065490-PM1 - Construction-Related - Contract - GRBK Edgewood LLC and Klutz Construction LLC
CSC No. 65490 -PM! 8/12/2026 FORT WORTH PROJECT MANUAL FOR THE CONSTRUCTION OF Cibolo Hills Parkway Water, Sewer, Pavement, Stormwater & Street Lights IPRC Record No. IPRC25-0037 City Project No. 106104 FID NO. 30114-0200431-106104-E07685 FILE NO. K-3358 "X" NO. X-28490 Mattie Parker Jesus "Jay" Chapa Mayor City Manager Christopher P. Harder, P.E. Director, Water Department Lauren Prieur, P.E., PMP, CCM Director, Transportation and Public Works Department Prepared for The City of Fort Worth August 2026 LA14 LJA ENGINEERING LJA Engineering, Inc. 6060 North Central Expressway, Suite 400 Dallas, TX 75206 TBPE Firm Number F-1386 OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX 0000 10 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 1 of 5 SECTION 00 0010 TABLE OF CONTENTS DEVELOPER AWARDED PROJECTS Division 00 - General Conditions Last Revised 00 1113 Invitation to Bidders 03/20/2020 00 2113 Instructions to Bidders 03/20/2020 00 41 00 Bid Form 04/02/2014 00 42 43 Proposal Form Unit Price 05/22/2019 00 43 13 Bid Bond 04/02/2014 00 45 11 Bidders Pre ualification's 04/02/2014 00 45 12 Pre ualification Statement 09/01/2015 00 45 13 Bidder Pre ualification Application 03/09/2020 00 45 26 Contractor Compliance with Workers' Compensation Law 04/02/2014 00 45 40 Minority Business Enterprise Goal 08/21/2018 005243 Agreement 06/16/2016 00 61 25 Certificate of Insurance 07/01/2011 00 62 13 Performance Bond 01/31/2012 00 62 14 Payment Bond 01/31/2012 00 62 19 Maintenance Bond 01/31/2012 0072 00 General Conditions 11/15/2017 00 73 00 Supplementary Conditions 07/01/2011 00 73 10 Standard City Conditions of the Construction Contract for Developer Awarded Projects 01/10/2013 Division 01- General Requirements Last Revised 01 11 00 Summary of Work 12/20/2012 01 25 00 Substitution Procedures 08/30/2013 01 3119 Preconstruction Meeting 08/30/2013 00 i�o Project Meetings 0'0m7 /2011 01 32 33 Preconstruction Video 08/30/2013 01 33 00 Submittals 08/30/2013 01 35 13 Special Project Procedures 08/30/2013 01 45 23 Testing and Inspection Services 03/20/2020 01 50 00 Temporary Facilities and Controls 07/01/2011 01 55 26 Street Use Permit and Modifications to Traffic Control 07/01/2011 01 57 13 Storm Water Pollution Prevention Plan 07/01/2011 01 60 00 Product Requirements 03/20/2020 01 66 00 Product Storage and Handling Requirements 04/07/2014 01 70 00 Mobilization and Remobilization 04/07/2014 01 71 23 Construction Staking 04/07/2014 01 74 23 Cleaning 04/07/2014 01 77 19 Closeout Requirements 04/07/2014 01 78 23 Operation and Maintenance Data 04/07/2014 01 78 39 Project Record Documents 04/07/2014 CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised March 20, 2020 0000 10 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 2 of 5 Technical Specifications which have been modified by the Engineer specifically for this Project; hard copies are included in the Project's Contract Documents Technical Specifications listed below are included for this Project by reference and can be viewed/downloaded from the City's website at: http://fortworthtexas.iov/tpw/contractors/ or https://apps.fortworthtexas.2ov/Prof ectResources/ Division 02 - Existing Conditions Last Revised 02 4113 Selective Site Demolition 12/20/2012 02 41 1 n 12,'20120 12 vz-TrrT r-�z 02 41 15 Paving Removal 02/02/2016 Division 03 - Concrete 03 30 00 Cast -In -Place Concrete 12/20/2012 03 34 13 Controlled Low Strength Material CLSM 12/20/2012 02 3n 1� vT7Z'ry 12/20/2012 �-svrav�z 03 80 00 Modifications to Existing Concrete Structures 12/20/2012 Division 26 - Electrical 26--05 0e Geff.,naf \Vork Results for Electrical 11122,'2013 26 05 Demolition for Electrical Systems 121 /2z 26 05 33 Raceways and Boxes for Electrical Systems 12/20/2012 26 05 43 Underground Ducts and Raceways for Electrical Systems 07/01/2011 26 0c 50 zo-v�-�v Communications Multi Duct Conduit 02/26'2016 vzrzvrtviv Division 31- Earthwork 31 10 00 Site Clearing 12/20/2012 31 23 16 Unclassified Excavation 01/28/2013 31 23 23 Boow 0101/�Q/20113 321 00 Embankments 01/28/2013 31 25 00 Erosion and Sediment Control 12/20/2012 3 1� 1 36-040 Gabiions 1 2 /7zzr20/2012 31 37 00 Riprap 12/20/2012 Division 32 - Exterior Improvements 27 0117 Pennanent Asphalt Paving Repair 12/2-20/2012 374QPaving121 /20/20,112 32 01 29 Concrete Paving Repair 12/20/2012 32 11 23 Flexible Base Courses 12/20/2012 32 11 29 Lime Treated Base Courses 12/20/2012 32 11 33 Cement Treated Base Courses 12/20/2012 32 11 37 Liquid Treated Soil Stabilizer 08/21/2015 CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised March 20, 2020 0000 10 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 3 of 5 2' 12 16 Asphalt Paving 12,'20/2012 2' 12 73 Asphalt Paving Crack Sealants 121 /2O/2O12 32 13 13 Concrete Paving 12/20/2012 32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps 06/05/2018 32 13 733 Concrete Paving Joint Sealants 12/20/2012 32 11 d Brick Unit Paving 12/20,'2012 32 16 13 Concrete Curb and Gutters and Valley Gutters 10/05/2016 32 17 23 Pavement Markings 11/22/2013 32 17 25 Curb Address Painting 1111/0 17 3113 Chain Fences and Gates 12,'2012012 32 31 26 Wire Fences and Gates 12,'20/2012 32 31 29 Wood Fences and Gates 12/20/2012 37 32 3 Cast in Place Concrete Retaining Walls 06/0o 5�II 32 9119 Topsoil Placement and Finishing of Parkways 12/20/2012 32 92 13 Hydro -Mulching, Seeding, and Sodding 12/20/2012 32 93 43 Trees and Shrubs 12/20/2012 Division 33 - Utilities 33 01 30 Sewer and Manhole Testing 1 7'2-20/2012 33 01 31 Closed Circuit Television (CCTV) Inspection 03/03/2016 3 Zoo Pumpingypassg1 21 /2z 33 04 Joint Bonding and Electrical Isolation 12/20/20z 1'2 04 11 Corrosion Control Test Stations 12/20/2012 33 0112 Magnesium Anode Cathodic Protection System 11 /�12 33 01 8 07/0o 1�1 33 04 40 Cleaning and Acceptance Testing of Water Mains 02/06/2013 33 04-50 Cleaning of Sewer Mains 12/20/2012 33 05 10 Utility Trench Excavation, Embedment, and Backfill 12/12/2016 33 05 12 Water Line Lowering 05/08/2013 33 05 13 Frame, Cover and Grade Rings — Cast Iron 12/01/2021 33 05 13.10 Frame, Cover and Grade Rings s — Composite 12/01/2021 33 05 14 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to Grade 12/20/2012 33 05 16 Concrete Water Vaults 12/20/2012 33 05 17 Concrete Collars 12/20/2012 33 05 Auger Boring 12/20/2012 33 05 21 Tunnel Liner er Plate 12/20,'2012 2 05 22 Steel Casing Pipe 1 21 /2z 33 05 23 Hand Tunneling 121 /2z 33 05 24 Installation of Carrier Pipe in Casing or Tunnel Liner Plate 5/15/2015 33 05 26 Utility Markers/Locators 12/20/2012 33 05 30 Location of Existing Utilities 12/20/2012 33 11 05 Bolts, Nuts, and Gaskets 12/20/2012 33 11 10 Ductile Iron Pipe e 12/20/2012 33 11 11 Ductile Iron Fittings 12/20/2012 33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe 11/16/2018 33 1113 � - 12,'20/2012 , , 33 4Buried Steel Pipe and Fittings12/20/2012 x 33 12 10 Water Services 1 -inch to 2 -inch 02/14/2017 CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised March 20, 2020 0000 10 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 4 of 5 ZZ 12 11 Large Water Meters 17/20/20,112 33 12 20 Resilient Seated Gate Valve 12/20/2012 ZZ 3 2-24 AWWA Rubber Seated Butterfly Valves 1 2 /zzr20zv12 33 12 25 Connection to Existing Water Mains 02/06/2013 33 12 30 Combination Air Valve Assemblies for Potable Water Systems 06/10/2022 33 12 40 Fire Hydrants 01/03/2014 33 12 50 , 71 /7z 33 12 60 Standard Blow -off Valve Assembly 11/01/2016 33 3112 12,'20,'2012 ZZ Z 3113 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers 12,'20/2012 Zr ZZ 3115High17/20/20112 ZZ31 oChloridety06/12 Chloride Closed Profile Gravity Sanitary Sewer 33 31zPolyvinyl (PVC) 121 /2 1 ZZ Z�z Sanitary Sewer Slip Lining 1 21 /2z ZZZ 31 23 Sanitary Sewer Pipe Enlargement 12/20/2012 33 31 Sanitary Sewer Service Connections and Service Line 0101/2 13 3Z 31 eforCombination12/2 0�2 33 39 10 Cast in Place Concrete Manholes 12/01,'2021 39-20 Precast Concrete Manholes 1212/0? ZZ 39 30 Fiberglass Manholes 12/20/2012 33 394v 12/20/2012 33 39 60 Linerspoxy12/20,'20 12 33 Reinforced Concrete Storm Sewer Pipe/Culverts 07/01/2011 X110 1 33--` 1111High12 /7zzr20/2012 33 4112Reinforced11,'13/2015 - ZZ46 no Subdrainage 12/22 33 n 6 n 1 T✓--Tv-vT 07/0 /201 1 mTv�vsz ZZ 16 07 Trench Drains 07/01/2011 33 49 10 Cast -in -Place Manholes and Junction Boxes 12/20/2012 33 49 20 Curb and Drop Inlets 12/20/2012 33 49 40 Storm Drainage Headwalls and Wingwalls 07/01/2011 Division 34 - Transportation 34 4110 Traffic Signals 10/12/2015 Zn 4110.01 �� ��tztEa���t���tl•6-n�r� Attachment Controller Cabinet 12/14/2015 q4-4140-.02Controller02/2012 34 4110.03 2 31 1111 Temporary Traffic Signals 1 1 /�13 34 4113 Removing Traffic Signals 12/20/2012 344 4115 Rectangular Rapid Flashing Beacon 11/22,'2013 34 4116 an1 11 1 /2z Z1 11 v Roadway Illumination Assemblies 12,'20/20 2 Zn n�vz Arterial LED Roadway Luminaires 06,'15/2015 34 41 20.02 06/10 5�15 34 41 20.03 Residential LED Roadway Luminaires 06/15/2015 34 41 30 Aluminum Si s 11/12/2013 34 41 50 Single -Mode Fiber Optic Cable 02/26/2016 34 7113 Traffic Control 11/22/2013 CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised March 20, 2020 0000 10 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 5 of 5 Appendix GC 4.01 Availability of Lands GC -4.02 Subsurface and Physical Conditions GC 104 Underground Facilities GC 4.06 Hazardous Environmental Condition at Site GC -6.06.D Minority and Women Owned Business Enterprise Compliance GC 6.07 \Vamates GC 6.09 Permits and Utilities GC -6.24 Nondiscrimination GR-01 60 00 Product Requirements END OF SECTION CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised March 20, 2020 00 11 13 INVITATION TO BIDDERS Page 1 of 3 SECTION 00 11 13 INVITATION TO BIDDERS RECEIPT OF BIDS Electronic bids for the construction of CPN: 106104: Cibolo Hills Parkway ("Project") will be received by the City of Fort Worth via the Procurement Portal https://fortworthtexas.bonfirehub.com/portal/?tab=openopportunities, under the respective Project until 2:00 P.M. CST, Thursday, March 26, 2026. Bids will then be opened publicly and read aloud beginning at 2:00 PM CST in the New City Hall, 100 Fort Worth Trl, Fort Worth, TX,76102. Your submissions must be uploaded, finalized and submitted prior to the Project's posted due date. The City strongly recommends allowing sufficient time to complete this process (ideally a week prior to the deadline) to begin the uploading process and to finalize your submission. Uploading large documents may take time, depending on the size of the file(s) and your Internet connection speed. The Bonfire portal can be accessed using Microsoft Edge, Google Chrome, or Mozilla Firefox. Javascript must be enabled. Browser cookies must be enabled. Electronic submission is subject to electronic interface latency, which can result in transmission delays. All bidders or proposers assume the risk of late transmission/ submission. The City shall not be held liable if an interested bidder or proposer is unable to submit a complete bid/response before the published deadline due to transmission delays or any other technical issues or obstructions. The City strongly recommends allowing sufficient time to complete the submission process (ideally a week before the deadline) to begin the uploading process and to finalize your submission to give adequate time in the event an issue arises. All submissions must be submitted electronically prior to the close date and time under the respective Project via the Procurement Portal: hops://fortworthtexas.bonfirehub.com/portal/?tab=openOpportunities Failure to submit all completed required information listed in the respective Solicitation will be grounds for rejection of a bid as non -responsive. No late bids/proposals shall be accepted. Bids delivered in any other manner than using the Bonfire Platform (Procurement Portal) will not be accepted or considered. If, upon being opened, a submission is unreadable to the degree that material conformance to the requirements of the procurement specifications cannot be ascertained, such submission will be rejected without liability to the City, unless such bidder provides clear and convincing evidence (a) of the content of the submission as originally submitted and (b) that the unreadable condition of the Electronic Bid was caused solely by error or malfunction of the Bonfire Platform (Procurement Portal). Failure to scan a clear or readable copy of a bid into the system does not constitute and shall not be considered an error or malfunction of the Bonfire Platform (Procurement Portal). Bidders are encouraged to fully review each page of every document within their submission prior to submitting to ensure all documents are clear, legible, and complete. SUPPORT For technical questions, visit Bonfire's help forum at https://vendorsupport.gobonfire.com/hc/en- us CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENT City Project No. 106104 Revised 2/08/24 00 11 13 INVITATION TO BIDDERS Page 2 of 3 Contact the Bonfire support team at Support@GoBonfire.com or by calling 1-800-354-8010. To get started with Bonfire, watch this five-minute training video: Vendor Registration and Submission [VIDEO] — Bonfire Vendor Support (gobonfire.com) GENERAL DESCRIPTION OF WORK The major work will consist of the (approximate) following: Including approximately 1,569 LF of 16 -inch PVC waterline, 348 LF of 16 -inch DIP waterline, and 30 -inch steel casing by open cut; 1,069 LF of 21 -inch through 42 -inch reinforced concrete pipe, 1,010 LF of storm box culverts, associated storm drain inlets, junction boxes, headwalls, and appurtenances; 6,369 SY of 10 -inch concrete pavement, 24,287 SF of concrete sidewalk, lime stabilization, pavement markings, signage, and related paving improvements; and 22 roadway lighting assemblies including LED fixtures, conduit, electrical conductors, foundations, and associated appurtenances. PREQUALIFICATION Certain improvements included in this project must be performed by a contractor or designated subcontractor who is pre -qualified by the City at the time of bid opening. The procedures for qualification and pre -qualification are outlined in the Section 3 of 00 21 13 - INSTRUCTIONS TO BIDDERS. DOCUMENT EXAMINATION AND PROCUREMENTS The Bidding and Contract Documents may be examined or obtained via the Procurement Portal https://fortworthtexas.bonfirehub.com/portal/?tab=openOpportunities, under the respective Project. Contract Documents may be downloaded, viewed, and printed by interested contractors and/or suppliers. EXPRESSION OF INTEREST To ensure potential bidders are kept up to date of any new information pertinent to this project, all interested parties should indicate their intent to bid in the Procurement Portal by selecting "yes" under the Intent to Bid section. All Addenda will be posted in the Procurement Portal https://fortworthtexas.bonfirehub.com/portal/?tab=openOpportunities, under the respective Project. PREBID CONFERENCE - In -person and Web Conference A prebid conference will be held as discussed in Section 00 21 13 - INSTRUCTIONS TO BIDDERS at the following date, and time, as well as simultaneously via a web conferencing application: DATE: Friday, March 13, 2026 TIME: 10:00 A.M. Invitations with links to the web conferencing application will be distributed directly to those who have submitted an Expression of Interest. If a prebid conference is held, the presentation and any questions and answers provided at the prebid conference will be issued as an Addendum to the call for bids. If a prebid conference is not being held, prospective bidders should direct all questions about the meaning and intent of the Bidding Documents electronically through the Vendors discussions section under the respective Project via the Procurement Portal. If necessary, Addenda will be issued pursuant to the Instructions to Bidders. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENT City Project No. 106104 Revised 2/08/24 001113 INVITATION TO BIDDERS Page 3 of 3 CITY'S RIGHT TO ACCEPT OR REJECT BIDS City reserves the right to waive irregularities and to accept or reject any or all bids. AWARD City will award a contract to the Bidder presenting the lowest price, qualifications and competencies considered. ADVERTISEMENT DATES March 4, 2026 March 11, 2026 March 18, 2026 I iZITW*J X0N-Re)zI CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENT City Project No. 106104 Revised 2/08/24 0021 13 INSTRUCTIONS TO BIDDERS DAP Page 1 of 10 SECTION 00 21 13 INSTRUCTIONS TO BIDDERS DEVELOPER AWARDED CONTRACTS FOR PUBLICLY BID PROJECTS ONLY 1. Defined Terms 1.1. Certain additional terms used in these INSTRUCTIONS TO BIDDERS have the meanings indicated below which are applicable to both the singular and plural thereof. 1.1.1. Bidder: Any person, firm, partnership, company, association, or corporation acting directly through a duly authorized representative, submitting a bid for performing the work contemplated under the Contract Documents. 1.2. Nonresident Bidder: Any person, firm, partnership, company, association, or corporation acting directly through a duly authorized representative, submitting a bid for performing the work contemplated under the Contract Documents whose principal place of business is not in the State of Texas. 1.1.3. Successful Bidder: The responsible and responsive Bidder to whom Developer/City (on the basis of the evaluation as hereinafter provided) makes an award. 2. Copies of Bidding Documents 2.1. Developer, City, and Engineer shall not assume any responsibility for errors or misinterpretations resulting from the Bidders use of incomplete sets of Bidding Documents. 2.2. Developer, City, and Engineer, in making copies of Bidding Documents available, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license or grant for any other use. 3. Prequalification of Bidders (Prime Contractors and Subcontractors) 3.1. Bidders or their designated subcontractors are required to be prequalified for the work types requiring prequalification as per Sections 00 45 11 BIDDERS PREQUALIFICATIONS and 00 45 12 PREQUALIFICATION STATEMENT. Firms seeking pre -qualification, must submit the documentation identified in Section 00 45 11 on Section 00 45 13 PREQUALIFICATION APPLICATION at least seven (7) calendar days prior to Bid opening for review and, if qualified, acceptance. The subcontractors listed by a Bidder on 00 45 12 must be prequalified for the appropriate work types. Subcontractors must follow the same timelines as Bidders for obtaining prequalification review. Bidders or Subcontractors who are not prequalified at the time bids are opened and reviewed may cause the bid to be rejected. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised September 1, 2025 0021 13 INSTRUCTIONS TO BIDDERS DAP Page 2 of 10 Prequalification requirement work types and documentation are available by accessing all required files through the City's website at: https://www.fortworthtexas. ov/departments/tpw/development/cfw-departments-tpw- contractors under Division 00 - General Conditions and as follows: 3.1.1. Paving — Requirements document located at: https://app-us3.e- builder.net/public/publicLanding.aspx?QS=4d00804b 133b408a85a69323548dda25 3.1.2. Roadway and Pedestrian Lighting — Requirements document located at: https://app-us3.e- builder.net/public/publicLanding.aspx?QS=e43c4239775f4b2583552c029c6a 1 ed2 3.1.3. Water and Sanitary Sewer — Requirements document located at: https://app-us3.e- builder.net/public/publicLanding.aspx?QS=4fc66ff8c36c4c029d542d4e55 l l4e8d 3.2. Each Bidder unless currently prequalified, must be prepared to submit to City at least seven (7) calendar days prior to Bid opening, the documentation identified in Section 00 45 11, BIDDERS PREQUALIFICATIONS. 3.2.1. Submission of and/or questions related to prequalification should be addressed to the City contact as provided in Paragraph 6.1. 3.3. The City and Developer reserve the right to require any pre -qualified contractor who is the apparent low bidder for a project to submit such additional information as the City and Developer, in their sole discretion, may require, including but not limited to manpower and equipment records, information about key personnel to be assigned to the project, and construction schedule to assist the City and Developer in evaluating and assessing the ability of the apparent low bidder to deliver a quality product and successfully complete projects for the amount bid within the stipulated time frame. Failure to submit the additional information, if requested, may be grounds for rejecting the apparent low bidder as non -responsive. 3.4. In addition to prequalification, additional requirements for qualification may be required within various sections of the Contract Documents. 4. Examination of Bidding and Contract Documents, Other Related Data, and Site 4.1. Before submitting a Bid, each Bidder: 4.1.1. Shall examine and carefully study the Contract Documents and other related data identified in the Bidding Documents (including "technical data" referred to in Paragraph 4.2. below). No information given by Developer or City or any representative of the Developer or City other than that contained in the Contract Documents and officially promulgated addenda thereto, shall be binding upon the Developer or City. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised September 1, 2025 0021 13 INSTRUCTIONS TO BIDDERS DAP Page 3 of 10 4.1.2. Should visit the site to become familiar with and satisfy Bidder as to the general, local and site conditions that may affect cost, progress, performance or furnishing of the Work. 4.1.3. Shall consider federal, state and local Laws and Regulations that may affect cost, progress, performance or furnishing of the Work. 4.1.4. <Include this Paragraph if Federal Assistance is being provided for this Contract, otherwise delete> Is advised that, City, in accordance with Title VI of the Civil Rights Act of 1964, 78 Stat. 252, 42 U.S.C. 2000d to 2000d-4 and Title 49, Code of Federal Regulations, Department of Transportation, Subtitle A, Office of the Secretary, Part 21, Nondiscrimination in Federally -assisted programs of the Department of Transportation issued pursuant to such Act, hereby notifies all bidders that it will affirmatively insure that in any contract entered into pursuant to this advertisement, minority business enterprises will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, or national origin in consideration of award. 4.1.5. Study all: (i) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities) that have been identified in the Contract Documents as containing reliable "technical data" and (ii) reports and drawings of Hazardous Environmental Conditions, if any, at the Site that have been identified in the Contract Documents as containing reliable "technical data." 4.1.6. Is advised that the Contract Documents on file with the City shall constitute all of the information which the City and Developer will furnish. All additional information and data which the City or Developer will supply after promulgation of the formal Contract Documents shall be issued in the form of written addenda and shall become part of the Contract Documents just as though such addenda were actually written into the original Contract Documents. No information given by the City or Developer other than that contained in the Contract Documents and officially promulgated addenda thereto, shall be binding upon the City or Developer. 4.1.7. Should perform independent research, investigations, tests, borings, and such other means as may be necessary to gain a complete knowledge of the conditions which will be encountered during the construction of the project. For projects with restricted access, upon request, City or Developer may provide each Bidder access to the site to conduct such examinations, investigations, explorations, tests and studies as each Bidder deems necessary for submission of a Bid. Bidder must fill all holes and clean up and restore the site to its former conditions upon completion of such explorations, investigations, tests and studies. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised September 1, 2025 0021 13 INSTRUCTIONS TO BIDDERS DAP Page 4 of 10 4.1.8. Determine the difficulties of the Work and all attending circumstances affecting the cost of doing the Work, time required for its completion, and obtain all information required to make a proposal. Bidders shall rely exclusively and solely upon their own estimates, investigation, research, tests, explorations, and other data which are necessary for full and complete information upon which the proposal is to be based. It is understood that the submission of a proposal is prima-facie evidence that the Bidder has made the investigation, examinations and tests herein required. 4.1.9. Shall promptly notify City and Developer of all conflicts, errors, ambiguities or discrepancies in or between the Contract Documents and such other related documents. The Contractor shall not take advantage of any gross error or omission in the Contract Documents, and the City and Developer shall be permitted to make such corrections or interpretations as may be deemed necessary for fulfillment of the intent of the Contract Documents. 4.1.10. Indicate their intent to bid by selecting "yes" in the Procurement Portal under the Intent to Bid section. You must indicate your intent to bid to be able to submit a bid to the City and Developer. 4.2. Reference is made to Section 00 73 00 — Supplementary Conditions for identification of: 4.2.1. those reports of explorations and tests of subsurface conditions at or contiguous to the site which have been utilized by City in preparation of the Contract Documents. The logs of Soil Borings, if any, on the plans are for general information only. Neither the City nor the Engineer guarantee that the data shown is representative of conditions which actually exist. 4.2.2. those drawings of physical conditions in or relating to existing surface and subsurface structures (except Underground Facilities) which are at or contiguous to the site that have been utilized by City in preparation of the Contract Documents. 4.2.3. copies of such reports and drawings will be made available by City to any Bidder on request. Those reports and drawings may not be part of the Contract Documents, but the "technical data" contained therein upon which Bidder is entitled to rely as provided in Paragraph 4.02. of the General Conditions has been identified and established in Paragraph SC 4.02 of the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion drawn from any "technical data" or any other data, interpretations, opinions or information. 4.2.4. Standard insurance requirements, coverages and limits. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised September 1, 2025 0021 13 INSTRUCTIONS TO BIDDERS DAP Page 5 of 10 4.3. The submission of a Bid will constitute an incontrovertible representation by Bidder (i) that Bidder has complied with every requirement of this Paragraph 4, (ii) that without exception the Bid is premised upon performing and furnishing the Work required by the Contract Documents and applying the specific means, methods, techniques, sequences or procedures of construction (if any) that may be shown or indicated or expressly required by the Contract Documents, (iii) that Bidder has given City and Developer written notice of all conflicts, errors, ambiguities and discrepancies in the Contract Documents and the written resolutions thereof by City and Developer are acceptable to Bidder, and when said conflicts, etc., have not been resolved through the interpretations by City and Developer as described in Paragraph 6., and (iv) that the Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work. 4.4. The provisions of this Paragraph 4, inclusive, do not apply to Asbestos, Polychlorinated biphenyls (PCBs), Petroleum, Hazardous Waste or Radioactive Material, unless specifically identified in the Contract Documents. 5. Availability of Lands for Work, Etc. 5.1. The lands upon which the Work is to be performed, rights -of -way and easements for access thereto and other lands designated for use by Contractor in performing the Work are identified in the Contract Documents. All additional lands and access thereto required for temporary construction facilities, construction equipment or storage of materials and equipment to be incorporated in the Work are to be obtained and paid for by Contractor. Easements for permanent structures or permanent changes in existing facilities are to be obtained and paid for by Developer. 5.2. Outstanding right-of-way, easements, and/or permits to be acquired by the City are listed in Paragraph SC 4.01 of the Supplementary Conditions. In the event the necessary right- of-way, easements, or permits are not obtained, the Developer reserve the right to cancel the award of contract at any time before the Bidder begins any construction work on the project. 5.3. The Bidder shall be prepared to commence construction without all executed right-of- way, easements, and/or permits, and shall submit a schedule to the City and Developer of how construction will proceed in the other areas of the project that do not require permits and/or easements. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised September 1, 2025 0021 13 INSTRUCTIONS TO BIDDERS DAP Page 6 of 10 6. Interpretations and Addenda 6.1. All questions about the meaning or intent of the Bidding Documents are to be directed to City and Developer electrically through the Vendor Discussions section under the respective Project via the Procurement Portal https://fortworthtexas.bonfirehub.com/portal/?tab=open0pportunities on or before 2 p.m., the FRIDAY prior to the Bid opening. Questions received after this day may not be responded to. Interpretations or clarifications considered necessary by Developer and City in response to such questions will be issued by Addenda. Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect. 6.2. Addenda may also be issued to modify the Bidding Documents as deemed advisable by Developer and City. 6.3. Addenda or clarifications shall be posted under the respective Project via the Procurement Portal https://fortworthtexas.bonfirehub.com/portal/?tab=openOpportunities 6.4. A prebid conference may be held at the time and place indicated in the Advertisement or INVITATION TO BIDDERS. Representatives of the Developer and City will be present to discuss the Project. Bidders are encouraged to attend and participate in the conference. Developer and City will transmit to all prospective Bidders of record such Addenda as Developer and City consider necessary in response to questions arising at the conference. Oral statements may not be relied upon and will not be binding or legally effective. 7. Bid Security 7.1. Each Bid must be accompanied by a Bid Bond made payable to City in an amount of five (5) percent of Bidder's maximum Bid price, on the form attached or equivalent, issued by a surety meeting the requirements of Paragraph 5.01 of the General Conditions. 7.2. The Bid Bonds provided by a Bidder will be retained until the conditions of the Notice of Award have been satisfied. If the Successful Bidder fails to execute and return the Contract Documents within 14 days after the Notice of Award conveying same, City and Developer may consider Bidder to be in default, rescind the Notice of Award and act on the Bid Bond. Such action shall be City and Developer's exclusive remedy in the event Bidder is deemed to have defaulted. The Bid Bond of all other Bidders whom Developer believes to have a reasonable chance of receiving the award will be retained by Developer until final contract execution. 8. Contract Times The number of days within which, or the dates by which, Milestones are to be achieved in accordance with the General Requirements and the Work is to be completed and ready for Final Acceptance is set forth in the Agreement or incorporated therein by reference to the attached Bid Form. 9. Liquidated Damages Provisions for liquidated damages are set forth in the Agreement. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised September 1, 2025 0021 13 INSTRUCTIONS TO BIDDERS DAP Page 7 of 10 10. Substitute and "Or -Equal" Items The Contract, if awarded, will be on the basis of materials and equipment described in the Bidding Documents without consideration of possible substitute or "or -equal" items. Whenever it is indicated or specified in the Bidding Documents that a "substitute" or "or - equal" item of material or equipment may be furnished or used by Contractor if acceptable to City and Developer, application for such acceptance will not be considered by City and Developer until after the Effective Date of the Agreement. The procedure for submission of any such application by Contractor and consideration by City and Developer is set forth in Paragraphs 6.05A., 6.05B. and 6.05C. of the General Conditions and is supplemented in Section 01 25 00 of the General Requirements. 11. Subcontractors, Suppliers and Others 11.1. In accordance with the City's Small Business Ordinance No. 27832-08-25, the City has established a goal for the participation of small businesses for contracts that have City Participation in the amount of $1,000,000 or greater. See Section 00 45 41 for the Project Goal and additional requirements. Failure to comply may render the Bidder non -responsive. 11.2. No Contractor shall be required to employ any Subcontractor, Supplier, other person or organization against whom Contractor, Developer, or City has reasonable objection. 12. Bid Form 12.1. The Bid Form is included with the Bidding Documents. 12.2. All blanks on the Bid Form must be completed and the Bid Form signed electronically or signed in ink and scanned. A Bid price shall be indicated for each Bid item, alternative, and unit price item listed therein. In the case of optional alternatives, the words "No Bid," "No Change," or "Not Applicable" may be entered. Bidder shall state the prices for which the Bidder proposes to do the work contemplated or furnish materials required. 12.3. Bids by corporations shall be executed in the corporate name by the president or a vice-president or other corporate officer accompanied by evidence of authority to sign. The corporate seal shall be affixed. The corporate name, address and state of incorporation shall be shown below the signature. 12.4. Bids by partnerships shall be executed in the partnership name and signed by a partner, whose title must appear under the signature accompanied by evidence of authority to sign. The official name and address of the partnership shall be shown below the signature. 12.5. Bids by limited liability companies shall be executed in the name of the firm by a member and accompanied by evidence of authority to sign. The name and state of formation of the firm and the official address of the firm shall be shown. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised September 1, 2025 0021 13 INSTRUCTIONS TO BIDDERS DAP Page 8 of 10 12.6. Bids by individuals shall show the Bidder's name and official address. 12.7. Bids by joint ventures shall be executed by each joint venturer in the manner indicated on the Bid Form. The official address of the joint venture shall be shown. 12.8. All names shall be typed or printed in ink below the signature. 12.9. The Bid shall contain an acknowledgement of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form. 12.10. Postal and e-mail addresses and telephone number for communications regarding the Bid shall be shown. 12.11. Evidence of authority to conduct business as a Nonresident Bidder in the state of Texas shall be provided in accordance with Section 00 43 37 — Vendor Compliance to State Law Non Resident Bidder. 13. Submission of Bids 13.1. Bids shall be submitted electronically in the Procurement Portal on the prescribed Bid Form, provided with the Bidding Documents, prior to the time indicated in the Advertisement or INVITATION TO BIDDERS. 14. Withdrawal of Bids 14.1. Bids submitted electronically may be withdrawn prior to the time set for bid opening via the Procurement Portal hops://fortworthtexas.bonfirehub.com/portal/?tab=openOpportunities. 