AMENDMENT No.1
TO CITY SECRETARY CONTRACT No. 57422
WHEREAS, the City of Fort Worth (CITY) and Dunaway Associates, LLC(ENGINEER)
made and entered into City Secretary Contract No. 57422, (the CONTRACT) which was
authorized by M&C 22-0182 on the Bs' day of August, 2022 in the amount of $
376,009.00; and
WHEREAS, the CONTRACT involves engineering services for the following
project:
Water and Sanitary Sewer Replacement Contract 2020, WSM-G, CPN 103411;
and
WHEREAS, it has become necessary to execute Amendment No. 1 to the CONTRACT
to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their duly
authorized representatives, enter into the following agreement, which amends the
CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional engineering
services specified in proposal attached hereto and incorporated herein. The cost
to City for the additional design services to be performed by Engineer totals
$161,774.00. (Water: $10,417.00; Sewer: $151,357.00)
2.
Article II of the CONTRACT is amended to provide for an increase in the fee
to be paid to Engineer for all work and services performed under the Contract, as
amended, so that the total fee paid by the City for all work and services shall
be an amount of $537,783.00.
3.
All other provisions of the Contract, which are not expressly amended herein,
shall remain in full force and effect.
EXECUTED and EFFECTIVE as of the date subscribed by the City's designated
Assistant City Manager.
OFFICIAL RECORD
CITY SECRETARY
City of Fort Worth, Texas FT. WORTH, TX
Prof Services Agreement Amendment Template
Revision Date: June 13, 2025
Page 1 of 2
W&SS Rehabilitation Concract 2020, WSM-G
103411
APPROVED:
City of Fort Worth
Jesica McEachern
Assistant City Manager
DATE: 08/28/2026
boovvpIl
— 4 FORT
ATTEST:
00o =10 °
}Q Za
pPP'f
'���A�A, aap TEXASo�o
nIlIlaoud'�'
Jannette Goodall
City Secretary
APPROVAL RECOMMENDED:
Christopher Larder 08/24/2026
Christopher Harder (Aug 24, 2026 12.57.59 CDT)
Chris Harder, P.E.
Director, Water Department
Contract Compliance Manager:
ENGINEER
Dunawa :s,.sociat LLC.
Kervin M. Campbell, P.E.
Vice President I Principal
DATE: August 20, 2026
By signing, I acknowledge that I am the person responsible for the monitoring
and administration of this contract, including ensuring all performance and
reporting requirements.
W 4-6�" On Behalf of:
Parvat"fii Sreekumaran Unnithan, P.E.
Project Manager
APPROVED AS TO FORM AND LEGALITY: M&C No.#: 26-0725
`_,i — M&C Date: August 11, 2026
Douglas Black (Aug 25, 2026 09:55:44 CDT)
Douglas W. Black
Sr. Assistant City Attorney
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth, Texas W&SS Rchabi.i.i.tati.oa. Contract 2020, WSM-G
Prof Services Agreement Amendment Template 10311.1,
Revision Date: June 13, 2025
Page 2 of 2
DUNAWA
y
Dunaway No. 7332.001
June 24, 2026
Ms. Parvathi Sreekumaran Unnithan
City of Fort Worth
200 Texas St, Fort Worth, TX 76102
Reference: CPN 103411, Contract 2020 WSM-G Scope Adjustments - Amendment No. 1
Dear Ms. Sreekumaran Unnithan:
Whereas Dunaway Associates was prepared to bid the above project in the summer of 2025,
and whereas upon City Review, adjustments were requested that were outside of the original
scope - notably the change of a 12" water main in White Settlement to a 16" water main and
the adjustment of M-206 from a 24" sanitary sewer to a 30" sanitary sewer, and whereas upon
further field investigation was provided showing that M-206 is collapsing at the manhole north
of the Tarrant Regional Water District Levee, and as a result several teleconferences were held,
one site visit, and schematics showing alternates and costs were prepared to help determine
a solution, and therefore the solution, as described by Dean Kuhn, representative for the
Tarrant Regional Water District that work would need to proceed as if a Section 408 permit
would be required, the following services are provided, a full detailed description of each
project modification is described below:
Upsizing the 12" water main in White Settlement to a 16" main.
