HomeMy WebLinkAbout26-28683 - City Council - OrdinanceAN ORDINANCE ADJUSTING ESTIMATED RECEIPTS AND APPROPRIATIONS IN
THE GENERAL CAPITAL PROJECTS FUND IN THE AMOUNT OF $89,072.58, BY
INCREASING APPROPRIATIONS IN THE 22 BOND WATER GARDEN PROJECT (CITY
PROJECT NO. 104751), AND DECREASING APPROPRIATIONS IN THE WATER
GARDENS SOUTH WALL REMOVAL PROJECT (CITY PROJECT NO. 100556) BY THE
SAME AMOUNT; PROVIDING FOR A SEVERABILITY CLAUSE; MAKING THIS
ORDINANCE CUMULATIVE OF PRIOR ORDINANCES; REPEALING ALL
ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF
FORT WORTH, TEXAS THAT:
SECTION 1.
The budget of the City of Fort Worth for Fiscal Year 2025-2026, as enacted by Ordinance 27979-
09 2025 as amended, is hereby further amended to adjust estimated receipts and appropriations in the
General Capital Projects Fund in the amount of $89,072.58, by increasing appropriations in the 22 Bond
Water Garden project (City Project No. 104751), and decreasing appropriations in the Water Gardens South
Wall Removal project (City Project No. 100556) by the same amount.
SECTION 2.
Should any portion, section or part of a section of this ordinance be declared invalid, inoperative or
void for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way
impair the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions
shall be and remain in full force and effect.
SECTION 3.
This ordinance shall be cumulative of Ordinance No. 27979-09-2025 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions
of said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APP TO FORM AND LEGALITY:
Douglas Black (Aug 26, 2026 12:54:39 CDT)
Assistant City Attorney
ADOPTED: August 11, 2026
EFFECTIVE: August 11, 2026
Jannette S. Goodall
City Secretary
Ordinance No. 26-28683
Page 1 of 1
FORT WORTH.
MAYOR AND COUNCIL COMMUNICATION
7.5.4 WATER GARDENS RENOVATION CMAR
DATE: 08/11/26 M&C FILE NUMBER: M&C 26-0614
DEPARTMENT: PARK AND RECREATION
SUBJECT
(CD 9) Authorize Execution of a Construction Manager at Risk Agreement with Thos. S. Byrne,
Inc. dba Byrne Construction Services for the Fort Worth Water Gardens Project, with a
Preconstruction Phase Services Fee in the Amount of $15,000.00 and a Construction Phase
Services Fee of 2.55% within a Project Construction Budget of $4,050,000.00, Adopt
Appropriation Ordinance, and Amend the Fiscal Year 2026-2030 Capital Improvement
Program (2022 Bond Program)
RECOMMENDATION
It is recommended that the City Council:
Authorize execution of a Construction Manager at Risk Agreement with Thos. S. Byrne,
Inc. dba Byrne Construction Services, for the 22 Bond Water Garden project (City
Project No. 104751) with a Preconstruction Phase Services Fee in the amount of
$15,000.00 and a Construction Phase Services Fee of two and fifty-five tenths percent
(2.55%) within a Project Construction Budget of $4,050,000.00;
2. Adopt the attached appropriation ordinance adjusting estimated receipts and
appropriations in the General Capital Projects Fund in the amount of $89,072.58, by
increasing appropriations in the 22 Bond Water Garden project (City Project No.
104751), and decreasing appropriations in the Water Gardens South Wall Removal
project (City Project No. 100556) by the same amount; and
3. Amend the Fiscal Years 2026-2030 Capital Improvement Program.
DISCUSSION
The purpose of this Mayor and Council Communication (M&C) is to authorize execution of a
Construction Manager at Risk (CMAR) agreement with Thos. S. Byrne, Inc. dba Byrne
Construction Services, for the Fort Worth Water Gardens project with a Pre -construction
Phase Services Fee in the amount of $15,000.00 and a Construction Phase Services Fee of
2.55% based on the construction cost, which will collectively be contained within the
Guaranteed Maximum Price. The project's construction budget of $4,050,000.00.
1 of 4
FORT WORTH.
The park is a historic example of late mid-century design, completed in the mid -1970s. It
features three distinct fountain areas: the Quiet Pool on the west side, the Mist Pool at the
center of the park, and the Active Pool on the east side, its most iconic feature.
This project includes modernizing and replacing the mechanical systems serving the Active
Pool fountain along Commerce Street. Improvements include expanding the existing pump
house, replacing pumps and electrical equipment, and upgrading the piping systems that
feed the fountain. Together, these enhancements are intended to preserve the fountain's
operation, ensure another half century of enjoyment for visitors, and continue fostering civic
pride within the community.
