION 07 -- THERMAL AND MOISTURE PROTECTION
07 21 00
Thermal Insulation
04.28.2026
07 41 13
Metal Roof Panels
04.28.2026
0742 13
Metal Wall Panels
04.28.2026
07 62 00
Sheet Metal Flashing and Trim
04.28.2026
07 71 00
Roof Specialties
04.28.2026
07 84 00
Firestopping
04.28.2026
07 92 00
Joint Sealants
04.28.2026
DIVISION 08 -- OPENINGS
08 11 13
Hollow Metal Doors and Frames
04.28.2026
08 14 16
Flush Wood Doors
04.28.2026
08 31 00
Access Doors and Panels
04.28.2026
08 33 44
Overhead Coiling Fire Shutters
04.28.2026
08 36 13
Sectional Doors
04.28.2026
7843 13
Aluminum -Framed Storefronts
04.28.2026
06.19.2026
08 71 00
Door Hardware
04.28.2026
788000
Glazing
04.28.2026
DIVISION 09 -- FINISHES
09 21 16
Gypsum Board Assemblies
04.28.2026
09 22 16
Non -Structural Metal Framing
04.28.2026
09 30 00
Tiling
04.28.2026
09 51 00
Acoustical Ceilings
04.28.2026
09 65 00
Resilient Flooring
04.28.2026
06.19.2026
09 91 13
Exterior Painting
04.28.2026
09 91 23
Interior Painting
04.28.2026
06.19.2026
DIVISION 10 -- SPECIALTIES
10 1400
Signage
06.19.2026
10 26 00
Wall and Door Protection
04.28.2026
10 28 00
Toilet, Bath, and Laundry Accessories
04.28.2026
74400
Fire Protection Specialties
04.28.2026
10 51 13
Metal Lockers
04.28.2026
10 73 10
Prefinished Aluminum Canopies And Shade Structures
04.28.2026
DIVISION 11 -- EQUIPMENT
11 30 13
Residential Appliances
04.28.2026
DIVISION 12 -- FURNISHINGS
12 24 00
Window Shades
04.28.2026
12 36 00
Countertops
04.28.2026
DIVISION 13 -- SPECIAL CONSTRUCTION
13 34 19
Metal Building Systems
04.28.2026
DIVISION 22 - PLUMBING
2200 10
BASIC PLUMBING REQUIREMENTS
O4.28.2026
2205 12
PLUMBING AND ELECTRICAL COORDINATION
04.28.2026
7255 19
PLUMBING METERS AND GAUGES
O4.28.2026
22 05 29
PLUMBING SUPPORTS AND ANCHORS
O4.28.2026
725553
PLUMBING IDENTIFICATION
04.28.2026
22 05 93
PLUMBING TESTING, ADJUSTING AND BALANCING
04.28.2026
2207 16
PLUMBING PIPING AND EQUIPMENT INSULATION
04.28.2026
22 10 00
PLUMBING PIPING
04.28.2026
22 1001
PLUMBING SPECIALTIES
O4.28.2026
22 11 19
PIPING SPECIALTIES
O4.28.2026
22 30 00
PLUMBING EQUIPMENT
04.28.2026
22 40 00
PLUMBING FIXTURES
O4.28.2026
DIVISION 23 - HEATING, VENTILATING, AND AIR-CONDITIONING
HVAC
2300 10
BASIC MECHANICAL REQUIREMENTS
O4.28.2026
2305 12
MECHANICAL AND ELECTRICAL COORDINATION
04.28.2026
730529
MECHANICAL SUPPORTS AND ANCHORS
