HomeMy WebLinkAbout065411-CO1 - Construction-Related - Contract - GRBK Edgewood LLCDowsign Envelope ID'. 9BF34084A611-8601-BOCC-46633A914A4D r 0 FORT WORTH,,, Developer -Awarded -Project Change order CSC NO. 65411-CO 1 Change Order Number: 1 Project Name: CIBOLO HILLS WEST 16-INCH WATERLINE IPRC Record: IPRC26-0035 City Secretary Number: 65411 X Number: X-28911 City Participated Project: O Yes No Inspector Name: Leticia Flores Project Manager Name: Ahmed Musa Date: 8/4/2026 CPN: 106849 CFA Number: CFA26-0043 FID: FID # 30114-0200431-106849-EO7685 File Number: N/A Email: Leticia. Flores(afortworthtem—ov Email: Ahmed, Mus Afortworthtexas.aov Phone: 682-454-2732 Phone: 817-392-2084 CONTRACT UNIT WATER Working Days Credits/Extras Developer Cost City Cost Original Contract $188,327.40 $184,130.60 30 Extras to Date $0.00 $0.00 0 Credits to Date $0.00 $0.00 0 Contract to Date $188,327.40 $184,130.60 30 Amount of Proposed CO $15,187.50 $0.00 0 Revised Contract Amount $203,514.90 $184,130.60 30 Total Revised Contract Per Unit $387,645.50 Revised Cost Share Dev. Cost: $203,514.90 City Cost: $184,130.60 Total Revised Contract $387,645.50 Reason for Change Order Additional water line and appurtenances added to facilitate chlorine and pressure testing of 16" WL. Changes correspond to Revision No. 1 as shown on sheets 6R7. 7R1, & SR1 of the construction plans. OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX CITY OF FORT WORTH STANDARD CONSTRUCTION DOCUMENT — DEVELOPER AWARDED PROJECTS REVISED DATE: March 10.2026 1 Of 3 D—,ign Envelope ID: 98F3408 611-8601-80CC46n3A914A4D FORT WORTH Change Order Number: Project Name: CIBOLO HILLS WEST 16-INCH WATERLINE You are directed to make the following changes in the contract documents: Asterisk (*) indicates New Pay Item Developer-Awar ed roject Change Order Date: 8/4/2026 CPN: 106849 UNIT I: WATER IMPROVEMENTS PAY ITEM # CITY BID ITEM # QUANTITY UNIT ITEM DESCRIPTION UNIT PRICE Developer Cost City Cost TOTAL 3 3311.0001 0.275 TON Ductile Iron Water Fittings w/ Restraint $12500.00 $3 437.50 $0.00 $3 437.50 12* 3312.0117 1 EA Connection to Existing 4"-12" Water Main $1200.00 $1,200.00 $0.00 $1,200.00 13* 3312.3003 1 EA 8" Gate Valve $1550.00 $1,550.00 $0.00 $1 550.00 14* 9999.0001 2 EA 2" Flushing Valve $4,500.00 $9,000.00 $0,00 $9,000.00 TOTAL UNIT I: WATER IMPROVEMENTS $15,187.50 $0.00 1 $15,187.50 CITY OF FORT WORTH STANDARD CONSTRUCTION DOCUMENT — DEVELOPER AWARDED PROJECTS REVISED DATE: March 10.2026 PXiiil:3 Dowsign Envelope ID'. 9BF340M4 611-8601-BOCC-46633A914A4D FORT WORTH Developer-Awar ed Change Order Number: 1 Project Name: CIBOLO HILLS WEST 16-INCH WATERLINE Name: Adam Burns Contractor Requested: Sign ture: Name: Natanael Gonzalez, P.E. Engineer Recommended: Signature: � (� Name: A—d Guthrie Developer Approved: wed by. I/q'� C,{,{/, t. Si nature: U.mw �`^� 668053045F8543D... Name: Mosadage Mohammdeen AG Project Manager: Andrew Goodman Signature: Motas(age Mohaer'Hdeen,E t MI"fi'�� CoFW Participating DepartmenIIL Name: Suby Varu hese Si nature: Sub l�2ucysrwcad P` !!// CoFW Assistant City Attorney: Name: Richard McCracken �¢eei�¢ UJe�w.¢au Signature: 0 Name: Dana Dur hdoff CoFW Assistant City Manager:4 �Imw&,— Si nature: Dianna Giordano (Aug 14. 