HomeMy WebLinkAbout056603-A3 - Construction-Related - Contract - Freese and Nichols, Inc.OFFICIAL RECORD
CSC No. 56603-A3
CITY SECRETARY AMENDMENT No . 3
FT. WORTH, TX
TO CITY SECRETARY CONTRACT No. 56603
WHEREAS, the City of Fort Worth (CITY) and Freese and Nichols, Inc.,
(ENGINEER) made and entered into City Secretary Contract No. 56603, (the
CONTRACT) which was authorized by M&C 21-0770 on the 28th day of September,
2021 in the amount of $ 1,291,465.00; and
WHEREAS, the CONTRACT was subsequently revised by:Amendment No. 1 in
the amount of $40,193.00 which was administratively authorized on May 09,
2022, and Amendment No. 2 in the amount of $613,052.00 which was authorized
by M&C 24-0518 on June 11, 2024; and
WHEREAS, the CONTRACT involves engineering services for the following
project:
West Fork Collector Parallel, Phase-1 - Trinity River Siphon to
Walker Branch Connection, CPN 103291; and
WHEREAS, it has become necessary to execute Amendment No. 3 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement, which
amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional
engineering services specified in proposal attached hereto and incorporated
herein. The cost to City for the additional design services to be performed
by Engineer totals $21,805.00 (Sewer).
2.
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $1,966,515.00.
3.
All other provisions of the Contract, which are not expressly amended
herein, shall remain in full force and effect.
City of Fort Worth, Texas West Fork Collector Parallel, Phase 1 - Trinity River Siphon to Walker Branch Connection
Prof Services Agreement Amendment Template 103291
Revision Date: June 13, 2025
Page 1 of 2
EXECUTED and EFFECTIVE as of the date subscribed by the City's
designated Assistant City Manager.
APPROVED:
City of Fort Worth ENGINEER
Freese and Nichols, Inc.
N
Jesica McEachern
Assistant City Manager
DATE: 08/27/2026
o �nnuIl
p O� FORT�pdd
ATTEST:
lG��(.��./Q/L/t'L� �GGti dace nEXA?a4`
Jannette Goodall
City Secretary
APPROVAL RECOMMENDED:
Christopher Hard& (Aug 19, 2026 07:42:34 CDT)
Chris Harder, P.E.
Director, Water Department
Contract Compliance Manager:
Nicholas Lester, P.E.
Vice President
DATE: 08/07/2026
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements.
r_-XLT��
Cla on M. Torrance, P.E.
Pr ject Manager
APPROVED AS TO FORM AND LEGALITY:
a&-gor—
Douglas Black (Aug 19, 2029 14:05:10 CDT)
Douglas W. Black
Sr. Assistant City Attorney
M&C No.#: N/A
M&C Date: N/A
City of Fort Worth, Texas West Fcrk Collector Parallel, Phase 1 - Trinity River Siphon to Walker Branch Connection
Prof Services Agreement Amendment Template 103291
Revision Date: June 13, 2025
Page 2 of 2
801 Cherry Street, Suite 2800 + Fort Worth, Texas 76102 + 817-735-7300 + FAX 817-735-7491
July 30, 2026
Clayton M. Torrance, P.E.
Project Manager
City of Fort Worth Water Department
100 Fort Worth Trail
Fort Worth, TX 76102
Re: Amendment No.3 for the West Fork Collector Parallel, Phase 1
(City Project No. 103291)
Geomorph Areas 4 and 5 at VCWRF
Dear Mr. Torrance:
www.freese.com
Freese and Nichols, Inc. (FNI) is providing this proposal to amend the Engineering Design Services for the
Geomorph Areas 4 and 5 (City Project Number 103291). The following fee includes the costs for an
archeological surveying as required by the Texas Historical Commission (THC). FNI records show that this
proposal would serve as Contract Amendment No. 3.
A summary of the additional costs is shown below:
Item
Archeological Survey
Total
Fee
$21,805
$ 21, 805
CPN 103291 Amendment No. 3
Geomorph Areas 4 and 5 at VCWRF
July 30, 2026
Page 2 of 2
Original Contract Amount
$
1,291,465
Amendment No. 1
$
40,193
Amendment No.2
$
613,052
Amendment No. 3
$
21,805
Contract Amount to Date
$
1,966,515
Freese and Nichols, Inc. appreciates this opportunity, and we would like to meet with you to discuss
these additional services at your convenience.
Sincerely,
J W�0. �'�
Amanda Johnson, P.E.