O4.28.2026
23 05 53
MECHANICAL IDENTIFICATION
04.28.2026
735593
MECHANICAL TESTING, ADJUSTING AND BALANCING
04.28.2026
23 07 13
HVAC DUCT INSULATION
04.28.2026
23 31 13
METAL DUCTWORK
04.28.2026
23 31 13.19
DUCTWORK ACCESSORIES
O4.28.2026
23 3400
FANS
O4.28.2026
23 37 13
AIR OUTLETS AND INLETS
O4.28.2026
23 3723
GRAVITY VENTILATORS
O4.28.2026
23 51 00
BREECHING, CHIMNEYS, AND STACKS
O4.28.2026
06.19.2026
23 5500
FUEL -FIRED HEATERS
O4.28.2026
2381 26
SPLIT DX COOLING/HEATING SYSTEMS
04_28.2026
23 89 65
MOTOR CONTROLLERS
O4.28.2026
DIVISION 26 - ELECTRICAL
2605 10
GENERAL REQUIREMENTS FOR ELECTRICAL WORK
04.28.2026
2605 12
MECHANICAL AND ELECTRICAL COORDINATION
04.28.2026
2605 19
WIRES AND CABLES
O4.28.2026
26 05 26
GROUNDING
04.28.2026
26 05 26.01
WIRE CONNECTION AND DEVICES (EXO-THERM WELD)
04.28.2026
26 05 27
SEALING OF PENETRATIONS
O4.28.2026
26 05 29
SUPPORTING DEVICES
O4.28.2026
760532
PULL AND JUNCTION BOXES
O4.28.2026
26 05 33
CONDUITS
O4.28.2026
06.19.2026
26 05 34
OUTLET BOXES
O4.28.2026
26 05 35
WIREWAY
04.28.2026
760926
MISCELLANEOUS ITEMS
O4.28.2026
2622 13
DRY TYPE TRANSFORMERS
O4.28.2026
7624 16
PANELBOARDS
O4.28.2026
2624 17
DISTRIBUTION PANELBOARDS
O4.28.2026
2627 13
ELECTRIC SERVICE ENTRANCE
04.28.2026
2627 16
CABINETS
O4.28.2026
26 27 26
WIRING DEVICES
O4.28.2026
2628 16
OVERCURRENT PROTECTIVE DEVICES
O4.28.2026
2628 17
DISCONNECT SWITCHES
O4.28.2026
2629 13
MOTORS, MOTOR STARTERS AND CONTROLS
O4.28.2026
2641 13
LIGHTNING PROTECTION FOR STRUCTURES
O4.28.2026
2643 13
SURGE PROTECTION DEVICES (SPDS)
04.28.2026
06.19.2026
2651 13
LIGHTING
04.28.2026
06.19.2026
DIVISION 27 - COMMUNICATIONS
27 05 28
EMPTY CONDUIT SYSTEMS
O4.28.2026
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 00
ANALOG ADDRESSABLE FIRE ALARM SYSTEM
04.28.2026
DIVISION 31 -- EARTHWORK
31 6329
Drilled Concrete Piers and Shafts
04.28.2026
END.
Ll
A
TAB 6
PROJECT SCHEDULE
SpawGlass
A p T fn
d
D D D D D D D
d p d
W W W W W
V V
W W D7 W m W A O A A 8
. . .N
0 0 0 0 0 0 0 0 0 0 0 0 0
N
+ N +
O= m Q
o o
T T T O Gi V)
m m m °
O p 0
.g o p
O (/> O C. O 0 p Ow -. T T O T �_ W T Z C) G) p 0 m
.p p .g p ,� w N m o 3
O
m
Q y y c N
co
mT A - T m 3 3
a
w N m
w
o W o a o w a
Oa.
0 3 a a a o
' o m m c3q' - v 2
3
m o m
a
O m O N a S A 6
p iA p iA p a c
- O
» m D a
m m
m
3 A F
m m
181
yF N
F
II d
3 0
�D ?