2. Additional topographic survey and boundary survey to help establish the new
horizontal alignment of the re -aligned sanitary M-206 sewer main.
3. Additional topographic survey for the extension of the 16" water main between
Merrit Street and Priddy Streets.
4. Coordination with TRWD, USACE, including the production of exhibits, an
alternative and a site visit to help establish an alignment that would be
acceptable to all permitting parties,
5. Upsizing and realigning the 24" sanitary sewer main to a 30" main. Realignment
will be both horizontally and vertically and will be replaced by construction
methods other than slip lining. Abandonment plans for the remaining pipe,
6. Geotechnical boring as required by TRWD and the USACE for permitting open
cutting within the levee area.
7. Four temporary construction easements to support open cut operations,
8. USACE Section 408 Permitting as described in detail:
dunaway.com
DUNAWAY
CPN 103411, Contract 2020 WSM-G Scope Adjustments - Amendment No. 1
June 24, 2026
Page 2
A. Section 408 Permitting Assistance - Dunaway will provide United States Army Corps
of Engineers (USACE) Section 408 Permitting assistance for the proposed project. As
part of this scope of work, a comprehensive analysis report will be created to
analyze the proposed alteration of the Sump #6 Levee, part of Fort Worth Floodway
Civil Works Project. Dunaway will create the submittal based on the Engineer
Circular 1165-2-220. Dunaway will coordinate the submittal of the Section 408
request Tarrant Regional Water District (TRWD) the USACE Section 408 Division.
USACE will have a 30-day period from date of submittal to conduct their
"completeness" review. Typical 408 requests go through two or three completeness
reviews. Dunaway will address any comments raised during the review process and
attend pertinent field/virtual meetings with USACE and/or subconsultants on the
Client's behalf to obtain an approved permit.
B. Waters of the U.S. Delineation - Environmental Scientists from Dunaway will conduct
a field assessment of the proposed site to assess potential aquatic resources. Field
staff will use a Global Positioning System (GPS) to map aquatic resources, including
wetlands; data collected in the field will be downloaded and prepared for
inclusion in the Waters of the U.S. Delineation Report. The Waters of the U.S.
Delineation Report will utilize existing datasets (USGS Topographic, USDA Soils,
USFWS NWI, etc.) along with data collected during the field assessment. The limits
and descriptions of delineated aquatic features found during the field assessment
will be described and shown within the report and site exhibits. A professional
opinion will be provided for each feature to determine whether the feature meets
the current regulatory definition of Waters of the U.S. The assessment will include
potential permitting scenarios for the project of the project and impact thresholds
associated with the use of such permits.
This scope and fee does not include any Section 404 permitting assistance with
USACE. If Waters of the U.S. are discovered within the site boundary and are
impacted by the proposed project, a Section 404 permit may be
necessary. Additionally, a Section 404 permit would require a Section 106 Cultural
Resources review and a species -specific impact assessment for Threatened or
Endangered (T&E) species -specific impact assessments or Section 7 consultation
with USFWS. If the habitat meets the criteria to support any of the listed T&E species
in Tarrant County, a species -specific field survey may be required. This scope and
fee does not include any archaeological review or surveys or T&E Species impact
assessment/field surveys.
