HomeMy WebLinkAbout065035-CO1 - Construction-Related - Contract - GPFT HF Alliance 2026, LPFo,
Developer -Awarded -Project Change Order
Change Order Number:
1
Project Name:
INDCO 1-35 Eagle
IPRC Record:
IPRC25-0170
City Secretary Number:
65035
X Number:
X-28758
City Participated Project:
O yes O No
Inspector Name:
Rowdy Glover
Project Manager Name:
Madiha Alshammry
Date: 8/4/2026
CPN: 106547
CFA Number: 25-0189
FID: 30114-0200431-106547-EO7685
File Number:
Email: rowdvalover2fortworthtexas.00v
Email: madiha.alshammw(rDfortworthtems.00v
Phone:
Phone:
817-395-5887
817-392-7252
CONTRACT UNIT
WATER
SEWER
DRAINAGE
PAVING
STREET LIGHTS
Working Days
Credits/Extras
Developer Cost
City Cost
Developer Cost
City Cost
Developer Cost
Ci Cost
Developer Cost
CityCost
Developer Cost
CityCost
Original Contract
$914,868.24
$907,287.76
$94,561.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
120
Extras to Date
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Credits to Date
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Contract to Date
$914,868.24
$907,287.76
$94,561.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
120
Amount of Proposed CO
$1,924.00
$3,120.'0
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
0
Revised Contract Amount
$912,944.24
$904, 16T76
$94,561.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
120
Total Revised Contract Per Unit
$1,817,112.00
$94,561.00
$0.00
$0.00
$0.00
Revised Cost Share
Dev. Cost:
$1,007,505.24
City Cost:
$904,167.76
Total Revised Contract
$1,911,673.00
Reason for Change Order 16inch Water Line shortened by 26ft at end of line due to an existing 24inch Sewer Line conflict. We evaluated potentially lowering the 16inch Water Line below the 24inch Sewer Line but there is insufficient space to lower the
waterline below the 24inch sewer while staying within the Public 20' Water Easement. Per input from City of Fort Worth DSWS (Development Services Water Section), ending the line 26ft shortis acceptable.
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
CITY OF FORT WORTH
STANDARD CONSTRUCTION DOCUMENT - DEVELOPER AWARDED PROJECTS
REVISED DATE: March 10.2026 1 of 3
FORT WORTH.
Change Order Number:
Project Name: INDCO 1-35 Eagle
You are directed to make the following changes in the contract documents:
Asterisk (') indicates New Pay Item
Developer -Awarded -Project Change Order
Date: 8/4/2026
CPN: 106547
REVIEWED
By Madiha Alshammry at 8:f8 am, Aug 17, 2026
UNIT I: WATER IMPROVEMENTS
PAY ITEM #
CITY BID ITEM #
QUANTITY
UNIT
ITEM DESCRIPTION
CIFW DELTA PRICE
UNIT PRICE
Developer Cost
City Cost
TOTAL
8
3311.0541
26
LF
16" Water Pie
$120.00
$194.00
$1 924.00
$3 120.00
$5 044.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
0.00
0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
0.00
$0.00
$0.00
0.00
$0.00
$0.00
0.00
$0.00
$0.00
$0.00
$0.00
$0.00
0.00
$0.00
0.00
0.00
0.00
0.00
TOTAL UNIT I: WATER IMPROVEMENTS
($1,924.00)
1 ($3,120.00)
($5,044.00)
UNIT It: SANITARY SEWER IMPROVEMENTS
PAY ITEM #
CITY BID ITEM #
QUANTITY
UNIT
ITEM DESCRIPTION
UNIT PRICE
Developer Cost
City Cost
TOTAL
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
0.00
$0.00
$0.00
0.00
$0.00
0.00
$0.00
0.00
1
0.00
$0.00
$0.00
1
$0.00
0.00
0.00
0.00
0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.000.00
0.00
$0.00
$0.00
$0.00
$0.00
$0.00
TOTAL UNIT It: SANITARY SEWER IMPROVEMENTS
$0.00
1 $0.00
$0.00
CITY OF FORT WORTH
STANDARD CONSTRUCTION DOCUMENT - DEVELOPER AWARDED PROJECTS
REVISED DATE: March 10.2026 2 of 3
FORT WORTH.
Developer -Awarded -Project Change Order
REVIEWED
By Madlha A1shammryat 8:18 am, Aug 17, 2026
Change Order Number:
1
Date:
8/4/2026
Project Name:
INDCO 1-35 Eagle
CPN:
106547
MM
Name:
FA Peinado Construction LLC -
Title:
Trey Walker
Contractor Requested:
g3iqnature:
% 7t/aPln
Date:
8/4/2026
Name:
Kimle Hom - Jared Earney
Title:
Associate
Engineer Recommended:
ISignature:
14211� V
Date:
8/12/2026
Name:
GPFT HF Alliance 2026, LP -
Title:
Michael Flowers — Manager
Developer Approved:
'"� '"
8-12-2026
Signature:
Date:
r
Madiha Alshammry
Senior Professional Engineer
Name:
Title:
Project Manager:
08/17/2026
Signature:
Date:
Suby Varughese
Engineering Manager
Name:
Title:
CoFW Participating Department:
08/24/2026
Signature:
Date:
Jessika Williams
Assistant City Attorney
Name:
Title:
CoFW Assistant City Attorney:
08/26/2026
Signature:
Date:
Jesica McEachern
Assistant City Manager
Title:
aName:
CoFW Assistant City Manager:
08�31/2O2G
nature:
4aFORtnn4
Date:
p� �,,.o ., o�y0 0
Name:
Jannette Goodall o°max om�ao
Title:
City Secretary
CoFW City Secretary:
Opa * *tea
Signature:
U 4
datt� tp5 o
Date:
nna 4��
M&C Number:
26-0225 M&C Date Approved:
3/31/2026
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
CITY OF FORT WORTH
STANDARD CONSTRUCTION DOCUMENT — DEVELOPER AWARDED PROJECTS
REVISED DATE: March 10.2026 3 of 3
3 VI
REVIEWED
`\ ` ` \. erm.mn. am,Rmr•, m:aan,,�msT, xss
eIN �a .N
�v,11
''P��a I �RFRfI a ., CRY uL.,PI I .