15. Opening of Bids 15.1. Bids will be opened and read aloud publicly. An abstract of the amounts of the base Bids and major alternates (if any) will be made available to Bidders after the opening of Bids. 16. Bids to Remain Subject to Acceptance 16.1. All Bids will remain subject to acceptance for a minimum of 90 days or the time period specified for Notice of Award and execution and delivery of a complete Agreement by Successful Bidder. City and Developer may, at their discretion, release any Bid and nullify the Bid security prior to that date. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised September 1, 2025 0021 13 INSTRUCTIONS TO BIDDERS DAP Page 9 of 10 17. Evaluation of Bids and Award of Contract 17.1. Developer and City reserve the right to reject any or all Bids, including without limitation the rights to reject any or all nonconforming, nonresponsive, unbalanced or conditional Bids and to reject the Bid of any Bidder if Developer or City believes that it would not be in the best interest of the Project to make an award to that. Developer and City also reserve the right to waive informalities not involving price, contract time or changes in the Work with the Successful Bidder. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. Discrepancies between words and figures will be resolved in favor of the words. 17.1.1. Any or all bids will be rejected if Developer or City has reason to believe that collusion exists among the Bidders, Bidder is an interested party to any litigation against Developer or City, Developer, or City and the Bidder may have a claim against the other or be engaged in litigation, Bidder is in arrears on any existing contract or has defaulted on a previous contract, Bidder has performed a prior contract in an unsatisfactory manner, or Bidder has uncompleted work which in the judgment of the Developer or City will prevent or hinder the prompt completion of additional work if awarded. 17.2. In addition to Bidder's relevant prequalification requirements, Developer and City may consider the qualifications and experience of Subcontractors, Suppliers, and other persons and organizations proposed for those portions of the Work as to which the identity of Subcontractors, Suppliers, and other persons and organizations must be submitted as provided in the Contract Documents or upon the request of the Developer and City. Developer and City also may consider the operating costs, maintenance requirements, performance data and guarantees of major items of materials and equipment proposed for incorporation in the Work when such data is required to be submitted prior to the Notice of Award. 17.3. Developer and City may conduct such investigations as Developer and City deem necessary to assist in the evaluation of any Bid and to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers and other persons and organizations to perform and furnish the Work in accordance with the Contract Documents to Developer's and City's satisfaction within the prescribed time. 17.4. If the Contract is to be awarded, it will be awarded to lowest responsible and responsive Bidder whose evaluation by Developer and City indicates that the award will be in the best interests of the Developer and City. 17.5. Pursuant to Texas Government Code Chapter 2252.002, a contract will not be awarded to a Nonresident Bidder unless the Nonresident Bidder's bid is lower than the lowest bid submitted by a responsible Texas Bidder by the same amount that a Texas resident bidder would be required to underbid a Nonresident Bidder to obtain a comparable contract in the state in which the nonresident's principal place of business is located. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised September 1, 2025 0021 13 INSTRUCTIONS TO BIDDERS DAP Page 10 of 10 17.6. If a contract is to be awarded, Developer will award the contract within 90 days after the day of the Bid opening unless extended in writing. No other act of City, Developer, or others will constitute acceptance of a Bid. Upon the contract award, a Notice of Award will be issued by the Developer. 17.7. Failure or refusal to comply with the requirements may result in rejection of Bid. 18. Signing of Agreement 18.1. When the Developer issues a Notice of Award to the Successful Bidder, it will be accompanied by the required number of unsigned counterparts of the Project Manual. Contractor shall sign and deliver the required number of counterparts of the Project Manual to the Developer with the required Bonds, Certificates of Insurance, and all other required documentation within 14 days of execution of Community Facilities Agreement or Interlocal Agreement. END OF SECTION CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised September 1, 2025 0035 13 CONFLICT OF INTEREST STATEMENT Page Iof13 SECTION 00 35 13 CONFLICT OF INTEREST STATEMENT Each bidder, offeror or respondent to a City of Fort Worth procurement is required to complete a Conflict of Interest Questionnaire or certify that one is current and on file with the City Secretary's Office pursuant to state law. If a member of the Fort Worth City Council, any one or more of the City Manager or Assistant City Managers, or an agent of the City who exercise discretion in the planning, recommending, selecting or contracting with a bidder, offeror or respondent is affiliated with your company, then a Local Government Officer Conflicts Disclosure Statement (CIS) may be required. You are urged to consult with counsel regarding the applicability of these forms and Local Government Code Chapter 176 to your company. The referenced forms may be downloaded from the links provided below. Form CIQ (Conflict of interest Questionnaire) (state.tx,us) https:I/www ethics state tx us/datafforms1conflict/CIPdf CIQ Form does not apply CIQ Form is on file with City Secretary CIQ Form is being provided to the City Secretary CIS Form does not apply CIS Form is on File with City Secretary CIS Form is being provided to the City Secretary BIDDER: Klufz LLCi END OF SECTION By: P, Signature: Title: 1� 12�a IY7 eay & - CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised February 24, 2020 00 35 13_00 41 00_00 42 43_00_43 I300 45 12 Bid Proposal Workbook Template_DAP CERTIFICATE OF INTERESTED PARTIES FORM 1295 1of1 Complete Nos. 1- 4 and 6 if there are interested parties. OFFICE USE ONLY Complete Nos. 1, 2, 3, 5, and 6 if there are no interested parties. CERTIFICATION OF FILING Certificate Number: I Name of business entity filing form, and the city, state and country of the business entity's place of business. 2026-1491521 Charles Klutz Kennedale, TX United States Date Filed: 07/21/2026 2 Name of governmental entity or state agency that is a party to the contract for which the form is being filed. City of Fort Worth Date Acknowledged: 3 Provide the identification number used by the governmental entity or state agency to track or identify the contract, and provide a description of the services, goods, or other property to be provided under the contract. 106104 Cibolo Hills Parkway Water, Drainage, Paving and Street Lighting Improvements 4 Name of Interested Party City, State, Country (place of business) Nature of interest (check applicable) Controlling Intermediary Klutz, Charlie Kennedale, TX United States X Woody, Troy Kennedale, TX United States X Woody, Trent Kennedale, TX United States X 5 Check only if there is NO Interested Party. 6 UNSWORN DECLARATION My name is �' t= �`L-' �— and my date of birth is My address is ✓Z' 1 7. V —W gyp, r " &J 4 . TX , �p ! 0 c (city) (state) (zip code) (country) I declare under penalty ofperjury that the foregoing is true and correct. Executed in Co State of T , on the day of .%—V , 20 onth) (year) Signature of authorized agent of contracting business entity (Declarant) Forms provided by I exas Ethics Commission www.ethics.state.tx.us Version V4.1.0.477b1118 0041 00 DAP BID FORM FOR PUBLICLY BID PROJECTS ONLY Page 2 of 13 SECTION 00 41 00 BID Publicly Bid Developer Awarded Projects - BID FORM TO: GRBK Edgewood LLC. 5501 Headquarters Drive, Suite 300W Plano, TX 75024 FOR: Cibolo Hills Parkway City Project No.: 1061041-1 Units/Sections: UNIT I: WATER IMPROVEMENTS UNIT III: DRAINAGE IMPROVEMENTS UNIT IV: PAVING IMPROVEMENTS UNIT V: STREET LIGHTING IMPROVEMENTS 1. Enter Into Agreement The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Developer in the form included in the Bidding Documents to perform and furnish all Work as specified or indicated in the Contract Documents for the Bid Price and within the Contract Time indicated in this Bid and in accordance with the other terms and conditions of the Contract Documents. This Agreement may not be used outside of the public bidding process through the City of Fort Worth. 2. BIDDER Acknowledgements and Certification 2.1. In submitting this Bid, Bidder accepts all of the terms and conditions of the INVITATION TO BIDDERS and INSTRUCTIONS TO BIDDERS, including without limitation those dealing with the disposition of Bid Bond. 2.2. Bidder is aware of all costs to provide the required insurance, will do so pending contract award, and will provide a valid insurance certificate meeting all requirements in the construction contract. 2.3. Bidder certifies that this Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation. 2.4. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid. 2.5. Bidder has not solicited or induced any individual or entity to refrain from bidding. 2.6. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph: a. "corrupt practice" means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process. b. "fraudulent practice" means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Developer (b) to establish Bid prices at artificial non-competitive levels, or (c) to deprive Developer of the benefits of free and open competition. c. "collusive practice" means a scheme or arrangement between two or more Bidders, with or without the knowledge of Developer, a purpose of which is to establish Bid prices at artificial, non - CITY OF FORT WORTH STANDARD CONSTRUCTION BID FORM - DEVELOPER AWARDED PROJECTS Form Revised April 2, 2014 00 41 00 BID FORM DAP 0041 00 DAP BID FORM FOR PUBLICLY BID PROJECTS ONLY Page 3 of 13 competitive levels. d. "coercive practice" means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract. 3. Prequalification The Bidder acknowledges that the following work types must be performed only by prequalified contractors and subcontractors: a. Water New Development Open Cut (16') b. Concrete Paving Construction (LESS THAN 15, 000 square yards) c. Roadway Lighting 4. Time of Completion 4.1. Bidder agrees to complete WORK for FINAL ACCEPTANCE within 240 working days after the date when the Contract Time commences to run as provided in the General Conditions. 4.2. Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work {and/or achievement of Milestones} within the times specified in the Agreement. 5. Attached to this Bid The following documents are attached to and made a part of this Bid: a. This Bid Form, Section 00 41 00 Required Bid Bond, Section 00 43 13 issued by a surety meeting the requirements of paragraph b' 4.01 of the Standard City Conditions of the Construction Contract for Developer Awarded Projects c. Proposal Form, Section 00 42 43 d. Vendor Compliance to State Law Non Resident Bidder, Section 00 43 37 e SBE Forms f. Prequalification Statement, Section 00 45 12 g. Conflict of Interest Affidavit, Section 00 35 13 h. Any additional documents that may be required by Section 12 of the Instructions to Bidders i. Bidder pre -qualification application (if applicable) 6. Total Bid Amount CITY OF FORT WORTH STANDARD CONSTRUCTION BID FORM - DEVELOPER AWARDED PROJECTS Form Revised April 2, 2014 00 41 00 BID FORM DAP 0041 00 DAP BID FORM FOR PUBLICLY BID PROJECTS ONLY Page 4 of 13 6.1. Bidder will complete the Work in accordance with the Contract Documents for the following bid amount. In the space provided below, please enter the total bid amount for this project. Only this figure will be read publicly by the City at the bid opening. 6.2. It is understood and agreed by the Bidder in signing this proposal that the total bid amount entered below is subject to verification and/or modification by multiplying the unit bid prices for each pay item by the respective estimated quantities shown in this proposal and then totaling all of the extended amounts. 6.3 TOTAL BID i 3.7 d l 7# 6� vNDl2 'rte 1 Ary V„ JE 7 HO 4,vP otgC Q► ev 7. Bid Submittal lChy / �{i u�J $ Awl 7 k :V'r7' a�i VL tom= 17' S This Bid is submitted on M� �f. 26 e 0U�� by the entity named below. Respe tfully s mitt 4 8y: (Signature) e 1lIuz (Printed Name) Title: [V Glvl SS. lk1�( PP✓'!yet' Company: f ( Wf Z CoYj E c/ Doi r✓ CI Address: /&I( 1(5 Ili Y CJ cth) -(. G o State of Incorporation: T2 S Email: C/ka(II'C 6) k-fu,fzc,t7►)s- KAuA -o4occ)M Phone: g r - 5(.v1 --SS 9 END OF SECTION CITY OF FORT WORTH STANDARD CONSTRUCTION BID FORM - DEVELOPER AWARDED PROJECTS Form Revised April 2, 2014 Receipt is acknowledged of the Initial following Addenda: Addendum No. 1: Addendum No. 2: Addendum No. 3: Addendum No. 4: Corporate Seal: <Seal Here> 00 41 00 BID FORM DAP 004243-SEC1I&SEC III DAP - BID PROPOSAL Page I o13 SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM CIBOLO HILLS PARKWAY - SECTION II & SECTION III UNIT PRICE BID Bidder's Application Project Item Information Bidder's Proposal Bidlist Description Specification Unit of Item No. p Section No. Measure Bid Quantity Unit Price Bid Value UNIT III: DRAINAGE IMPROVEMENTS 1 3305.0109 Trench Safety 33 05 10 LF 2079 $1.00 $2,079.00 2 3301.0012 Post -CCTV Inspection of Storm Drain 330132 LF 2079 $2.65 $5,509.35 3 3341 .0201 21" RCP, Class III 3341 10 LF 304 $103.00 $31,312.00 4 3341.0205 24" RCP, Class III 3341 10 LF 84 $115.50 $9,702.00 5 3341.0208 27" RCP, crass IIf 33 41 10 LF 166 $132.50 $21,995.00 6 3341.0309 36" RCP, Class III 33 4110 LF 386 $196.50 $75;849.00 7 3341.0402 42" RCP, Class III 33 4110 LF 129 $234.00 $30,186.00 8 3341.2003 10x6 Box Culvert 33 41 10 LF 808 $760.00 $614,080.00 9 3341.2004 10x7 Box Culvert 34 41 10 LF 202 $760.00 $153,520.00 10 3349.0001 4' Storm Junction Box 33 49 10 EA 2 $11,500.00 $23,000.00 11 3349.0002 5' Storm Junction Box 3349 10 EA 1 $14,900.00 $14,900.00 12 3349.0102 4' Manhole Riser 33 49 10 EA 2 $6,300.00 $12,600.00 13 3349.6001 10' Recessed Inlet 33 49 20 EA 7 $6,550.00 $45,850.00 14 3349.7001 4' X 4' Drop Inlet 33 4920 EA 1 $12,200.00 $12,200.00 15 3349.7002 5' X 5' Drop Inlet 33 49 20 EA 1 $12,600.00 $12,600.00 16 3137.0104 Medium Stone Riprap, dry 31 3700 SY 1443 $147.00 $212,121.00 17 9999.0001 PW-1 15° Skew 4:1 Wingwall W/5' Extended Curb 00 00 00 EA 2 $170,000.00 $340,000.00 18 9999.0002 36" 6:1 Sloped End HW 00 00 00 EA 2 $7,500.00 $15,000.00 19 9999.0003 42" 4:1 Sloped End HW 0000 00 EA 1 $7,600.00 $7,600.00 20 9999.0004 Remove 20 LF of 42" RCP and Headwall 00 00 00 LS 1 $2,835.00 $2,835.00 21 9999.0005 12" Large Stone Type "A" Dry Rip Rap 00 00 00 SY 110 $147.00 $16,170.00 22 9999.0006 Reuse and Install 12" Large Stone Type "A" Dry Rip Rap_00 00 00 SY 43 $147.00 $6,321.00 23 9999.0007 Inlet Protection 00 00 00 EA 9 $1,000.00 $9,000.00 TOTAL UNIT III: DRAINAGE IMPROVEMENTS $1,674,429.35 CITY OF FORT WORTH Northbound Brewer Blvd STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS- DEVELOPER AWARDED PROJECTS City Protect No. 103435 Fonn Version May 22, 2010 Addendum 1 0035 130041000042430043 13 00 45 12 Bid Proposal Workbook Tanpinte DAP 004243•SECII&SEC m DAP - BID PROPOSAL Page 2 of 3 UNIT IV: PAVING IMPROVEMENTS 1 3211.0400 Hydrated Lime (42 Ibs/sy) 32 11 29 TON 145.4 $440.00 $63,976.00 2 3211.0502 8" Lime Treatment 3211 29 SY 6920 $4.00 $27,680.00 3 3213.0105 10" Conc Pvmt 32 13 13 SY 6369 $96.00 $611,424.00 4 3213.0301 4" Conc Sidewalk (10') 32 13 13 SF 24287 $7.00 $170,009.00 5 3217.2103 REFL Raised Marker TY II -A -A 32 17 23 EA 57 $11.00 $627.00 6 3217.0504 Preformed Thermoplastic Contrast Markings - 24" Stop Bars 00 00 00 LF 44 $46.00 $2,024.00 7 3217.1003 Lane Legend DBL Arrow 32 17 23 EA 2 $360.00 $720.00 8 3213.0506 Barrier Free Ramp, Type P-1 32 1320 EA 2 $2,330.00 $4,660.00 9 3291.0100 Topsoil 32 9119 CY 958 $62.50 $59,875.00 10 3292.0100 Block Sod Placement 32 92 13 SY 5746 $7.70 $44,244.20 11 9999.0008 Construct Std. Pvmt Header 00 00 00 LF 46 $16.00 $736.00 12 9999.0009 Constr Barricade 00 00 00 EA 2 $1,925.00 $3,850.00 13 9999.0010 Remove Barricade and Connect to Existing Pavement Header 00 00 00 EA 2 $325.00 $650.00 14 9999.0011 REFL PAV MRK TY I(Y)(6")(DBL)(SLD) 00 00 00 LF 2241 $5.00 $11,205.00 15 9999.0012 Gravel Access Road 0000 00 SY 139 $50.00 $6,950.00 16 9999.0013 Stop Signs 00 00 00 EA 2 $220.00 $440.00 17 9999.0014 All Way Sign R1 -3P 00 00 00 EA 3 $55.00 $165.00 18 9999.0015 Street Sign (Speed Limit) R2-1 00 0000 EA 1 $55.00 $55.00 19 9999.0016 Street Sign R4-7 00 00 00 EA 1 $55.00 $55.00 20 9999.0017 Street Sign R5-1 0000 00 EA 1 $55.00 $55.00 21 9999.0018 Street Sign Pole 0000 00 EA 4 $475.00 $1,900.00 22 9999.0019 6" Yellow Skip Lane Line wl Type II-CR 4" Raised Pvmt Markers 00 00 00 LF 122 $3.45 $420.90 TOTAL UNIT IV: PAVING IMPROVEMENTS $1,011,721.10 CITY OF FORT WORTH Northbound Brewer Blvd STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER ,AWARDED PROJECTS City Project No. 103435 Form Versi❑n May 22, 2019 Addendum 1 00 35 13 00 41 00 00 42 43 00 43 13 00 45 12 Bid Proposal WorkbookTemplate DAP 004243 -SEC ir& SEC III DAP - BID PROPOSAL Page3of3 UNIT V: STREET LIGHTING IMPROVEMENTS 1 2605.3015 2" CONDT PVC SCH 80 T 26 05 33 LF 2157 $23.00 $49,611.00 2 3441.3003 Rdwy Ilium AssmblyTY 18,18A,19, and D-40 3441 20 LF 11 $3,845.00 $42,295.00 3 3441.3201 LED Lighting Fixture (138W) 3441 20 EA 22 $1,050.00 $23,100.00 4 3441.1632 Install Type 33A Arm 3441 20 EA 22 $660.00 $14,520.00 5 3441.3302 Rdwy Ilium Foundation TY 3,5,6, and 8 3441 20 EA 11 $2,600.00 $28,600.00 6 3441.1405 NO 2 Insulated Elec Condr 3441 10 LF 6471 $8.00 $51,768.00 7 3441.1502 Furnish/Install Ground Box Type B, w/Apron 3441 10 EA 3 $1,770.00 $5,310.00 TOTAL UNIT V: STREET LIGHTING IMPROVEMENTSI $215,204.00 Bid Summary - UNIT III: DRAINAGE IMPROVEMENTS $1,674,429.3 UNIT IV: PAVING IMPROVEMENTS $1,011,721.1 UNIT V: STREET LIGHTING IMPROVEMENTS $215,204.0 Total Construction Bid P2An4 AAA e This Bid is submitted by the entity named below: BIDDER: BY: Klutz Construction L.L.C P.O. Box 185 TITLE: Kennedale TX 76060 DATE: Contractor agrees to complete WORK for FINAL ACCEPTANCE within CONTRACT commences to run as provided In the General Conditions. SECTION tarles ti Managing Partner 3126/2026 s :249 working days after the date when the CITY OF PORT WORTH Northbound Brewer Blvd STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS. DEVELOPER AWARDED PROJECTS City Project No. 103435 Form Version May 22, 2019 Addendum 1 00 35 13 00 41 00 00 42 43 00 43 13 00 45 12 Bid Proposal Workbook Templale DAP 00 42 43 - 16in Waler DAP - BID PROPOSAL Page I of] SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM CIB0L0 HILLS PARKWAY - 16 -INCH WATERLINE UNIT PRICE BID Bidder's Application Project Item Information Bidder's Proposal Bidlist Description Specification ion No. Unit of Measure Bid Quantity Unit Price Bid Value UNIT I: WATER IMPROVEMENTS 1 3305.0109 Trench Safety 33 05 ID LF 1917 $2.10 $4,025.70 2 3311.0001 Ductile Iron Water Fittings w/ Restraint 33 1111 TON 3.93 $13,860.00 $54,469.80 3 3311.0541 16" Water Pipe 12 LF 1569 $222.00 $348,318.00 4 3311.0551 16" DIP Water 33 11 10 LF 283 $273.00 $77,259.00 5 3305.0203 Imported Embedment/Backfill, CLSM 3305 10 CY 407.3 $181.00 $73,721.30 6 3305.2005 16" Water Carrier Pipe 33 0524 LF 65 $273.00 $17,745.00 7 3305.1005 30" Casing By Open Cut 33 0522 LF 65 $410.00 $26,650.00 8 3312.3006 16" Gate Valve w/ Vault 33 1220 EA 3 $36,855.00 $110,565.00 9 3312.0106 Connection to Existing 16" Water Main 33 1225 EA 2 $4,200.00 $8,400.00 10 3312.1002 2" Combination Air Valve Assembly for Water 33 12 30 EA 2 $30,240.00 $60,480.00 11 3312.0001 Fire Hydrant 33 12 40 EA 2 $11,200.00 $22,400.00 12 3312.6002 6" Blow Off Valve 33 1260 EA 2 $30,000.00 $60,000.00 13 9999.0020 16" Cleaning Wye 0000 00 EA 1 $3,800.00 $3,800.00 TOTAL UNIT I: WATER IMPROVEMENTS $867,833.80 tsla summary UNIT I: WATER IMPROVEMENTS This Bid is submitted by the entity named below: BIDDER: BY: Klotz Construction J .I..C P.O. Bu s 185 TITLE I' eoncdaic IX 760611 DATE: Contractor agrees to complete WORK for FINAL ACCEPTANCE within CONTRACT commences to run as provided in the General Conditions. SECTION Total Construction (lest utr \lanaging Partner 3/26/2026 240 .iworlring days after the date when the CITY OF FORT WORTH Northbound Brewer Blvd STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 103435 Form Version May 22, 2019 Addendum 1 00 35 13 00 41 00 00 42 43 00 43 13 00 45 12 Bid Proposal Workbook Template DAP 0043 13 DAP BID BOND FORM FOR PUBLICLY BID PROJECTS ONLY Page 1 of I SECTION 0043 13 DAP - BID BOND BY THESE PRESENTS: That we, Klutz Construction, LLC called the Principal, and Vigilant Insurance Company a corporation or firm duly authorized to transact surety business in the State of Texas, hereinafter called the Surety, are held and firmly bound unto the City, hereinafter called the Obligee, in the sum of Five Percent of Bid Amount (5%) and No/100 Dollars said Principal and the said Surety, bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firm by these presents. WHEREAS the Principal has submitted a proposal to perform work for the following project of the Obligee identified as: Cibolo Hills Parkway NOW, THEREFORE, if the Obligee shall award the Contract for the foregoing project to the Principal, and the Principal shall satisfy all requirements and conditions required for the execution of the Contract and shall enter into the Contract in writing with the Obligee in accordance with the terms of such proposal, then this bond shall be null and void. If the Principal fails to execute such Contract in accordance with the terms of such proposal or fails to satisfy all requirements and conditions required for the execution of the Contract in accordance with the proposal, this bond shall become the property of the Obligee, without recourse of the Principal and/or Surety, not to exceed the penalty hereof, and shall be used to compensate Obligee for the difference between Principal's Total Bid Amount and the next selected Bidder's Total Bid Amount. (Signature and Title of Principal) Charles M. Klutz, Managing Partner By: Vigilant Insurance Company (Signature of *Attach Power of Attorney (Surety) for Attorney -in -Fact END OF SECTION Kyl . Sweeney, Attorney -in -Fact Impressed Surety Seal Only CITY OF FORT WORTH STANDARD CONSTRUCTION BID BOND FORM — DEVELOPER AWARDED PROJECTS Form Version April 2, 2014 0043 13Bld Bond_DAP (1) 1... LJ B T power o€ Attorney .der iI>lsura[tice Company i Vigil ntlnsuranceC_mpany { Pa .f 0-j.ndetnnit f Company Westchester Fire Insurance Company I ACE American Insurance Company Itnow All by These Presenra;tthat FEIIIilt 1. iNBUItANCB COMPANYr an Indiana corporation, VIGILANT INRURANCR COMPANY, a New York corpryratfonR PACIFIC JNCl);Mi1[Flt COMPANY, a tielaware corporatibn WESTCHRS'FElt FIRE INSURANCE COMPANY and ACE AMERICAN INS(3RANCYi COMPANY corporations of the Commonwealth of Pepnsyivatiia do eaciiliereUyconsttwteauttiappolnr Charles D. Sweeney, David W. Sweeney, Elizabeth Gray, Kyle W. Sweeney, and Michael A Sweeney of Fort Worth, Texas ---------______.._._.___.._M.___ - --------------------_--------_------------------ each astheif true and laWlttl Aaol'ney-1t► Fact to exciteupder siren destgtiattoir Irt their names and to a[lix their ctirp'orate sus tit and deliver fol.and on theirbelialf as surety thereon or.otlt aw .;.bonds: and undertakings: and .ttttier liteitings obligatory in the nature (hereof (other tha( bail bonds) given or executed in the chorea or business, and any instrtmientg ritiiending nr alterittg the:Sanle� and'con9eilts.t rittxliucatloIiof aitei atton of auy lnsttumedt re reed to fnsatd bond l tsrtlblfgadclns: In Witness whereof said REDERAG 1NSURANCI COMPANY ��I.G11 `INS Ah10E)COMPANYMACWtC INDEMNITY COMPh,ZfY,,lWESTCHESTER FIRE INSURANCE COMPANY —__._.�. __L...-.;....,...:.t:,...:�..,.r�i;,�„moo„i��„rtat'f��lfht:3rtsoroorate:seaisfm titiS R4!!'.daynf October., 2025.. SCsais E1pNEw{EiiSEY Cowttyoflfttnterft Ottttiis7E1' day 0! October 2025 befareme,aNOtaryPublicofNewj ey.petsdO RifpertHD'Swandellsand5tephetill3:Haitey,tomeknowntobeAssLctanrSt etaryan Vice EresidentPespecuvely, of FEDM- LINSURANCE COMPA y'tt1GGLANTINSURANCECOMP.ANZPACIFIC INDEMNITY COMPANY, W STCI3ESTERp'CREINSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY the conapatiles'which executed the foregoing F6wer of .Attorney, and thesaid Rupert HD Swindells: and Stephen -M. Haney; being by nme. duly sworn severally and each for blmself did depose and say that they are :Ass fantSecretary and We President respectively of FEDERAL INSURANCE COMPANY VIGILANT iNSURANCECOMPANY, PACIFIC INDEMNITY COMPANY WIIS7 GIIPSrER FIRE INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY aiadlaiow the corporate.seals. n,,,,. n n,m' iriich cortrorate seals and Were thereto at xedbyauthorhyofsaidC4inpanies, andthattheirstgttattlres assuch officers were duly affix.. a tulsubscrliied by lilte:autliarlty: NOtarlal Seal 11 tY QR NE1Y iERSEi v rt OGT 15,182b Notary Public `�6iflli;StOiI CERTITIGATION Resolutions adopted by the bomtls.of nheCtlita i2f t1P3)ERAL INSURANCE COMPANY, VIGILANT INSURANCE COMPANY; aDd PACiItIC INDEMNITY COMPANY on August 30; 2OI . . yyR57 CfIRSTER l; IRE iNSIIRANCE COMPANY onDeceitiber1t 0001 And ICAN INSURANCE COMPANYOR Mai 2Q, 2009:. ,tEsOI,VBD, that the Pailowli gaathii Nations relate to theexeudon, for andgn;l4ehaf ofifiefiimlx,Ay;otponds ursder(akings tecagrii i?cam actsand otherini)tgn ?mtnittnenis bf the Coin pany. miteredintoiitt6ordtuaiy cau'rse:0Fbnsine3s (egtlta"Wtitteu Commuinent'1e (S): *h of rho Chahnimk the FresidtM and the- Vice Pro stdents :ofthe .pumpanyisherelry Bulhluiied roestiecute;tnyliltittatrComrnitwent fprandotrtrellalCofthe;Company ;under the . seal of the }7ompany or othewJse; (�J NachdulyptxrhttedaituureinGrctoftheGompanYlsherebYanthm'toteanyvVtittep!kctfnmitmenrfaraaclotfisetralofYlteCanpany,unclertbeaealuftlteCompanyar'u erwrse. rotheexteitchatauclmactionl5anthotizedbytttegranCofpowerspritvfttetlfiirllrsuslrperson'swr'itten:ppQinquButas' dtfatdlrltCyin•faCt...... - .. .. (3} Each of the Gbaim>an. the President and the Vice Presidents of the -Cori panyls'herebyauthotized,for .and on behalf ofihetbriipany,t6appointmvnlihig any person the attdrttey intact of the Company with huh power arr$autharitytoexerute, for and on"behaltofthe Cemipany.ulirirr the seairifiheCon anywotherwlsn,snehwrltten:Commitments ofthe Comwuyas may t1e speelled itr such written appointment, which specift4alion shay be by general type.or class of. written ••Cotnniitnle its or: byapecloatitin.of.onc.'or. rtiote parilcular' Wtitton Gnmmtantnfs= (4): gads of mite Chairman, the Pi and the- Vice Presidents of the. GotnpauyEhecebyautharired,forandonbehalf ottheCompany .todelegaietnwridngtoanyotherofilcerartist Company the authority to execute for and onbeltaif of:.the Company under the Company's .seal or. "otherwise such Written Commitments of the Company as are spedfed hi such written delegation, whtohspiGScadua rtecybe byS m type or .hit of Written Commitments or byspeclhcadattaf0ne ormoeepardcuLitWrit enGotntoltments. ( � y � delegation ptirsutiiieto thls:ResoittUori, and.dreteal ofilie Company; may a affixed The s attire of an officer or other person execudngah . wr Written CogitiilUnenf of appointmettl oe d facslmde:on rich written (itmmitment bewrtttenappolntruent or delegation t+(JRTIIERRsSOLVED::that the foregoing Resolution shall not b040100 6beanexciiisivestatemeitofthepoweizaiidauO6*.of6mcem�i!.f�6playeesi(not be -deemed tobean excivaivestatenscntof the poweisand authoilIyof0fflCera.etflPlu nesandotherpersonstoactforaridonyeliaifoftht Cot any and suchResoludonshallnotlirnitarotiterwtsetafIectthe.exerclseofanysuchpowerorauthoutyotherwisevalidlygrantedorvested L Rupert HI) Swindeils,: Assistant Secretary of FEDERAL INSURANCE COMPANY VIGILANT INIlURANCIl COMPANY; PACIFIC: INDEMNITY. COMPANY ES`SRS INSURAlVC1i:COMPANY and ACE AMER[GAN INSURANCE COMPANY {the "Companies°3.do tierebycetd that (0 . the foregoing Resoiutiobs adopted by the Board ol' tots of the Conipanlesareltuc correctandinfullforceaudeffect, (Il): the fpregoingPowerof AttOrd..dsttue cblTe:et anditiuliforce anti effect. Combined: F[D-VIG-PI-WFIC-AAIC (rev. 11-19) SECTION 00 43 37 VENDOR COMPLIANCE TO STATE LAW NON RESIDENT BIDDER Texas Government Code Chapter 2252 was adopted for the award of contracts to nonresident bidders. This law provides that, in order to be awarded a contract as low bidder, nonresident bidders (out-of-state contractors whose corporate offices or principal place of business are outside the State of Texas) bid projects for construction, improvements, supplies or services in Texas at an amount lower than the lowest Texas resident bidder by the same amount that a Texas resident bidder would be required to underbid a nonresident bidder in order to obtain a comparable contract in the State which the nonresident's principal place of business is located. The appropriate blanks in Section A must be filled out by all nonresident bidders in order for your bid to meet specifications. The failure of nonresident bidders to do so will automatically disqualify that bidder. Resident bidders must check the box in Section B. A. Nonresident bidders in the State of , our principal place of business, are required to be percent lower than resident bidders by State Law. A copy of the statute is attached. Nonresident bidders in the State of , our principal place of business, are not required to underbid resident bidders. B. The principal place of business of our company or our parent company or majority owner is in the State of Texas. ], BIDDER: By: (Signature) Title: Managing Partner Date: 7/31/2026 c22 AIIL(& END OF SECTION r',f_ 00 45 12 PREQUALIFICATION STATEMENT Page l of 1 SECTION 00 4512 PREQUALIFICATION STATEMENT Each Bidder for a City or Non -City procurment is required to complete the information below by identifying the prequalified contractors and/or subcontractors whom they intend to utilize for the major work type(s) listed. Major Work Type Contractor/Subcontractor Company Name Prequalification Expiration Date 6/30/26 Burnsco Construction INC Water New Development Open Cut (16') Concrete Paving Construction (LESS Stabile & Winn 9/30/26 THAN 15, 000 square yards) 3/24/27 Roadway Lighting Lumina Transportation L.L.C. The undersigned hereby certifies that the contractors and/or subcontractors described in the table above are currently prequalified for the work types listed. BIDDER: Klutz Construction L.L. C BY: Ch rles lu P.O. Box 985 q z_ Kennedale TX 76060 (Signiture) TITLE Managing Partner DATE: 3/26/26 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENT'S Revised 09/30/2021 Addendum 1 00 35 13 0041 00 00 42 43 00 43 13 00 45 12 Bid Proposal Workbook Template DAP 004513-8 BIDDER PREQUALIFICATION APPLICATION Page 8 of 8 BIDDER PREQUALIFICATION AFFIDAVIT STATE OF COUNTY OF —T` *xr uy* The undersigned hereby declares that the foregoing is a true statement of the financial condition of the entity herein first named, as of the date herein first given; that this statement is for the express purpose of inducing the party to whom it is submitted to award the submitter a contract; and that the accountant who prepared the balance sheet accompanying this report as well as any depository, vendor or any other agency herein named is hereby authorized to supply each party with any information, while this statement is in force, necessary to verify said statement. ( -e S . (C IL4,f-L , being duly sworn, deposes and says that he/she is the OA irl 1VL CW- kev of 1 O t1 -Cs the entity described in and which execut d the foregoing statement that he/she is familiar with the books of the said entity showing its financial condition; that the foregoing financial statement taken from the books of the said entity as of the date thereof and that the answers to the questions of the foregoing Bidder Prequalification Application are correct and true as of the date of this affidavit. Firm Name: Signature: r Z' Sworn to before me this 2 (g day of M t rU i r �y w �i' �"I� ' � 1NIlMt�a,$IM, aTe>ars Mf CINhml.si n E wss �f /lpIil26, xa2r i24 CL"�t • v NO1MY lI� 2890410 otary Public Notary Public must not be an officer, director, or stockholder or relative thereof. CITY OF FORT WORTI-1 Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No. 106104 Revised June 13, 2025 rn 00 45 26- 1 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW Page 1 of 1 1 SECTION 00 45 26 2 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW 3 Pursuant to Texas Labor Code Section 406.096(a), as amended, Contractor certifies that it 4 provides worker's compensation insurance coverage for all of its employees employed on City 5 Project No. 106104. Contractor further certifies that, pursuant to Texas Labor Code, Section 6 406.096(b), as amended, it will provide to City its subcontractor's certificates of compliance with 7 worker's compensation coverage. 8 9 CONTRACTOR: 10 11 /l UZ &21744WO 00, UI By: 12 Company ea ri }7 14 Pu to (f Signature:13 4• 15 Address 16 �Jfn In,� 17 ! I ,, d ` e r , 7` - �0 O c O Title: //1 /4GTi,iM7" rn 18 City/State/Zip (Ple se -int) 19 20 21 THE STATE OF TEXAS § 22 23 COUNTY OF TARRANT § 24 25 BEFORE ME, the undersi ned authority, on this day personally appeared 26 CY'1eS M , , u f Z •, known to me to be the person whose name is 27 subscribed to the foregoing instrument, and acknowledged to me That he/she executed the same as �I 28 the act and deed of jL l uf� C9h S fYu G•h oY, (L& for the purposes and { 29 consideration therein expressed and in the capacitytherein stated. 30 31 GIVEN UNDER MY HAND AND'SEAL OF OFFICE this (o day of 32 UV1 ,�rt,V� , 204p 33 wrsn,,.,�w X1111 ., t 34 0; N'� ► 'X LUZ A ¢ AVELO 7 35 a otarY l�ubllo, gtree of ices #, ICY Comrniestan Expires 36 April 2912027 Notary Pub ' in and for the State of Texas '441Ng1' NOTARY ID 12sw4io-0 37 38 END OF SECTION im CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised April 2, 2014 Cibolo Hills Parkway City Project No. 106104 1 00 45 41 - SMALL BUSINESS ENTERPRISE GOAL DAP Page 1 of 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 SECTION 00 45 41 SMALL BUSINESS GOAL FOR DEVELOPER AWARDED PROJECTS APPLICATION OF POLICY If the City Participation in the contract is $ l ,000,000.00 or more the Small Business goal will be set for the contract. POLICY STATEMENT It is the policy of the City of Fort Worth to foster competition, expand the supplier base, and promote and encourage the participation of small business firms in the City's contracting opportunities. SMALL BUSINESS GOAL The Small Business goal is 30% of the amount bid (if bid alternates are requested, the goal shall be applied to the total bid amount inclusive of any selected alternates). COMPLIANCE Bidders shall comply with the Small Business Goal by meeting or exceeding the small business goal through self -performance and/or Small Business subcontracting participation. Small businesses are based on SBA definitions and must be located within the five Fort Worth counties: Tarrant, Denton, Wise, Parker and Johnson. Small businesses shall be certified via one of the following certifying agencies: • North Central Texas Regional Certifying Agency (NCTRCA) • Women's Business Council — Southwest (WBCS) • Dallas -Fort Worth Business Council • Texas Historically Underutilized Business (HUB) Program • Texas Unified Certification Program (TUCP) DBE/ACDBE • Texas Department of Transportation SBE Directory (TxDOT) SUBMITTAL OF REQUIRED DOCUMENTATION The following documents must be submitted with the bid documents at the time of bidding: • Completed Small Business Utilization form • Certificates identifying themselves or subcontractors as Small Businesses FAILURE TO COMPLY WITH THE CITY'S SMALL BUSINESS ORDINANCE WILL RESULT IN THE BID BEING CONSIDERED NON -RESPONSIVE. 