C. USACE Regulatory/Section 404 Approval - If it is determined after completing the
Waters of the U.S. Delineation Task that the proposed sanitary sewer project would
have no potential to impact potentially jurisdictional Waters of the U.S., Dunaway
will prepare a No Permit Required submittal for USACE Regulatory review and
dunaway.com
DUNAWAY
CPN 103411, Contract 2020 WSM-G Scope Adjustments - Amendment No. 1
June 24, 2026
Page 3
approval. If it is determined after completing the Waters of the U.S. Delineation Task
that the project would impact potentially jurisdictional Waters of the U.S., Dunaway
will provide USACE Nationwide Permitting assistance for the proposed sanitary
sewer project. Based on discussion with Dunaway's engineering team, impacts to
potentially jurisdictional aquatic features could occur under Nationwide Permit
(NWP) 58. Dunaway will prepare necessary items for a Pre -Construction Notification
for formal review of the proposed impacts to the aquatic features. As part of this
scope of work, an approved jurisdictional determination (AJD) request will be
submitted to determine the official jurisdictional status of stream features currently
proposed to be impacted with the existing site plan. Dunaway will address any
comments raised during the review process of the submitted report and attend
pertinent field/virtual meetings with USACE and/or subconsultants on the Client's
behalf to obtain an approved permit.
D. Project Specific Species Impact Assessment - As part of National Environmental
Policy Act (NEPA) due diligence and/or NWP assistance, a project specific species
impact assessment may be requested by USACE for the project. An assessment of
federally threatened, endangered, proposed, and candidate species, as well as
proposed and final designated critical habitat, will be conducted. The assessment
will determine whether the undertaking of the proposed project has the potential
to affect any of the listed species or their potential habitats. The assessment will also
determine if the project has potential for a species "Take", as defined by the United
States Fish and Wildlife Service.
This scope and fee does not include any species -specific field surveys or Section 7
consultation with the local United States Fish and Wildlife Service Office. If it is
determined during the Nationwide Permitting process that these may be
warranted, this would be considered additional services.
E. Cultural Resources Desktop Review - Coordination with USACE and the Texas
Historical Commission (THC) will be initiated through the submittal of a desktop
analysis, which will provide analysis and information pertaining to:
• Project location and design;
• Soils;
• Topography and geology;
• Known archeological sites, National Register properties and districts, historic -
aged buildings and structures, cemeteries, and historical markers within the
project area;
• Previously conducted archeological surveys within 1 mile of the project area;
• Cultural resources probability assessment; and
• Recommendations
dunaway.com
DUNAWAY
CPN 103411, Contract 2020 WSM-G Scope Adjustments - Amendment No. 1
June 24, 2026
Page 4
As a result of the coordination established through this task, the USACE and THC will
determine if an archeological survey is required for the project.
F. Archeological Survey and Agency Coordination - Required Antiquities Code of
Texas and National Historic Preservation Act (NHPA) Section 106 compliance will be
completed (if triggered). The following services will be performed, if requested by
the Texas Historical Commission:
• Obtain a Texas Antiquities permit from the THC to conduct the survey;
• Complete a full, intensive pedestrian survey to document archeological
resources 50 years or older that could be impacted by the project;
• Draft a technical report that documents the archeological background
review, survey methods, survey results, any necessary National Register of
Historic Places (NRHP) eligibility assessment, and recommendations; and
• Conduct all necessary coordination with THC to obtain agency comment.
If a survey is required, it is assumed that USACE and THC will require an assessment
of deeply buried deposits that could be impacted by proposed project. Backhoe
trenching for the project would occur where deeply buried archeological deposits
(greater than 3 ft [feet] below surface) could be impacted by the project.
Archeological survey standards require that a minimum of one trench be
excavated every 200 meters where potential for deeply buried archeological
deposits exist. As such it is anticipated that approximately one trench will be
required for the project. Backhoe trenches will be excavated to the maximum
vertical depth of the project, or to the extent of Holocene -age soils capable of
containing archeological deposits. Backhoe trench excavation will be monitored
for the presence of archeological materials. When each trench has been
excavated to a depth of approximately 4 feet, an Occupational Safety and Health
Administration (OSHA) competent field supervisor will assess the stability of the
trench prior to recording soil profile data. If soil stability is low, the trench may be
widened through benching and/or limited to a safe depth for detailed recording
of the soil profile. The physical properties of each natural stratigraphic level will be
recorded. Investigators will document the results of each backhoe trench on
standardized forms. A 5-gallon bucket of soil will be screened through 0.25-inch
hardware mesh from every third excavator bucket load during excavation. The
remaining excavated soil will be visually inspected as it is placed on the spoil pile.