t0
�
0 0�
p p W 0 0 0
�•., O O O
0 0 0 0 0 0 0 0� 0 0 0 0- �
O O O O O O O O O O O O O V
V
d
L m
o
0 o b b b o m
3
N � N N
N
61 m
N N N
O W m
D D D D
D >>
N lb51
N N N
O N dNi C
N N IN W N W N N
D D D D D D D D D D D D D rn D D D
OW
T`
O V Q N
d N
N q Oq��
O
>>
z V V � Np tp V W+ O O O V N O f Ntpp ccpp
Z O Z Z V L
o 0 0 o o= D
o o F p D? C
d P
:::mSSS
N
P
.. --
N `�A�
N>>
3 4
N N N
I
W °�
D D
ONJ m m T
D D D
ONi T (NT
D D D
(NSA (NJt N (Nl� (Nl� °1 VNi fNl� v N m N N
D D D D D D D D D D r `I +I D D D D D D D
D
-
�
O
o 0
0
o e e o 0
0 0 0
°'" o 0 0 0 0 0 0 0 0 0.12
0 0 0 0 0 0 0 0 0 o a off. o 0 0 0 0 0 0 0 0 0 0 o wl
m•
a
-----------gamg-- -
h
m
*------------------------------------- -----
--------------- •----- _--_----- _--- ._________-_----
........................................................................:...................-____
_--- --- _---- _---------- ------------------- `--------
__ _.
------------------ •__._--------------•-_--------- ______-
------ ,,......__yi ..
______ ____--- __---------
_ __ m
--------' •- __"__ __
O
- _
------------------- - --- -- ---
-
-
a I
3 3
-------------------- ----------------
- 3 -
a
3
CD
................
r------------------
---------------- = T
.- - --- -----
--_-- •--�- o
------------------
5
p
a
'-----------------
°
- -
------------- ---
° 0
------------ ------- ____ O ,
E�
a
_----
----------
+---------------------- m c
___ -
'
.a____ .... _
-
iD.a----------
m
7
_
'_a______A _____'------------------------------------
A o.
------------------;____3- �
b -'�
D a.
0
Cl
2 A 2 gm
_________�
--------------
-----------------;--------
d
m-
n----�--
-W p --W--N - ---- -----------
C
------------------ �_-----------------`----------------
---------------- A� D-
p m v s
m m
mm_. a
N v
------------- ------- ------
a m
g'
,
d
f ai ---------a°(�
--------- ---------
•
_-------------------
_ m
d
-------- --
T
___________*_._______.___-_-.---.__-_;__•________.___.__;_
-------------_----_
-
m
---------------'------------------'-----------------'---------------'-----------------`----------------'--------m--------'------------------'-------------
---
---------------`------------'-`------------'--'---'-------------'------------------'-------------------`--------3-------`------------------'-------------
�I �
---
w
d
-;
------
i
p O
i
a
m
-
��
m �
� � � -=
� �
D � � D D
i
i i
-
, .f iF i
•�if i
•�i �i �i �i �i � .�i ��i
�v .�i �i � D D D
p o0
N d m
N
[t O
C O O
O
A t0 A
A 0 0 0 0
_ .F
(O
O
.F .f
OJ
O O
O
O O
A
O O
N O 01 A
0 0 0 0 0 0 0 0 0
w�i
o
O 0 0 O O
0
n
T c
O c0
A A
(� m [n n In m .�. 1.0
3 3
3
`G
-= n
•
O m o
£➢
3 3
m
f o A °�
Fd
W N
U p
n
Q
-� N N m y N Noo
n m N t0
o
m
c
d=
O m y 3 N
m
m
� m
�
o
a o-
a v
j44ry7
3 3
3
Dy
2
n
3
C)
v
3
? N Ut
• O [n
Cn J' O W
°� N O®
Ut E N O
In O (l� N O
�_ 0�
(° N�
� N
N O O W (n � O O O
O O O
N 0 0 0 0 O O
O•
W '
m
N
W O
➢ �
N
.� �
� �
� �
j � S �
p
c � � '� �
N m � o a a
♦
� c
N N N
�
" N `N
—���
c > > >
W W ONi m
c c
__
m
m
m m
m m m m
_ `<
m m m m
m m m m m m m
3
D D
D D
•- D D➢
D D D
y
o y S
�
m Q
�
D c d
D= y d D
d
L
• (°
N N
I
N
J m N m
m rn
N m m N ONi
D D O1 D
N N
m rn
N
D D
m m
n D
N m m
°� D D
11 N m
O1 °� D➢
T N m N N
°� n D D D ..-.,.� D D D
D
2
m
0
0
Q
C1
_________________ ________________ __________________ _ _________________ -------------------
__-------_____--- _
O
:
6
m '<
__________
______________
_________ D_------------ _ ----------------------------- __--_.__-___-_-_
o D
- - AO .