42 END OF SECTION CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised September 1, 2025 ORT WORTH Small Business Utilization Form Page 1 of 5 PRIME Klutz Construction L.L.C BIDDER/OFFEROR COMPANY NAME: PROJECT NAME: Ciboto Hills Parkway PROJECT NUMBER: 106104 City's Small Business Goal Bidder/Offerors Commitment BID DATE: 30% 68 3/26/26 Check all applicable Not 42 Small boxes to describe Certified Business Prime Bidder/Offeror Owner's Classification: Certifying Agency: NCTRA fl WBCS DFW BC ❑ HUB ❑TUCP ❑ TXDOT ALL SMALL BUSINESS FIRMS MUST BE CERTIFIED BEFORE BID Failure to complete this form in its entirety and submit it with the Bid/Offer may result in the bid being considered non -responsive to bid specifications. Should the City of Fort Worth determine that the Prime Bidder/Offeror is qualified for award of contract, upon execution of said contract, the undersigned Prime Bidder/Offeror shall enter into a formal agreement with the Small Business firm(s) listed in this utilization schedule. Small Business firms listed toward meeting the project goal must be located in Denton. Parker. Wise. Tarrant and Johnson counties. Certified means those Small Business Firms that have been determined to be bona fide Small Businesses by one of the following Certifying Agencies: North Central Texas Regional Certification Agency (NCTRCA), Women's Business Council —Southwest (WBCS), Dallas/Fort Worth Business Council (DFW BC), Texas Historically Underutilized Business Program (HUB), Texas Unified Certification Program DBE/ACDBE (TUCP), and Texas Department of Transportation SBE Directory (1)(DOT). Please note that only certified Small Business firms will be counted to meet the Small Business goal. Prime Bidders/Offerors are required to identify ALL subcontractors/suppliers, regardless of status. Revised 9/18/2025(dwbRL10.15.25) FORT WORTH. Small Business Utilization Form Page2of5 Certified Small Business Prime/Bidder/Offeror Contractors, counting their self -performance towards meeting the contract goal, must be certified within those NAICS commodity codes for the work it intends to perform. Certified Small Business Prime/Bidder/Offeror counting self -performing services towards the goal should be listed first on the Utilization form. Check this box if certified Prime Contractor services will be counted towards the Small Business contracting goal. 2 Ii III hi IflTtIflT1 NAMES AND ADDRESSES OF TYPE OF SERVICES/SUPPLIES PROVIDED Specify Certification Agency CONTRACTORS/SUPPLIERS (List Prime (NAICS Required) Tier Contractor first if Prime Contractor will be counted toward meeting the SB Goal Business Name: Klutz Construction L.L.C Type of Services/Supplies: Prime Contractor Certified by: Address P.O. 185 Concrete Structures ❑ NCTRCA (including Kennedale TX 76060 Box Culvert County): Tarrant County WBCS DFW BC TXDOT Phone: 817-561-5591 Email: CharIie@kiutzconstructloncorn ` NAICS Code: 2381 10 Contact Person: Charlie Klutz $AMOUNT: 1,537,410.60 NAMES AND ADDRESSES OF TYPE OF SERVICES/SUPPLIES PROVIDED Specify Certification Agency CONTRACTORS/SUPPLIERS (NAICS Required) Tier Business Name: GJ Seeding Type of Services/Supplies: 1St Certified by: Address 1080 S Burleson BLVD Landscaping NCTRCA (including Burleson TX 7602$ Johnson County County): WBCS El DFW BC TXDOT Phone: 817-426-8284 Email: gjseeding@gmail.com NAICS Code: 561730 Contact Person: Gayle Juraschek ' $AMOUNT: 64,000.00 Revised 9/18/2025(dwbRL10.15.25) FORT WORTH. Small Business Utilization Form Page 2of5 Certified Small Business Prime/Bidder/Offeror Contractors, counting their self -performance towards meeting the contract goal, must be certified within those NAICS commodity codes for the work it intends to perform. Certified Small Business Prime/Bidder/Offeror counting sel₹-performing services towards the goat should be listed first on the Utilization form. Check this box if certified Prime Contractor services will be counted towards the Small Business contracting goaL ❑ NAMES AND ADDRESSES OF TYPE OF SERVICES/SUPPLIES PROVIDED Specify Certification Agency CONTRACTORS/SUPPLIERS (List Prime (NAICS Required) Tier Contractor first if Prime Contractor will be counted toward meeting the SB Goal Business Name: Lumin8 Transportation Technologies LLC Type of Services/Supplies: Certified by: Address 821 E Enon St NCTRCA (including Fort Worth Tx 76140 County): Tarrant County WBCS ❑ DFW BC TXDOT Phone: 817-561-7400 Email: Jay.Johnson@lumin8.com NAICS Code: 1288210 Contact Person: Jay Johnson $AMOUNT: 204,690.05 NAMES AND ADDRESSES OF TYPE OF SERVICES/SUPPLIES PROVIDED Specify Certification Agency CONTRACTORS/SUPPLIERS (NAICS Required) Tier Business Name: Type of Services/Supplies: Certified by: Address NCTRCA ❑ (including County): ❑ WBCS ❑ DFW BC ❑ TXDOT Phone: Email: NAICS Code: Contact Person: $AMOUNT: Revised 9/18/2025(dwb RL10.15.25) FORT WORTH. Small Business Utilization Farm Page3of5 Please include multiple copies of this page if needed to list all contractors and suppliers. NAMES AND ADDRESSES OF TYPE OF SERVICES/SUPPLIES PROVIDED Specify Certification Agency CONTRACTORS/SUPPLIERS (NAICS Required) Tier Business Name: Cowtown Redi Mix Inc Type of Services/Supplies: 1St Certified by: Address Concrete Supplier NCTRCA F0RT0W0RTH, TEXAS 76161 (including County): Tarrant County ❑ WBCS ❑ DFW BC ❑ TXDOT Phone: 817-759-2599 Email: maxcowtown@yahoo.com NAICS Code: 327320 Contact Person: Max Ulrich $AMOUNT: 220,000.00 NAMES AND ADDRESSES OF TYPE OF SERVICES/SUPPLIES PROVIDED Specify Certification Agency CONTRACTORS/SUPPLIERS (NAICS Required) Tier Business Name: Stabile &'Winn INC Type of Services/Supplies: 1St Certified by: Address P.O. Box.79380 Concrete Paving NCTRCA (including Saginaw Texas 79179 County): Tarrant County ❑ WBCS ❑ DFW BC ❑ TXDOT Phone: 817=735-1600 Email: Tanner@gilcocontracting.com NAICS Code: NAICS 237310 Contact Person: Tanner Jump $AMOUNT: 770,094.50 NAMES AND ADDRESSES OF TYPE OF SERVICES/SUPPLIES PROVIDED Specify Certification Agency CONTRACTORS/SUPPLIERS (NAICS Required) Tier Business Name: BurnsCo Construction Inc Type of Services/Supplies: Certified by: Revised 9/18/2025(dwbRL10.15.25) FORT WORTH Small Business Utilization Form Page4of5 Address 6331 Southwest Blvd 1st El NCTRCA (including Benbrook Texas 76132 County): Tarrant County Phone: 817-738-3200 WBCS Email: grantges@burnsco.net NAICS Code: 237110 El DEW BC Contact Person: Ab GrantgeS $AMOUNT: 972,993.10 TXDOT Total Dollar Amount of Certified Prime Bidder/Offeror Services towards contract goal $ 1,537,410.60 Total Dollar Amount of Small Business Subcontractors/Suppliers $1,054,094.50 Total Dollar Amount of Non -Small Business Subcontractors/Suppliers $1,177,683.15 TOTAL DOLLAR AM OU NT OF PRIME/ALL SUBCONTRACTORS/SUPPLIERS $ 3,769,188.25 The Prime Bidder/Offeror wilt not make additions, deletions, or substitutions to this certified list without the prior approval of the City of Fort Worth.. Any unjustified change or deletion may be a material breach of contract. By affixing a signature to this form, the Prime Bidder/Offeror further agrees to provide, directly to the City upon request, complete and accurate information regarding actual work performed by all subcontractors. The Prime Bidder/Offeror also agrees to allow an audit and/or examination of any books, records and files held by their company. The Prime Bidder/Offeror agrees to allow interviews with owners, principals, officers, employees and applicable subcontractors/suppliers participating on the contract that will substantiate the actual work performed by the Small Business firms on this contract, by an authorized officer or employee of the City. A Prime Bidder/Offeror who intentionally and/or knowingly misrepresents material facts may be considered not to be a responsible bidder on futi,w id or rtunif.ew. Authorized Signature 04t1G-Z t�/C-t "N Title 9/18/2025(dwbRL10.15.25) Printed Signature Contact Name and Title (if different) Revised FORT WORTH Small Business Utilization Form Page5of5 Klutz Construction 817-561-5591 Company Name Phone Number P.O. BOx 185 Charlie@klutzconstruction.com Address Kennedale TX 76060 City/State/Zip Code 9/18/2025(dwbRL1 0.15.25) Email Address 3/26/26 Date Revised Small Business Enterprise (S•BE) Klutz Construction, LLC Klutz Construction, LLC has filed with the Agency an Affidavit as defined by NCTRCA Small Business Enterprise (SBE) Policies & Procedures and is hereby certified to provide service(s) in the following areas: NAICS 237310: CONCRETE PAVING (I.E., HIGHWAY, ROAD, STREET, PUBLIC SIDEWALK) NAICS 238110: FOOTING AND FOUNDATION CONCRETE CONTRACTORS NAICS 327331: CONCRETE BLOCK AND BRICK MANUFACTURING This Certification commences March 5, 2026 and supersedes any registration or listing previously issued. This certification must be updated every two years by submission of an Annual Update Affidavit. At any time there is a change in ownership, control of the firm or operation, notification must be made immediately to the North Central Texas Regional Certification Agency for eligibility evaluation. Certification Expiration: March 31, 2028 Issued Date: March 5, 2026 CERTIFICATION NO. PMSB67514N0328 Certification Administrator Small Business Enterprise (SBE) BOA G.J. Seeding, LLC G.J. Seeding, LLC has filed with the Agency an Affidavit as defined by NCTRCA Small Business Enterprise (SBE) Policies & Procedures and is hereby certified to provide service(s) in the following areas: NAICS 221310: WATER SUPPLY AND IRRIGATION SYSTEMS NAICS 236220: BROADCASTING STATION CONSTRUCTION NAICS 237110: IRRIGATION PROJECT CONSTRUCTION (EXCEPT LAWN) NAICS 423390: SILT FENCE AND OTHER FABRICS (E.G., FOR EROSION CONTROL) MERCHANT WHOLESALERS NAICS 561730: HYDROSEEDING SERVICES (E.G., DECORATIVE, EROSION CONTROL PURPOSES) NAICS 561730: LANDSCAPING SERVICES NAICS 561730: LAWN MULCHING SERVICES NAICS 561730: SOD LAYING SERVICES This Certification commences August 19, 2024 and supersedes any registration or listing previously issued. This certification must be updated every two years by submission of an Annual Update Affidavit. At any time there is a change in ownership, control of the firm or operation, notification must be made immediately to the North Central Texas Regional Certification Agency for eligibility evaluation. Certification Expiration: August 31, 2026 Issued Date: August 19, 2024 CERTIFICATION NO. HMSB84585N0826 Certification Administrator Small Business Enterprise (SBE) ),NCTRCA Cowtown Redi Mix, Inc. Cowtown Redi Mix, Inc. has filed with the Agency an Affidavit as defined by NCTRCA Small Business Enterprise (SBE) Policies & Procedures and is hereby certified to provide service(s) in the following areas: NAICS 327320: READY -MIX CONCRETE MANUFACTURING This Certification commences January 14, 2026 and supersedes any registration or listing previously issued. This certification must be updated every two years by submission of an Annual Update Affidavit. At any time there is a change in ownership, control of the firm or operation, notification must be made immediately to the North Central Texas Regional Certification Agency for eligibility evaluation. Certification Expiration: January 31, 2028 Issued Date: January 14, 2026 CERTIFICATION NO. WFSB17200N0128 Certification Administrator '5 Small Business Enterprise (SBE) NCTRCA Stabile & Winn, Inc. Stabile & Winn, Inc, has filed with the Agency an Affidavit as defined by NCTRCA Small Business Enterprise (SBE) Policies & Procedures and is hereby certified to provide service(s) in the following areas: NAICS 237310: HIGHWAY, STREET, AND BRIDGE CONSTRUCTION This Certification commences September 26, 2025 and supersedes any registration or listing previously issued. This certification must be updated every two years by submission of an Annual Update Affidavit. At any time there is a change in ownership, control of the firm or operation, notification must be made immediately to the North Central Texas Regional Certification Agency for eligibility evaluation. Certification Expiration: September 30, 2027 Issued Date: September 26, 2025 CERTIFICATION NO. WMSB81753N0927 Certification Administrator 00 52 43 - 1 Developer Awarded Project Agreement Page 1 of 4 1 SECTION 00 52 43 2 AGREEMENT 3 4 THIS AGREEMENT, authorized on 7/31/2026 is made by and between the Developer, 5 GRBK Edgewood LLC., authorized to do business in Texas ("Developer") , and Klutz 6 Construction LLC. authorized to do business in Texas, acting by and through its duly authorized 7 representative, ("Contractor"). 8 Developer and Contractor, in consideration of the mutual covenants hereinafter set forth, agree as 9 follows: 10 Article 1. WORK 11 Contractor shall complete all Work as specified or indicated in the Contract Documents for the 12 Project identified herein. 13 Article 2. PROJECT 14 The project for which the Work under the Contract Documents may be the whole or only a part is 15 generally described as follows: 16 Cibolo Hills Parkway 17 City Project No. 106104 18 Article 3. CONTRACT PRICE 19 Developer agrees to pay Contractor for performance of the Work in accordance with the Contract 20 Documents an amount in current funds of _Three Million, Seven Hundred Sixty -Nine Thousand, 21 One Hundred Eighty -Eight Dollars and Twenty -Five Cents ($3, 769,188.25). 22 Article 4. CONTRACT TIME 23 4.1 Final Acceptance. 24 The Work will be complete for Final Acceptance within 240 working days after the 25 date when the Contract Time commences to run as provided in Paragraph 12.04 of the 26 Standard City Conditions of the Construction Contract for Developer Awarded Projects. 27 4.2 Liquidated damages 28 Contractor recognizes that time is of the essence of this Agreement and that Developer 29 will suffer financial loss if the Work is not completed within the times specified in 30 Paragraph 4.1 above, plus any extension thereof allowed in accordance with Article 10 of 31 the Standard City Conditions of the Construction Contract for Developer Awarded 32 Projects. The Contractor also recognizes the delays, expense and difficulties involved in 33 proving in a legal proceeding the actual loss suffered by the Developer if the Work is not 34 completed on time. Accordingly, instead of requiring any such proof, Contractor agrees 35 that as liquidated damages for delay (but not as a penalty), Contractor shall pay 36 Developer five hundred Dollars ($500.00) for each day that expires after the time 37 specified in Paragraph 4.1 for Final Acceptance until the City issues the Final Letter of 38 Acceptance. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No 106104 Revised September 1,2025 005243-2 Developer Awarded Project Agreement Page 2 of 4 39 Article 5. CONTRACT DOCUMENTS 40 5.1 CONTENTS: 41 A. The Contract Documents which comprise the entire agreement between Developer and 42 Contractor concerning the Work consist of the following: 43 1. This Agreement. 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 2. Attachments to this Agreement: a. Bid Form (DAP Version) 1) Proposal Form (DAP Version) 2) Vendor Compliance to State Law Non -Resident Bidder 3) Prequalification Statement 4) State and Federal documents (project specific) b. Current Prevailing Wage Rate Table c. Insurance Certification Form (ACORD) d. Payment Bond (DAP Version) e. Performance Bond (DAP Version) f. Maintenance Bond (DAP Version) g. Power of Attorney for the Bonds h. Worker's Compensation Affidavit i. SBE Small Business Utilization Form 3. Standard City Conditions of the Construction Contract for Developer Awarded Projects. 4. Supplementary Conditions. 5. Specifications specifically made a part of the Contract Documents by attachment or, if not attached, as incorporated by reference and described in the Table of Contents of the Project's Contract Documents. 6. Drawings. 7. Addenda. 8. Documentation submitted by Contractor prior to Notice of Award. 9. The following which may be delivered or issued after the Effective Date of the Agreement and, if issued, become an incorporated part of the Contract Documents: a. Notice to Proceed. b. Field Orders. c. Change Orders. d. Letter of Final Acceptance. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No 106104 Revised September 1,2025 005243-3 Developer Awarded Project Agreement Page 3 of 4 75 Article 6. INDEMNIFICATION 76 6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own 77 expense, the city, its officers, servants and employees, from and against any and all 78 claims arising out of, or alleged to arise out of, the work and services to be performed 79 by the contractor, its officers, agents, employees, subcontractors, licenses or invitees 80 under this contract. This indemnification provision is specifically intended to operate 81 and be effective even if it is alleged or proven that all or some of the damages being 82 sought were caused, in whole or in part, by any act, omission or negligence of the city. 83 This indemnity provision is intended to include, without limitation, indemnity for 84 costs, expenses and legal fees incurred by the city in defending against such claims and 85 causes of actions. 86 87 6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense, 88 the city, its officers, servants and employees, from and against any and all loss, damage 89 or destruction of property of the city, arising out of, or alleged to arise out of, the work 90 and services to be performed by the contractor, its officers, agents, employees, 91 subcontractors, licensees or invitees under this contract. This indemnification 92 provision is specifically intended to operate and be effective even if it is alleged or 93 proven that all or some of the damages being sought were caused, in whole or in part, 94 by any act. omission or negligence of the city. 95 96 Article 7. MISCELLANEOUS 97 7.1 Terms. 98 Terms used in this Agreement are defined in Article 1 of the Standard City Conditions of 99 the Construction Contract for Developer Awarded Projects. 100 7.2 Assignment of Contract. 101 This Agreement, including all of the Contract Documents may not be assigned by the 102 Contractor without the advanced express written consent of the Developer. 103 7.3 Successors and Assigns. 104 Developer and Contractor each binds itself, its partners, successors, assigns and legal 105 representatives to the other party hereto, in respect to all covenants, agreements and 106 obligations contained in the Contract Documents. 107 7.4 Severability. 108 Any provision or part of the Contract Documents held to be unconstitutional, void or 109 unenforceable by a court of competent jurisdiction shall be deemed stricken, and all 110 remaining provisions shall continue to be valid and binding upon DEVELOPER and 111 CONTRACTOR. 112 7.5 Governing Law and Venue. 113 This Agreement, including all of the Contract Documents is performable in the State of 114 Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the 115 Northern District of Texas, Fort Worth Division. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No 106104 Revised September 1,2025 Docusign Envelope ID: C4A00FC8-9609-8D60-83F3-B4B2CCA7EB65 005243-4 Developer Awarded Project Agreement Page 4of4 116 117 7.6 Authority to Sign. 118 Contractor shall attach evidence of authority to sign Agreement, if other than duly 119 authorized signatory of the Contractor. 120 121 122 123 IN WITNESS WHEREOF, Developer and Contractor have executed this Agreement in multiple 124 counterparts. 125 126 This Agreement is effective as of the last date signed by the Parties ("Effective Date"). 127 128 ContractQr: /L,L iPT 1 / It.t, er g (.LC. WM�M1 (Signature) (Printed Name) Developer: GRBK Edgewood LLC. Signed by: �� By: Qa,V " Lo{At1A Vlt. ignature) Aaron Guthrie (Printed Name) Title: H A�TI,4L'1 +�aa Title: Authorized Signer Company Name: / J_ L- C-1JS + ' 1p- Company name: GRBK Edgewood LLC. Address: Address: 9D_- 7-_. 5501 Headquarters Drive, Suite 300W City/State/Zip: a%� '��j7-� 74& City/State/Zip: Plan, TX 75024 7&L ' 31 �. Date 7/31/2026 112:14 PM CDT Datc CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No 106104 Revised September 1,2025 006213-1 PERFORMANCE BOND Page I o!'2 Bond No. K42081814 1 SECTION 00 62 13 2 PERFORMANCE BOND 3 4 THE STATE OF TEXAS § 5 § KNOW ALL BY THESE PRESENTS: 6 COUNTY OF TARRANT § 7 That we, Klutz Construction, LLC , known as "Principal" herein and 8 Vigilant Insurance Company , a corporate surety(sureties, if 9 more than one) duly authorized to do business in the State of Texas, known as "Surety" herein 10 (whether one or more), are held and firmly bound unto the Developer, GRBK Edgewood LLC. 11 authorized to do business in Texas ("Developer") and the City of Fort Worth, a Texas municipal 12 corporation ("City"), in the penal sum of, Three Million, Seven Hundred Sixty -Nine Thousand, One 13 Hundred Eighty -Eight Dollars & Twenty -Five Cents Dollars ($3,769,188.25), lawful money of the 14 United States, to be paid in Fort Worth, Tarrant County, Texas for the payment of which sum well 15 and truly to be made jointly unto the Developer and the City as dual obligees, we bind ourselves, 16 our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these 17 presents. 18 WHEREAS, Developer and City have entered into an Agreement for the construction of 19 community facilities in the City of Fort Worth by and through a Community Facilities Agreement, 20 CFA25-056; and 21 WHEREAS, the Principal has entered into a certain written contract with the Developer awarded 22 the 31St day of July , 2026 , which Contract is hereby referred to and made a part 23 hereof for all purposes as if fully set forth herein, to furnish all materials, equipment labor and other 24 accessories defined by law, in the prosecution of the Work, including any Change Orders, as 25 provided for in said Contract designated as Cibolo I -fills Parkway — Water, Paving & Drainage 26 Improvements. 27 NOW, THEREFORE, the condition of this obligation is such that if the said Principal 28 shall faithfully perform it obligations under the Contract and shall in all respects duly and faithfully 29 perform the Work, including Change Orders, under the Contract, according to the plans, 30 specifications, and contract documents therein referred to, and as well during any period of 31 extension of the Contract that may be granted on the part of the Developer and/or City, then this 32 obligation shall be and become null and void, otherwise to remain in full force and effect. CITY OF FORT WORTI I Cibolo Hills Parkway STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised January 31, 2012 006213-2 PERFORMANCE BOND Page 2 of 2 Bond No. K42081814 PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in 2 Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort 3 Worth Division. 4 6 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 This bond is made and executed in compliance with the provisions of Chapter 2253 of the Texas Government Code, as amended, and all liabilities on this bond shall be determined in accordance with the provisions of said statue. IN WITNESS WHEREOF, the Principal and the Surety have SIGNED and SEALED this instrument by duly authorized agents and officers on this the31 Stday of July , 20 26 . Witness as to Principal ness as Surety Jennifer L. Alt PRINCIPAL: KLUTZ NST UC 1ON LLC BY: 4'/J Signature Charles M. Klutz, Managing Partner Name and Title Address: P.O. Box 185 Kennedale, TX 76060 SURETY: VIGILANT INSURANCE COMPANY Elizabeth Gray, Attorney -in -Fact Name and Title Address: 5400 LBJ Frwy, Suite 600 Dallas, TX 75240 Telephone Number: 214-754-0777 *Note: If signed by an officer of the Surety Company, there must be on file a certified extract from the by-laws showing that this person has authority to sign such obligation. If Surety's physical address is different from its mailing address, both must be provided. The date of the bond shall not be prior to the date the Contract is awarded. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CITY CONDITIONS -- DEVELOPER AWARDED PROJECTS City Proiect No. 106104 Revised January 31. 2012 0062 14- 1 PAYMENT BOND Page 1 oF2 Bond No. K42081814 I SECTION 00 62 14 2 PAYMENT BOND 3 4 THE STATE OF TEXAS § 5 § KNOW ALL BY THESE PRESENTS: 6 COUNTY OF TARRANT § 7 That we, Klutz Construction, LLC , known as "Principal" 8 herein, and Vigilant Insurance Company , a corporate surety ( or 9 sureties if more than one), duly authorized to do business in the State of Texas, known as "Surety" 10 herein (whether one or more), are held and firmly bound unto the Developer, GRBK Edgewood LLC. II authorized to do business in Texas "(Developer"), and the City of Fort Worth, a Texas municipal 12 corporation ("City"), in the penal sum of Three Million. Seven Hundred Sixty -Nine Thousand, One 13 Hundred Eighty -Eight Dollars & Twenty -Five Cents Dollars ($3,769,188.25), lawful money of the 14 United States, to be paid in Fort Worth, Tarrant County, Texas, for the payment of which sum well 15 and truly be made jointly unto the Developer and the City as dual obligees, we bind ourselves, our 16 heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these 17 presents: 18 WHEREAS, Developer and City have entered into an Agreement for the construction of 9 community facilities in the City of Fort Worth, by and through a Community Facilities Agreement, 20 CFA25-0056; and 21 WHEREAS, Principal has entered into a certain written Contract with Developer, awarded 22 the 31st day of July ., 2026, which Contract is hereby referred to and made a 23 part hereof for all purposes as if fully set forth herein, to furnish all materials, equipment, labor and 24 other accessories as defined by law, in the prosecution of the Work as provided for in said Contract 25 and designated as Cibolo Hills Parkway — Water, Paving & Drainage Improvements. 26 NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if Principal 27 shall pay all monies owing to any (and all) payment bond beneficiary (as defined in Chapter 2253 of 28 the Texas Government Code, as amended) in the prosecution of the Work under the Contract, then 29 this obligation shall be and become null and void; otherwise to remain in full force and effect. 30 This bond is made and executed in compliance with the provisions of Chapter 2253 of the 31 Texas Government Code, as amended, and all liabilities on this bond shall be determined in 32 accordance with the provisions of said statute. CITY OF FORT WORTH Cibolo Bills Parkway STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS City Project No, 106104 Revised January 31, 2012 006214-2 PAYMENT BOND Page 2 of 2 Bond No. K42081814 IN WITNESS WHEREOF, the Principal and Surety have each SIGNED and SEALED this instrument by duly authorized agents and officers on this the31 Stday of July , 2026 4 5 6 7 9 ATTEST: ATTEST: r' Rapeac. RD 3w i,dells. Assistant Secretary (Surety) Secretary Rupert HD Swindells WVI tness a to Surety Jennifer L. Alt riii.jr; Charles M. Klutz, lvlanagina Partner Name and Title Address: P.O. Box 185 Kennedale, TX 76060 SURETY: VIGILANT INSURANCE COMPANY Elizabeth Gray, Attorney -in -Fact Name and Title Address: 5400 LBJ Frwy, Suite 5400 Dallas, TX 752440 Telephone Number: 214-754-0777 Note: If signed by an officer of the Surety, there must be on file a certified extract from the bylaws showing that this person has authority to sign such obligation. If Surety's physical address is different from its mailing address, both must be provided. The date of the bond shall not be prior to the date the Contract is awarded. 10 END OF SECTION CITY OF FORT WCR.TH STANDARD CITY i" ONDFI IONS — DEVELOPER AWARDED PROJECTS Revised Jaiiiar•, 31. 2012 Cibulo Hills Parkway City Project No. 106104 006219-1 MAINTENANCE BOND Page 1 of 3 Bond No. K42081814 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 SECTION 00 62 19 MAINTENANCE BOND THE STATE OF TEXAS § § KNOW ALL BY THESE PRESENTS: COUNTY OF TARRANT § That we Klutz Construction, LLC , known as "Principal" herein and Vigilant Insurance Company , a corporate surety (sureties, if more than one) duly authorized to do business in the State of Texas, known as "Surety" herein (whether one or more), are held and firmly bound unto the Developer, GRBK Edgewood LLC. authorized to do business in Texas ("Developer") and the City of Fort Worth, a Texas municipal corporation ("City"), in the sum of Three Million, Seven I lundred Sixty -Nine Thousand, One Hundred Eighty - Eight Dollars & Twenty -Five Cents Dollars ($3,769,188.25), lawful money of the United States, to be paid in Fort Worth, Tarrant County, Texas, for payment of which sum well and truly be made jointly unto the Developer and the City as dual obligees and their successors, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents. WHEREAS, Developer and City have entered into an Agreement for the construction of community facilities in the City of Fort Worth by and through a Community Facilities Agreement, CFA25-0056; and WHEREAS, the Principal has entered into a certain written contract with the Developer awarded the 31St day of July , 2026, which Contract is hereby referred to and a made part hereof for all purposes as if fully set forth herein, to furnish all materials, equipment labor and other accessories as defined by law, in the prosecution of the Work, including any Work resulting from a duly authorized Change Order (collectively herein, the "Work") as provided for in said Contract and designated as Cibolo Hills Parkway — Water, Paving & Drainage Improvements.; and WHEREAS, Principal binds itself to use such materials and to so construct the Work in accordance with the plans, specifications and Contract Documents that the Work is and will remain free from defects in materials or workmanship for and during the period of two (2) years after the date of Final Acceptance of the Work by the City ("Maintenance Period"); and CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised January 31, 2012 Cibolo I -tills Parkway City Project No. 106104 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 006219-2 MAINTENANCE BOND Page 2 of 3 Bond No. K42081814 WHEREAS, Principal binds itself to repair or reconstruct the Work in whole or in part upon receiving notice from the Developer and/or City of the need thereof at any time within the Maintenance Period. NOW THEREFORE, the condition of this obligation is such that if Principal shall remedy any defective Work, for which timely notice was provided by Developer or City, to a completion satisfactory to the City, then this obligation shall become null and void; otherwise to remain in full force and effect. PROVIDED, HOWEVER, if Principal shall fail so to repair or reconstruct any timely noticed defective Work, it is agreed that the Developer or City may cause any and all such defective Work to be repaired and/or reconstructed with all associated costs thereof being borne by the Principal and the Surety under this Maintenance Bond; and PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort Worth Division; and PROVIDED FURTHER, that this obligation shall be continuous in nature and successive recoveries may be had hereon for successive breaches. CITY OF FORT WORTI-I STANDARD CITY CONDITIONS - DEVELOPER AWARDED PROJECTS Revised January 31, 2012 Cibolo Ilills Parkway City Project No. 106104 006219-3 MAINTENANCE BOND Page 3 of 3 Bond No. K42081814 2 4 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 IN WITNESS WHEREOF, the Principal and the Surety have each SIGNED and SEALED this instrument by duly authorized agents and officers on this the31 Stday of July , 2026. ATTEST: (P c al tart' '(t'7Z/&" Witness as to Principal ATTEST: Rupen RD istaer iecretrg (Surety) Secretary Rupert HD Swindells i ess as Surety Jennifer L. Alt PRINCIPAL: KLUTZ T N LL BY: Signature Charles M. Klutz, Managing Partner Name and Title Address: P.O. Box 185 Kennedale, TX 76060 SURETY: VIGILANT INSURANCE COMPANY s:..�.. �.i►, LPL �� Elizabeth Gray, Attorney -in -Fact Name and Title Address: 5400 LBJ Frwy, Suite 600 Dallas, TX 75240 Telephone Number: 214-754-0777 *Note: If signed by an officer of the Surety Company, there must be on file a certified extract from the by-laws showing that this person has authority to sign such obligation. If Surety's physical address is different from its mailing address, both must be provided. The date of the bond shall not be prior to the date the Contract is awarded. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised January 31.2012 C4uolo Hills Parkway City Project No. 106104 Policyholder information Notice IMPORTANT NOTICE To obtain information or make a complaint: You may call Chubb's toll -free telephone number for information or to make a complaint at 1-800-36-CHUBB You may contact the Texas Department of Insurance to obtain information on companies, coverages, rights or complaints at 1-800-252-3439 You may write the Texas Department of Insurance P.O. Box 149104 Austin, TX 78714-9104 FAX # (512) 475-1771. Web: http://www.tdi.state.tx.us E-mail: ConsumerProtection@tdi.state.tx.us PREMIUM OR CLAIM DISPUTES: Should you have a dispute concerning your premium or about a claim you should contact the agent first. If the dispute is not resolved, you may contact the Texas Department of Insurance. ATTACH THIS NOTICE TO YOUR POLICY: This notice is for information only and does not become a part or condition of the attached document. AVISO IMPORTANTE Para obtener informacion o para someter una queja: Usted puede llamar al numero de telefono gratis de Chubb's para informacion o para someter una queja al 1-800-36-CHUBB Puede comunicarse con el Departamento de Seguros de Texas para obtener informacion acerca de companies, coberturas, derechos o quejas al 1-800-252-3439 Puede escribir al Departamento de Seguros de Texas P.O. Box 1491.04 Austin, TX 78714-9104 FAX # (512) 475-1771 Web: http://www.tdi.state.tx.us E-mail: ConsumerProtection@tdi.state.tx.us DISPUTAS SOBRE PRIMAS 0 RECLAMOS: Si tiene una disputa concerniente a su prima o a un reclamo, debe comunicarse con el agente primero. Si no se resueve la disputa, puede entonces comunicarse con el departamento (TDI). UNA ESTE AV1SO A SU POLIZA: Este aviso es solo para prop6sito de informacion y no se convierte en parte o condition del documento adj unto. Form 99-10-0299 (Rev. 1-08) CHUBB Power of Attorney Federal Insurance Company I Vigilant Insurance Company I Pacific Indemnity Company Westchester Fire Insurance Company I ACE American Insurance Company Know All byThese Presents, that FEDERAL INSURANCE COMPANY, an Indiana corporation, VIGILANT INSURANCE COMPANY, a New York corporation. PACIFIC INDEMNITY COMPANY, a Delaware corporation, WESTCHIISrPR FIRE INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY corporations or the Commonwealth of Pennsylvania, doeach hereby constitute and appoint. Charles D. Sweeney, David W, Sweeney, Elizabeth Gray, Kyle W. Sweeney, and Michael A. Sweeney of FortWorth, Texas - -w- - - - -- - -- ---- --- ---_ --------------------------------------------------------------- each as their true and lawful Attorney-iu-Fact to execute under such designation In their names and to affix their corporate seals to and deliver for and on their behalf as surety thereon or otherwise, bonds anti undertakings and other writings obligatory hl the nature thereof (other than ball bonds) given or executed in the course of business, and any Instruments amending or altering the same, and consents to the modification or alteration of any Instrument referred to to said bonds or obligations. In Witness Whereof, said FEDERAL INSURANCE COMPANY, VIGILANT INSURANCE COMPANY, PACIFIC INDEMNITY COMPANY, WESTCHESTER FIRE INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY have each executed and attested these presents and affixed their corporate seals on this 24" day of October , 2025. Rupert HD Swtndeol}s, Assistant Secretary �F�• •r'lWttl� �y r STATE OF NEW JERSEY County of Hunterdon Stephcin M. Haney. Vice President H+' � ✓� max/ [v��'J�{ On this 24'x' day ofOctober, 2025 before me, a Notary Public of New Jersey, personallycame Rupert HD Swindells and Stephen M. Haney, to me known to be Assistant Secretaryand Voce President, respectively, of FEDERAL TNSU RANCE COMPANY, VIGII..AN'i' INSURANCE COM PANY, PACIFIC INDEMN I'TY COMPANY. WESTCHESTER FIRE INSU RA.NCE COMPANY and ACE AMERICAN INSURANCE COMPANY. the companies which executed the foregoing Power of Attorney, and die said Rupert HD Swindells and Stephen in. i laney, being by me duly sworn, severally and each for himself did depose and say that they are Assistant Secretary and Vice President, respectively, of FEDERAL, INSURANCE COMPANY, VIGILANT INSURANCE COMPANY, PACIFIC INDEMNITY COMPANY, WESTCHESTER FIRE INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY and know the corporate seals thereof, that the seals affixed to the foregoing Power of Attorney are such corporate seals and were thereto affixed by authority of Said Companies, and that their signatures as such officers were duty affixed and subscribed by like authority. Notarial Seal to Y J Inuit e W)TARY 1r(}B�iC Orr NEW jUW y 7Atty z No. 54175200 %y ••^" '' Aaa c C4�Alt1KSIClt�1 EXPW$ OCT IS, XW Notary Public CERTIFICATION Resolutions adopted by the Boards of Directors of FEDERAL INSURANCE COMPANY, VIGILANT INSURANCE COMPANY, and PACIFIC INDEMNITY COMPANY on August 30, 2016; WESTCHESTER FIRE INSURANCE COMPANY on December 11, 2006; and ACE AMERICAN INSURANCE COMPANY on March 20, 2009: "RESOLVED. that the following autliori7atons relateto the execution, for and on beihalfof the Company, of bonds, underhaldtigs, recognliances. cotnracis and otter written commitments of the Qtupany entered into ht the ordinary course of bttsbhess leach a "Written Conimltmenf'h (1) Each of the Chairman. die President and doe Vice Presidents or the Company is hereby authorized to execute any Written Commitment forand on behalf of the Company. under the seal of the Coinpatw or otherwise. (2) L'achdulyapprhtntedartorney-in-facroftheCompanyls herebyattdtorizedtoexecutemyWrittenCutnniimtentforandonbehalfoftheCoutp;the.underthesealofdteCompanyorotherwise. to the extent that such action Is authorized by diegnitit of powers prat-ided I'orin such person's written appointment as such atrorney-in-fact. (3) Each of cite CAhalrtnatt. die President anti the Vice Presidents of the Company is hereby authorized. torarid on behaifof the compahny, to appoint in writing any person the attorney in -tact of the Corupauy with full power and authority to execute, for and on behalf of the Company. tinder rite seal of the Company or otherwise, such Written Connuitnients or the Company as may be speciled in such written appoIinitent, which specification may be by general type or class of Written Conmittnents or by specification of one or note particular Written Cotnutitnrethts. (4) Each of the Chairman, die President and the Vice Presidents of the Company is hereby authorized. for and on behalf of die Company. to delegate in writing to any other officer of the Company' the authority to execute, ibr and on behalf of die Company. under the Company's seal or otherwise. such Written commitments of the Company as are specified in such written delegation. which speciecaton may be by general type or class of Written Cmtnhdunents or byspecificationafoncormote particularWrhtencotttnimhcnts. (5) The signature of any olllcerorotherperson executmgany Written Commitment orappohinneut or delegallon pursuant to this Resolution, and the seat of the Company. may be affixed by facsimile on such Written Coniminnent or written appornunent or delegation. FUR'f}lERRSSOLVED, that the foregoing Resolution shaft not be deemed to beanecdusivestatementofthepowersandauthorityofoRcers.emplocetsandothe'personstoaccforandonbehalfofthe Companyamid such Resolution shall not limitor otherwise a4'ect rite exercise ofauyssich power orautiority otherwise tautly gmnlel or vested: 1. Rupert HD Swindells, Assistant' Secretary of FEDERAL INSURANCE COMPANY, VIGILANT INSURANCE COMPANY, PACIFIC INDEMNITY COMPANY, WESTCHESTER FIRE INSURANCE COMPANY and -ACE AMERICAN INSURANCE COMPANY (the "Companies) do hereby certiljt that (0 the l'aregobhg Resolutions adopted by the Board of Directors of the Companies are true, correct and in lull force;md effect, (if) the foregoing Power ofAttorney is true, correct and In full force and effect. Given under my hand and seals ol'safd Companies at Whitehouse Station, NJ, this 31 st day of July, 2026 RRupeFt Fin Stviadelis. Assistant Secretary IN THE EVENT YOI.' WISH TOVERIFYTHEA(1'i-lE,NTICrrYOFTHISBONDORNOT)FYISOFANYOTHFRMArrtiR.PLEASE00-%rACTISAT., ^^� Telepitorie(908)903-3453 Fax(908)9t13.3656 coned• suretydfihubbcrom Combined: FED-VIG-PI-WFIC-AAIC (rev- 11-19) STANDARD CITY CONDITIONS OF THE CONSTRUCTION CONTRACT FOR DEVELOPER AWARDED PROJECTS CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 STANDARD CITY CONDITIONS OF THE CONSTRUCTION CONTRACT FOR DEVELOPER AWARDED PROJECTS TABLE OF CONTENTS Page Article 1 — Definitions and Terminology.......................................................................................................... l 1.01 Defined Terms...............................................................................................................................1 1.02 Terminology.................................................................................................................................. 