Associate
Attachments
Level of Effort Spreadsheet
Attachment A - Scope
ATTACHMENTA
DESIGN SERVICES FOR
WEST FORK COLLECTOR PARALELL, PHASE 1
ATTACHMENT A
Scope for Engineering Design Related Services for Water and/or Sanitary Sewer
Improvements
DESIGN SERVICES FOR
WEST FORK COLLECTOR PARALLEL, PHASE
AMENDMENT NO.3
CITY PROJECT NO.: 103291
The scope set forth herein defines the work to be performed by the ENGINEER in completing
the project. Both the CITY and ENGINEER have attempted to clearly define the work to be
performed and address the needs of the Project. Task Nos. 1-11 were previously defined
under the original contract. Although not included here the language in the original contract
apply to this amendment, as if included herein.
The purpose of this amendment is to amend Task 11 (Area 4 Bank Protection and Area 5
Outfall Protection Plan Development) by including additional effort for performing an
archaeological investigation due to the requirement by the Texas Historical Commission
(THC).
WORK TO BE PERFORMED
Task 11.12 Archeological Investigation
Task 11.12 Archeological Investigation
An archaeological investigation shall be carried out by a subcontractor and will include the
following:
• Coordinate with THC and United States Corps of Engineers (USACE) to develop
scope of work and permit application of the field survey.
• Conduct field survey that will involve visual inspection supplemented by backhoe
trenching. Assumed to perform approximately 8 shovel tests and 4 backhoe trenches.
• Draft a single report that summarizes all background data, previous investigations, the
results of the current investigation, and regulatory investigations.
• Draft report will be submitted for review.
• Submit draft report to THC and USACE for regulatory review and concurrence of
findings.
• Submit final report and curate all project documents.
ADDITIONAL SERVICES NOT INCLUDED IN THE EXISTING SCOPE OF SERVICES
Additional Services not included in the existing Scope of Services — Refer to original
contract for additional services not included in the scope of services.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 1 of 1
EXHIBIT 6.2
Level of Effort Spreadsheet
TASK/HOUR BREAKDOWN
Design Services for
Geornorph - Areas 4 and 5
Pge.m RpunIt ..
n Drt.:Fmm
S.rvin DN.:To %Xx
m.om. on.: na
ICPN 103291
nonnopm
I
ESp....
ToEDnen
ke pnon
"n"'°l'r lel.ox o.m.Ae s.nmr
JPIC EnRlnnr Tnnl I GBTnnI Env
Owlolnn Fnpinnr Selenll.t
I rrol.cl D snlor 10.0 Pnvit
GI31 Atlmin wlnlMljJH
Env G13
Tpml Lebpr
Cost
s x Im t
u emu n
Tomt E.pmn T. a pm
ni br I ae
Tnv.l R.protlupAtlmin
wBrom roml
Butlpn t0%aub 'uep.l
t IAArtxertollnie0(mpuon
1 apl
teal
eI )
511 I
���
S_0
SST,Bl0 SDI
StT.ipl
Sli
Sy 301
51.18]]0 tt1,BDB.N SD.D0 i^l,B0f.T1
0•J f0J St.IB).JD 5 1BI 0000 S 1b1b
0
m l t 1
01 DI 0
C �I
1
sa0B/I
StT.BT' S01
511, t]D.0IB
s l n/ 8501
t
1 o ill sL18'1..1ri fm.B05.]I f0l snaD5.1t1
D
1
�mo �pe✓�
Rom Ip c1ry:
romrlsonouooeonAG5d01lm1.
rn.-r..nI
02 on
SUF0nl m0riup. Olson, c0lumm AB .ntl. vnr.
no
ptleetl c0 N01 numb.n mucxn pttpcFm.nl B -t
Ipl oml Fop
(BI SurvM Fen
I uBEISBE Su® �m 211 B]]
I OnuBE/sBE subcOmulla
to M., F.,g�I00% IIC1
I 3 .00
I I
I
1ptpl en,. ' .
I P l.0n T.t.B0t.0D
A,�pIFpBWenn, np
AIAO,trsnr , Ira vi.. EBoe S10,rtmenl
lyprnl Wpm.0m Sever O0µ31tmem
FYVATR Oneul Releooe Dole 101.2012
FORT WORTH.
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: Freese and Nichols, Inc.
Subject of the Agreement: West Fork Collector Parallel, Phase 1 - Trinity River Siphon to Walker Branch
Connection
M&C Approved by the Council? * Yes ❑ No M
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes 0 No ❑ 56603-A3
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 0 No ❑
If unsure, see backpage for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 0 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date: N/A
If different from the approval date.
Expiration Date: N/A
If applicable.
Is a 1295 Form required? * Yes ❑ No ED
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 103291
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 0 No ❑
Contracts need to be routed for CSO processing in the followingorder:
rder:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.