_-___--____ __-----------
a� ----------------
_____----------_
i
<
_.
W
it_______________;_________________
of
° <
NID
�
°'
-�1:3 � N
-_
-
c 3 c
n
a N y m 3 3
O
m'
I v m o I o A o Q-*-_A o�-[--a
2o5.
<, o
-' A 31 �-'s-'a----`--
.r
3 m
0- m �----
: 5.
m
�-g-- 3-----------
A m L.o
3 c w o m 3:
----� -m--�--zc--3 sf-�j---=- x-- '--31----�--P--zo--v.
5. : n [)
------ --a--- --
4N
U
3
3
,
3 3
_ 3
a
3--a
SR: _
_
�._
3
, ^,
O
�__________
n
c u o.
m
-I
o.
s _
OI to
; N
? 3--
3
r-: 3
m Gl___________
`.
v
__
O
4.
m
o
A O m rn
p o p
Q D D D D D D D D D
D D
D D D D D D D D D
D
O O O O O O .O. O.
t0 . O O
o 0
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 o D 0 0 .
0 - r O °i ?! > > � v 5 0 - A ❑ 0 m m � > > 0 w F � n c ❑
o3
rn rn N
N
r D _I -oC = p, m n v K ❑ 3 a Q X D o a
_v
�o A ❑ m m a ()
N v ? o x
1 m A s=
O o ° m o a 4= o o $ o
N � m
ro vl �
Q
O S
d S 3
5 p o 2
� d tli � � N A » �
o lD � � �' N ❑ � W
� d =� N �
�
�
�
N y
ai of p
3
m
0 x �
0
3
II d
t0
Zt
N N N N N J N V N N N N
N N N N N N N N N
N
N
a 3 0
-aD -oD D -oD -oD 3 3 3 m L❑ Z
m a d a a a
L O❑ Z Z
o 0
Im
� �I �I J JId JI Jle�h J V V J J m m
v m m m rn
rn
A
-
m
0
o O o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o e o 0 00 0o e o 0 e
0 0 0 0 0 0 0 0 0
e0 0 0 0 0 0 0
0
m
o
a
- ---------------- ---------------- ---------------------------------------
I I I
•
--------------- ------------------
I
S
--
01
I I I
----------- ------------------ ------------------ ;------------------ ;------------------ ;--------------------------------------- ------------------I
I
w C
•
I
m
d
0 0 —'
' --'
-----------'----------------'------------------------------
`----------------
----------
-'-
o_ D a•
I
p CDi —.
----------- '------------------ •------------------------------ ------------------------------------------------------------------
------------'----- ---
- 3
.r
d-----------
•-------- _______•__ ___------ _---- _------------------ '__________________�_ _
------ -----------
y
I I
I
p
CD
N
.►
K
------------------------------------------------- ----------------- ---------------- -------------------------------------------------- `-------------- ■
------------------------------------------------ _
------------- _____________
• --- --�--- a'
_-------------O-
'
o_
-------------------'------------------------------
----------------------------------'-------,---- -7�d-
- -�— ---
--Q----Tm
d
',�
________—____N_______o■_____.__;_m______-■----■----■-__________________---------------_-;_-----------------` n___�_ qa
_--_
_
AA•�
�----------
¢_
�a'•�N--
___________ ---------- N_��
—da
�v m_ :•—N■
___>______m'd O
❑--
�m
7f••_
-_---_-_-_-_-_l■_i �dda
9
--------- -
C
ZF
m■
O
a O1 A m g.
--------------------
----^ �__
-�
d_N--p'•-------------------
•____D_O_-p-" Npd�
�d ••
-od
.-�•
-"----dd--�_I---�-
�
.
Uri aga
N' --- '
----!---------------- ------------ --o-. ---
-m,AG-�
----------------,.....
o
O p O p D w w 25 D D D l� y D yy y y y D
W - N N N N N N N
O N d m 0 0 O. O 07 m A 0 N C O
N H O O O
0 0 0 0 0 0 0
O O O +
N N
-
O
m m v N O O T d• T "000 '�
m O y o 0..