5 Article2 — Preliminary Matters......................................................................................................................... 6 2.01 Before Starting Construction........................................................................................................6 2.02 Preconstruction Conference.......................................................................................................... 6 2.03 Public Meeting.............................................................................................................................. 6 Article 3 — Contract Documents and Amending............................................................................................... 6 3.01 Reference Standards..................................................................................................................... 6 3.02 Amending and Supplementing Contract Documents.................................................................. 6 Article 4 — Bonds and Insurance....................................................................................................................... 7 4.01 Licensed Sureties and Insurers..................................................................................................... 7 4.02 Performance, Payment, and Maintenance Bonds........................................................................ 7 4.03 Certificates of Insurance............................................................................................................... 7 4.04 Contractor's Insurance.................................................................................................................. 9 4.05 Acceptance of Bonds and Insurance; Option to Replace...........................................................12 Article 5 — Contractor's Responsibilities........................................................................................................12 5.01 Supervision and Superintendent.................................................................................................12 5.02 Labor; Working Hours................................................................................................................13 5.03 Services, Materials, and Equipment...........................................................................................13 5.04 Project Schedule..........................................................................................................................14 5.05 Substitutes and "Or-Equals".......................................................................................................14 5.06 Pre -Qualification of Bidders (Prime Contractors and Subcontractors) .....................................16 5.07 Concerning Subcontractors, Suppliers, and Others...................................................................16 5.08 Wage Rates..................................................................................................................................18 5.09 Patent Fees and Royalties...........................................................................................................19 5.10 Laws and Regulations.................................................................................................................19 5.11 Use of Site and Other Areas.......................................................................................................19 5.12 Record Documents...................................................................................................................... 20 5.13 Safety and Protection.................................................................................................................. 21 5.14 Safety Representative.................................................................................................................21 5.15 Hazard Communication Programs.............................................................................................22 5.16 Submittals.................................................................................................................................... 22 5.17 Contractor's General Warranty and Guarantee..........................................................................23 CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 5.18 Indemnification........................................................................................................................... 24 5.19 Delegation of Professional Design Services.............................................................................. 24 5.20 Right to Audit:............................................................................................................................25 5.21 Nondiscrimination....................................................................................................................... 25 Article 6 — Other Work at the Site...................................................................................................................26 6.01 Related Work at Site................................................................................................................... 26 Article 7 — City's Responsibilities...................................................................................................................26 7.01 Inspections, Tests, and Approvals.............................................................................................. 26 7.02 Limitations on City's Responsibilities....................................................................................... 26 7.03 Compliance with Safety Program...............................................................................................27 Article 8 — City's Observation Status During Construction...........................................................................27 8.01 City's Project Representative.....................................................................................................27 8.02 Authorized Variations in Work.................................................................................................. 27 8.03 Rejecting Defective Work..........................................................................................................27 8.04 Determinations for Work Performed..........................................................................................28 Article9 —Changes in the Work.....................................................................................................................28 9.01 Authorized Changes in the Work............................................................................................... 28 9.02 Notification to Surety..................................................................................................................28 Article 10 — Change of Contract Price; Change of Contract Time................................................................28 10.01 Change of Contract Price............................................................................................................28 10.02 Change of Contract Time............................................................................................................28 10.03 Delays.......................................................................................................................................... 28 Article 11 — Tests and Inspections; Correction, Removal or Acceptance of Defective Work......................29 11.01 Notice of Defects........................................................................................................................ 29 11.02 Access to Work...........................................................................................................................29 11.03 Tests and Inspections.................................................................................................................. 29 11.04 Uncovering Work.......................................................................................................................30 11.05 City May Stop the Work.............................................................................................................30 11.06 Correction or Removal of Defective Work................................................................................30 11.07 Correction Period........................................................................................................................ 30 11.08 City May Correct Defective Work............................................................................................. 31 Article12 — Completion.................................................................................................................................. 32 12.01 Contractor's Warranty of Title................................................................................................... 32 12.02 Partial Utilization........................................................................................................................ 32 12.03 Final Inspection........................................................................................................................... 32 12.04 Final Acceptance......................................................................................................................... 33 Article 13 — Suspension of Work.................................................................................................................... 33 13.01 City May Suspend Work............................................................................................................ 33 Article 14 — Miscellaneous ..................................... 14.01 Giving Notice..................................... CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ....................... 34 ....................... 34 14.02 Computation of Times................................................................................................................ 34 14.03 Cumulative Remedies................................................................................................................. 34 14.04 Survival of Obligations.. 14.05 Headings ......................... CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ............... 35 ............... 35 00 73 10- 1 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 1 of 35 ARTICLE 1- DEFINITIONS AND TERMINOLOGY 1.01 Defined Terms A. Wherever used in these General Conditions or in other Contract Documents, the terms listed below have the meanings indicated which are applicable to both the singular and plural thereof, and words denoting gender shall include the masculine, feminine and neuter. Said terms are generally capitalized or written in italics, but not always. When used in a context consistent with the defmition of a listed -defined term, the term shall have a meaning as defined below whether capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms. 1. Agreement - The written instrument which is evidence of the agreement between Developer and Contractor covering the Work 2. Asbestos —Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States Occupational Safety and Health Administration. 3. Business Day — A business day is defined as a day that the City conducts normal business, generally Monday through Friday, except for federal or state holidays observed by the City. 4. Buzzsaw — City's on-line, electronic document management and collaboration system. 5. Calendar Day — A day consisting of 24 hours measured from midnight to the next midnight. 6. City— The City of Fort Worth, Texas, a Texas home -rule municipal corporation, acting by, its governing body through its City Manager, his designee, or agents authorized pursuant to its duly authorized charter on his behalf. 7. Community Facilities Agreement (CFA) —A Contract between the Developer and the City for the Construction of one or more following public facilities within the City public right-of- way or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs. A CFA may include private facilities within the right-of-way dedicated as private right-of- way or easement on a recorded plat. 8. Contract —The entire and integrated written document incorporating the Contract Documents between the Developer, Contractor, and/or City concerning the Work. The Contract supersedes prior negotiations, representations, or agreements, whether written or oral. 9. Contract Documents —Those items that make up the contract and which must include the Agreement, and it's attachments such as standard construction specifications, standard City Conditions, other general conditions of the Developer, including: a. An Agreement CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 007310-2 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 2 of 35 b. Attachments to the Agreement i. Bid Form ii. Vendor Compliance with State Law Non -Resident Bidder iii. Prequalification Statement c. Current Prevailing Wage Rates Table (if required by City) d. Insurance Accord Form e. Payment Bond f. Performance Bond g. Maintenance Bond h. Power of Attorney for Bonds i. Workers Compensation Affidavit j. MWBE Commitment Form( If required by City) k. General Conditions 1. Supplementary Conditions m. The Standard City Conditions n. Specifications specifically made part of the Contract Documents by attachment, if not attached, as incorporated by reference and described in the Table of Contents of the Project's Contract Documents o. Drawings p. Documentation submitted by contractor prior to Notice of Award. q. The following which may be delivered or issued after the effective date if the Agreement and, if issued become an incorporated part of the Contract Documents i. Notice to Proceed ii. Field Orders iii. Change Orders iv. Letters of Final Acceptance r. Approved Submittals, other Contractor submittals, and the reports and drawings of subsurface and physical conditions are not Contract Documents. 10. Contractor —The individual or entity with whom Developer has entered into the Agreement. 11. Day or day — A day, unless otherwise defined, shall mean a Calendar Day. 12. Developer — An individual or entity that desires to make certain improvements within the City of Fort Worth 13. Drawings —That part of the Contract Documents prepared or approved by Engineer which graphically shows the scope, extent, and character of the Work to be performed by Contractor. Submittals are not Drawings as so defined. 14. Engineer —The licensed professional engineer or engineering firm registered in the State of Texas performing professional services for the Developer. 15. Final Acceptance — The written notice given by the City to the Developer and/or Contractor that the Work specified in the Contract Documents has been completed to the satisfaction of the City. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 007310-3 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 3 of 35 16. Final Inspection — Inspection carried out by the City to verify that the Contractor has completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in conformance with the Contract Documents. 17. General Requirements —A part of the Contract Documents between the Developer and a Contractor. 18. Laws and Regulations Any and all applicable laws, rules, regulations, ordinances, codes, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction. 19. Liens —Charges, security interests, or encumbrances upon Project funds, real property, or personal property. 20. Milestone —A principal event specified in the Contract Documents relating to an intermediate Contract Time prior to Final Acceptance of the Work. 21. Non -Participating Change Order —A document, which is prepared for and reviewed by the City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. 22. Participating Change Order —A document, which is prepared for and approved by the City, which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. 23. Plans — See definition of Drawings. 24. Project Schedule —A schedule, prepared and maintained by Contractor, in accordance with the General Requirements, describing the sequence and duration of the activities comprising the Contractor's plan to accomplish the Work within the Contract Time. 25. Project —The Work to be performed under the Contract Documents. 26. Project Representative —The authorized representative of the City who will be assigned to the Site. 27. Public Meeting — An announced meeting conducted by the Developer to facilitate public participation and to assist the public in gaining an informed view of the Project. 28. Regular Working Hours — Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday thru Friday (excluding legal holidays). 29. Samples Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the Work will be judged. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 007310-4 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 4 of 35 30. Schedule of Submittals —A schedule, prepared and maintained by Contractor, of required submittals and the time requirements to support scheduled performance of related construction activities. 31. Site —Lands or areas indicated in the Contract Documents as being furnished by City or Developer upon which the Work is to be performed, including rights -of -way, permits, and easements for access thereto, and such other lands furnished by City or Developer which are designated for the use of Contractor. 32. Specifications —That part of the Contract Documents consisting of written requirements for materials, equipment, systems, standards and workmanship as applied to the Work, and certain administrative requirements and procedural matters applicable thereto. Specifications may be specifically made a part of the Contract Documents by attachment or, if not attached, may be incorporated by reference as indicated in the Table of Contents (Division 00 00 00) of each Project. 33. Standard City Conditions — That part of the Contract Documents setting forth requirements of the City. 34. Subcontractor An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of a part of the Work at the Site. 35. Submittals All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the Work. 36. Superintendent — The representative of the Contractor who is available at all times and able to receive instructions from the City and/or Developer and to act for the Contractor. 37. Supplementary Conditions —That part of the Contract Documents which amends or supplements the General Conditions. 38. Supplier —A manufacturer, fabricator, supplier, distributor, materialman, or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by Contractor or Subcontractor. 39. Underground Facilities All underground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including but not limited to, those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems. 40. Weekend Working Hours — Hours beginning at 9:00 a.m. and ending at 5: 00 p.m., Saturday, Sunday or legal holiday, as approved in advance by the City. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 007310-5 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 5 of 35 41. Work —The entire construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction including any Participating Change Order, Non -Participating Change Order, or Field Order, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by the Contract Documents. 42. Working Day — A working day is defined as a day, not including Saturdays, Sundays, or legal holidays authorized by the City for contract purposes, in which weather or other conditions not under the control of the Contractor will permit the performance of the principal unit of work underway for a continuous period of not less than 7 hours between 7 a.m. and 6p.m. m. 1.02 Terminology A. The words and terms discussed in Paragraph 1.02.B through D are not defined but, when used in the Bidding Requirements or Contract Documents, have the indicated meaning. B. Defective: 1. The word "defective," when modifying the word "Work," refers to Work that is unsatisfactory, faulty, or deficient in that it: a. does not conform to the Contract Documents; or b. does not meet the requirements of any applicable inspection, reference standard, test, or approval referred to in the Contract Documents; or c. has been damaged prior to City's written acceptance. C. Furnish, Install, Perform, Provide: 1. The word "Furnish" or the word "Install" or the word "Perform" or the word "Provide" or the word "Supply," or any combination or similar directive or usage thereof, shall mean furnishing and incorporating in the Work including all necessary labor, materials, equipment, and everything necessary to perform the Work indicated, unless specifically limited in the context used. D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known technical or construction industry or trade meaning are used in the Contract Documents in accordance with such recognized meaning. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 007310-6 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 6 of 35 ARTICLE 2- PRELIMINARY MATTERS 2.01 Before Starting Construction Baseline Schedules: Submit to City in accordance with the Contract Documents, and prior to starting the Work. New schedules will be submitted to City when Participating Change Orders or Non - Participating Change Orders occur. 2.02 Preconstruction Conference Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as specified in the Contract Documents. 2.03 Public Meeting Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor attending the Public Meeting as scheduled by the City. ARTICLE 3— CONTRACT DOCUMENTS AND AMENDING 3.01 Reference Standards A. Standards, Specifications, Codes, Laws, and Regulations 1. Reference to standards, specifications, manuals, or codes of any technical society, organization, or association, or to Laws or Regulations, whether such reference be specific or by implication, shall mean the standard, specification, manual, code, or Laws or Regulations in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract Documents. 2. No provision or instruction shall be effective to assign to City, or any of its officers, directors, members, partners, employees, agents, consultants, or subcontractors, any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of the Contract Documents. 3.02 Amending and Supplementing Contract Documents A. The Contract Documents may be amended to provide for additions, deletions, and revisions in the Work or to modify the terms and conditions thereof by a Participating Change Order or a Non -Participating Change Order. B. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work not involving a change in Contract Price or Contract Time, may be authorized, by one or more of the following ways: 1. A Field Order; CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-7 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 7 of 35 1. City's or Engineer's review of a Submittal (subject to the provisions of Paragraph 5.16.C); or 2. City's written interpretation or clarification. ARTICLE 4- BONDS AND INSURANCE 4.01 Licensed Sureties and Insurers All bonds and insurance required by the Contract Documents to be purchased and maintained by Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized in the State of Texas to issue bonds or insurance policies for the limits and coverage so required. Such surety and insurance companies shall also meet such additional requirements and qualifications as may be provided Section 4.04. 4.02 Performance, Payment, and Maintenance Bonds A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount equal to the Contract Price as security for the faithful performance and payment of all of Contractor's obligations under the Contract Documents. B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount equal to the Contract Price as security to protect the City against any defects in any portion of the Work described in the Contract Documents. Maintenance bonds shall remain in effect for two (2) years after the date of Final Acceptance by the City. C. All bonds shall be in the form prescribed by the Contract Documents except as provided otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list of "Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies" as published in Circular 570 (amended) by the Financial Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed by an agent or attorney -in -fact must be accompanied by a sealed and dated power of attorney which shall show that it is effective on the date the agent or attorney -in -fact signed each bond. D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or its right to do business is terminated in the State of Texas or it ceases to meet the requirements of Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event giving rise to such notification, provide another bond and surety, both of which shall comply with the requirements of Paragraphs 4.01 and 4.02.C. 4.03 Certificates of Insurance Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee identified in these Standard City Conditions certificates of insurance (and other evidence of insurance requested by City or any other additional insured) which Contractor is required to purchase and maintain. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 007310-8 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 8 of 35 1. The certificate of insurance shall document the City, an as "Additional Insured" on all liability policies. 2. The Contractor's general liability insurance shall include a, "per project" or "per location", endorsement, which shall be identified in the certificate of insurance provided to the City. 3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the insured, be complete in its entirety, and show complete insurance carrier names as listed in the current A.M. Best Property & Casualty Guide 4. The insurers for all policies must be licensed and/or approved to do business in the State of Texas. Except for workers' compensation, all insurers must have a minimum rating of A-: VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial strength and solvency to the satisfaction of Risk Management. If the rating is below that required, written approval of City is required. 5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor of the City. In addition, the Contractor agrees to waive all rights of subrogation against the Engineer (if applicable), and each additional insured identified in these Standard City Conditions. Failure of the City to demand such certificates or other evidence of full compliance with the insurance requirements or failure of the City to identify a deficiency from evidence that is provided shall not be construed as a waiver of Contractor's obligation to maintain such lines of insurance coverage. 6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess Liability insurance for any differences is required. Excess Liability shall follow form of the primary coverage. 7. Unless otherwise stated, all required insurance shall be written on the "occurrence basis". If coverage is underwritten on a claims -made basis, the retroactive date shall be coincident with or prior to the date of the effective date of the agreement and the certificate of insurance shall state that the coverage is claims -made and the retroactive date. The insurance coverage shall be maintained for the duration of the Contract and for three (3) years following Final Acceptance provided under the Contract Documents or for the warranty period, whichever is longer. An annual certificate of insurance submitted to the City shall evidence such insurance coverage. 8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the required lines of coverage, nor decrease the limits of said coverage unless such endorsements are approved in writing by the City. In the event a Contract has been bid or executed and the exclusions are determined to be unacceptable or the City desires additional insurance coverage, and the City desires the contractor/engineer to obtain such coverage, the contract price shall be adjusted by the cost of the premium for such additional coverage plus 10%. 9. Any self -insured retention (SIR), in excess of $25,000.00, affecting required insurance coverage shall be approved by the City in regards to asset value and stockholders' equity. In CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 007310-9 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 9 of 35 lieu of traditional insurance, alternative coverage maintained through insurance pools or risk retention groups, must also be approved by City. 10. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a first -dollar basis, must be acceptable to and approved by the City. 11. City, at its sole discretion, reserves the right to review the insurance requirements and to make reasonable adjustments to insurance coverage's and their limits when deemed necessary and prudent by the City based upon changes in statutory law, court decision or the claims history of the industry as well as of the contracting party to the City. The City shall be required to provide prior notice of 90 days, and the insurance adjustments shall be incorporated into the Work by Change Order. 12. City shall be entitled, upon written request and without expense, to receive copies of policies and endorsements thereto and may make any reasonable requests for deletion or revision or modifications of particular policy terms, conditions, limitations, or exclusions necessary to conform the policy and endorsements to the requirements of the Contract. Deletions, revisions, or modifications shall not be required where policy provisions are established by law or regulations binding upon either party or the underwriter on any such policies. 13. City shall not be responsible for the direct payment of insurance premium costs for Contractor's insurance. 4.04 Contractor's Insurance A. Workers Compensation and Employers' Liability. Contractor shall purchase and maintain such insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers' Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for Employers' Liability as is appropriate for the Work being performed and as will provide protection from claims set forth below which may arise out of or result from Contractor's performance of the Work and Contractor's other obligations under the Contract Documents, whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable: 1. claims under workers' compensation, disability benefits, and other similar employee benefit acts; 2. claims for damages because of bodily injury, occupational sickness or disease, or death of Contractor's employees. 3. The limits of liability for the insurance shall provide the following coverages for not less than the following amounts or greater where required by Laws and Regulations a. Statutory limits b. Employer's liability CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10- 10 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 10 of 35 1) $100,000 each accident/occurrence 2) $100,000 Disease - each employee 3) $500,000 Disease - policy limit B. Commercial General Liability. Coverage shall include but not be limited to covering liability (bodily injury or property damage) arising from: premises/operations, independent contractors, products/completed operations, personal injury, and liability under an insured contract. Insurance shall be provided on an occurrence basis, and as comprehensive as the current Insurance Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to any other insurance or self-insurance programs afforded to the City. The Commercial General Liability policy, shall have no exclusions by endorsements that would alter of nullify premises/operations, products/completed operations, contractual, personal injury, or advertising injury, which are normally contained with the policy, unless the City approves such exclusions in writing. 