FRONTAGEROAO _
FOR PUBLIC WATER
PLAIN - —
J
� INTERSTATE IGHWA 35W �
NUMBERDP wATBIEAMNlNG TAB4E
D nonawATsasaNPUNG MscR DPsnrvvlrs
al o of i TA
3.1 RR . — u1NGER'IHA D
AI FREUNE l
5: HroRAM lll FA
sUSTOTAI 4
TOiArsAMPU,FS,FD CO INGI=
�/Eaa MATEn wsrvonwARERsnMmuNG
Immw,ua wnrzRsarwr,u,mey
�®00m
SEEPUBLIC PUBLISHEC
WATER
] _ E
FOR WATEE R J
PLAN .
8 T I
dO2
c scetElry FEET
LEGEND-- Pru�snNc waTER UNE
EMTNG SEWER UNE
w — PRovosMPURUG Fl UNE
—w PROPOSED PRIVATE —ER UM
PROPOSED us'- "'
E SENERUNE
PROPOSED—M
REHYDRANT
HIGHWA"'W
RONTAGE ROAD VOL�B1'� F
!•
SEE SHEETS iFOft
77
PUBUCWATERPLAN
�41
INTERSTATE HIGHWAY 35W
-- eu��t� .�.........,.,Te...
I
LOT2 BL.C—
NORTHPORTAOOITION
(DEC. NO. 2DIB-340)
I
"° xW EP.. oN
°N KROw, what'sow.
I^w r Call
befom before you dig.
in
Z
J J
J d
of Of
i
O3
aLEET f R1ER
6
0
Iurxr .,
\ \, . . ........
1 _ 2 / �
vwc¢rn m
L 1 ------ ------ ------ ----
W --- a.w r rt v/ i T — � n•w ae-w w.ao s
rw,cwn—ux¢n--
t
1 p va -]HIGHWAY 35W FRONTAGE ROAD$sr
uwnww�wnww>aa✓.ai F. �—�
® c y
INTERSTraATEorxmwTwwn-oHIGHWAY.11, �
1 rnvnms,ervmn
PUBLIC WATER LINE A n
665
665
660
66o
655
NM
i
sv.. ceno
650
— 4 — —
660
645
645
-
"a
ru
Pa .x
s
ssca
x•ea
„xc
640
as
REVIEWED
ernroam,4,:nPmPrn•ae ao:u.m. aP,sr.mx
FAPHIe C: FEET
NOTESAN-
NIAIL
vm ncreuru.eenr v
a9.00 x.00 asoo Tsoa aT•w aeoo ) 38.00 ( AIM
- � j
AY���t9�' u
KDoWwhat's below.
Call before yor, dig.
.GEND Pn
3
Ne
pa r"awe uue wre"n
m rr�aree¢n rwucvmren wre"
�
s
vvv�
k
VICINITY MAP
N.T.S.
WI
J
X
I.
to
c� 3
0-.
Z
0 0
Z LL
go
a 'D
�w
J
>LLI �
(Y
a
11-R1
I ¢oe
I
Imal+o.grmmm�l f
v.
\
\ \ asPANcs J
\ L
\\ sw
\
/J \ \ r
Bo wos auuEJ ' SEE SHEET I3FR
PUBLIC SEW ER VLtW � —
I I I
PROP. 1 STORY BUILDING
111 923 SF
� s
\ 60
\ \ y
REVIEWED
\
`\ C EE-. N rEEr 120
\
\
\
\
1
\
\
xa. V'maYs� 1
I
I
I
i ��ff3
HIGHWAY ES RONTAGE ROAD
aP.ui \ sEwiB u.Eme �TE HIGHWAY 3EVJ
—1% P�aYN".,o as,=r�m TERBTAN.P�E 40/0
LEGEND— srtE eourvoARv
LINE
EMETING SEVER LINE
• paoposEo pueuc WgreauNp
PROPOSED PRIVATE-TEa 11
..� PROPOSED PUBYO SEwEa YNE
PROPOSED PRIVATE SEVER LINE
PRO10SEDN9.TERMETER
$O PROPOSEDMPNHOIE
{I} RE HYDRANT
�,VOL A
BENCH MARK LIST
Z
O W
O
2C"c.
NTIDN
• IM Know what's I76IOW.
TL
< Call before you dig. HEErry E
B12-R1R
FORT WORTH.,
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: GPFT HF Alliance 2026, LP
Subject of the Agreement: The 16-inch water main was reduced in length by 26 feet at the end of the line due
to a conflict with an existing 24-inch sewer Iine.The engineer evaluated lowering the 16-inch water main below the 24-inch
sewer line; however, there is insufficient space to do so while remaining within the 20-foot Public Water Easement
Per DSWS (Development Services Water Section), reducing the water main by 26 feet is acceptable.
M&C Approved by the Council? * Yes ❑ No 0
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes 0 No ❑
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 0 No ❑
If unsure, see back page, for permanent contract listing.
65035
Is this entire contract Confidential? *Yes ❑ No 8 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date:
If different from the approval date.
Expiration Date:
If applicable.
Is a 1295 Form required? * Yes ❑ No 0
*Ifso, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 106547
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes ❑■ No ❑
Contracts need to be routed for CSO processing in the followingorder:
rder:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.