HomeMy WebLinkAbout26-28656 - City Council - OrdinanceORDINANCE 26-28656
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER AND SEWER CAPITAL PROJECTS
FUND IN THE AMOUNT OF $13,698,960.00, TRANSFERRED FROM
AVAILABLE PAYGO FUNDS IN THE WATER AND SEWER FUND, FOR
THE PURPOSE OF FUNDING THE WATER AND SANITARY SEWER
REPLACEMENT CONTRACT 2020, WSM-J PROJECT (CITY PROJECT
NO. 103420); PROVIDING FOR A SEVERABILITY CLAUSE; MAKING
THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES;
REPEALING ALL ORDINANCES IN CONFLICT HEREWITH; AND
PROVIDING AN EFFECTIVE DATE.
NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY
OF FORT WORTH, TEXAS THAT:
SECTION 1.
The budget of the City of Fort Worth for Fiscal Year 2025-2026, as enacted by Ordinance
27979-09-2025, as amended, is hereby further amended by increasing estimated receipts and
appropriations in the Water and Sewer Capital Projects Fund in the amount of $13,698,960.00,
transferred from available PayGo funds in the Water and Sewer Fund.
SECTION 2.
Should any portion, section or part of a section of this ordinance be declared invalid,
inoperative or void for any reason by a court of competent jurisdiction, such decision, opinion or
judgment shall in no way impair the remaining portions, sections, or parts of sections of this
ordinance, which said remaining provisions shall be and remain in full force and effect.
SECTION 3.
This ordinance shall be cumulative of Ordinance No. 27979-09-2025 and all other
ordinances and appropriations amending the same except in those instances where the provisions of
this ordinance are in direct conflict with such other ordinances and appropriations, in which instance
said conflicting provisions of said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Douglas Bla�26, 2026 12:45:41 CDT)
Douglas W. Black
Sr. Assistant City Attorney
ADOPTED: August 11, 2026
EFFECTIVE: August 11.2026
Jannette S. Goodall
City Secretary
bdd��111:i.
nn
a °OOOOOOOO
nu X pSo�A"
Ordinance No. 26-28656
Page 1 of 1
MAYOR AND COUNCIL COMMUNICATION MAP
60WSSC20WSMJ-JACKSON+N EELSA3
.
FORT WORTH®
COUNCIL
BIDEKER!AVE
---t
SHAW AVE
1
t .!
MAYOR AND COUNCIL COMMUNICATION MAP
60WSSC20WSMJ-JACKSON+N EELSA3
7
lt-1
D o
MORESBY ST
FORT WORTH®
FORT WORTH.
MAYOR AND COUNCIL COMMUNICATION
7.1.31 WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2020 WSM-J PROJECT
CONSTRUCTION CONTRACT AND ENGINEERING AMENDMENT
DATE: 08/11/26 M&C FILE NUMBER: M&C 26-0601
DEPARTMENT: WATER
SUBJECT
(CD 8) Authorize Execution of a Contract with Jackson Construction, Ltd., in the Amount
of $12,592,547.50 and Authorize Execution of Amendment No. 3 in the Amount of
$100,000.00 to an Engineering Agreement with Neel -Schaffer, Inc., for Water and
Sanitary Sewer Replacement Contract 2020, WSM-J Project, and Adopt Appropriation
Ordinance to Effect a Portion of Water's Contribution to the Fiscal Years 2026-2030
Capital Improvement Program
RECOMMENDATION
It is recommended that the City Council:
1. Authorize execution of a contract with Jackson Construction, Ltd., in the amount of
$12,592,547.50 for Water and Sanitary Sewer Replacement 2020, WSM-J project (City
Project No. 103420);
2. Authorize Execution of Amendment No. 3 to City Secretary Contract No. 57029, an
Engineering Agreement with Neel -Schaffer, Inc., in the amount of $100,000.00, for Water
and Sanitary Sewer Replacement Contract 2020, WSM-J project (City Project No.
103420) for a revised contract amount of $717,272.00; and
3. Adopt the attached appropriation ordinance increasing estimated receipts and
appropriations in the Water and Sewer Capital Projects Fund in the amount of
$13,698,960.00, transferred from available PayGo funds in the Water and Sewer Fund,
for the purpose of funding the Water and Sanitary Sewer Replacement Contract 2020,
WSM-J project (City Project No. 103420) and to effect a portion of Water's contribution
to the Fiscal Years 2026-2030 Capital Improvement Program.
DISCUSSION
The purpose of this Mayor & Council Communication (M&C) is to authorize execution of a
construction contract with Jackson Construction, Ltd., and authorize Amendment No. 3 to an
Engineering Agreement with Neel Schaffer, Inc. for the Water and Sanitary Sewer
Replacement Contract 2020, WSM-J project.
1 of 5
FORT WORTH.
On January 11, 2022, M&C 22-0049 authorized an engineering agreement with Neel -Schaffer,
Inc., (city Secretary Contract No. 57029) in the amount of $543,512.00 for the preparation of
plans and specifications for the Water and Sanitary Sewer Replacement Contract 2020,
WSM-J project. The agreement was subsequently revised by Amendment No. 1 in the
amount of $53,760.00 administratively authorized on September 22, 2023, for design of
additional water and sanitary sewer mains on the project and Amendment No. 2 in the
amount of $20,000.00 administratively authorized on December 8, 2025, for the preparation
of plans and specifications for pavement replacement revisions. Amendment No. 3 in the
amount of $100,000.00 will provide for additional construction phase services including site
inspections, Request for Information (RFI) review, submittal review, and shop drawing review.