1. For construction projects that present a substantial completed operation exposure, the City may require the contractor to maintain completed operations coverage for a minimum of no less than three (3) years following the completion of the project 2. Contractor's Liability Insurance under this Section which shall be on a per project basis covering the Contractor with minimum limits of a. $1,000,000 each occurrence b. $2,000,000 aggregate limit 3. The policy must have an endorsement (Amendment — Aggregate Limits of Insurance) making the General Aggregate Limits apply separately to each job site. 4. The Commercial General Liability Insurance policies shall provide "X", "C", and "U" coverage's. Verification of such coverage must be shown in the Remarks Article of the Certificate of Insurance. C. Automobile Liability. A commercial business auto policy shall provide coverage on "any auto", defined as autos owned, hired and non -owned and provide indemnity for claims for damages because bodily injury or death of any person and or property damage arising out of the work, maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable. 1. Automobile Liability, Contractor's Liability Insurance under this Section, which shall be in an amount not less than the following amounts: a. Automobile Liability - a commercial business policy shall provide coverage on "Any Auto", defined as autos owned, hired and non -owned. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-11 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 11 of 35 1) $1,000,000 each accident on a combined single limit basis. Split limits are acceptable if limits are at least: 2) $250,000 Bodily Injury per person 3) $500,000 Bodily Injury per accident / 4) $100,000 Property Damage D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of railroad right-of-way, the Contractor shall comply with the following requirements: 1. The Contractor's construction activities will require its employees, agents, subcontractors, equipment, and material deliveries to cross railroad properties and tracks owned and operated by: none Write the name of the railroad company. (If none, then write none) 2. The Contractor shall conduct its operations on railroad properties in such a manner as not to interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use or operation of its/their trains or other property. Such operations on railroad properties may require that Contractor to execute a "Right of Entry Agreement" with the particular railroad company or companies involved, and to this end the Contractor should satisfy itself as to the requirements of each railroad company and be prepared to execute the right -of -entry (if any) required by a railroad company. The requirements specified herein likewise relate to the Contractor's use of private and/or construction access roads crossing said railroad company's properties. 3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions shall provide coverage for not less than the following amounts, issued by companies satisfactory to the City and to the Railroad Company for a term that continues for so long as the Contractor's operations and work cross, occupy, or touch railroad property: a. General Aggregate: none Enter limits provided by Railroad Company (If none, write none) b. Each Occurrence:: none Enter limits provided by Railroad Company (If none, write none) 4. With respect to the above outlined insurance requirements, the following shall govern: a. Where a single railroad company is involved, the Contractor shall provide one insurance policy in the name of the railroad company. However, if more than one grade separation or at -grade crossing is affected by the Project at entirely separate locations on the line or lines of the same railroad company, separate coverage may be required, each in the amount stated above. b. Where more than one railroad company is operating on the same right-of-way or where several railroad companies are involved and operated on their own separate rights -of - CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10- 12 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 12 of 35 way, the Contractor may be required to provide separate insurance policies in the name of each railroad company. c. If, in addition to a grade separation or an at -grade crossing, other work or activity is proposed on a railroad company's right-of-way at a location entirely separate from the grade separation or at -grade crossing, insurance coverage for this work must be included in the policy covering the grade separation. d. If no grade separation is involved but other work is proposed on a railroad company's right-of-way, all such other work may be covered in a single policy for that railroad, even though the work may be at two or more separate locations. 5. No work or activities on a railroad company's property to be performed by the Contractor shall be commenced until the Contractor has furnished the City with an original policy or policies of the insurance for each railroad company named, as required above. All such insurance must be approved by the City and each affected Railroad Company prior to the Contractor's beginning work. 6. The insurance specified above must be carried until all Work to be performed on the railroad right-of-way has been completed and the grade crossing, if any, is no longer used by the Contractor. In addition, insurance must be carried during all maintenance and/or repair work performed in the railroad right-of-way. Such insurance must name the railroad company as the insured, together with any tenant or lessee of the railroad company operating over tracks involved in the Project. E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation or other loss of insurance coverage. Contractor shall stop work until replacement insurance has been procured. There shall be no time credit for days not worked pursuant to this section. 4.05 Acceptance of Bonds and Insurance; Option to Replace If City has any objection to the coverage afforded by or other provisions of the bonds or insurance required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis of non-conformance with the Contract Documents, the Developer and City shall so notify the Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence requested). Contractor shall provide to the City such additional information in respect of insurance provided as the Developer or City may reasonably request. If Contractor does not purchase or maintain all of the bonds and insurance required by the Contract Documents, the Developer or City shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure to maintain prior to any change in the required coverage. ARTICLE 5- CONTRACTOR'S RESPONSIBILITIES 5.01 Supervision and Superintendent A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10- 13 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 13 of 35 Work in accordance with the Contract Documents. Contractor shall be solely responsible for the means, methods, techniques, sequences, and procedures of construction. B. At all times during the progress of the Work, Contractor shall assign a competent, English- speaking, Superintendent who shall not be replaced without written notice to City. The Superintendent will be Contractor's representative at the Site and shall have authority to act on behalf of Contractor. All communication given to or received from the Superintendent shall be binding on Contractor. C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of construction. 5.02 Labor; Working Hours A. Contractor shall provide competent, suitably qualified personnel to perform construction as required by the Contract Documents. Contractor shall at all times maintain good discipline and order at the Site. B. Except as otherwise required for the safety or protection of persons or the Work or property at the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during Regular Working Hours. Contractor will not permit the performance of Work beyond Regular Working Hours or for Weekend Working Hours without City's written consent (which will not be unreasonably withheld). Written request (by letter or electronic communication) to perform Work: 1. for beyond Regular Working Hours request must be made by noon at least two (2) Business Days prior 2. for Weekend Working Hours request must be made by noon of the preceding Thursday 3. for legal holidays request must be made by noon two Business Days prior to the legal holiday. 5.03 Services, Materials, and Equipment A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full responsibility for all services, materials, equipment, labor, transportation, construction equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities, and all other facilities and incidentals necessary for the performance, Contractor required testing, start-up, and completion of the Work. B. All materials and equipment incorporated into the Work shall be as specified or, if not specified, shall be of good quality and new, except as otherwise provided in the Contract Documents. All special warranties and guarantees required by the Specifications shall expressly run to the benefit of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of required tests) as to the source, kind, and quality of materials and equipment. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10- 14 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 14 of 35 C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed, connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of the applicable Supplier, except as otherwise may be provided in the Contract Documents. 5.04 Project Schedule A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01 and the General Requirements as it may be adjusted from time to time as provided below. 1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and the General Requirements) proposed adjustments in the Project Schedule. 2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be submitted in accordance with the requirements of Article 9. Adjustments in Contract Time for projects with City participation shall be made by participating change orders. 5.05 Substitutes and "Or -Equals" A. Whenever an item of material or equipment is specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular Supplier, the specification or description is intended to establish the type, function, appearance, and quality required. Unless the specification or description contains or is followed by words reading that no like, equivalent, or "or -equal" item or no substitution is permitted, other items of material or equipment of other Suppliers may be submitted to City for review under the circumstances described below. 1. "Or -Equal " Items: If in City's sole discretion an item of material or equipment proposed by Contractor is functionally equal to that named and sufficiently similar so that no change in related Work will be required, it may be considered by City as an "or -equal" item, in which case review and approval of the proposed item may, in City's sole discretion, be accomplished without compliance with some or all of the requirements for approval of proposed substitute items. For the purposes of this Paragraph 5.05.A.1, a proposed item of material or equipment will be considered functionally equal to an item so named if: a. City determines that: 1) it is at least equal in materials of construction, quality, durability, appearance, strength, and design characteristics; 2) it will reliably perform at least equally well the function and achieve the results imposed by the design concept of the completed Project as a functioning whole; and 3) it has a proven record of performance and availability of responsive service; and b. Contractor certifies that, if approved and incorporated into the Work: 1) there will be no increase in cost to the City or increase in Contract Time; and CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10- 15 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 15 of 35 2) it will conform substantially to the detailed requirements of the item named in the Contract Documents. 2. Substitute Items: a. If in City's sole discretion an item of material or equipment proposed by Contractor does not qualify as an "or -equal" item under Paragraph 5.05.A.1, it may be submitted as a proposed substitute item. b. Contractor shall submit sufficient information as provided below to allow City to determine if the item of material or equipment proposed is essentially equivalent to that named and an acceptable substitute therefor. Requests for review of proposed substitute items of material or equipment will not be accepted by City from anyone other than Contractor. c. Contractor shall make written application to City for review of a proposed substitute item of material or equipment that Contractor seeks to furnish or use. The application shall comply with Section 01 25 00 and: 1) shall certify that the proposed substitute item will: i. perform adequately the functions and achieve the results called for by the general design; ii. be similar in substance to that specified; iii. be suited to the same use as that specified; and 2) will state: i. the extent, if any, to which the use of the proposed substitute item will prejudice Contractor's achievement of final completion on time; ii. whether use of the proposed substitute item in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with City for other work on the Project) to adapt the design to the proposed substitute item; iii. whether incorporation or use of the proposed substitute item in connection with the Work is subject to payment of any license fee or royalty; and 3) will identify: i. all variations of the proposed substitute item from that specified; ii. available engineering, sales, maintenance, repair, and replacement services; and CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10- 16 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 16 of 35 4) shall contain an itemized estimate of all costs or credits that will result directly or indirectly from use of such substitute item, including costs of redesign and Damage Claims of other contractors affected by any resulting change. B. Substitute Construction Methods or Procedures: If a specific means, method, technique, sequence, or procedure of construction is expressly required by the Contract Documents, Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure of construction approved by City. Contractor shall submit sufficient information to allow City, in City's sole discretion, to determine that the substitute proposed is equivalent to that expressly called for by the Contract Documents. Contractor shall make written application to City for review in the same manner as those provided in Paragraph 5.05.A.2. C. City's Evaluation: City will be allowed a reasonable time within which to evaluate each proposal or submittal made pursuant to Paragraphs 5.05.A and 5.05.B. City may require Contractor to furnish additional data about the proposed substitute. City will be the sole judge of acceptability. No "or -equal" or substitute will be ordered, installed or utilized until City's review is complete, which will be evidenced by a Change Order in the case of a substitute and an accepted Submittal for an "or -equal." City will advise Contractor in writing of its determination. D. Special Guarantee: City may require Contractor to furnish at Contractor's expense a special performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall indemnify and hold harmless City and anyone directly or indirectly employed by them from and against any and all claims, damages, losses and expenses (including attorneys fees) arising out of the use of substituted materials or equipment. E. City's Cost Reimbursement: City will record City's costs in evaluating a substitute proposed or submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.B. Whether or not City approves a substitute so proposed or submitted by Contractor, Contractor may be required to reimburse City for evaluating each such proposed substitute. Contractor may also be required to reimburse City for the charges for making changes in the Contract Documents. F. Contractor's Expense: Contractor shall provide all data in support of any proposed substitute or "or -equal" at Contractor's expense. G. Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute shall be incorporated to the Contract by Participating Change Order. 5.06 Pre -Qualification of Bidders (Prime Contractors and Subcontractors) A. The Contractor and any subcontractors are required to be prequalified for the work types requiring pre -qualification 5.07 Concerning Subcontractors, Suppliers, and Others A. Minority and Women Owned Business Enterprise Compliance: CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10- 17 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 17 of 35 2' Required for this Contract. (Check this box if there is any City Participation) ❑ Not Required for this Contract. It is City policy to ensure the full and equitable participation by Minority and Women Business Enterprises (MWBE) in the procurement of goods and services on a contractual basis. If the Contract Documents provide for a MWBE goal, Contractor is required to comply with the intent of the City's MWBE Ordinance (as amended) by the following: 1. Contractor shall, upon request by City, provide complete and accurate information regarding actual work performed by a MWBE on the Contract and payment therefor. 2. Contractor will not make additions, deletions, or substitutions of accepted MWBE without written consent of the City. Any unjustified change or deletion shall be a material breach of Contract and may result in debarment in accordance with the procedures outlined in the Ordinance. 3. Contractor shall, upon request by City, allow an audit and/or examination of any books, records, or files in the possession of the Contractor that will substantiate the actual work performed by an MWBE. Material misrepresentation of any nature will be grounds for termination of the Contract. Any such misrepresentation may be grounds for disqualification of Contractor to bid on future contracts with the City for a period of not less than three years. B. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work just as Contractor is responsible for Contractor's own acts and omissions. Nothing in the Contract Documents: 1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity any contractual relationship between City and any such Subcontractor, Supplier or other individual or entity; nor 2. shall create any obligation on the part of City to pay or to see to the payment of any moneys due any such Subcontractor, Supplier, or other individual or entity except as may otherwise be required by Laws and Regulations. C. Contractor shall be solely responsible for scheduling and coordinating the Work of Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work under a direct or indirect contract with Contractor. D. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing any of the Work shall communicate with City through Contractor. E. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an appropriate agreement between Contractor and the Subcontractor or Supplier which specifically binds the Subcontractor or Supplier to the applicable terms and conditions of these Contract CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10- 18 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 18 of 35 Documents, Contractor shall provide City contract numbers and reference numbers to the Subcontractors and/or Suppliers. 5.08 Wage Rates Q' Required for this Contract. ❑ Not Required for this Contract. A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of Chapter 2258, Texas Government Code (as amended), including the payment of not less than the rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in accordance with Chapter 2258. Such prevailing wage rates are included in these Contract Documents. B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage shall, upon demand made by the City, pay to the City $60 for each worker employed for each calendar day or part of the day that the worker is paid less than the prevailing wage rates stipulated in these contract documents. This penalty shall be retained by the City to offset its administrative costs, pursuant to Texas Government Code 2258.023. C. Complaints of Violations and City Determination of Good Cause. On receipt of information, including a complaint by a worker, concerning an alleged violation of 2258.023, Texas Government Code, by a Contractor or Subcontractor, the City shall make an initial determination, before the 31st day after the date the City receives the information, as to whether good cause exists to believe that the violation occurred. The City shall notify in writing the Contractor or Subcontractor and any affected worker of its initial determination. Upon the City's determination that there is good cause to believe the Contractor or Subcontractor has violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or claimants as the difference between wages paid and wages due under the prevailing wage rates, such amounts being subtracted from successive progress payments pending a final determination of the violation. D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected worker, shall be submitted to binding arbitration in accordance with the Texas General Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any affected worker does not resolve the issue by agreement before the 15th day after the date the City makes its initial determination pursuant to Paragraph C above. If the persons required to arbitrate under this section do not agree on an arbitrator before the 11th day after the date that arbitration is required, a district court shall appoint an arbitrator on the petition of any of the persons. The City is not a party in the arbitration. The decision and award of the arbitrator is final and binding on all parties and may be enforced in any court of competent jurisdiction. E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3) years following the date of acceptance of the work, maintain records that show (i) the name and CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10- 19 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 19 of 35 occupation of each worker employed by the Contractor in the construction of the Work provided for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right to Audit, shall pertain to this inspection. F. Progress Payments. With each progress payment or payroll period, whichever is less, the Contractor shall submit an affidavit stating that the Contractor has complied with the requirements of Chapter 2258, Texas Government Code. G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at all times. H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall otherwise require all of its Subcontractors to comply with Paragraphs A through G above. 5.09 Patent Fees and Royalties A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless City, from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to any infringement of patent rights or copyrights incident to the use in the performance of the Work or resulting from the incorporation in the Work of any invention, design, process, product, or device not specified in the Contract Documents. 5.10 Laws and Regulations A. Contractor shall give all notices required by and shall comply with all Laws and Regulations applicable to the performance of the Work. Except where otherwise expressly required by applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor's compliance with any Laws or Regulations. B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such Work. However, it shall not be Contractor's responsibility to make certain that the Specifications and Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of Contractor's obligations under Paragraph 3.01. 5.11 Use of Site and Other Areas A. Limitation on Use of Site and Other Areas: 1. Contractor shall confine construction equipment, the storage of materials and equipment, and the operations of workers to the Site and other areas permitted by Laws and Regulations, and shall not unreasonably encumber the Site and other areas with construction equipment or CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-20 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 20 of 35 other materials or equipment. Contractor shall assume full responsibility for any damage to any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas resulting from the performance of the Work. 2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is carrying on operations in a portion of a street, right-of-way, or easement greater than is necessary for proper execution of the Work, the City may require the Contractor to finish the section on which operations are in progress before work is commenced on any additional area of the Site. 3. Should any Damage Claim be made by any such owner or occupant because of the performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim. 4. Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and against all claims, costs, losses, and damages arising out of or relating to any claim or action, legal or equitable, brought by any such owner or occupant against City. B. Removal of Debris During Performance of the Work: During the progress of the Work Contractor shall keep the Site and other areas free from accumulations of waste materials, rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other debris shall conform to applicable Laws and Regulations. C. Site Maintenance Cleaning. • 24 hours after written notice is given to the Contractor that the clean-up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the written notice (by letter or electronic communication), and shall be entitled to recover its cost in doing so. The City may withhold Final Acceptance until clean-up is complete and cost are recovered. D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and the Work and make it ready for utilization by City or adjacent property owner. At the completion of the Work Contractor shall remove from the Site all tools, appliances, construction equipment and machinery, and surplus materials and shall restore to original condition or better all property disturbed by the Work. E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded in any manner that will endanger the structure, nor shall Contractor subject any part of the Work or adjacent property to stresses or pressures that will endanger it. 5.12 Record Documents A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change Orders, Field Orders, and written interpretations and clarifications in good order and annotated to show changes made during construction. These record documents together with all approved CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-21 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 21 of 35 Samples and a counterpart of all accepted Submittals will be available to City for reference. Upon completion of the Work, these record documents, any operation and maintenance manuals, and Submittals will be delivered to City prior to Final Inspection. Contractor shall include accurate locations for buried and imbedded items. 5.13 Safety and Protection A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. Such responsibility does not relieve Subcontractors of their responsibility for the safety of persons or property in the performance of their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to: 1. all persons on the Site or who may be affected by the Work; 2. all the Work and materials and equipment to be incorporated therein, whether in storage on or off the Site; and 3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities, and Underground Facilities not designated for removal, relocation, or replacement in the course of construction. B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of persons or property, or to the protection of persons or property from damage, injury, or loss; and shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall notify owners of adjacent property and of Underground Facilities and other utility owners when prosecution of the Work may affect them, and shall cooperate with them in the protection, removal, relocation, and replacement of their property. C. Contractor shall comply with the applicable requirements of City's safety programs, if any. D. Contractor shall inform City of the specific requirements of Contractor's safety program, if any, with which City's employees and representatives must comply while at the Site. E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused, directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any other individual or entity directly or indirectly employed by any of them to perform any of the Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor. F. Contractor's duties and responsibilities for safety and for protection of the Work shall continue until such time as all the Work is completed and City has accepted the Work. 5.14 Safety Representative Contractor shall inform City in writing of Contractor's designated safety representative at the Site. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-22 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 22 of 35 5.15 Hazard Communication Programs Contractor shall be responsible for coordinating any exchange of material safety data sheets or other hazard communication information required to be made available to or exchanged between or among employers in accordance with Laws or Regulations. 5.16 Submittals A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal will be identified as required by City. 1. Submit number of copies specified in the General Requirements. 2. Data shown on the Submittals will be complete with respect to quantities, dimensions, specified performance and design criteria, materials, and similar data to show City the services, materials, and equipment Contractor proposes to provide and to enable City to review the information for the limited purposes required by Paragraph 5.16.C. 3. Submittals submitted as herein provided by Contractor and reviewed by City for conformance with the design concept shall be executed in conformity with the Contract Documents unless otherwise required by City. 4. When Submittals are submitted for the purpose of showing the installation in greater detail, their review shall not excuse Contractor from requirements shown on the Drawings and Specifications. 5. For -Information -Only submittals upon which the City is not expected to conduct review or take responsive action may be so identified in the Contract Documents. 6. Submit required number of Samples specified in the Specifications. 7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers, the use for which intended and other data as City may require to enable City to review the submittal for the limited purposes required by Paragraph 5.16.C. B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any related Work performed prior to City's review and acceptance of the pertinent submittal will be at the sole expense and responsibility of Contractor. C. City's Review: 1. City will provide timely review of required Submittals in accordance with the Schedule of Submittals acceptable to City. City's review and acceptance will be only to determine if the items covered by the submittals will, after installation or incorporation in the Work, conform to the information given in the Contract Documents and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-23 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 23 of 35 2. City's review and acceptance will not extend to means, methods, techniques, sequences, or procedures of construction (except where a particular means, method, technique, sequence, or procedure of construction is specifically and expressly called for by the Contract Documents) or to safety precautions or programs incident thereto. The review and acceptance of a separate item as such will not indicate approval of the assembly in which the item functions. 3. City's review and acceptance shall not relieve Contractor from responsibility for any variation from the requirements of the Contract Documents unless Contractor has complied with the requirements of Section 01 33 00 and City has given written acceptance of each such variation by specific written notation thereof incorporated in or accompanying the Submittal. City's review and acceptance shall not relieve Contractor from responsibility for complying with the requirements of the Contract Documents. 5.17 Contractor's General Warranty and Guarantee A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract Documents and will not be defective. City and its officers, directors, members, partners, employees, agents, consultants, and subcontractors shall be entitled to rely on representation of Contractor's warranty and guarantee. B. Contractor's warranty and guarantee hereunder excludes defects or damage caused by: 1. abuse, modification, or improper maintenance or operation by persons other than Contractor, Subcontractors, Suppliers, or any other individual or entity for whom Contractor is responsible; or 2. normal wear and tear under normal usage. C. Contractor's obligation to perform and complete the Work in accordance with the Contract Documents shall be absolute. None of the following will constitute an acceptance of Work that is not in accordance with the Contract Documents or a release of Contractor's obligation to perform the Work in accordance with the Contract Documents: 1. observations by City; 2. recommendation or payment by City or Developer of any progress or fmal payment; 3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by City; 4. use or occupancy of the Work or any part thereof by City; 5. any review and acceptance of a Submittal by City; 6. any inspection, test, or approval by others; or CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-24 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 24 of 35 7. any correction of defective Work by City. D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to other work or property resulting therefrom which shall appear within a period of two (2) years from the date of Final Acceptance of the Work unless a longer period is specified and shall furnish a good and sufficient maintenance bond, complying with the requirements of Article 4.02.B. The City will give notice of observed defects with reasonable promptness. 5.18 Indemnification A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the City, its officers, servants and employees, from and against any and all claims arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licenses or invitees under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by the City in defending against such claims and causes of actions. B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its officers, servants and employees, from and against any and all loss, damage or destruction of property of the City, arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. 5.19 Delegation of Professional Design Services A. Contractor will not be required to provide professional design services unless such services are specifically required by the Contract Documents for a portion of the Work or unless such services are required to carry out Contractor's responsibilities for construction means, methods, techniques, sequences and procedures. B. If professional design services or certifications by a design professional related to systems, materials or equipment are specifically required of Contractor by the Contract Documents, City will specify all performance and design criteria that such services must satisfy. Contractor shall cause such services or certifications to be provided by a properly licensed professional, whose signature and seal shall appear on all drawings, calculations, specifications, certifications, and Submittals prepared by such professional. Submittals related to the Work designed or certified by such professional, if prepared by others, shall bear such professional's written approval when submitted to City. