HomeMy WebLinkAbout059062-A1 - Construction-Related - Contract - Tarrant CountyCSC No. 59062-A1
STATE OF TEXAS §
§ Amendment No. 1 of Interlocal Agreement
§ for Camp Bowie Boulevard Improvements
COUNTY OF TARRANT §
BACKGROUND
Tarrant County ("COUNTY") and the City of Fort Worth ("CITY") entered into an Interlocal
Agreement approved by Tarrant County Commissioners Court Order No. 139814, City Secretary
No. 59062, for financial support of up to $2,690,000.00, for the cooperative funding of
improvements to Camp Bowie Boulevard from Montgomery Street to University Drive ("Project")
as described in the Tarrant County 2021 Transportation Bond Program.
Therefore, the COUNTY and CITY agree to the following revisions. Paragraphs III, IV, and V
from the original Interlocal Agreement are repealed and replaced with the following language:
III.
TERM
This ILA shall become effective upon the approval of both parties and shall terminate on
September 30, 2026, unless terminated as described in Section XIII in the original ILA or extended
in writing and approved by both parties.
IV.
FISCAL FUNDING ACKNOWLEDGEMENT
Tarrant County bond funds will be encumbered on a fiscal year basis in accordance with the
Certification of Available Funds shown herein. In the event no funds or insufficient funds are
appropriated and budgeted or are otherwise unavailable by any means whatsoever in any fiscal
period for payments due under this ILA Amendment, then the affected party will immediately
notify the other party of such occurrence and this ILA as amended may be terminated on the last
day of the fiscal period for which appropriations were received without penalty or expense to the
affected party of any kind whatsoever, except to the portions of annual payments herein agreed
upon for which funds shall have been appropriated.
V.
REIMBURSEMENT PROCESS
The COUNTY agrees to reimburse the CITY for the actual eligible PROJECT costs in an
amount not to exceed $2,690,000.00. Any reimbursement request from the CITY should include:
1) a copy of the invoice or billing for design services, right-of-way acquisition purchase, -and
construction; and 2) a copy of the check, a certification letter, or other documentation to verify the
CITY's proof of payment. The final reimbursement payment to the CITY will be contingent upon
the City Manager or Mayor providing written notification to the COUNTY that the project is
complete along with identification of final project costs. COUNTY bond funds for the Project are
allocated as follows:
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Interlocal Agreement Amendment No. 1— 2021 TBP —Camp Bowie Blvd Improvements Project Page 1
County Pavinent by Phase`
Design:
$0.00
ROW Acquisition:
$0.00
Construction:
$992,026.00 (2006 TBP)
$1,697,974.00 (2021 TBP)
TOTAL:
$2,690,000.00
TBP Funding Category: 2006 Discretionary Pct 4, 2021 Discretionary Judge
* Reimbursement payments will be issued by the COUNTYfor eligible expenses incurred
during the Fiscal Year for which bond funds are certified by the Tarrant County Auditor.
The CITY understands that the CITY will be responsible for cost overruns and any other
expenses incurred by the CITY in performing the services described herein. The CITY agrees that
the COUNTY retains control over when reimbursement payments will be disbursed to the CITY.
In addition to the foregoing replacement language, Attachment A is removed and deleted from
the original Interlocal Agreement in full. All other paragraphs, terms and language outside of
paragraphs III, IV, and V as well as Attachment A remain unchanged and in effect.
APPROVED on this day the day of , 2024, by Tarrant County.
Commissioners Court Order No. �1 i L.
TARRANT COUNTY, TEXAS CITY OF FORT WORTH
Tim O'Hare, County Judge
Manny Ramirez, Commissia ct 4
APPROVED AS TO FORM. -
Criminal District Atto y's Office*
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Jesica McEachern, Assistant City Manager
M&C M&C 23-0024
Date: 1/10/2023
Douglas BEack (Nov 19, 202417:36 CST)
City Attorney
Font°yea
OO,e^09�10
Gp g=d
tt pPQ�F"a ve
A. l3 �1nJt1 Opn�q�X65e
City Secretary (If applicable)
Interlocal Aereement Amendment No. 1— 2021 TBP — Camp Bowie Blvd Improvements Project Page 2
* By law, the Criminal District Attorney's Office may only approve contracts for its clients. We reviewed
this document as to form from our client's legal perspective. Other parties may not rely on this approval.