Additionally, this Mayor and Council Communication (M&C) will authorize execution of a
construction contract with Jackson Construction, Inc., in the amount of $12,592,547.50 for the
replacement of deteriorated sanitary sewer and cast iron mains as indicated on the
following streets.
Street
Mitchell Boulevard
E. Berry Street
Canberra Court
Malvern Trail
Shropshire Street
Sandgate Street
From
E. Berry Street
Canberra Court
E. Berry Street
Canberra Court
Mitchell
Boulevard
To
Moresby Street
Mitchell
Boulevard
Scope of Work
Water/ Sewer
Water
Shropshire Street Water/Sewer
Mitchell
Boulevard
Dead End
Shropshire Street E. Berry Street
Water
Water/Sewer
Water/Sewer
Mitchell
Lowriemore Lane Sandgate Street Water/Sewer
Boulevard
Mitchell
Spiller Street Sandgate Street Water/Sewer
Boulevard
2 of 5
FORT WORTH.
Mitchell
Rattikin Road Sandgate Street Water/Sewer
Boulevard
Mitchell
Moresby Street Sandgate Street Water/Sewer
Boulevard
Mitchell
Burchill Road Binkley Street Sewer/water
Boulevard
McKenzie Street Burchill Road North 150 Feet
Asphalt pavement rehabilitation will be conducted on all the roadways curb to curb
subsequent to the water and sanitary sewer main replacement.
The project was advertised for bids on February 4, and February 11, 2026, in the Fort Worth
Star -Telegram. On May 28, 2026, the following bids were received:
Bidder Amount Time of Completion
Jackson Construction, Inc. $12,592,547.50 750 Calendar Days
DDM Construction Corporation $12,641,623.00
Woody Contractors, Inc. $13,733,924.50
SYB Construction Co., Inc $13,825,820.62
William J. Schultz, Inc. dba $14,248,822.50
Circle C Construction
Company
Western Municipal $15,200,002.00
Construction of Texas, LLC
SMALL BUSINESS (SB) GOAL - Jackson Construction, Inc, is in compliance with the small
business goal. Jackson Construction, Inc, is committed to 30 percent SBE participation. The
City's SBE goal is 30 percent.
In addition to the contract amount, $599,664.50 (Water: $426,416.00, Sewer: $173,248.50) is
required for project management, material testing, and inspection. Project contingencies
are provided in the amount of $406,748.00 (Water: $290,863.00; Sewer: $115,885.00).
The sanitary sewer component of this project is part of the Sanitary Sewer Overflow Initiative
Program of the Water Department. Approximately 17,400 linear feet of cast iron water pipe
and 5,250 linear feet of deteriorated sanitary sewer pipe will be removed and replaced as
part of this project.
3 of 5
FORT WORTH,U
It is the practice of the Water Department to appropriate its Capital Improvement Program
(CIP) plan throughout the Fiscal Year (FY) instead of within the annual budget ordinance, as
projects commence, additional funding needs are identified, and to comply with bond
covenants.
Funding is budgeted in the Transfer to Water/Sewer account of the Water and Sewer
operating budget for the purpose of funding the W/SS Replace Contract 2020 WSM-J project
within the Water & Sewer Capital Projects Fund.
FY2026 - Water PAYGO Appropriations per City Ordinance 27979-09-2025
FY2026
Original
Adopted
PayGo
$101,090,082.00
FY2026
Amended
PayGo
(Includes any
council actions
subsequent to
budget
adoption)
$162,457,207.00
YTD PayGo This M&C
Approved
for/Moved to
Capital Projects
$162,457,207.00 $13,698,960.00
r' i z
Remaining
PayGo Balance
$148,758,247.00
Note: There may be other pending actions or recently approved actions that are not
reflected in the table due to timing.
Appropriations for the Water and Sanitary Sewer Replacement Contract 2020 WSM-J project
are as depicted below:
Fund
W&S Capital Projects
- Fund 56002
Project Total
Existing
Appropriations
$760,779.00
$760,779.00
*Numbers rounded for presentation purposes.
The project is located in COUNCIL DISTRICT 8.
This contract requires a Form 1295.
Additional
Appropriations
$13,698,960.00
$13,698,960.00
Project Total*
$14,459,739.00
$14,459,739.00
4 of 5
FORT WORTH.
FISCAL INFORMATION/CERTIFICATION
The Director of Finance certifies that funds are currently available in the Water & Sewer Fund,
and upon approval of the above recommendations and adoption of the attached
appropriation ordinance, funds will be available in the W&S Capital Projects for the W/SS REPL
Contract 2020, WSM-J project to support the execution of the construction contract and the
engineering amendment. Prior to an expense being incurred, the Water Department has the
responsibility of verifying the availability of funds.
SUBMITTED FOR CITY MANAGER'S OFFICE BY: Jesica L. McEachern, # 5804
ORIGINATING BUSINESS UNIT HEAD: Chris Harder, # 5020
ADDITIONAL INFORMATION CONTACT: Jose Andrade, # 8084
ATTACHMENTS
1. Map 1 - Water and Sewer Replcmt 2020, WSM-J Project [7.1.31.1 - 1 page]
2. Map 2 - Water and Sewer Replcmt 2020, WSM-J Project [7.1.31.2 - 1 page]
3. Ordinance Appropriation (R3) - Water and Sewer Replcmt 2020, WSM-J Project [7.1.31.3
- 1 page]
5 of 5