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-25 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 25 of 35 C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services, certifications or approvals performed by such design professionals, provided City has specified to Contractor performance and design criteria that such services must satisfy. D. Pursuant to this Paragraph 5.19, City's review and acceptance of design calculations and design drawings will be only for the limited purpose of checking for conformance with performance and design criteria given and the design concept expressed in the Contract Documents. City's review and acceptance of Submittals (except design calculations and design drawings) will be only for the purpose stated in Paragraph 5.16.C. 5.20 Right to Audit: A. The City reserves the right to audit all projects utilizing City funds B. The Contractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents, papers, and records of the Contractor involving transactions relating to this Contract. Contractor agrees that the City shall have access during Regular Working Hours to all necessary Contractor facilities and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Contractor reasonable advance notice of intended audits. C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that the subcontractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents, papers, and records of such Subcontractor, involving transactions to the subcontract, and further, that City shall have access during Regular Working Hours to all Subcontractor facilities, and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Subcontractor reasonable advance notice of intended audits. D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate published in the Texas Administrative Code in effect as of the time copying is performed. 5.21 Nondiscrimination A. The City is responsible for operating Public Transportation Programs and implementing transit - related projects, which are funded in part with Federal financial assistance awarded by the U.S. Department of Transportation and the Federal Transit Administration (FTA), without discriminating against any person in the United States on the basis of race, color, or national origin. B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of the Act and the Regulations as further defined in the Supplementary Conditions for any project receiving Federal assistance. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-26 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 26 of 35 ARTICLE 6- OTHER WORK AT THE SITE 6.01 Related Work at Site A. City may perform other work related to the Project at the Site with City's employees, or other City contractors, or through other direct contracts therefor, or have other work performed by utility owners. If such other work is not noted in the Contract Documents, then written notice thereof will be given to Contractor prior to starting any such other work; and B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility owner, and City, if City is performing other work with City's employees or other City contractors, proper and safe access to the Site, provide a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such other work, and properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of the Work that may be required to properly connect or otherwise make its several parts come together and properly integrate with such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering such work; provided, however, that Contractor may cut or alter others' work with the written consent of City and the others whose work will be affected. C. If the proper execution or results of any part of Contractor's Work depends upon work performed by others under this Article 7, Contractor shall inspect such other work and promptly report to City in writing any delays, defects, or deficiencies in such other work that render it unavailable or unsuitable for the proper execution and results of Contractor's Work. Contractor's failure to so report will constitute an acceptance of such other work as fit and proper for integration with Contractor's Work except for latent defects in the work provided by others. ARTICLE 7- CITY'S RESPONSIBILITIES 7.01 Inspections, Tests, and Approvals City's responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph 11.03. 7.02 Limitations on City's Responsibilities A. The City shall not supervise, direct, or have control or authority over, nor be responsible for, Contractor's means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and Regulations applicable to the performance of the Work. City will not be responsible for Contractor's failure to perform the Work in accordance with the Contract Documents. B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-27 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 27 of 35 7.03 Compliance with Safety Program While at the Site, City's employees and representatives shall comply with the specific applicable requirements of Contractor's safety programs of which City has been informed pursuant to Paragraph 5.13. ARTICLE 8- CITY'S OBSERVATION STATUS DURING CONSTRUCTION 8.01 City s Project Representative City will provide one or more Project Representative(s) during the construction period. The duties and responsibilities and the limitations of authority of City's representative during construction are set forth in the Contract Documents. A. City's Project Representative will make visits to the Site at intervals appropriate to the various stages of construction as City deems necessary in order to observe the progress that has been made and the quality of the various aspects of Contractor's executed Work. Based on information obtained during such visits and observations, City's Project Representative will determine, in general, if the Work is proceeding in accordance with the Contract Documents. City's Project Representative will not be required to make exhaustive or continuous inspections on the Site to check the quality or quantity of the Work. City's Project Representative's efforts will be directed toward providing City a greater degree of confidence that the completed Work will conform generally to the Contract Documents. B. City's Project Representative's visits and observations are subject to all the limitations on authority and responsibility in the Contract Documents. 8.02 Authorized Variations in Work City's Project Representative may authorize minor variations in the Work from the requirements of the Contract Documents which do not involve an adjustment in the Contract Price or the Contract Time and are compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. These may be accomplished by a Field Order and will be binding on City Developer, and also on Contractor, who shall perform the Work involved promptly. 8.03 Rejecting Defective Work City will have authority to reject Work which City's Project Representative believes to be defective, or will not produce a completed Project that conforms to the Contract Documents or that will prejudice the integrity of the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. City will have authority to conduct special inspection or testing of the Work as provided in Article 11, whether or not the Work is fabricated, installed, or completed. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-28 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 28 of 35 8.04 Determinations for Work Performed Contractor will determine the actual quantities and classifications of Work performed. City's Project Representative will review with Contractor the preliminary determinations on such matters before rendering a written recommendation. City's written decision will be final (except as modified to reflect changed factual conditions or more accurate data). ARTICLE 9— CHANGES IN THE WORK 9.01 Authorized Changes in the Work A. Without invalidating the Contract and without notice to any surety, City may, at any time or from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall promptly proceed with the Work involved which will be performed under the applicable conditions of the Contract Documents (except as otherwise specifically provided). Extra Work shall be memorialized by a Participating Change Order which may or may not precede an order of Extra work. B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a project with City participation, a Field Order may be issued by the City. 9.02 Notification to Surety If the provisions of any bond require notice to be given to a surety of any change affecting the general scope of the Work or the provisions of the Contract Documents (including, but not limited to, Contract Price or Contract Time), the giving of any such notice will be Contractor's responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the effect of any such change. ARTICLE 10 — CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME 10.01 Change of Contract Price A. The Contract Price may only be changed by a Participating Change Order for projects with City participation. 10.02 Change of Contract Time A. The Contract Time may only be changed by a Participating Change Order for projects with City participation. 10.03 Delays A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-29 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 29 of 35 ARTICLE 11- TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK 11.01 Notice of Defects Notice of all defective Work of which City has actual knowledge will be given to Contractor. Defective Work may be rejected, corrected, or accepted as provided in this Article 13. 11.02 Access to Work City, independent testing laboratories, and governmental agencies with jurisdictional interests will have access to the Site and the Work at reasonable times for their observation, inspection, and testing. Contractor shall provide them proper and safe conditions for such access and advise them of Contractor's safety procedures and programs so that they may comply therewith as applicable. 11.03 Tests and Inspections A. Contractor shall give City timely notice of readiness of the Work for all required inspections, tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required inspections or tests. B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full responsibility for arranging and obtaining such independent inspections, tests, retests or approvals, pay all costs in connection therewith, and furnish City the required certificates of inspection or approval; excepting, however, those fees specifically identified in the Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR) inspections, which shall be paid as described in the Supplementary Conditions. C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection with any inspections, tests, re -tests, or approvals required for City's acceptance of materials or equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment submitted for approval prior to Contractor's purchase thereof for incorporation in the Work. Such inspections, tests, re -tests, or approvals shall be performed by organizations approved by City. D. City may arrange for the services of an independent testing laboratory ("Testing Lab") to perform any inspections or tests ("Testing") for any part of the Work, as determined solely by City. 1. City will coordinate such Testing to the extent possible, with Contractor; 2. Should any Testing under this Section 11.03 D result in a "fail", "did not pass" or other similar negative result, the Contractor shall be responsible for paying for any and all retests. Contractor's cancellation without cause of City initiated Testing shall be deemed a negative result and require a retest. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-30 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 30 of 35 3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the Testing Lab by Contractor. City will forward all invoices for retests to Developer/Contractor. 4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance until the Testing Lab is Paid E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by Contractor without written concurrence of City, Contractor shall, if requested by City, uncover such Work for observation. 11.04 Uncovering Work A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it must, if requested by City, be uncovered for City's observation and replaced at Contractor's expense. 11.05 City May Stop the Work If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials or equipment, or fails to perform the Work in such a way that the completed Work will conform to the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of City to stop the Work shall not give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent of any of them. 11.06 Correction or Removal of Defective Work A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has been rejected by City, remove it from the Project and replace it with Work that is not defective. Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such correction or removal (including but not limited to all costs of repair or replacement of work of others). Failure to require the removal of any defective Work shall not constitute acceptance of such Work. B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07, Contractor shall take no action that would void or otherwise impair City's special warranty and guarantee, if any, on said Work. 11.07 Correction Period A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may be prescribed by the terms of any applicable special guarantee required by the Contract CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-31 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 31 of 35 Documents), any Work is found to be defective, or if the repair of any damages to the land or areas made available for Contractor's use by City or permitted by Laws and Regulations as contemplated in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without cost to City and in accordance with City's written instructions: 1. repair such defective land or areas; or 2. correct such defective Work; or 3. if the defective Work has been rejected by City, remove it from the Project and replace it with Work that is not defective, and 4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work of others or other land or areas resulting therefrom. B. If Contractor does not promptly comply with the terms of City's written instructions, or in an emergency where delay would cause serious risk of loss or damage, City may have the defective Work corrected or repaired or may have the rejected Work removed and replaced. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) arising out of or relating to such correction or repair or such removal and replacement (including but not limited to all costs of repair or replacement of work of others) will be paid by Contractor. C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or removed and replaced under this Paragraph 11.07, the correction period hereunder with respect to such Work may be required to be extended for an additional period of one year after the end of the initial correction period. City shall provide 30 days written notice to Contractor and Developer should such additional warranty coverage be required. Contractor's obligations under this Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any applicable statute of limitation or repose. 11.08 City May Correct Defective Work A. If Contractor fails within a reasonable time after written notice from City to correct defective Work, or to remove and replace rejected Work as required by City in accordance with Paragraph 11.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply with any other provision of the Contract Documents, City may, after seven (7) days written notice to Contractor and the Developer, correct, or remedy any such deficiency. B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed expeditiously. In connection with such corrective or remedial action, City may exclude Contractor from all or part of the Site, take possession of all or part of the Work and suspend Contractor's services related thereto, and incorporate in the Work all materials and equipment incorporated in the Work, stored at the Site or for which City has paid Contractor but which are CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-32 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 32 of 35 stored elsewhere. Contractor shall allow City, City's representatives, agents, consultants, employees, and City's other contractors, access to the Site to enable City to exercise the rights and remedies under this Paragraph. C. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph 13.09 will be charged against Contractor, and a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work; and City shall be entitled to an appropriate decrease in the Contract Price. D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the performance of the Work attributable to the exercise of City's rights and remedies under this Paragraph 11.09. ARTICLE 12 - COMPLETION 12.01 Contractor's Warranty of Title Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any Application for Payment will pass to City no later than the time of Final Acceptance and shall be free and clear of all Liens. 12.02 Partial Utilization A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed part of the Work which has specifically been identified in the Contract Documents, or which City, determines constitutes a separately functioning and usable part of the Work that can be used by City for its intended purpose without significant interference with Contractor's performance of the remainder of the Work. City at any time may notify Contractor in writing to permit City to use or occupy any such part of the Work which City determines to be ready for its intended use, subject to the following conditions: 1. Contractor at any time may notify City in writing that Contractor considers any such part of the Work ready for its intended use. 2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and Contractor shall make an inspection of that part of the Work to determine its status of completion. If City does not consider that part of the Work to be substantially complete, City will notify Contractor in writing giving the reasons therefor. 3. Partial Utilization will not constitute Final Acceptance by City. 12.03 Final -Inspection A. Upon written notice from Contractor that the entire Work is complete in accordance with the Contract Documents: CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-33 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 33 of 35 1. within 10 days, City will schedule a Final Inspection with Contractor. 2. City will notify Contractor in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. Contractor shall immediately take such measures as are necessary to complete such Work or remedy such deficiencies. 12.04 Final Acceptance A. Upon completion by Contractor to City's satisfaction, of any additional Work identified in the Final Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction of the following: 1. All documentation called for in the Contract Documents, including but not limited to the evidence of insurance required by Paragraph 5.03; 2. consent of the surety, if any, to Final Acceptance; 3. a list of all pending or released Damage Claims against City that Contractor believes are unsettled; and 4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to City) of all Lien rights arising out of or Liens filed in connection with the Work. 5. after all Damage Claims have been resolved: a. directly by the Contractor or; b. Contractor provides evidence that the Damage Claim has been reported to Contractor's insurance provider for resolution. 6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or other requirements of the Contract Documents which specifically continue thereafter. ARTICLE 13 - SUSPENSION OF WORK 13.01 City May Suspend Work A. At any time and without cause, City may suspend the Work or any portion thereof by written notice to Contractor and which may fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. During temporary suspension of the Work covered by these Contract Documents, for any reason, the City will stop contract time on City participation projects. B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the control of and without the fault or negligence of the Contractor, and should it be determined by mutual consent of the Contractor and City that a solution to allow construction to proceed is not CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-34 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 34 of 35 available within a reasonable period of time, Contractor may request an extension in Contract Time, directly attributable to any such suspension. C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall store all materials in such a manner that they will not obstruct or impede the public unnecessarily nor become damaged in any way, and he shall take every precaution to prevent damage or deterioration of the work performed; he shall provide suitable drainage about the work, and erect temporary structures where necessary. ARTICLE 14 - MISCELLANEOUS 14.01 Giving Notice A. Whenever any provision of the Contract Documents requires the giving of written notice, it will be deemed to have been validly given if: 1. delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended; or 2. delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice. B. Business address changes must be promptly made in writing to the other party. C. Whenever the Contract Documents specifies giving notice by electronic means such electronic notice shall be deemed sufficient upon confirmation of receipt by the receiving party. 14.02 Computation of Times When any period of time is referred to in the Contract Documents by days, it will be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last day of the period. 14.03 Cumulative Remedies The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto are in addition to, and are not to be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically in the Contract Documents in connection with each particular duty, obligation, right, and remedy to which they apply. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-35 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 35 of 35 14.04 Survival of Obligations All representations, indemnifications, warranties, and guarantees made in, required by, or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Documents, will survive final payment, completion, and acceptance of the Work or termination or completion of the Contract or termination of the services of Contractor. 14.05 Headings Article and paragraph headings are inserted for convenience only and do not constitute parts of these General Conditions. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 011100-1 DAP SUMMARY OF WORK Page 1 of 3 1 2 3 PART1- GENERAL 4 1.1 SUMMARY SECTION 01 11 00 SUMMARY OF WORK 5 A. Section Includes: 6 1. Summary of Work to be performed in accordance with the Contract Documents 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract 11 2. Division 1 - General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES [NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 A. Work Covered by Contract Documents 1. Work is to include furnishing all labor, materials, and equipment, and performing all Work necessary for this construction project as detailed in the Drawings and Specifications. B. Subsidiary Work 1. Any and all Work specifically governed by documentary requirements for the project, such as conditions imposed by the Drawings or Contract Documents in which no specific item for bid has been provided for in the Proposal and the item is not a typical unit bid item included on the standard bid item list, then the item shall be considered as a subsidiary item of Work, the cost of which shall be included in the price bid in the Proposal for various bid items. C. Use of Premises 1. Coordinate uses of premises under direction of the City. 2. Assume full responsibility for protection and safekeeping of materials and equipment stored on the Site. 3. Use and occupy only portions of the public streets and alleys, or other public places or other rights -of -way as provided for in the ordinances of the City, as shown in the Contract Documents, or as may be specifically authorized in writing by the City. a. A reasonable amount of tools, materials, and equipment for construction purposes may be stored in such space, but no more than is necessary to avoid delay in the construction operations. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects City Project No. 106104 Revised December 20, 2012 011100-2 DAP SUMMARY OF WORK Page 2 of 3 1 b. Excavated and waste materials shall be stored in such a way as not to interfere 2 with the use of spaces that may be designated to be left free and unobstructed 3 and so as not to inconvenience occupants of adjacent property. 4 c. If the street is occupied by railroad tracks, the Work shall be carried on in such 5 manner as not to interfere with the operation of the railroad. 6 1) All Work shall be in accordance with railroad requirements set forth in 7 Division 0 as well as the railroad permit. 8 D. Work within Easements 9 1. Do not enter upon private property for any purpose without having previously 10 obtained permission from the owner of such property. 11 2. Do not store equipment or material on private property unless and until the 12 specified approval of the property owner has been secured in writing by the 13 Contractor and a copy furnished to the City. 14 3. Unless specifically provided otherwise, clear all rights -of -way or easements of 15 obstructions which must be removed to make possible proper prosecution of the 16 Work as a part of the project construction operations. 17 4. Preserve and use every precaution to prevent damage to, all trees, shrubbery, plants, 18 lawns, fences, culverts, curbing, and all other types of structures or improvements, 19 to all water, sewer, and gas lines, to all conduits, overhead pole lines, or 20 appurtenances thereof, including the construction of temporary fences and to all 21 other public or private property adjacent to the Work. 22 5. Notify the proper representatives of the owners or occupants of the public or private 23 lands of interest in lands which might be affected by the Work. 24 a. Such notice shall be made at least 48 hours in advance of the beginning of the 25 Work. 26 b. Notices shall be applicable to both public and private utility companies and any 27 corporation, company, individual, or other, either as owners or occupants, 28 whose land or interest in land might be affected by the Work. 29 c. Be responsible for all damage or injury to property of any character resulting 30 from any act, omission, neglect, or misconduct in the manner or method or 31 execution of the Work, or at any time due to defective work, material, or 32 equipment. 33 6. Fence 34 a. Restore all fences encountered and removed during construction of the Project 35 to the original or a better than original condition. 36 b. Erect temporary fencing in place of the fencing removed whenever the Work is 37 not in progress and when the site is vacated overnight, and/or at all times to 38 provide site security. 39 c. The cost for all fence work within easements, including removal, temporary 40 closures and replacement, shall be subsidiary to the various items bid in the 41 project proposal, unless a bid item is specifically provided in the proposal. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects City Project No. 106104 Revised December 20, 2012 011100-3 DAP SUMMARY OF WORK Page 3 of 3 1 1.5 SUBMITTALS [NOT USED] 2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 3 1.7 CLOSEOUT SUBMITTALS [NOT USED] 4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 5 1.9 QUALITY ASSURANCE [NOT USED] 6 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 7 1.11 FIELD [SITE] CONDITIONS [NOT USED] 8 1.12 WARRANTY [NOT USED] 9 PART 2- PRODUCTS [NOT USED] 10 PART 3- EXECUTION [NOT USED] 11 12 13 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects City Project No. 106104 Revised December 20, 2012 012500-1 DAP SUBSTITUTION PROCEDURES Page 1 of 4 1 SECTION 0125 00 2 SUBSTITUTION PROCEDURES 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. The procedure for requesting the approval of substitution of a product that is not 7 equivalent to a product which is specified by descriptive or performance criteria or 8 defined by reference to 1 or more of the following: 9 a. Name of manufacturer 10 b. Name of vendor 11 c. Trade name 12 d. Catalog number 13 2. Substitutions are not "or -equals". 14 B. Deviations from this City of Fort Worth Standard Specification 15 1. None. 16 C. Related Specification Sections include, but are not necessarily limited to: 17 1. Division 0— Bidding Requirements, Contract Forms and Conditions of the Contract 18 2. Division 1 — General Requirements 19 1.2 PRICE AND PAYMENT PROCEDURES 20 A. Measurement and Payment 21 1. Work associated with this Item is considered subsidiary to the various items bid. No 22 separate payment will be allowed for this Item. 23 1.3 REFERENCES [NOT USED] 24 1.4 ADMINISTRATIVE REQUIREMENTS 25 A. Request for Substitution - General 26 1. Within 30 days after award of Contract (unless noted otherwise), the City will 27 consider formal requests from Contractor for substitution of products in place of 28 those specified. 29 2. Certain types of equipment and kinds of material are described in Specifications by 30 means of references to names of manufacturers and vendors, trade names, or catalog 31 numbers. 32 a. When this method of specifying is used, it is not intended to exclude from 33 consideration other products bearing other manufacturer's or vendor's names, 34 trade names, or catalog numbers, provided said products are "or -equals," as 35 determined by City. 36 3. Other types of equipment and kinds of material may be acceptable substitutions 37 under the following conditions: 38 a. Or -equals are unavailable due to strike, discontinued production of products 39 meeting specified requirements, or other factors beyond control of Contractor; 40 or, CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August 30, 2013 012500-2 DAP SUBSTITUTION PROCEDURES Page 2 of 4 1 b. Contractor proposes a cost and/or time reduction incentive to the City. 2 1.5 SUBMITTALS 3 A. See Request for Substitution Form (attached) 4 B. Procedure for Requesting Substitution 5 1. Substitution shall be considered only: 6 a. After award of Contract 7 b. Under the conditions stated herein 8 2. Submit 3 copies of each written request for substitution, including: 9 a. Documentation 10 1) Complete data substantiating compliance of proposed substitution with 11 Contract Documents 12 2) Data relating to changes in construction schedule, when a reduction is 13 proposed 14 3) Data relating to changes in cost 15 b. For products 16 1) Product identification 17 a) Manufacturer's name 18 b) Telephone number and representative contact name 19 c) Specification Section or Drawing reference of originally specified 20 product, including discrete name or tag number assigned to original 21 product in the Contract Documents 22 2) Manufacturer's literature clearly marked to show compliance of proposed 23 product with Contract Documents 24 3) Itemized comparison of original and proposed product addressing product 25 characteristics including, but not necessarily limited to: 26 a) Size 27 b) Composition or materials of construction 28 c) Weight 29 d) Electrical or mechanical requirements 30 4) Product experience 31 a) Location of past projects utilizing product 32 b) Name and telephone number of persons associated with referenced 33 projects knowledgeable concerning proposed product 34 c) Available field data and reports associated with proposed product 35 5) Samples 36 a) Provide at request of City. 37 b) Samples become the property of the City. 38 c. For construction methods: 39 1) Detailed description of proposed method 40 2) Illustration drawings 41 C. Approval or Rejection 42 1. Written approval or rejection of substitution given by the City 43 2. City reserves the right to require proposed product to comply with color and pattern 44 of specified product if necessary to secure design intent. 45 3. In the event the substitution is approved, if a reduction in cost or time results, it will 46 be documented by Change Order. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August 30, 2013 012500-3 DAP SUBSTITUTION PROCEDURES Page 3 of 4 1 4. Substitution will be rejected if: 2 a. Submittal is not through the Contractor with his stamp of approval 3 b. Request is not made in accordance with this Specification Section 4 c. In the Developer's opinion, acceptance will require substantial revision of the 5 original design 6 d. In the City's or Developer's opinion, substitution will not perform adequately 7 the function consistent with the design intent 8 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 9 1.7 CLOSEOUT SUBMITTALS [NOT USED] 10 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 11 1.9 QUALITY ASSURANCE 12 A. In making request for substitution or in using an approved product, the Contractor 13 represents that the Contractor: 14 1. Has investigated proposed product, and has determined that it is adequate or 15 superior in all respects to that specified, and that it will perform function for which it 16 is intended 17 2. Will provide same guarantee for substitute item as for product specified 18 3. Will coordinate installation of accepted substitution into Work, to include building 19 modifications if necessary, making such changes as may be required for Work to be 20 complete in all respects 21 4. Waives all claims for additional costs related to substitution which subsequently 22 arise 23 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 24 1.11 FIELD [SITE] CONDITIONS [NOT USED] 25 1.12 WARRANTY [NOT USED] 26 PART 2- PRODUCTS [NOT USED] 27 PART 3- EXECUTION [NOT USED] 28 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 29 CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August 30, 2013 0125 00-4 DAP SUBSTITUTION PROCEDURES Page 4 of 4 1 2 3 4 5 6 7 8 9 EXHIBIT A REQUEST FOR SUBSTITUTION FORM: TO: PROJECT: DATE: We hereby submit for your consideration the following product instead of the specified item for the above project: SECTION PARAGRAPH SPECIFIED ITEM 10 Proposed Substitution: 11 Reason for Substitution: 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 Include complete information on changes to Drawings and/or Specifications which proposed substitution will require for its proper installation. Fill in Blanks Below: A. Will the undersigned contractor pay for changes to the building design, including engineering and detailing costs caused by the requested substitution? B. What effect does substitution have on other trades? C. Differences between proposed substitution and specified item? D. Differences in product cost or product delivery time? E. Manufacturer's guarantees of the proposed and specified items are: Equal Better (explain on attachment) The undersigned states that the function, appearance and quality are equivalent or superior to the specified item. Submitted By: For Use by City Signature as noted Firm Address Date Telephone For Use by City: Approved City Recommended Recommended Not recommended Received late By Date Remarks Date Rejected CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August 30, 2013 000000-1 MATERIALS ON HAND Page 1 of3 2 3 PART1- GENERAL 4 1.1 SUMMARY SECTION 0129 75 MATERIALS ON HAND 5 A.This section should be used if payment is requested based on materials and equipment not 6 incorporated in the Work but delivered and suitably stored at the Site or at another 7 location agreed to in writing (Materials On Hand). 8 B.Payment for Materials On Hand (MOH) may be made for non-perishable materials that 9 are considered long lead-time items and have been approved for MOH payment. 10 1.2 SECTION INCLUDES: 11 A.Materials approved for MOH payment are as follows: 12 1. Water & Sewer Pipe greater than or equal to 24" diameter 13 2. Water Valves greater than or equal to 36" diameter 14 3. Reinforced Concrete Pipe greater than or equal to 84" diameter 15 4. Reinforced Concrete Box greater than or equal to 8' x 6' 16 5. Traffic Signal Poles, Masts, and Cabinets 17 6. Street and Pedestrian Light Poles 18 19 B.Requirements for MOH 20 1. Materials must be stored on -site for a minimum of two (2) progress payment cycles 21 to qualify for MOH reimbursement. If materials are expected to be stored for a 22 shorter duration, MOH will not be paid. 23 2. For Materials on Hand to be paid for, required submittal must been submitted and 24 approved. No MOH will be paid when MOH submittal have not been approved. 