Instead, those parties should seek contract review from independent counsel.
CERTIFICATION OF AVAILABLE FUNDS IN THE AMOUNT OF:
1. 3�0. QQ0. ccxas follows:
".
Fiscal Year ending September 30, 2025: $992,026.00 2006 TBP Discretionary - Pct 4
$357,974.00 2021 TBP Discretionary -Judge
Auditor's Offic
Interlucal Agreement Amendment No. 1— 2021 TBP — Camp Bowie Blvd Improvements Project Page 3
Consideration of Amendment No. I to the Interlocal Agreement between Tarrant County and the
City of Fort Worth Related to the Camp Bowie Boulevard Improvements Project - 2006 and
2021 Transportation Bond Program
SIGNED AND EXECUTED this 17 day of December, 2024.
COUNTY OF TARRANT
STATE OF TEXAS
Tnm O'Hare - County Judge
Tim O'Hare
County Judge
<#deefee5c-dd95-451 e-039c-08dcb56d40e8-DateSigned#>
Consideration of Amendment No. I to the Interlocal Agreement between Tarrant County and the
City of Fort Worth Related to the Camp Bowie Boulevard Improvements Project - 2006 and
2021 Transportation Bond Program
SIGNED AND EXECUTED this 17 day of December, 2024.
COUNTY OF TARRANT
STATE OF TEXAS
Tim O'Hare
County Judge
1/15/2025
\9 �yt, Qq5-t(/
COMMISSIONERS COURT
r COMMUNICATION
COURT ORDER NUMBER
PAGE 1 OF 5
DATE: 1/14/2025
SUBJECT: CONSIDERATION OF AMENDMENTNO. TO THE INTERLOCAL
AGREEMENT BETWEEN TARRANT COUNTY AND THE CITY OF FORT
WORTH RELATED TO THE CAMP BOWIE BOULEVARD
IMPROVEMENTS PROJECT - 2006 AND 2021 TRANSPORTATION BOND
PROGRAM
*** CONSENT AGENDA ***
COMMISSIONERS COURT ACTION REQUESTED
It is requested that the Commissioners Court consider Amendment No. 1 to the Interlocal Agreement (ILA)
between Tarrant County and the City of Fort Worth related to the Camp Bowie Boulevard Improvements
Project - 2006 and 2021 Transportation Bond Program (TBP), located in Precinct 4.
BACKGROUND
ND
On December 6, 2022, the Commissioners Court, through Court Order # 139814, approved an ILA with the City
of Fort Worth for financial support of up to $2,690,000.00 related to improvements to the Camp Bowie
Boulevard project from Montgomery Street to University Drive as described in the 2021 Tarrant County Bond
Program. The 2006 and the 2021 TBP funding for this project will be provided through the Discretionary
funding category.
The project is in the final design phase, requiring that the agreement expiration term be extended.
With approval, the original ILA will be amended to extend the expiration date to September 30, 2026, to
continue the 2006 and the 2021 TBP funding for this project, and Articles III, IV, and V, are repealed and
replaced, and Attachment A is repealed in its entirety.
This ILA has been reviewed by the Auditor's Office and approved as to form by the Criminal District Attorney's
Off ce.
FISCAL IMPACT
The fiscal impact to Tarrant County for the entire project will be $2,690,000.00 in 2006 and the 2021 TBP
funds.
The fiscal impact for the 2006 TBP, FY 2025 will be $992,026.00 and is available in account 47700-2025 2006
TBP DIS P4 / 6840100000 Transportation / 579061 County Projects.
The fiscal impact for the 2021 TBP, FY 2025 will be $357,974.00 and is available in account 47800-2025 2021
TBP DIS Judge / 6840100000 Transportation / 579061 County Projects.
SUBMITTED BY
Transportation Services
PREPARED BY:
Abbas Rastandeh
APPROVED BY:
Scott Hall