Each backhoe trench will be backfilled following documentation of the completed
trench.
G. Above Ground Resources Survey - If an above ground resources survey is required
by the USACE or THC through coordination conducted through the Cultural
Resources Desktop Review, the following services will be conducted:
• A reconnaissance architectural survey of above ground resources that are
50 years in age or older within and adjacent to the project footprint;
dunaway.com
DUNAWAY
CPN 103411, Contract 2020 WSM-G Scope Adjustments - Amendment No. 1
June 24, 2026
Page 5
• Sufficient research to evaluate each resource's current condition in
comparison with its historical construction, as well as its historical
significance with its context;
• Evaluations of each identified architectural resource for listing on the NRHP;
and,
A technical report that documents the background research, survey
methods, survey results, NRHP eligibility assessment, and recommendations.
H. Deed and Title Archival Research - Although not anticipated, if a historic period
(greater than 50 years in age) residential site is encountered during the survey,
deed title and/or archival research may be required to determine if the site was
associated with any historically significant individuals or historical events that would
qualify the site for NRHP eligibility under Criteria A and B. Due to the uncertainty of
this task being required for the project and the unknown status of deed records of
the subject property, this task is presented as an if required task and would be
invoiced on a time and materials basis upon authorization from the Client. If
required, IES will prepare a deed chain -of -title table that details the grantor,
grantee, date, and deed record volume and page for each property transfer from
current to land patent or to the date of origin associated with the encountered
resource.
A summary of the total project is as follows:
Contract
Water
Sanitary Sewer
White Settlement Water Line 12" to 16"
$ 10,417.00
Schematics and Coordination for M-206
$
12,666.00
Design Changes to M-206
$
24,290.00
Topographic Survey
$
10,000.00
Boundary Survey
$
10,000.00
Section 408 Permitting Assistance
$
15,160.00
Waters of the U.S. Delineation - Environmental Scientists
$
8,750.00
USACE Regulatory/Section 404 Approval
$
8,750.00
Project Specific Species Impact Assessment
$
3,000.00
Cultural Resources Desktop Review *
$
3,000.00
Archeological Survey and Agency Coordination *
$
20,000.00
Above Ground Resources Survey
$
16,000.00
Deed and Title Archival Research *
$
2,500.00
Geotechnical Investigation *
$
11,944.00
* Subconsultant- 10%Subconsultant Markup
$
5,297.00
dunaway.com
DUNAWAY
CPN 103411, Contract 2020 WSM-G Scope Adjustments - Amendment No. 1
June 24, 2026
Page 6
Contract
Water
Sanitary Sewer
Fee
Original Contract
$ 186,455.00
$ 189,554.00
$ 376,009.00
Amendment No. 1
$ 10,417.00
$ 151,357.00
$ 161,774.00
TOTAL PROJECT
$ 196,872.00
$ 340,91 1.00
$ 537,783.00
If this proposal meets with your approval, please sign below and return one copy to our
office as our notice to proceed. We appreciate the opportunity to assist you with this
project and look forward to its success.
Sincerely,
DUNAWAY ASSOCIATES, LLC
a Texas limited liability company
J
44 L
'z
BrySherneb, P.E.