01
_ o
m
N
ICI
0 A D
m 2
g W. d
O• - O O J J J
O O N NO
1. L L Sc L 1. c o 3
♦ J V V V J V N v N� N `G
� 3 O y o
I c > > r
V V N V V
a J�
N O O O O O O O O O O O I O O O
0 0 0 0 0 0 0
N
O
M
m
o
W
n
C1 '
O
CD
ID
o _
m
A Q
o D
A D
K
O
0
----------------------------------------
5.
0 0
m r rn m ��-- m obi d d
__ _�
y�-- m O N'
o
T iK-' m n
r________ q,_4_ID_,
m o �'�c S. of � o c��n
3 �; -
m m � •
Best
Construction Experience
KERRY FELLERS
PROJECT MANAGER I EMPLOYEE OWNER
As project manager, Kerry will be responsible for the overall management of
the project. Kerry's esponsibilities include budget conformance, subcontractor
coordination, contract administration and construction operations oversight
including safety and quality assurance.
MEACHAM AIRPORT FIELD MAINTENANCE FACILITY
Fort Worth, TX 1 $5,500,000 11,500 SF
New field maintenance facility adjacent to the existing one on a 0.32-acre site that
will provide office space and storage for personnel, equipment and materials with a
focus on furniture, fixtures and equipment (FF&E)
PARMER AND MOPAC H-E-B
Austin, TX I Confidential 173,000 SF
Phased, complete interior remodel of an active and operational grocery store,
including new pharmacy, bakery and curbside departments and new elevator
TEXAS STATE UNIVERSITY BRUCE AND GLORIA INGRAM HALL
San Marcos, TX 1 $90,403,710 1166,851 SF
New six -level, 166,851 SF science and engineering building, including spaces for
administrative office, research and teaching labs, maker space, classrooms and
common areas; and an extension of the campus utilities to serve the new facility
CEDAR HILL STATE PARK CAMP LOOP REPAIRS
Cedar Hill, TX 1$20,185,097
Renovations of 160 Camp Sites and construction of four new restroom and shower
buildings
AUSTIN COMMUNITY COLLEGE HIGHLAND SOUTH PARKING GARAGE
Austin, TX 1 $52,858,073 1812,000 SF
New seven -level, 2,385-space cast -in -place parking garage with five portal gates,
four elevators in two towers, six sets of cast -in -place concrete stairs and a below -
grade 1,000,000-gallon rainwater and condensate harvesting cistern that provides
irrigation for this area of campus
ALTERMAN DALLAS RENOVATION
Lewisville, TX 1 $9,721,000 144,600 SF
Renovation of existing tilt wall building, including 25,400 SF office space and 19,200
SF warehouse space, and new storage/parking area
YEARS OF EXPERIENCE
9 years in the Industry
8 years with SpawGlass
EDUCATION / TRAINING
B.S. Construction Science and
Management,
Texas State University
OSHA 30-Hour
First Aid/CPR/AED
SpawGlass
LANCE MULLENS
SUPERINTENDENT I EMPLOYEE OWNER
As superintendent, Lance will be responsible for safety, organization and
mobilization of field operations, continuing project planning, documentation of daily
activities, inspection of work for quality conformance and ensuring activities align
with the project schedule
MEACHAM AIRPORT FIELD MAINTENANCE FACILITY
Fort Worth, TX 1 $5,500,000 11,500 SF
New field maintenance facility adjacent to the existing one on a 0.32-acre site that
will provide office space and storage for personnel, equipment and materials with a
focus on furniture, fixtures and equipment (FF&E)
CORPUS CHRISTI STATE SUPPORTED LIVING CENTER REPAIRS, ROOFING AND MEP-
HVAC UPGRADES
Corpus Christi, TX 1 $6,806,847 10 SF
Renovation of building systems, materials and equipment to meet code
requirements
CONFIDENTIAL CLIENT CEMENT TERMINAL STORAGE EXPANSION
Corpus Christi, TX I Confidential
Construction of a tilt -wall warehouse building with MEP scopes, overhead doors,
canopies and interior finishes; exterior scope of work includes a 19,000 square -foot
parking lot addition, new utilities and fencing
BEEVILLE ISO A.C. JONES HIGH SCHOOL AUDITORIUM RENOVATION
Beeville, TX 1 $3,003,150 111,380 SF
The ACJ Auditorium Renovation includes upgrades to seating, lighting, finishes,
acoustics and audiovisual systems, along with improvements to mechanical,
electrical and accessibility features
FROST LAKE ARLINGTON FINANCIAL CENTER
Arlington, TX I $Confidential
New 4,000 GSF Frost Financial Center. Demolition of existing Frost building.
