HomeMy WebLinkAbout26-28642 - City Council - OrdinanceORDINANCE 26-28642
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE SEWER IMPACT FEE FUND IN THE
AMOUNT OF $674,171.25, FROM AVAILABLE SEWER IMPACT FEES
WITHIN THE WATER/WASTEWATER WHOLESALE IMPACT FEES
PROJECT (CITY PROJECT NO. B20004) IN THE AMOUNT OF $121,350.83
AND THE WATER/WASTEWATER RETAIL IMPACT FEES PROJECT
(CITY PROJECT NO. B20005) IN THE AMOUNT OF $552,820.42 FOR THE
PURPOSE OF TRANSFERRING TO THE SILVER CREEK LIFT
STATION, FORCE MAIN, AND GRAVITY MAIN PROJECT (CITY
PROJECT NO. 104489); PROVIDING FOR A SEVERABILITY CLAUSE;
MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES;
REPEALING ALL ORDINANCES IN CONFLICT HEREWITH; AND
PROVIDING AN EFFECTIVE DATE.
NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY
OF FORT WORTH, TEXAS THAT:
SECTION 1.
The budget of the City of Fort Worth for Fiscal Year 2025-2026, as enacted by Ordinance
27979-09-2025, as amended, is hereby further amended to increasing estimated receipts and
appropriations in the Sewer Impact Fee Fund in the amount of $674,171.25, from available sewer
impact fees within the Water/Wastewater Wholesale Impact Fees project (City Project No.
B20004) in the amount of $121,350.83 and the Water/Wastewater Retail Impact Fees project (City
Project No. B20005) in the amount of $552,820.42 for the purpose of transferring to the Silver
Creek Lift Station, Force Main, and Gravity Main project (City Project No. 104489).
SECTION 2.
Should any portion, section or part of a section of this ordinance be declared invalid,
inoperative or void for any reason by a court of competent jurisdiction, such decision, opinion or
judgment shall in no way impair the remaining portions, sections, or parts of sections of this
ordinance, which said remaining provisions shall be and remain in full force and effect.
SECTION 3.
This ordinance shall be cumulative of Ordinance No. 27979-09-2025 and all other
ordinances and appropriations amending the same except in those instances where the provisions of
this ordinance are in direct conflict with such other ordinances and appropriations, in which instance
said conflicting provisions of said prior ordinances and appropriations are hereby expressly repealed.
Ordinance No. _ 26-28642
Page 1 of 2
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY
Q e
Douglas Black (Aug 26, 2026 12:37:48 CDT)
Douglas W. Black
Sr. Assistant City Attorney
ADOPTED: August 11.2026
EFFECTIVE: August 11.2026
Jannette S. Goodall
City Secretary
Ordinance No. 26-28642
Page 2 of 2
MAYOR AND COUNCIL COMMUNICATION MAP
FORT WORTH.
MAYOR AND COUNCIL COMMUNICATION
7.1.16 MOUNTAIN CASCADE OF TEXAS, LLC CONSTRUCTION CONTRACT SILVER CREEK
FORCE MAIN, GRAVITY MAIN AND WATER MAIN, PART 2
DATE: 08/11/26 M&C FILE NUMBER: M&C 26-0576
DEPARTMENT: WATER
SUBJECT
(CD 7) Authorize Execution of a Contract with Mountain Cascade of Texas, LLC in the Amount
of $16,320,562.00 for Construction of the Silver Creek Force Main, Gravity Main and Water
Main, Part 2, Authorize Execution of Amendment No. 3, in the Amount of $320,000.00 to an
Engineering Agreement with Kimley-Horn and Associates, Inc. for the Silver Creek Lift Station,
Force Main, and Gravity Main Project Part 2, and Adopt Appropriation Ordinances to Effect a
Portion of Water's Contribution to the Fiscal Years 2026-2030 Capital Improvement Program
RECOMMENDATION
It is recommended that the City Council:
1. Authorize execution of a contract with Mountain Cascade of Texas, LLC in the amount of
$16,320,562.00 for construction of the Silver Creek Force Main, Gravity Main and Water
Main, Part 2;
2. Authorize execution of Amendment No. 3 to City Secretary Contract No. 59809, an
Engineering Agreement with Kimley-Horn and Associates, Inc., in the amount of
$320,000.00 for construction support services for the Silver Creek Lift Station, Force