Senior Project Manager I Associate
BES/lau
P:\007300\7332\001\Proposal\Addendum No. 1\7332.001 WSM-G Draft Amendment #l.docx
dunaway.com
i
I;Il11
FORT WORTH,
MAYOR AND COUNCIL COMMUNICATION
7.1.42 DUNAWAY ASSOCIATES, LLC ENGINEERING AGREEMENT AMENDMENT NO.1 FOR
WSM-G WATER AND SEWER REHABILITATION
DATE: 08/11/26 M&C FILE NUMBER: M&C 26-0725
DEPARTMENT: WATER
SUBJECT
(CD 7) Authorize Execution of Amendment No. 1 in the Amount of $161,774.00 for a Revised
Contract Amount of $537,783.00 to an Engineering Agreement with Dunaway Associates, LLC
for the Water and Sanitary Sewer Rehabilitation Contract 2020 WSM-G Project, and Adopt
Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal Years 2026-
2030 Capital Improvement Program
RECOMMENDATION
It is recommended that the City Council:
1. Authorize execution of Amendment No. 1 in the amount of $161,774.00 to City Secretary
Contract No. 57422, an engineering agreement with Dunaway Associates, LLC, for the
Water and Sanitary Sewer Rehabilitation Contract 2020 WSM-G Project for a revised
contract amount of $537,783.00; and
2. Adopt the attached appropriation ordinance increasing estimated receipts and
appropriations in the Water and Sewer Capital Projects Fund in the amount of
$161,774.00, transferred from available PayGo funds within the Water and Sewer Fund,
for the purpose of funding the Rehabilitation Contract 2020 WSM-G project (City
Project No. 103411) and to effect a portion of Water's contribution to the Fiscal Years
2026-2030 Capital Improvement Program.
DISCUSSION
The purpose of this Mayor and Council Communication (M&C) is to authorize execution of
Amendment No. 1 to City Secretary Contract No. 57422 with Dunaway Associates, LLC in the
amount of $161,774.00 for a revised contract amount of $537,783.00 for the Water and
Sanitary Sewer Rehabilitation Contract 2020 WSM-G project.
On March 8, 2022, M&C 22-0182, the City Council authorized an engineering agreement in the
amount of $376,009.00 with -Dunaway Associates, LLC, (City Secretary Contract No. 57422) for
the Water and Sanitary Sewer Rehabilitation Contract 2020 WSM-G project.
1of12
FORT WORTH,
Amendment No. 1 will provide for the preparation of plans and specifications and permits for
additional water main and upsizing the water and sanitary sewer mains as indicated on the
following streets and easements:
Street
From
To
Scope of Work
White Settlement
Merrit Street
Fort Worth City Limit
Water Pipe
Road
Upsize 12" to 16"
White Settlement
Merrit Street
Priddy Lane
Water
Road
Additional Scope
Easement east of
White Settlement
South 415 feet
Sewer Pipe
Fort Worth City Limit
Road
Upsize 24" to 30"
McGee Drive
360 feet west and
Westfork Drive
Sewer Pipe
415 feet south of the
Intersection
Upsize 24" to 30"
White Settlement
Road /Westfork Drive
Intersection
Easement south of
McGee Drive
Redbud Lane
Sewer Pipe
McGee Drive
Upsize 24" to 30"
Scott Road
Slate Street
South 280 feet
Sewer Pipe
Upsize 24" to 30"
Slate Street
Redbud Lane
South 275 feet
Sewer Pipe
Upsize 24" to 30"
Easement east of
Scott Road
South 360 feet
Sewer Pipe
Fort Worth City Limit
Upsize 24" to 30"
It is the practice of the Water Department to appropriate its Capital Improvement Program
plan throughout the Fiscal Year (FY), instead of within the annual budget ordinance, as
projects commence, additional funding needs are identified, and to comply with bond
covenants.
Funding is budgeted in the Transfer to Water/Sewer account of the Water and Sewer
operating budget for the purpose of funding the Water and Sanitary Sewer Rehabilitation
Contract 2020 WSM-G project.
FY2026 - Water PAYGO Appropriations per City Ordinance 27979-09-2025
2of12
FORT WORTH,
FY2026 Amended
PayGo (Includes
YTD PayGo
FY2026 Original
any council actions
Approved
This MSC
FY2026 Remaining
Adopted PayGo
subsequent to
for/Moved to
PayGo Balance
budget adoption)
Capital Projects
$101,090,082.00
$162,457,207.00
($88,133,086.29)
($161,774.00)
$74,162,346.71
Note: There may be other pending actions or recently approved actions that are not reflected
in the table due to timing.
Appropriations for Water and Sanitary Sewer Rehabilitation's Contract 2020 WSM-G project
are as depicted below:
Fund
Existing
Additional
Project Total*
Appropriations
Appropriations
W&S Capital Projects
$644,292.00
$161,774.00
$806,066.00
- Fund 56002
Project Total
$644,292.00
$161,774.00
$806,066.00
*Numbers rounded for presentation purposes.