2026 11:24:52 CDT) Name: Jannette S. Goodall /�c roject Change Order Date: 8/4/2026 CPN: 106849 Title: Manager Date: 8/5/26 CoFW City Secretary: h Signature: > anb @4pOgr �Ca °°e °°°° o?'p9�10 I.e M&C Number: M&C 26-0357 pv^ o =P&C Date Approved: 5/12/2026 aa4IlbnEooS�4.o Title: Sr. Project Engineer 8/4/2026 AuMon,ed Signer Date: e/5/2026 i 2:35 PM CDT Title: Sr. Professional Engineer 08/07/2026 Title: Engineering Manager Date: 08/11 /2026 Title: Senior Assistant City Attorney Date: 08/12/2026 Title: Assistant City Manager 08/14/2026 Date: 08/17/2026 OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX CITY OF FORT WORTH STANDARD CONSTRUCTION DOCUMENT — DEVELOPER AWARDED PROJECTS REVISED DATE: March 10.2026 3 of 3 FORT WORTH. I City Secretary's Office Contract Routing & Transmittal Slip Contractor's Name: GRBK Edgewood LLC Subject of the Agreement: Additional water line and appurtenances added to facilitate chlorine and pressure testing of 16" WL. Changes correspond to Revision No. 1 as shown on sheets 6R1, 7R1, & 8R1 of the construction plans. This will be for Change order 1. M&C Approved by the Council? * Yes ❑ No M If so, the M&C must be attached to the contract. Is this an Amendment to an Existing contract? Yes 0 No ❑ CFA26-0043 If so, provide the original contract number and the amendment number. Is the Contract "Permanent"? *Yes 0 No ❑ If unsure, see backpage for permanent contract listing. Is this entire contract Confidential? *Yes ❑ No 0 If only specific information is Confidential, please list what information is Confidential and the page it is located. Effective Date: 06/22/2026 If different from the approval date. Expiration Date: 06/22/2028 If applicable. Is a 1295 Form required? * Yes ❑ No 21 *If so, please ensure it is attached to the approving M&C or attached to the contract. Project Number: If applicable. 106849 *Did you include a Text field on the contract to add the City Secretary Contract (CSC) number? Yes 0 No ❑ Contracts need to be routed for CSO processing in the followingorder: rder: 1. Katherine Cenicola (Approver) 2. Jannette S. Goodall (Signer) 3. Allison Tidwell (Form Filler) *Indicates the information is required and if the information is not provided, the contract will be returned to the department. Permanent Contracts Advanced Funding Agreements Architect Service Community Facilities Completion Agreement Construction Agreement Credit Agreement/ Impact Fees Crossing Agreement Design Procurement Development Agreement Drainage Improvements Economic Development Engineering Services Escrow Agreement Interlocal Agreements Lake Worth Sale Maintenance Agreement/Storm Water Parks/Improvement Parks/Other Amenities Parks/Play Equipment Project Development Property/Purchase (Property owned by the City) Property/Sales (Property owned by the City) Property/Transfers (Property owned by the City) Public Art Sanitary Sewer Main Replacements Sanitary Sewer Rehabilitations Settlements (Employees Only) Streets/Maintenance Streets/Redevelopment Streets/Repairs Streets/Traffic Signals Structural Demolition (City owned properties) Utility Relocation Water Reclamation Facility Water/Emergency Repair Water/Interceptor Water/Main Repairs Water/Main Replacement Water/Sanitary Sewer Rehabilitation Water/Sewer Service Water/Storage Tank