25 3. MOH must be stored in accordance with approved submittal requirements. 26 4. The contractor must maintain the proper insurance and retain the duty to protect the 27 materials per the included material specification or equipment per the 28 manufacturer's specifications. 29 C. Material storage at a third -party facility may be permitted, provided the facility is bonded 30 and insured. Any off -site storage location must receive prior written approval from the 31 City Project Manager, Developer, and Participating Department. A copy of the written 32 approval must be included with the corresponding pay application. 33 D.Deviations from this City of Fort Worth Standard Specification 34 1. None. 35 E. Related Specification Sections include, but are not necessarily limited to: 36 1. Division 0— Bidding Requirements, Contract Forms, and Conditions of the 37 Contract 38 2. Division 1 — General Requirements CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No. 106104 Revised September 12, 2025 000000-2 MATERIALS ON HAND Page 2 of 3 1 1.3 PRICE AND PAYMENT PROCEDURES 2 A.Measurement and Payment 3 1. Measurement and Payment 4 a. The material furnished in accordance with the specific item for which MOH is 5 allowed shall be measured and paid by the Lump Sum. 6 2. The price shall include: 7 a. Invoiced Cost of material ONLY 8 1.4 REFERENCES [NOT USED] 9 1.5 ADMINISTRATIVE REQUIREMENTS 10 A.A Change Order will be necessary. It will deduct the Bill of Sale quantity from the 11 original Furnish and Install quantity and add two separate line items —one for Furnish 12 and one for Install —each with its corresponding pricing. 13 1.6 SUBMITTALS 14 A.Contractor shall submit a Bill of Sale for the materials on hand properly identifying the 15 Project which shall be attached to the pay application and applicable materials to be 16 circled or highlighted, properly added up and totaled in documentation. 17 B. Submittals shall be in accordance with Section 01 33 00. 18 C.All submittals shall be approved by the Engineer or the City prior to delivery and/or 19 fabrication for specials. 20 1.7 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 21 A. Written agreement for offsite storage location 22 1.8 CLOSEOUT SUBMITTALS [NOT USED] 23 A.Maintenance Contracts 24 B. Operation and Maintenance Data 25 C. Warranty Documentation 26 D.Record Documentation 27 1.9 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 28 1.10 QUALITY ASSURANCE 29 A.The City shall confirm that the material or equipment conforms to specifications and is 30 properly marked and secured. 31 B.City's decision on what quantity of received material is to be paid is final. 32 1.11 DELIVERY, STORAGE, AND HANDLING 33 A.The risk of loss for the material or equipment does not pass to the City until the 34 associated Work is accepted. 35 1.12 DELIVERY AND ACCEPTANCE REQUIREMENTS 36 A. Storage and Handling Requirements CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No. 106104 Revised September 12, 2025 000000-3 MATERIALS ON HAND Page 3 of 3 1 B. Packaging Waste Management 2 1.13 FIELD [SITE] CONDITIONS [NOT USED] 3 A.Ambient Conditions 4 B.Existing Conditions 5 1.14 WARRANTY [NOT USED] 6 PART 2- PRODUCTS [NOT USED] 7 PART 3- EXECUTION [NOT USED] 8 9 10 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No. 106104 Revised September 12, 2025 01 3119- 1 DAP PRECONSTRUCTION MEETING Page 1 of 3 1 2 3 PART1- GENERAL SECTION 0131 19 PRECONSTRUCTION MEETING 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Provisions for the preconstruction meeting to be held prior to the start of Work to 7 clarify construction contract administration procedures 8 B. Deviations from this City of Fort Worth Standard Specification 9 1. No construction schedule required unless requested by the City. 10 C. Related Specification Sections include, but are not necessarily limited to: 11 1. Division 0— Bidding Requirements, Contract Forms and Conditions of the Contract 12 2. Division 1— General Requirements 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Work associated with this Item is considered subsidiary to the various items bid. 16 No separate payment will be allowed for this Item. 17 1.3 REFERENCES [NOT USED] 18 1.4 ADMINISTRATIVE REQUIREMENTS 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 A. Coordination 1. Attend preconstruction meeting. 2. Representatives of Contractor, subcontractors and suppliers attending meetings shall be qualified and authorized to act on behalf of the entity each represents. 3. Meeting administered by City may be tape recorded. a. If recorded, tapes will be used to prepare minutes and retained by City for future reference. B. Preconstruction Meeting 1. A preconstruction meeting will be held within 14 days after the delivery of the distribution package to the City. a. The meeting will be scheduled and administered by the City. 2. The Project Representative will preside at the meeting, prepare the notes of the meeting and distribute copies of same to all participants who so request by fully completing the attendance form to be circulated at the beginning of the meeting. 3. Attendance shall include: a. Developer and Consultant b. Contractor's project manager c. Contractor's superintendent d. Any subcontractor or supplier representatives whom the Contractor may desire to invite or the City may request CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August 30, 2013 013119-2 DAP PRECONSTRUCTION MEETING Page 2 of 3 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 e. Other City representatives f. Others as appropriate 4. Preliminary Agenda may include: a. Introduction of Project Personnel b. General Description of Project c. Status of right-of-way, utility clearances, easements or other pertinent permits d. Contractor's work plan and schedule e. Contract Time f. Notice to Proceed g. Construction Staking h. Progress Payments i. Extra Work and Change Order Procedures j. Field Orders k. Disposal Site Letter for Waste Material 1. Insurance Renewals m. Payroll Certification n. Material Certifications and Quality Control Testing o. Public Safety and Convenience p. Documentation of Pre -Construction Conditions q. Weekend Work Notification r. Legal Holidays s. Trench Safety Plans t. Confined Space Entry Standards u. Coordination with the City's representative for operations of existing water systems v. Storm Water Pollution Prevention Plan w. Coordination with other Contractors x. Early Warning System y. Contractor Evaluation z. Special Conditions applicable to the project aa. Damages Claims bb. Submittal Procedures cc. Substitution Procedures dd. Correspondence Routing ce. Record Drawings ff. Temporary construction facilities gg. MBE/SBE procedures hh. Final Acceptance ii. Final Payment CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August 30, 2013 013119-3 DAP PRECONSTRUCTION MEETING Page 3 of 3 1 jj. Questions or Comments 2 1.5 SUBMITTALS [NOT USED] 3 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 4 1.7 CLOSEOUT SUBMITTALS [NOT USED] 5 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 6 1.9 QUALITY ASSURANCE [NOT USED] 7 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 8 1.11 FIELD [SITE] CONDITIONS [NOT USED] 9 1.12 WARRANTY [NOT USED] 10 PART 2- PRODUCTS [NOT USED] 11 PART 3- EXECUTION [NOT USED] 12 13 14 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August 30, 2013 01 33 00 - 1 DAP SUBMITTALS Page 1 of8 1 2 3 PART1- GENERAL 4 1.1 SUMMARY SECTION 0133 00 DAP SUBMITTALS 5 A. Section Includes: 6 1. General methods and requirements of submissions applicable to the following 7 Work -related submittals: 8 a. Shop Drawings 9 b. Product Data (including Standard Product List submittals) 10 c. Samples 11 d. Mock Ups 12 B. Deviations from this City of Fort Worth Standard Specification 13 1. None. 14 C. Related Specification Sections include, but are not necessarily limited to: 15 1. Division 0— Bidding Requirements, Contract Forms and Conditions of the Contract 16 2. Division 1 — General Requirements 17 1.2 PRICE AND PAYMENT PROCEDURES 18 A. Measurement and Payment 19 1. Work associated with this Item is considered subsidiary to the various items bid. 20 No separate payment will be allowed for this Item. 21 1.3 REFERENCES [NOT USED] 22 1.4 ADMINISTRATIVE REQUIREMENTS 23 A. Coordination 24 1. Notify the City in writing, at the time of submittal, of any deviations in the 25 submittals from the requirements of the Contract Documents. 26 2. Coordination of Submittal Times 27 a. Prepare, prioritize and transmit each submittal sufficiently in advance of 28 performing the related Work or other applicable activities, or within the time 29 specified in the individual Work Sections, of the Specifications. 30 b. Contractor is responsible such that the installation will not be delayed by 31 processing times including, but not limited to: 32 a) Disapproval and resubmittal (if required) 33 b) Coordination with other submittals 34 c) Testing 35 d) Purchasing 36 e) Fabrication 37 f) Delivery 38 g) Similar sequenced activities 39 c. No extension of time will be authorized because of the Contractor's failure to 40 transmit submittals sufficiently in advance of the Work. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August 30, 2013 013300-2 DAP SUBMITTALS Page 2 of 8 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 d. Make submittals promptly in accordance with approved schedule, and in such sequence as to cause no delay in the Work or in the work of any other contractor. B. Submittal Numbering When submitting shop drawings or samples, utilize a 9 -character submittal cross- reference identification numbering system in the following manner: a. Use the first 6 digits of the applicable Specification Section Number. b. For the next 2 digits number use numbers 01-99 to sequentially number each initial separate item or drawing submitted under each specific Section number. c. Last use a letter, A -Z, indicating the resubmission of the same drawing (i.e. A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical submittal number would be as follows: 03 30 00-08-B 1) 03 30 00 is the Specification Section for Concrete 2) 08 is the eighth initial submittal under this Specification Section 3) B is the third submission (second resubmission) of that particular shop drawing C. Contractor Certification 1. Review shop drawings, product data and samples, including those by subcontractors, prior to submission to determine and verify the following: a. Field measurements b. Field construction criteria c. Catalog numbers and similar data d. Conformance with the Contract Documents 2. Provide each shop drawing, sample and product data submitted by the Contractor with a Certification Statement affixed including: a. The Contractor's Company name b. Signature of submittal reviewer c. Certification Statement 1) "By this submittal, I hereby represent that I have determined and verified field measurements, field construction criteria, materials, dimensions, catalog numbers and similar data and I have checked and coordinated each item with other applicable approved shop drawings." D. Submittal Format 1. Fold shop drawings larger than 8 '/2 inches x 11 inches to 8 1/2 inches x l l inches. 2. Bind shop drawings and product data sheets together. 3. Order a. Cover Sheet 1) Description of Packet 2) Contractor Certification b. List of items / Table of Contents c. Product Data /Shop Drawings/Samples /Calculations E. Submittal Content 1. The date of submission and the dates of any previous submissions CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August 30, 2013 01 3300-3 DAP SUBMITTALS Page 3 of 8 1 2. The Project title and number 2 3. Contractor identification 3 4. The names of: 4 a. Contractor 5 b. Supplier 6 c. Manufacturer 7 5. Identification of the product, with the Specification Section number, page and 8 paragraph(s) 9 6. Field dimensions, clearly identified as such 10 7. Relation to adjacent or critical features of the Work or materials 11 8. Applicable standards, such as ASTM or Federal Specification numbers 12 9. Identification by highlighting of deviations from Contract Documents 13 10. Identification by highlighting of revisions on resubmittals 14 11. An 8 -inch x 3 -inch blank space for Contractor and City stamps 15 F. Shop Drawings 16 1. As specified in individual Work Sections includes, but is not necessarily limited to: 17 a. Custom -prepared data such as fabrication and erection/installation (working) 18 drawings 19 b. Scheduled information 20 c. Setting diagrams 21 d. Actual shopwork manufacturing instructions 22 e. Custom templates 23 f. Special wiring diagrams 24 g. Coordination drawings 25 h. Individual system or equipment inspection and test reports including: 26 1) Performance curves and certifications 27 i. As applicable to the Work 28 2. Details 29 a. Relation of the various parts to the main members and lines of the structure 30 b. Where correct fabrication of the Work depends upon field measurements 31 1) Provide such measurements and note on the drawings prior to submitting 32 for approval. 33 G. Product Data 34 1. For submittals of product data for products included on the City's Standard Product 35 List, clearly identify each item selected for use on the Project. 36 2. For submittals of product data for products not included on the City's Standard 37 Product List, submittal data may include, but is not necessarily limited to: 38 a. Standard prepared data for manufactured products (sometimes referred to as 39 catalog data) 40 1) Such as the manufacturer's product specification and installation 41 instructions 42 2) Availability of colors and patterns 43 3) Manufacturer's printed statements of compliances and applicability 44 4) Roughing -in diagrams and templates 45 5) Catalog cuts 46 6) Product photographs CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August 30, 2013 013300-4 DAP SUBMITTALS Page 4 of 8 1 7) Standard wiring diagrams 2 8) Printed performance curves and operational -range diagrams 3 9) Production or quality control inspection and test reports and certifications 4 10) Mill reports 5 11) Product operating and maintenance instructions and recommended 6 spare -parts listing and printed product warranties 7 12) As applicable to the Work 8 H. Samples 9 1. As specified in individual Sections, include, but are not necessarily limited to: 10 a. Physical examples of the Work such as: 11 1) Sections of manufactured or fabricated Work 12 2) Small cuts or containers of materials 13 3) Complete units of repetitively used products color/texture/pattern swatches 14 and range sets 15 4) Specimens for coordination of visual effect 16 5) Graphic symbols and units of Work to be used by the City for independent 17 inspection and testing, as applicable to the Work 18 I. Do not start Work requiring a shop drawing, sample or product data nor any material to 19 be fabricated or installed prior to the approval or qualified approval of such item. 20 1. Fabrication performed, materials purchased or on -site construction accomplished 21 which does not conform to approved shop drawings and data is at the Contractor's 22 risk. 23 2. The City will not be liable for any expense or delay due to corrections or remedies 24 required to accomplish conformity. 25 3. Complete project Work, materials, fabrication, and installations in conformance 26 with approved shop drawings, applicable samples, and product data. 27 J. Submittal Distribution 28 1. Electronic Distribution 29 a. Confirm development of Project directory for electronic submittals to be 30 uploaded to City's Buzzsaw site, or another external FTP site approved by the 31 City. 32 b. Shop Drawings 33 1) Upload submittal to designated project directory and notify appropriate 34 City representatives via email of submittal posting. 35 2) Hard Copies 36 a) 3 copies for all submittals 37 b) If Contractor requires more than 1 hard copy of Shop Drawings 38 returned, Contractor shall submit more than the number of copies listed 39 above. 40 c. Product Data 41 1) Upload submittal to designated project directory and notify appropriate 42 City representatives via email of submittal posting. 43 2) Hard Copies 44 a) 3 copies for all submittals 45 d. Samples 46 1) Distributed to the Project Representative 47 2. Hard Copy Distribution (if required in lieu of electronic distribution) CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August 30, 2013 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 01 3300-5 DAP SUBMITTALS Page 5 of 8 a. Shop Drawings 1) Distributed to the City 2) Copies a) 8 copies for mechanical submittals b) 7 copies for all other submittals c) If Contractor requires more than 3 copies of Shop Drawings returned, Contractor shall submit more than the number of copies listed above. b. Product Data 1) Distributed to the City 2) Copies a) 4 copies c. Samples 1) Distributed to the Project Representative 2) Copies a) Submit the number stated in the respective Specification Sections. 3. Distribute reproductions of approved shop drawings and copies of approved product data and samples, where required, to the job site file and elsewhere as directed by the City. a. Provide number of copies as directed by the City but not exceeding the number previously specified. K. Submittal Review 1. The review of shop drawings, data and samples will be for general conformance with the design concept and Contract Documents. This is not to be construed as: a. Permitting any departure from the Contract requirements b. Relieving the Contractor of responsibility for any errors, including details, dimensions, and materials c. Approving departures from details furnished by the City, except as otherwise provided herein 2. The review and approval of shop drawings, samples or product data by the City does not relieve the Contractor from his/her responsibility with regard to the fulfillment of the terms of the Contract. a. All risks of error and omission are assumed by the Contractor, and the City will have no responsibility therefore. 3. The Contractor remains responsible for details and accuracy, for coordinating the Work with all other associated work and trades, for selecting fabrication processes, for techniques of assembly and for performing Work in a safe manner. 4. If the shop drawings, data or samples as submitted describe variations and show a departure from the Contract requirements which City finds to be in the interest of the City and to be so minor as not to involve a change in Contract Price or time for performance, the City may return the reviewed drawings without noting an exception. 5. Submittals will be returned to the Contractor under 1 of the following codes: a. Code 1 1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or comments on the submittal. a) When returned under this code the Contractor may release the equipment and/or material for manufacture. b. Code 2 CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August 30, 2013 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 01 3300-6 DAP SUBMITTALS Page 6 of 8 1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of the notations and comments IS NOT required by the Contractor. a) The Contractor may release the equipment or material for manufacture; however, all notations and comments must be incorporated into the final product. c. Code 3 1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is assigned when notations and comments are extensive enough to require a resubmittal of the package. a) The Contractor may release the equipment or material for manufacture; however, all notations and comments must be incorporated into the final product. b) This resubmittal is to address all comments, omissions and non -conforming items that were noted. c) Resubmittal is to be received by the City within 15 Calendar Days of the date of the City's transmittal requiring the resubmittal. d. Code 4 1) "NOT APPROVED" is assigned when the submittal does not meet the intent of the Contract Documents. a) The Contractor must resubmit the entire package revised to bring the submittal into conformance. b) It may be necessary to resubmit using a different manufacturer/vendor to meet the Contract Documents. 6. Resubmittals a. Handled in the same manner as first submittals 1) Corrections other than requested by the City 2) Marked with revision triangle or other similar method a) At Contractor's risk if not marked b. Submittals for each item will be reviewed no more than twice at the City's expense. 1) All subsequent reviews will be performed at times convenient to the City and at the Contractor's expense, based on the City's or City Representative's then prevailing rates. 2) Provide Contractor reimbursement to the City within 30 Calendar Days for all such fees invoiced by the City. c. The need for more than 1 resubmission or any other delay in obtaining City's review of submittals, will not entitle the Contractor to an extension of Contract Time. 7. Partial Submittals a. City reserves the right to not review submittals deemed partial, at the City's discretion. b. Submittals deemed by the City to be not complete will be returned to the Contractor, and will be considered "Not Approved" until resubmitted. c. The City may at its option provide a list or mark the submittal directing the Contractor to the areas that are incomplete. 8. If the Contractor considers any correction indicated on the shop drawings to constitute a change to the Contract Documents, then written notice must be provided thereof to the Developer at least 7 Calendar Days prior to release for manufacture. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August 30, 2013 01 3300-7 DAP SUBMITTALS Page 7 of 8 1 9. When the shop drawings have been completed to the satisfaction of the City, the 2 Contractor may carry out the construction in accordance therewith and no further 3 changes therein except upon written instructions from the City. 4 10. Each submittal, appropriately coded, will be returned within 30 Calendar Days 5 following receipt of submittal by the City. 6 L. Mock ups 7 1. Mock Up units as specified in individual Sections, include, but are not necessarily 8 limited to, complete units of the standard of acceptance for that type of Work to be 9 used on the Project. Remove at the completion of the Work or when directed. 10 M. Qualifications 11 1. If specifically required in other Sections of these Specifications, submit a P.E. 12 Certification for each item required. 13 N. Request for Information (RFI) 14 1. Contractor Request for additional information 15 a. Clarification or interpretation of the contract documents 16 b. When the Contractor believes there is a conflict between Contract Documents 17 c. When the Contractor believes there is a conflict between the Drawings and 18 Specifications 19 1) Identify the conflict and request clarification 20 2. Sufficient information shall be attached to permit a written response without further 21 information. 22 23 24 25 26 1.5 SUBMITTALS [NOT USED] 27 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 28 1.7 CLOSEOUT SUBMITTALS [NOT USED] 29 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 30 1.9 QUALITY ASSURANCE [NOT USED] 31 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 32 1.11 FIELD [SITE] CONDITIONS [NOT USED] 33 1.12 WARRANTY [NOT USED] CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August 30, 2013 01 3300-8 DAP SUBMITTALS Page 8 of 8 1 PART 2- PRODUCTS [NOT USED] 2 PART 3- EXECUTION [NOT USED] 3 END OF SECTION 4 Revision Log DATE NAME SUMMARY OF CHANGE CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August 30, 2013 013513-1 DAP SPECIAL PROJECT PROCEDURES Page 1 of 7 1 SECTION 0135 13 2 SPECIAL PROJECT PROCEDURES 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. The procedures for special project circumstances that includes, but is not limited to: 7 a. Coordination with the Texas Department of Transportation 8 b. Work near High Voltage Lines 9 c. Confined Space Entry Program 10 d. Air Pollution Watch Days 11 e. Use of Explosives, Drop Weight, Etc. 12 f. Water Department Notification 13 g. Public Notification Prior to Beginning Construction 14 h. Coordination with United States Army Corps of Engineers 15 i. Coordination within Railroad permits areas 16 j. Dust Control 17 k. Employee Parking 18 19 B. Deviations from this City of Fort Worth Standard Specification 20 1. None. 21 C. Related Specification Sections include, but are not necessarily limited to: 22 1. Division 0— Bidding Requirements, Contract Forms and Conditions of the Contract 23 2. Division 1 — General Requirements 24 3. Section 33 12 25 — Connection to Existing Water Mains 25 26 1.2 REFERENCES 27 A. Reference Standards 28 1. Reference standards cited in this Specification refer to the current reference 29 standard published at the time of the latest revision date logged at the end of this 30 Specification, unless a date is specifically cited. 31 2. Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752. 32 High Voltage Overhead Lines. 33 3. North Central Texas Council of Governments (NCTCOG) — Clean Construction 34 Specification 35 1.3 ADMINISTRATIVE REQUIREMENTS 36 A. Coordination with the Texas Department of Transportation 37 1. When work in the right-of-way which is under the jurisdiction of the Texas 38 Department of Transportation (TxDOT): 39 a. Notify the Texas Department of Transportation prior to commencing any work 40 therein in accordance with the provisions of the permit CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August, 30, 2013 013513-2 DAP SPECIAL PROJECT PROCEDURES Page 2 of 7 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 b. All work performed in the TxDOT right-of-way shall be performed in compliance with and subject to approval from the Texas Department of Transportation B. Work near High Voltage Lines 1. Regulatory Requirements a. All Work near High Voltage Lines (more than 600 volts measured between conductors or between a conductor and the ground) shall be in accordance with Health and Safety Code, Title 9, Subtitle A, Chapter 752. 2. Warning sign a. Provide sign of sufficient size meeting all OSHA requirements. 3. Equipment operating within 10 feet of high voltage lines will require the following safety features a. Insulating cage -type of guard about the boom or arm b. Insulator links on the lift hook connections for back hoes or dippers c. Equipment must meet the safety requirements as set forth by OSHA and the safety requirements of the owner of the high voltage lines 4. Work within 6 feet of high voltage electric lines a. Notification shall be given to: 1) The power company (example: ONCOR) a) Maintain an accurate log of all such calls to power company and record action taken in each case. b. Coordination with power company 1) After notification coordinate with the power company to: a) Erect temporary mechanical barriers, de -energize the lines, or raise or lower the lines c. No personnel may work within 6 feet of a high voltage line before the above requirements have been met. C. Confined Space Entry Program 1. Provide and follow approved Confined Space Entry Program in accordance with OSHA requirements. 2. Confined Spaces include: a. Manholes b. All other confined spaces in accordance with OSHA's Permit Required for Confined Spaces D. Use of Explosives, Drop Weight, Etc. 1. When Contract Documents permit on the project the following will apply: a. Public Notification 1) Submit notice to City and proof of adequate insurance coverage, 24 hours prior to commencing. 2) Minimum 24 hour public notification in accordance with Section 01 3113 E. Water Department Coordination 1. During the construction of this project, it will be necessary to deactivate, for a period of time, existing lines. The Contractor shall be required to coordinate with the Water Department to determine the best times for deactivating and activating those lines. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August, 30, 2013 01 35 13 -3 DAP SPECIAL PROJECT PROCEDURES Page 3 of 7 1 2. Coordinate any event that will require connecting to or the operation of an existing 2 City water line system with the City's representative. 3 a. Coordination shall be in accordance with Section 33 12 25. 4 b. If needed, obtain a hydrant water meter from the Water Department for use 5 during the life of named project. 6 c. In the event that a water valve on an existing live system be turned off and on 7 to accommodate the construction of the project is required, coordinate this 8 activity through the appropriate City representative. 9 1) Do not operate water line valves of existing water system. 10 a) Failure to comply will render the Contractor in violation of Texas Penal 11 Code Title 7, Chapter 28.03 (Criminal Mischief) and the Contractor 12 will be prosecuted to the full extent of the law. 13 b) In addition, the Contractor will assume all liabilities and 14 responsibilities as a result of these actions. 15 F. Public Notification Prior to Beginning Construction 16 1. Prior to beginning construction on any block in the project, on a block by block 17 basis, prepare and deliver a notice or flyer of the pending construction to the front 18 door of each residence or business that will be impacted by construction. The notice 19 shall be prepared as follows: 20 a. Post notice or flyer 7 days prior to beginning any construction activity on each 21 block in the project area. 22 1) Prepare flyer on the Contractor's letterhead and include the following 23 information: 24 a) Name of Project 25 b) City Project No (CPN) 26 c) Scope of Project (i.e. type of construction activity) 27 d) Actual construction duration within the block 28 e) Name of the contractor's foreman and phone number 29 f) Name of the City's inspector and phone number 30 g) City's after-hours phone number 31 2) A sample of the `pre -construction notification' flyer is attached as Exhibit 32 A. 33 3) Submit schedule showing the construction start and finish time for each 34 block of the project to the inspector. 35 4) Deliver flyer to the City Inspector for review prior to distribution. 36 b. No construction will be allowed to begin on any block until the flyer is 37 delivered to all residents of the block. 38 G. Public Notification of Temporary Water Service Interruption during Construction 39 1. In the event it becomes necessary to temporarily shut down water service to 40 residents or businesses during construction, prepare and deliver a notice or flyer of 41 the pending interruption to the front door of each affected resident. 42 2. Prepared notice as follows: 43 a. The notification or flyer shall be posted 24 hours prior to the temporary 44 interruption. 45 b. Prepare flyer on the contractor's letterhead and include the following 46 information: 47 1) Name of the project 48 2) City Project Number CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August, 30, 2013 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 013513-4 DAP SPECIAL PROJECT PROCEDURES Page 4 of 7 3) Date of the interruption of service 4) Period the interruption will take place 5) Name of the contractor's foreman and phone number 6) Name of the City's inspector and phone number c. A sample of the temporary water service interruption notification is attached as Exhibit B. d. Deliver a copy of the temporary interruption notification to the City inspector for review prior to being distributed. e. No interruption of water service can occur until the flyer has been delivered to all affected residents and businesses. f. Electronic versions of the sample flyers can be obtained from the Project Construction Inspector. H. Coordination with United States Army Corps of Engineers (USACE) At locations in the Project where construction activities occur in areas where USACE permits are required, meet all requirements set forth in each designated permit. I. Coordination within Railroad Permit Areas At locations in the project where construction activities occur in areas where railroad permits are required, meet all requirements set forth in each designated railroad permit. This includes, but is not limited to, provisions for: a. Flagmen b. Inspectors c. Safety training d. Additional insurance e. Insurance certificates f. Other employees required to protect the right-of-way and property of the Railroad Company from damage arising out of and/or from the construction of the project. Proper utility clearance procedures shall be used in accordance with the permit guidelines. 2. Obtain any supplemental information needed to comply with the railroad's requirements. J. Dust Control 1. Use acceptable measures to control dust at the Site. a. If water is used to control dust, capture and properly dispose of waste water. b. If wet saw cutting is performed, capture and properly dispose of slurry. K. Employee Parking 1. Provide parking for employees at locations approved by the City. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August, 30, 2013 01 35 13 -5 DAP SPECIAL PROJECT PROCEDURES Page 5 of 7 1 1.4 SUBMITTALS [NOT USED] 2 1.5 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 3 1.6 CLOSEOUT SUBMITTALS [NOT USED] 4 1.7 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 5 1.8 QUALITY ASSURANCE [NOT USED] 6 1.9 DELIVERY, STORAGE, AND HANDLING [NOT USED] 7 1.10 FIELD [SITE] CONDITIONS [NOT USED] 8 1.11 WARRANTY [NOT USED] 9 PART 2- PRODUCTS [NOT USED] 10 PART 3- EXECUTION [NOT USED] 11 12 13 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D. Johnson 1.3.B — Added requirement of compliance with Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752. High Voltage Overhead Lines. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August, 30, 2013 013513-6 DAP SPECIAL PROJECT PROCEDURES Page 6 of 7 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 EXHIBIT A (To be printed on Contractor's Letterhead) Date: CPN No.: Project Name: Mapsco Location: Limits of Construction: THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT WORTH, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR PROPERTY. CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE OF THIS NOTICE. IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER ISSUE, PLEASE CALL: Mr. <CONTRACTOR'S SUPERINTENDENT> AT <TELEPHONE NO.> OR Mr. <CITY INSPECTOR> AT < TELEPHONE NO.> AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL (817) 392 8306 PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August, 30, 2013 01 35 13 -7 DAP SPECIAL PROJECT PROCEDURES Page 7 of 7 1 EXHIBIT B Pa FORT WORTH Date: DOE NO. XXXX Project Name: NOTICE OF TEMPORARY WATER SERVICE INTERRUPTION DUE TO UTILITY IMPROVEMENTS IN YOUR NEIGHBORHOOD, YOUR WATER SERVICE WILL BE INTERRUPTED ON BETWEEN THE HOURS OF AND IF YOU HAVE QUESTIONS ABOUT THIS SHUT -OUT, PLEASE CALL: MR. AT (CONTRACTORS SUPERINTENDENT) (TELEPHONE NUMBER) 3 4 OR MR. (CITY INSPECTOR) AT (TELEPHONE NUMBER) THIS INCONVENIENCE WILL BE AS SHORT AS POSSIBLE. THANK YOU, CONTRACTOR CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised August, 30, 2013 014523-1 DAP TESTING AND INSPECTION SERVICES Page 1 of 2 1 SECTION 0145 23 2 TESTING AND INSPECTION SERVICES 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Testing and inspection services procedures and coordination 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0— Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division 1 — General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various Items bid. 15 No separate payment will be allowed for this Item. 16 a. Contractor is responsible for performing, coordinating, and payment of all 17 Quality Control testing. 18 b. City is responsible for performing and payment for first set of Quality 19 Assurance testing. 20 1) If the first Quality Assurance test performed by the City fails, the 21 Contractor is responsible for payment of subsequent Quality Assurance 22 testing until a passing test occurs. 23 a) Final acceptance will not be issued by City until all required payments 24 for testing by Contractor have been paid in full. 25 1.3 REFERENCES [NOT USED] 26 1.4 ADMINISTRATIVE REQUIREMENTS 27 A. Testing 28 1. Complete testing in accordance with the Contract Documents. 29 2. Coordination 30 a. When testing is required to be performed by the City, notify City, sufficiently 31 in advance, when testing is needed. 