This project is located in COUNCIL DISTRICT 7.
This contract requires a Form 1295.
FISCAL INFORMATION/CERTIFICATION
The Director of Finance certifies that funds are currently available in the Water & Sewer Fund
and upon approval of the above recommendations and adoption of the attached
appropriation ordinance, funds will be available in the W&S Capital Projects Fund, for the
Contract 2020 WSM-G project to support the execution of the engineering contract
amendment. Prior to any expense being incurred, the Water Department has the
responsibility to validate the availability of funds.
SUBMITTED FOR CITY MANAGER'S OFFICE BY:
ORIGINATING BUSINESS UNIT HEAD:
ADDITIONAL INFORMATION CONTACT:
ATTACHMENTS
Jesica L. McEachern, # 5804
Chris Harder, # 5020
Parvathi S., # 7803
3of12
FORT WORTH,
1. Map - WSM-G Water and Sewer Reb Engineering Agmt Amend 1 [7.1.42.1 -1 page]
2. Ordinance Approp (R2) - WSM-G Water and Sewer Reb Engineering Agmt Amend 1
[7.1.42.2 -1 page]
3. CONFIDENTIAL - Form 1295 - Dunaway Associates, LLC [7.1.42.4 - 1 page]
4. CONFIDENTIAL - Sam.gov - Dunaway Associates, LLC [7.1.42.5 - 2 pages]
5. CONFIDENTIAL - Project Budget Summary - WSM-G Water and Sewer Reb Engineering
Agmt Amend 1 [7.1.42.6 -1 page]
6. CONFIDENTIAL - FID Table - WSM-G Water and Sewer Reb Engineering Agmt Amend 1
[7.1.42.7 -1 page]
7. CONFIDENTIAL - Funds Availability - WSM-G Water and Sewer Reb Engineering Agmt
Amend 1 [7.1.42.8 -1 page]
4of12
�00
MEN!�
N
MEN
T
C
T
C
T
C
•
• QL
•
• Q„
•
• QL
m
m
a
n
D
n
D
n
n
n
n
O
O
O
-
-
�
•
�_
CD
M
m
-
-
-
a
-
a
a
m
C
'
m
0
'
X
m a
d a
vQ
d a
m
-
-
-
- �
rt
rt
rt
m
I
n
zillillo
N
A 111111
o
ul
o
ao fD
3
IN"
Z111111
(YQ
d
3
O
A
z
—
o
ao
d
3
rt.O.
_
21
G�
r
m
'"
o �p
O
O
c
c
c
3
3
r
(D
fD
fl.
_
�D
_
a
M
0
m
0
0
M
MAYOR AND COUNCIL COMMUNICATION MAP
L _—
N �. 7 -
MELBOURNE DR J
o -_
I o .
1
TRINITY RNER-TRLiqrZ:
� 0
\ w w
� gym' I
Z
1�= D WHITE SETTLEMENT RD
410;
F
v' y
I
�
Icc
Y
O
LL
1
�
I
W
u-
LL
F- F
w
o,�. -
0
Q
Z
w
2
REDBUDLN Q
-"i
SLATE ST
LAA=XlAAW♦ SCOTT RD
0
r
J i ♦ �R„ . .
p DENNIS AVE
_ FURSMAN AVE
FORT WORTH
FORT WORTH,
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: Dunaway Associates, LLC
Subject of the Agreement: Water and Sanitary Sewer Replacement Contract 2020, WSM-G
M&C Approved by the Council? * Yes 0 No ❑
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes 0 No ❑ 57422-Al
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 0 No ❑
If unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 0 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date: 8/11 /2026
If different from the approval date.
Expiration Date: N/A
If applicable.
Is a 1295 Form required? * Yes ❑ No ❑✓
*Ifso, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: Ifapplicable. 103411
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes ❑✓ No ❑
Contracts need to be routed for CSO processing in the followingorder:
rder:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.