Main, and Gravity Main project for a revised contract amount of $2,787,088.00;
3. Adopt the attached appropriation ordinance increasing estimated receipts and
appropriations in the Sewer Impact Fee Fund in the amount of $674,171.25, from
available sewer impact fees within the Water! Wastewater Wholesale Impact Fees
project (City Project No. B20004) in the amount of $121,350.83 and the
Water! Wastewater Retail Impact Fees project (City Project No. B20005) in the amount
of $552,820.42 for the purpose of transferring to the Silver Creek Lift Station, Force Main,
and Gravity Main project (City Project No. 104489);
4. Adopt the attached appropriation ordinance increasing estimated receipts and
appropriations in the Water Impact Fee Fund in the amount of $674,171.25, transferred
from the Water/Wastewater Wholesale Impact Fees project (City Project No. B20004)
and the Water! Wastewater Retail Impact Fees project (City Project No. B20005) for the
purpose of funding the Silver Creek Lift Station, Force Main, and Gravity Main project
(City Project No. 104489); and
1 of 5
FORT WORTH.
5. Adopt the attached appropriation ordinance adjusting estimated receipts and
appropriations in the Water & Sewer Revenue Bonds Series 2026B Fund by increasing
estimated receipts and appropriations in the Silver Creek Lift Station, Force Main, and
Gravity Main (City Project No. 104489) in the amount of $17,101,619.00 and decreasing
estimated receipts and appropriations in the Water & Sewer Commercial Paper project
(City Project No. UCMLPR) by the same amount, to effect a portion of Water's
contribution to the Fiscal Years 2026-2030 Capital Improvement Program.
DISCUSSION
The purpose of this Mayor and Council Communication (M&C) is to authorize execution of a
construction contract in the amount of $16,320,562.00 with Mountain Cascade of Texas, LLC
and the execution of Amendment No. 3 in the amount of $320,000.00 to an engineering
agreement with Kimley-Horn and Associates, Inc. for the Silver Creek Force Main, Gravity Main
and Water Main, Part 2.
On June 27, 2023, M&C 23-0529, the City Council authorized an engineering agreement in the
amount of $1,659,200.00 with Kimley-Horn and Associates, Inc., (city Secretary Contract No.
59809) for the Silver Creek Lift Station, Force Main, and Gravity Main project. The agreement
was subsequently revised by Amendment No. 1 in the amount of $305,400.00, authorized
December 10, 2024 (M&C 24-1135) that primarily provided design for two inverted siphons
that are necessary on the project and design for a 16 -inch water main that will connect a
developer proposed water main on the north end of the water main to an existing City -
owned 16 -inch water main near the Silver Creek/Heron Drive intersection and the preparation
of a bid package to separate the original project into two parts for construction, and
Amendment No. 2 in the amount of $502,488.00 authorized August 26, 2025 by MSC 25-0800
that provided for construction management, resident project representative and construction
support services for Part 3 construction.
Amendment No. 3 provides for construction management, resident project representative,
and construction support services including shop drawings, submittal reviews, change order
review, and record drawings for Part 2 construction.
Construction of the Silver Creek Force Main, Gravity Main and Water Main was advertised for
bid on April 15, 2026, and April 22, 2026, in the Fort Worth Star -Telegram. On May 21, 2026, the
following bids were received:
Bidder TOTAL B Contract Time
TOTAL A
Acadia Services, LLC* $220,000.00 $220,000.00
2 of 5
FORT WORTH.
Mountain Cascade of
Texas, LLC
William J. Schultz,
Inc. dba Circle C
Construction
Company
$16,320,562.00 **
$19,858,951.00
$16,674,136.00
$20,355,851.00
550 Calendar Days
*Acadia Services, LLC submitted an incomplete bid and is determined to be non -responsive
to the contract documents.