Desian Services
On June 10, 2025, a professional services engineering agreement with Freese and Nichols, Inc.
(Consultant) was authorized in the amount of $693,078.00 for engineering and preparation of
construction documents for this project (M&C 25- 0481, City Secretary Contract No. 63925).
CMAR Selection
A Request for Proposals for a CMAR was advertised in the Fort Worth Star -Telegram on
February 18th and 25th, 2026. A pre -proposal meeting was held on March 12, 2026. The City of
Fort Worth received 5 proposals on March 26, 2026, from the contractors listed below:
• Thos. S. Byrne, Inc. dba Byrne Construction Services,
• Scott Tucker Construction Company, LLC
• Falkenburg Construction
• CGC General Contractors, INC.
• Allen Teinert Construction, Co.
The proposers were scored based upon: (a) cover letter, (b) forms and certifications, (c)
corporate experience and financial stability, (d) pricing of CMAR services, (e) qualifications
and experience of key personnel, (f) pre -construction services approach, (g) construction
services approach, (h) Quality Assurance/Quality Control (QA/QC) and safety plan
approach, (i) cost and schedule controls, and (j) documentation of a minimum 30% small
business goal commitment for construction phase services. The individual scores were
totaled for the final score listed in the following table.
2 of 4
FORT WORTH.
Proposer Total (a) (b) (c) (d) (e) (f) (g) (h) (i) 0)
100 Pass/Fail Pass/ 10 pts 5 pts 20 pts 25 pts 10 pts 5 pts 25 pts Pass/Fail
pts Fail
Thos. S.
Byrne, Inc.
dba Byrne 90 Pass Pass 10 5 18 23 8 5 21 Pass
Construction
Services
Scott Tucker
Construction 22 4
88 Pass Pass 10 4 18 9 21 Pass
Company,
LLC
Falkenberg 79 Pass Fail 3 3 18 25 8 4 18 Fail
Construction
CGC General
Contractors, 76 Pass Pass 5 2 8 25 9 5 22 Pass
Inc.
Allen Teinert
Construction 75 Pass Fail 8 3 8 20 6 5 25 Fail
Co.
Thos. S. Byrne, Inc. dba Byrne Construction Services, will perform 30% of the construction
contract with certified small business subcontractors to be procured after this CMAR
agreement is executed.
Staff recommends that the City Council authorize the execution of the CMAR Construction
Contract with Thos. S. Byrne, Inc. dba Byrne Construction Services, for the construction of the
Fort Worth Water Gardens improvements.
Pre -construction services will commence upon award of this contract and issuance of a
notice to proceed.
This M&C will also reallocate $89,072.58 of the remaining residual balance from the
completed Water Gardens South Wall Removal project (City Project No. 100556) to the 22
Bond Water Garden project (City Project No. 104751).
Funding for this project was not included in the Fiscal Years (FY) 2026-2030 Capital
Improvement Program due to unforeseen increases in construction costs. The action in this
M&C will amend the FY2026-2030 Capital Improvement Program as approved in connection
with Ordinance 27979-09-2025.
Funding is available in the 2022 Bond Program Fund, the General Capital Projects Fund for the
Park & Recreation Department for the purpose of funding the 22 Bond Water Garden project.
3 of 4
FORT WORTH.
This project is included in the 2022 Bond Program. The City's Extendable Commercial Paper
(ECP) (M&C 22-0607; Ordinance 25675-08-2022) provides liquidity to support the
appropriation. Available resources will be used to make any interim progress payments until
debt is issued. Once debt associated with a project is sold, debt proceeds will reimburse the
interim financing source in accordance with the statement expressing official Intent to
reimburse that was adopted as part of the ordinance canvassing the bond election
(Ordinance 25515-05-2022).
Fort Worth Water Gardens is located in COUNCIL DISTRICT 9.
This contract requires a Form 1295.
FISCAL IN FORMATION/CERTIFICATION
The Director of Finance certifies that funds are currently available in the Water Gardens South
Wall Removal project and in the 22 Bond Water Garden project within the General Capital
Projects Fund and upon approval of the above recommendations and adoption of the
attached appropriation ordinance, funds will be available in the General Capital Projects
Fund for the 22 Bond Water Garden project to support the execution of the agreement. Prior
to an expenditure being incurred, the Park and Recreation Department has the responsibility
of verifying the availability of funds.
SUBMITTED FOR CITY MANAGER'S OFFICE BY:
ORIGINATING BUSINESS UNIT HEAD:
ADDITIONAL INFORMATION CONTACT:
Dana Burghdoff, # 8018
Teresa Thomason, # 5708
Scott Penn, # 5750