Storefront & stucco exterior with drywall & storefront interior
YEARS OF EXPERIENCE
7 years in the Industry
3 years with SpawGlass
EDUCATION / TRAINING
A.S. Construction Management,
Amarillo College
First Aid/CPR/AED
OSHA 10-Hour
OSHA 30-Hour
SpawGlass
KAIDEN HAMMOND
PROJECT SAFETY ASSISTANT I EMPLOYEE OWNER
As project safety assistant, Kaiden will direct and implement SpawGlass' safety
program to provide a safe, healthy and accident -free work environment. He will be
responsible for conducting jobsite training and orientations; risk assessments;
safety inspections; incident reporting; and safety reporting and documentation.
MEACHAM AIRPORT FIELD MAINTENANCE FACILITY
Fort Worth, TX 1 $5,500,000 11,500 SF
New field maintenance facility adjacent to the existing one on a 0.32-acre site that
will provide office space and storage for personnel, equipment and materials with a
focus on furniture, fixtures and equipment (FF&E)
THE UNIVERSITY OF TEXAS AT DALLAS STUDENT SUCCESS CENTER + STUDENT UNION
Richardson, TX 1 $246,338,007 1380,000 SF
The five -level building includes classrooms, student union, a 400-seat lecture hall,
Office of Undergraduate Education, Honors College, Education Abroad Office, Office
of Graduate Education, Center for Teaching and Learning, Instructional Technology,
administration and support space
GREGG COUNTY PARKING FACILITY
Longview, TX 1 $23,822,748 1117,735 SF
Construction of a 293-space multi -level cast -in -place parking facility with
office space; structure is partially enclosed with pre -cast panels to blend in with
surrounding downtown buildings
ALTERMAN DALLAS RENOVATION
Lewisville, TX 1$9,721,000144,600 SF
Renovation of existing tilt wall building, including 25,400 SF office space and 19,200
SF warehouse space, and new storage/parking area
YEARS OF EXPERIENCE
5 years in the Industry
2 years with SpawGlass
EDUCATION / TRAINING
B.S. Safety and Health
Management,
Central Washington University
Confined Space Entry
Fall Protection
First Aid/CPR/AED
OSHA 30-Hour
OSHA 510 Course
Trenching and Excavation
Cranes and Derricks Safety 1
Safe Scaffold Erection and
Inspection
UF_awGlass
1,
n
SITE LOGISTICS
SpawGlass
w
If If
0
0
m
Ck)
N
Y�
a
P ME
zi
7A
hm
V ---IF-r--v
17,
cN
11
SpawGlass Contractors, Inc.
3000 W. Loop 820 S.
Fort Worth, TX 76116
817-288-0890
www.SpawGlass.com
Connect with us today!
112 O-C; In
Signature:
Email: allison.tidwell@fortworthtexas.gov
FORT WORTH.
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: SpawGlass
Subject of the Agreement: Amendment #3 - Construction of Meacham Maintenance Facility and Associated Site work
M&C Approved by the Council? * Yes ❑ No 0
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes ❑✓ No ❑ CSC 64158
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 0 No ❑
If unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No ❑✓ If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date:
If different from the approval date.
Expiration Date:
If applicable.
Is a 1295 Form required? * Yes ❑ No ❑
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. CPN 105655
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes ❑ No ❑✓
Contracts need to be routed for CSO processing in the following order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be