** In an attempt to obtain alternative and competitive prices for the large diameter sanitary
sewer manholes, the project was advertised with alternate bid items for cast -in -place
concrete manholes and pre -cast polymer concrete manholes. Staff recommends award of
contract to Mountain Cascade of Texas, LLC for Total A which includes the cast -in -place
concrete manhole alternate.
SMALL BUSINESS (SB) GOAL - Mountain Cascade of Texas, LLC is in compliance with the City's
Small Business Program by committing to 31.4% participation.
In addition to the contract cost, $635,650.25 (Water: $175,056.00; Sewer: $460,594.25) is
required for project management, material testing and inspection and $499,578.00 (Water:
$183,128.00; Sewer: $316,450.00) is provided for project contingency.
This project will have no impact on the Water Department's operating budget when
completed.
Available cash within the Water and Sewer portfolio and the City's portfolio along with the
appropriation authority authorized under Callable Commercial Paper Program (CP) will be
used to provide interim financing for this project until debt is issued. Once debt associated
with this project is sold, bond proceeds will be used to reimburse the Water and Sewer
portfolio and the City's portfolio in accordance with the attached Reimbursement Resolution.
Under federal law, debt must be issued within approximately three years in order for these
expenses to be reimbursable. Adoption of the attached resolution does not obligate the City
to sell bonds, but preserves the ability of the City to reimburse itself from tax-exempt bond
proceeds.
It is the practice of the Water Department to appropriate its Capital Improvement Program
(CIP) plan throughout the Fiscal Year, instead of within the annual budget ordinance, as
projects commence, additional funding needs are identified, and to comply with bond
covenants.
Funding is budgeted in the Commercial Paper project within the W&S Bonds Series 2026B
Fund and in the Water/ Wastewater Wholesale Impact Fees and Water/Wastewater Retail
3 of 5
FORT WORTH.
Impact Fees projects within the Sewer Impact Fee Fund for the purpose of funding of the Silver
Creek LS/FM/GM project.
Funding for the Silver Creek Lift Station, Force Main, and Gravity Main are depicted below:
Fund
56022 - W&S Rev
Bonds Series 2024
56026 - W&S Bonds
Series 2026B
57003 - Sewer
Impact Fee
Project Total
Existing
Appropriations
$2,838,118.00
$ 9,884,128.00
$2,245,102.00
$14,967,348.00
*Numbers rounded for presentation purposes.
The project is located in COUNCIL DISTRICT 7.
FISCAL IN FORMATION/CERTIFICATION
Additional
Appropriations
$0.00
$17,101,619.00
$ 674,171.25
$17,775,790.25
Project Total*
$2,838,118.00
$26,985,747.00
$ 2,919,273.25
$ 32,743,138.25
The Director of Finance certifies that funds are available in the Commercial Paper project
within the W&S Revenue Bonds Series 2026B Fund and in the W/WW Wholesale Impact Fees
and W/WW Retail Impact Fees projects within the Sewer Impact Fee Fund and upon approval
of the above recommendations and adoption of the attached appropriation ordinances,
funds will be available in the W&S Revenue Bonds Series 2026B Fund and the Sewer Impact
Fee Fund for the Silver Creek LS/FM/GM project to support the execution of the contract and
amendment. Prior to an expenditure being incurred, the Water Department has the
responsibility of verifying the availability of funds.
SUBMITTED FOR CITY MANAGER'S OFFICE BY: Jesica L. McEachern, # 5804
ORIGINATING BUSINESS UNIT HEAD: Chris Harder, # 5020
ADDITIONAL INFORMATION CONTACT: Bijay Upreti, # 8909
ATTACHMENTS
1. Map - Silver Creek Force Main, Gravity Main and Water Main, Part 2 [7.1.16.1 - 1 page]
2. Ordinance Approp (R3) - Silver Creek Force Main, Gravity Main and Water Main, Part 2
[7.1.16.2 - 2 pages]
4 of 5
FORT WORTH.
3. Ordinance Approp (R4) - Silver Creek Force Main, Gravity Main and Water Main, Part 2
[7.1.16.4 - 2 pages]
4. Ordinance Approp (R5) - Silver Creek Force Main, Gravity Main and Water Main, Part 2
[7.1.16.6 - 2 pages]