32 b. When testing is required to be completed by the Contractor, notify City, 33 sufficiently in advance, that testing will be performed. 34 3. Distribution of Testing Reports 35 a. Electronic Distribution 36 1) Confirm development of Project directory for electronic submittals to be 37 uploaded to the City's document management system, or another form of 38 distribution approved by the City. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised March 20, 2020 014523-2 DAP TESTING AND INSPECTION SERVICES Page 2 of 2 1 2) Upload test reports to designated project directory and notify appropriate 2 City representatives via email of submittal posting. 3 3) Hard Copies 4 a) 1 copy for all submittals submitted to the Project Representative 5 b. Hard Copy Distribution (if required in lieu of electronic distribution) 6 1) Tests performed by City 7 a) Distribute 1 hard copy to the Contractor 8 2) Tests performed by the Contractor 9 a) Distribute 3 hard copies to City's Project Representative 10 4. Provide City's Project Representative with trip tickets for each delivered load of 11 Concrete or Lime material including the following information: 12 a. Name of pit 13 b. Date of delivery 14 c. Material delivered 15 B. Inspection 16 1. Inspection or lack of inspection does not relieve the Contractor from obligation to 17 perform work in accordance with the Contract Documents. 18 1.5 SUBMITTALS [NOT USED] 19 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 20 1.7 CLOSEOUT SUBMITTALS [NOT USED] 21 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 22 1.9 QUALITY ASSURANCE [NOT USED] 23 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 24 1.11 FIELD [SITE] CONDITIONS [NOT USED] 25 1.12 WARRANTY [NOT USED] 26 PART 2- PRODUCTS [NOT USED] 27 PART 3- EXECUTION [NOT USED] 28 29 30 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 03/20/2020 D.V. Magaiia Removed reference to Buzzsaw and noted that electronic submittals be uploaded through the City's document management system. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised March 20, 2020 01 50 00 - 1 DAP TEMPORARY FACILITIES AND CONTROLS Page 1 of 4 1 SECTION 01 50 00 2 TEMPORARY FACILITIES AND CONTROLS 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Provide temporary facilities and controls needed for the Work including, but not 7 necessarily limited to: 8 a. Temporary utilities 9 b. Sanitary facilities 10 c. Storage Sheds and Buildings 11 d. Dust control 12 e. Temporary fencing of the construction site 13 B. Deviations from this City of Fort Worth Standard Specification 14 1. None. 15 C. Related Specification Sections include, but are not necessarily limited to: 16 1. Division 0— Bidding Requirements, Contract Forms and Conditions of the Contract 17 2. Division 1 — General Requirements 18 1.2 PRICE AND PAYMENT PROCEDURES 19 A. Measurement and Payment 20 1. Work associated with this Item is considered subsidiary to the various Items bid. 21 No separate payment will be allowed for this Item. 22 1.3 REFERENCES [NOT USED] 23 1.4 ADMINISTRATIVE REQUIREMENTS 24 A. Temporary Utilities 25 1. Obtaining Temporary Service 26 a. Make arrangements with utility service companies for temporary services. 27 b. Abide by rules and regulations of utility service companies or authorities 28 having jurisdiction. 29 c. Be responsible for utility service costs until Work is approved for Final 30 Acceptance. 31 1) Included are fuel, power, light, heat and other utility services necessary for 32 execution, completion, testing and initial operation of Work. 33 2. Water 34 a. Contractor to provide water required for and in connection with Work to be 35 performed and for specified tests of piping, equipment, devices or other use as 36 required for the completion of the Work. 37 b. Provide and maintain adequate supply of potable water for domestic 38 consumption by Contractor personnel and City's Project Representatives. 39 c. Coordination 40 1) Contact City 1 week before water for construction is desired CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised JULY 1, 2011 015000-2 DAP TEMPORARY FACILITIES AND CONTROLS Page 2 of 4 1 d. Contractor Payment for Construction Water 2 1) Obtain construction water meter from City for payment as billed by City's 3 established rates. 4 3. Electricity and Lighting 5 a. Provide and pay for electric powered service as required for Work, including 6 testing of Work. 7 1) Provide power for lighting, operation of equipment, or other use. 8 b. Electric power service includes temporary power service or generator to 9 maintain operations during scheduled shutdown. 10 4. Telephone 11 a. Provide emergency telephone service at Site for use by Contractor personnel 12 and others performing work or furnishing services at Site. 13 5. Temporary Heat and Ventilation 14 a. Provide temporary heat as necessary for protection or completion of Work. 15 b. Provide temporary heat and ventilation to assure safe working conditions. 16 B. Sanitary Facilities 17 1. Provide and maintain sanitary facilities for persons on Site. 18 a. Comply with regulations of State and local departments of health. 19 2. Enforce use of sanitary facilities by construction personnel at job site. 20 a. Enclose and anchor sanitary facilities. 21 b. No discharge will be allowed from these facilities. 22 c. Collect and store sewage and waste so as not to cause nuisance or health 23 problem. 24 d. Haul sewage and waste off -site at no less than weekly intervals and properly 25 dispose in accordance with applicable regulation. 26 3. Locate facilities near Work Site and keep clean and maintained throughout Project. 27 4. Remove facilities at completion of Project 28 C. Storage Sheds and Buildings 29 1. Provide adequately ventilated, watertight, weatherproof storage facilities with floor 30 above ground level for materials and equipment susceptible to weather damage. 31 2. Storage of materials not susceptible to weather damage may be on blocks off 32 ground. 33 3. Store materials in a neat and orderly manner. 34 a. Place materials and equipment to permit easy access for identification, 35 inspection and inventory. 36 4. Equip building with lockable doors and lighting, and provide electrical service for 37 equipment space heaters and heating or ventilation as necessary to provide storage 38 environments acceptable to specified manufacturers. 39 5. Fill and grade site for temporary structures to provide drainage away from 40 temporary and existing buildings. 41 6. Remove building from site prior to Final Acceptance. 42 D. Temporary Fencing 43 1. Provide and maintain for the duration or construction when required in contract 44 documents 45 E. Dust Control CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised JULY 1, 2011 015000-3 DAP TEMPORARY FACILITIES AND CONTROLS Page 3 of 4 1 1. Contractor is responsible for maintaining dust control through the duration of the 2 project. 3 a. Contractor remains on -call at all times 4 b. Must respond in a timely manner 5 F. Temporary Protection of Construction 6 1. Contractor or subcontractors are responsible for protecting Work from damage due 7 to weather. 8 1.5 SUBMITTALS [NOT USED] 9 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 10 1.7 CLOSEOUT SUBMITTALS [NOT USED] 11 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 12 1.9 QUALITY ASSURANCE [NOT USED] 13 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 14 1.11 FIELD [SITE] CONDITIONS [NOT USED] 15 1.12 WARRANTY [NOT USED] 16 PART 2- PRODUCTS [NOT USED] 17 PART 3- EXECUTION [NOT USED] 18 3.1 INSTALLERS [NOT USED] 19 3.2 EXAMINATION [NOT USED] 20 3.3 PREPARATION [NOT USED] 21 3.4 INSTALLATION 22 A. Temporary Facilities 23 1. Maintain all temporary facilities for duration of construction activities as needed. 24 3.5 [REPAIR] / [RESTORATION] 25 3.6 RE -INSTALLATION 26 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 27 3.8 SYSTEM STARTUP [NOT USED] 28 3.9 ADJUSTING [NOT USED] 29 3.10 CLEANING [NOT USED] 30 3.11 CLOSEOUT ACTIVITIES 31 A. Temporary Facilities CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised JULY 1, 2011 015000-4 DAP TEMPORARY FACILITIES AND CONTROLS Page 4 of 4 1 1. Remove all temporary facilities and restore area after completion of the Work, to a 2 condition equal to or better than prior to start of Work. 3 3.12 PROTECTION [NOT USED] 4 3.13 MAINTENANCE [NOT USED] 5 3.14 ATTACHMENTS [NOT USED] 6 7 8 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised JULY 1, 2011 01 55 26 - 1 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 1 of 3 1 SECTION 01 55 26 2 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Administrative procedures for: 7 a. Street Use Permit 8 b. Modification of approved traffic control 9 c. Removal of Street Signs 10 B. Deviations from this City of Fort Worth Standard Specification 11 1. None. 12 C. Related Specification Sections include, but are not necessarily limited to: 13 1. Division 0— Bidding Requirements, Contract Forms and Conditions of the Contract 14 2. Division 1 — General Requirements 15 3. Section 34 71 13 — Traffic Control 16 1.2 PRICE AND PAYMENT PROCEDURES 17 A. Measurement and Payment 18 1. Work associated with this Item is considered subsidiary to the various Items bid. 19 No separate payment will be allowed for this Item. 20 1.3 REFERENCES 21 A. Reference Standards 22 1. Reference standards cited in this specification refer to the current reference standard 23 published at the time of the latest revision date logged at the end of this 24 specification, unless a date is specifically cited. 25 2. Texas Manual on Uniform Traffic Control Devices (TMUTCD). 26 1.4 ADMINISTRATIVE REQUIREMENTS 27 A. Traffic Control 28 1. General 29 a. When traffic control plans are included in the Drawings, provide Traffic 30 Control in accordance with Drawings and Section 34 71 13. 31 b. When traffic control plans are not included in the Drawings, prepare traffic 32 control plans in accordance with Section 34 71 13 and submit to City for 33 review. 34 1) Allow minimum 10 working days for review of proposed Traffic Control. 35 B. Street Use Permit 36 1. Prior to installation of Traffic Control, a City Street Use Permit is required. 37 a. To obtain Street Use Permit, submit Traffic Control Plans to City 38 Transportation and Public Works Department. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised July 1, 2011 015526-2 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 2 of 3 1 1) Allow a minimum of 5 working days for permit review. 2 2) Contractor's responsibility to coordinate review of Traffic Control plans for 3 Street Use Permit, such that construction is not delayed. 4 C. Modification to Approved Traffic Control 5 1. Prior to installation traffic control: 6 a. Submit revised traffic control plans to City Department Transportation and 7 Public Works Department. 8 1) Revise Traffic Control plans in accordance with Section 34 71 13. 9 2) Allow minimum 5 working days for review of revised Traffic Control. 10 3) It is the Contractor's responsibility to coordinate review of Traffic Control 11 plans for Street Use Permit, such that construction is not delayed. 12 D. Removal of Street Sign 13 1. If it is determined that a street sign must be removed for construction, then contact 14 City Transportation and Public Works Department, Signs and Markings Division to 15 remove the sign. 16 E. Temporary Signage 17 1. In the case of regulatory signs, replace permanent sign with temporary sign meeting 18 requirements of the latest edition of the Texas Manual on Uniform Traffic Control 19 Devices (MUTCD). 20 2. Install temporary sign before the removal of permanent sign. 21 3. When construction is complete, to the extent that the permanent sign can be 22 reinstalled, contact the City Transportation and Public Works Department, Signs 23 and Markings Division, to reinstall the permanent sign. 24 F. Traffic Control Standards 25 1. Traffic Control Standards can be found on the City's Buzzsaw website. 26 1.5 SUBMITTALS [NOT USED] 27 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 28 1.7 CLOSEOUT SUBMITTALS [NOT USED] 29 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 30 1.9 QUALITY ASSURANCE [NOT USED] 31 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 32 1.11 FIELD [SITE] CONDITIONS [NOT USED] 33 1.12 WARRANTY [NOT USED] 34 PART 2- PRODUCTS [NOT USED] 35 PART 3- EXECUTION [NOT USED] 36 END OF SECTION CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised July 1, 2011 015526-3 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 3 of 3 Revision Log DATE NAME SUMMARY OF CHANGE CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised July 1, 2011 015713-1 DAP STORM WATER POLLUTION PREVENTION Page 1 of 3 1 SECTION 01 57 13 2 STORM WATER POLLUTION PREVENTION 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Procedures for Storm Water Pollution Prevention Plans 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0— Bidding Requirements, Contract Forms and Conditions of the 11 Contract 12 2. Division 1— General Requirements 13 3. Section 31 25 00 — Erosion and Sediment Control 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Measurement and Payment 16 1. Construction Activities resulting in less than 1 acre of disturbance 17 a. Work associated with this Item is considered subsidiary to the various Items 18 bid. No separate payment will be allowed for this Item. 19 2. Construction Activities resulting in greater than 1 acre of disturbance 20 a. Measurement and Payment shall be in accordance with Section 31 25 00. 21 1.3 REFERENCES 22 A. Abbreviations and Acronyms 23 1. Notice of Intent: NOI 24 2. Notice of Termination: NOT 25 3. Storm Water Pollution Prevention Plan: SWPPP 26 4. Texas Commission on Environmental Quality: TCEQ 27 5. Notice of Change: NOC 28 A. Reference Standards 29 1. Reference standards cited in this Specification refer to the current reference 30 standard published at the time of the latest revision date logged at the end of this 31 Specification, unless a date is specifically cited. 32 2. Integrated Storm Management (iSWM) Technical Manual for Construction 33 Controls 34 1.4 ADMINISTRATIVE REQUIREMENTS 35 A. General 36 1. Contractor is responsible for resolution and payment of any fines issued associated 37 with compliance to Stormwater Pollution Prevention Plan. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised July 1, 2011 015713-2 DAP STORM WATER POLLUTION PREVENTION Page 2 of 3 B. Construction Activities resulting in: 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 1. Less than 1 acre of disturbance a. Provide erosion and sediment control in accordance with Section 31 25 00 and Drawings. 2. 1 to less than 5 acres of disturbance a. Texas Pollutant Discharge Elimination System (TPDES) General Construction Permit is required b. Complete SWPPP in accordance with TCEQ requirements 1) TCEQ Small Construction Site Notice Required under general permit TXR150000 a) Sign and post at job site b) Prior to Preconstruction Meeting, send 1 copy to City Department of Transportation and Public Works, Environmental Division, (817) 392- 6088. 2) Provide erosion and sediment control in accordance with: a) Section 31 25 00 b) The Drawings c) TXR150000 General Permit d) SWPPP e) TCEQ requirements 3. 5 acres or more of Disturbance a. Texas Pollutant Discharge Elimination System (TPDES) General Construction Permit is required b. Complete SWPPP in accordance with TCEQ requirements 1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee a) Sign and post at job site b) Send copy to City Department of Transportation and Public Works, Environmental Division, (817) 392-6088. 2) TCEQ Notice of Change required if making changes or updates to NOI 3) Provide erosion and sediment control in accordance with: a) Section 31 25 00 b) The Drawings c) TXR150000 General Permit d) SWPPP e) TCEQ requirements 4) Once the project has been completed and all the closeout requirements of TCEQ have been met a TCEQ Notice of Termination can be submitted. a) Send copy to City Department of Transportation and Public Works, Environmental Division, (817) 392-6088. 40 1.5 SUBMITTALS 41 42 43 44 45 46 47 A. SWPPP 1. Submit in accordance with Section 01 33 00, except as stated herein. a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City as follows: 1) 1 copy to the City Project Manager a) City Project Manager will forward to the City Department of Transportation and Public Works, Environmental Division for review CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised July 1, 2011 01 57 13 -3 DAP STORM WATER POLLUTION PREVENTION Page 3 of 3 1 B. Modified SWPPP 2 1. If the SWPPP is revised during construction, resubmit modified SWPPP to the City 3 in accordance with Section 01 33 00. 4 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 5 1.7 CLOSEOUT SUBMITTALS [NOT USED] 6 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 7 1.9 QUALITY ASSURANCE [NOT USED] 8 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 9 1.11 FIELD [SITE] CONDITIONS [NOT USED] 10 1.12 WARRANTY [NOT USED] 11 PART 2- PRODUCTS [NOT USED] 12 PART 3- EXECUTION [NOT USED] 13 14 15 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised July 1, 2011 016000-1 DAP PRODUCT REQUIREMENTS Page 1 of 2 1 2 3 PART1- GENERAL 4 1.1 SUMMARY SECTION 01 60 00 PRODUCT REQUIREMENTS 5 A. Section Includes: 6 1. References for Product Requirements and City Standard Products List 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0— Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division 1 — General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES [NOT USED] 13 1.3 REFERENCES [NOT USED] 14 1.4 ADMINISTRATIVE REQUIREMENTS 15 A. A list of City approved products for use is available through the City's website at: 16 1. https://apps.fortworthtexas.gov/ProjectResources/ v/ProjectResources/ and following the directory path: 17 02 — Construction Documents\Standard Products List 18 B. Only products specifically included on City's Standard Product List in these Contract 19 Documents shall be allowed for use on the Project. 20 1. Any subsequently approved products will only be allowed for use upon specific 21 approval by the City. 22 C. Any specific product requirements in the Contract Documents supersede similar 23 products included on the City's Standard Product List. 24 1. The City reserves the right to not allow products to be used for certain projects even 25 though the product is listed on the City's Standard Product List. 26 D. Although a specific product is included on City's Standard Product List, not all 27 products from that manufacturer are approved for use, including but not limited to, that 28 manufacturer's standard product. 29 E. See Section 01 33 00 for submittal requirements of Product Data included on City's 30 Standard Product List. 31 1.5 SUBMITTALS [NOT USED] 32 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 33 1.7 CLOSEOUT SUBMITTALS [NOT USED] 34 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 35 1.9 QUALITY ASSURANCE [NOT USED] CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised March 20, 2020 016000-2 DAP PRODUCT REQUIREMENTS Page 2 of 2 1 2 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 3 1.11 FIELD [SITE] CONDITIONS [NOT USED] 4 1.12 WARRANTY [NOT USED] 5 PART 2- PRODUCTS [NOT USED] 6 PART 3- EXECUTION [NOT USED] 7 8 9 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 10/12/12 D. Johnson Modified Location of City's Standard Product List 4/7/2014 M.Domenech Revised for DAP application 03/20/2020 D.V. Magaiia Removed reference to Buzzsaw and noted that the City approved products list is accessible through the City's website. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised March 20, 2020 01 6600- 1 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 1 of 4 1 SECTION 01 66 00 2 PRODUCT STORAGE AND HANDLING REQUIREMENTS 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Scheduling of product delivery 7 2. Packaging of products for delivery 8 3. Protection of products against damage from: 9 a. Handling 10 b. Exposure to elements or harsh environments 11 B. Deviations from this City of Fort Worth Standard Specification 12 1. None. 13 C. Related Specification Sections include, but are not necessarily limited to: 14 1. Division 0— Bidding Requirements, Contract Forms and Conditions of the Contract 15 2. Division 1 — General Requirements 16 1.2 PRICE AND PAYMENT PROCEDURES 17 A. Measurement and Payment 18 1. Work associated with this Item is considered subsidiary to the various Items bid. 19 No separate payment will be allowed for this Item. 20 1.3 REFERENCES [NOT USED] 21 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 22 1.5 SUBMITTALS [NOT USED] 23 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USEDI 24 1.7 CLOSEOUT SUBMITTALS [NOT USED] 25 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 26 1.9 QUALITY ASSURANCE [NOT USED] 27 1.10 DELIVERY AND HANDLING 28 A. Delivery Requirements 29 1. Schedule delivery of products or equipment as required to allow timely installation 30 and to avoid prolonged storage. 31 2. Provide appropriate personnel and equipment to receive deliveries. 32 3. Delivery trucks will not be permitted to wait extended periods of time on the Site 33 for personnel or equipment to receive the delivery. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 016600-2 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 2 of 4 1 4. Deliver products or equipment in manufacturer's original unbroken cartons or other 2 containers designed and constructed to protect the contents from physical or 3 environmental damage. 4 5. Clearly and fully mark and identify as to manufacturer, item and installation 5 location. 6 6. Provide manufacturer's instructions for storage and handling. 7 B. Handling Requirements 8 1. Handle products or equipment in accordance with these Contract Documents and 9 manufacturer's recommendations and instructions. 10 C. Storage Requirements 11 1. Store materials in accordance with manufacturer's recommendations and 12 requirements of these Specifications. 13 2. Make necessary provisions for safe storage of materials and equipment. 14 a. Place loose soil materials and materials to be incorporated into Work to prevent 15 damage to any part of Work or existing facilities and to maintain free access at 16 all times to all parts of Work and to utility service company installations in 17 vicinity of Work. 18 3. Keep materials and equipment neatly and compactly stored in locations that will 19 cause minimum inconvenience to other contractors, public travel, adjoining owners, 20 tenants and occupants. 21 a. Arrange storage to provide easy access for inspection. 22 4. Restrict storage to areas available on construction site for storage of material and 23 equipment as shown on Drawings, or approved by City's Project Representative. 24 5. Provide off -site storage and protection when on -site storage is not adequate. 25 a. Provide addresses of and access to off -site storage locations for inspection by 26 City's Project Representative. 27 6. Do not use lawns, grass plots or other private property for storage purposes without 28 written permission of owner or other person in possession or control of premises. 29 7. Store in manufacturers' unopened containers. 30 8. Neatly, safely and compactly stack materials delivered and stored along line of 31 Work to avoid inconvenience and damage to property owners and general public 32 and maintain at least 3 feet from fire hydrant. 33 9. Keep public and private driveways and street crossings open. 34 10. Repair or replace damaged lawns, sidewalks, streets or other improvements to 35 satisfaction of City's Project Representative. 36 a. Total length which materials may be distributed along route of construction at 37 one time is 1,000 linear feet, unless otherwise approved in writing by City's 38 Project Representative. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 016600-3 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 3 of 4 1 1.11 FIELD [SITE] CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED] 3 PART 2- PRODUCTS [NOT USED] 4 PART 3- EXECUTION 5 3.1 INSTALLERS [NOT USED] 6 3.2 EXAMINATION [NOT USED] 7 3.3 PREPARATION [NOT USED] 8 3.4 ERECTION [NOT USED] 9 3.5 REPAIR / RESTORATION [NOT USED] 10 3.6 RE -INSTALLATION [NOT USED] 11 3.7 FIELD [oR] SITE QUALITY CONTROL 12 A. Tests and Inspections 13 1. Inspect all products or equipment delivered to the site prior to unloading. 14 B. Non -Conforming Work 15 1. Reject all products or equipment that are damaged, used or in any other way 16 unsatisfactory for use on the project. 17 3.8 SYSTEM STARTUP [NOT USED] 18 3.9 ADJUSTING [NOT USED] 19 3.10 CLEANING [NOT USED] 20 3.11 CLOSEOUT ACTIVITIES [NOT USED] 21 3.12 PROTECTION 22 A. Protect all products or equipment in accordance with manufacturer's written directions. 23 B. Store products or equipment in location to avoid physical damage to items while in 24 storage. 25 C. Protect equipment from exposure to elements and keep thoroughly dry if required by 26 the manufacturer. 27 3.13 MAINTENANCE [NOT USED] 28 3.14 ATTACHMENTS [NOT USED] 29 END OF SECTION 30 CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 016600-4 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 4 of 4 Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 01 70 00 - 1 DAP MOBILIZATION AND REMOBILIZATION Page 1 of 4 1 SECTION 01 70 00 2 MOBILIZATION AND REMOBILIZATION 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 1. Mobilization and Demobilization a. Mobilization 1) Transportation of Contractor's personnel, equipment, and operating supplies to the Site 2) Establishment of necessary general facilities for the Contractor's operation at the Site 3) Premiums paid for performance and payment bonds 4) Transportation of Contractor's personnel, equipment, and operating supplies to another location within the designated Site 5) Relocation of necessary general facilities for the Contractor's operation from 1 location to another location on the Site. b. Demobilization 1) Transportation of Contractor's personnel, equipment, and operating supplies away from the Site including disassembly 2) Site Clean-up 3) Removal of all buildings and/or other facilities assembled at the Site for this Contract c. Mobilization and Demobilization do not include activities for specific items of work that are for which payment is provided elsewhere in the contract. 2. Remobilization a. Remobilization for Suspension of Work specifically required in the Contract Documents or as required by City includes: 1) Demobilization a) Transportation of Contractor's personnel, equipment, and operating supplies from the Site including disassembly or temporarily securing equipment, supplies, and other facilities as designated by the Contract Documents necessary to suspend the Work. b) Site Clean-up as designated in the Contract Documents 2) Remobilization a) Transportation of Contractor's personnel, equipment, and operating supplies to the Site necessary to resume the Work. b) Establishment of necessary general facilities for the Contractor's operation at the Site necessary to resume the Work. 3) No Payments will be made for: a) Mobilization and Demobilization from one location to another on the Site in the normal progress of performing the Work. b) Stand-by or idle time c) Lost profits 3. Mobilizations and Demobilization for Miscellaneous Projects a. Mobilization and Demobilization CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 017000-2 DAP MOBILIZATION AND REMOBILIZATION Page 2 of 4 1 1) Mobilization shall consist of the activities and cost on a Work Order basis 2 necessary for: 3 a) Transportation of Contractor's personnel, equipment, and operating 4 supplies to the Site for the issued Work Order. 5 b) Establishment of necessary general facilities for the Contractor's 6 operation at the Site for the issued Work Order 7 2) Demobilization shall consist of the activities and cost necessary for: 8 a) Transportation of Contractor's personnel, equipment, and operating 9 supplies from the Site including disassembly for each issued Work 10 Order 11 b) Site Clean-up for each issued Work Order 12 c) Removal of all buildings or other facilities assembled at the Site for 13 each Work Oder 14 b. Mobilization and Demobilization do not include activities for specific items of 15 work for which payment is provided elsewhere in the contract. 16 4. Emergency Mobilizations and Demobilization for Miscellaneous Projects 17 a. A Mobilization for Miscellaneous Projects when directed by the City and the 18 mobilization occurs within 24 hours of the issuance of the Work Order. 19 B. Deviations from this City of Fort Worth Standard Specification 20 1. None. 21 C. Related Specification Sections include, but are not necessarily limited to: 22 1. Division 0— Bidding Requirements, Contract Forms and Conditions of the Contract 23 2. Division 1— General Requirements 24 1.2 PRICE AND PAYMENT PROCEDURES 25 A. Measurement and Payment 26 1. Mobilization and Demobilization 27 a. Measure 28 1) This Item is considered subsidiary to the various Items bid. 29 b. Payment 30 1) The work performed and materials furnished in accordance with this Item 31 are subsidiary to the various Items bid and no other compensation will be 32 allowed. 33 2. Remobilization for suspension of Work as specifically required in the Contract 34 Documents 35 a. Measurement 36 1) Measurement for this Item shall be per each remobilization performed. 37 b. Payment 38 1) The work performed and materials furnished in accordance with this Item 39 and measured as provided under "Measurement" will be paid for at the unit 40 price per each "Specified Remobilization" in accordance with Contract 41 Documents. 42 c. The price shall include: 43 1) Demobilization as described in Section l.1.A.2.a.1) 44 2) Remobilization as described in Section 1.I.A.2.a.2) 45 d. No payments will be made for standby, idle time, or lost profits associated this 46 Item. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 017000-3 DAP MOBILIZATION AND REMOBILIZATION Page 3 of 4 1 3. Remobilization for suspension of Work as required by City 2 a. Measurement and Payment 3 1) This shall be submitted as a Contract Claim in accordance with Article 10 4 of Section 00 72 00. 5 2) No payments will be made for standby, idle time, or lost profits associated 6 with this Item. 7 4. Mobilizations and Demobilizations for Miscellaneous Projects 8 a. Measurement 9 1) Measurement for this Item shall be for each Mobilization and 10 Demobilization required by the Contract Documents 11 b. Payment 12 1) The Work performed and materials furnished in accordance with this Item 13 and measured as provided under "Measurement" will be paid for at the unit 14 price per each "Work Order Mobilization" in accordance with Contract 15 Documents. Demobilization shall be considered subsidiary to mobilization 16 and shall not be paid for separately. 17 c. The price shall include: 18 1) Mobilization as described in Section 1.I.A.3.a.1) 19 2) Demobilization as described in Section 1.l.A.3.a.2) 20 d. No payments will be made for standby, idle time, or lost profits associated this 21 Item. 22 5. Emergency Mobilizations and Demobilizations for Miscellaneous Projects 23 a. Measurement 24 1) Measurement for this Item shall be for each Mobilization and 25 Demobilization required by the Contract Documents 26 b. Payment 27 1) The Work performed and materials furnished in accordance with this Item 28 and measured as provided under "Measurement" will be paid for at the unit 29 price per each "Work Order Emergency Mobilization" in accordance with 30 Contract Documents. Demobilization shall be considered subsidiary to 31 mobilization and shall not be paid for separately. 32 c. The price shall include 33 1) Mobilization as described in Section l.1.A.4.a) 34 2) Demobilization as described in Section I.I.A.3.a.2) 35 d. No payments will be made for standby, idle time, or lost profits associated this 36 Item. 37 1.3 REFERENCES [NOT USED] 38 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 39 1.5 SUBMITTALS [NOT USED] 40 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 41 1.7 CLOSEOUT SUBMITTALS [NOT USED] 42 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 43 1.9 QUALITY ASSURANCE [NOT USED] 44 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 017000-4 DAP MOBILIZATION AND REMOBILIZATION Page 4 of 4 1 1.11 FIELD [SITE] CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED] 3 PART 2- PRODUCTS [NOT USED] 4 PART 3- EXECUTION [NOT USED] 5 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 01 71 23-1 CONSTRUCTION STAKING AND SURVEY Page 1 of 8 1 SECTION 01 71 23 2 CONSTRUCTION STAKING AND SURVEY 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Requirements for construction staking and construction survey 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. See Changes (Highlighted in Yellow). 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0— Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division 1— General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 A. Measurement and Payment 1. Construction Staking a. Measurement 1) This Item is considered subsidiary to the various Items bid. b. Payment 1) The work performed and the materials furnished in accordance with this Item are subsidiary to the various Items bid and no other compensation will be allowed. 2. Construction Survey a. Measurement 1) This Item is considered subsidiary to the various Items bid. b. Payment 1) The work performed and the materials furnished in accordance with this Item are subsidiary to the various Items bid and no other compensation will be allowed. 3. As -Built Survey a. Measurement 1) This Item is considered subsidiary to the various Items bid. b. Payment 1) The work performed and the materials furnished in accordance with this Item are subsidiary to the various Items bid and no other compensation will be allowed. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised February 14, 2018 017123-2 CONSTRUCTION STAKING AND SURVEY Page 2 of 8 1.3 REFERENCES 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 A. Definitions 1. Construction Survey - The survey measurements made prior to or while construction is in progress to control elevation, horizontal position, dimensions and configuration of structures/improvements included in the Project Drawings. 2. As -built Survey —The measurements made after the construction of the improvement features are complete to provide position coordinates for the features of a project. 3. Construction Staking — The placement of stakes and markings to provide offsets and elevations to cut and fill in order to locate on the ground the designed structures/improvements included in the Project Drawings. Construction staking shall include staking easements and/or right of way if indicated on the plans. 4. Survey "Field Checks" — Measurements made after construction staking is completed and before construction work begins to ensure that structures marked on the ground are accurately located per Project Drawings. B. Technical References 1. City of Fort Worth — Construction Staking Standards (available on City's Buzzsaw website) — 01 71 23.16.01_ Attachment A Survey Staking Standards 2. City of Fort Worth - Standard Survey Data Collector Library (fxl) files (available on City's Buzzsaw website). 3. Texas Department of Transportation (TxDOT) Survey Manual, latest revision 4. Texas Society of Professional Land Surveyors (TSPS), Manual of Practice for Land Surveying in the State of Texas, Category 5 25 1.4 ADMINISTRATIVE REQUIREMENTS 26 A. The Contractor's selection of a surveyor must comply with Texas Government 27 Code 2254 (qualifications based selection) for this project. 28 1.5 SUBMITTALS 29 A. Submittals, if required, shall be in accordance with Section 01 33 00. 30 B. All submittals shall be received and reviewed by the City prior to delivery of work. 31 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 32 A. Field Quality Control Submittals 33 1. Documentation verifying accuracy of field engineering work, including coordinate 34 conversions if plans do not indicate grid or ground coordinates. 35 2. Submit "Cut -Sheets" conforming to the standard template provided by the City 36 (refer to 01 71 23.16.01— Attachment A — Survey Staking Standards). 37 38 1.7 CLOSEOUT SUBMITTALS 39 B. As -built Redline Drawing Submittal CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised February 14, 2018 01 71 23-3 CONSTRUCTION STAKING AND SURVEY Page 3 of 8 1 1. Submit As -Built Survey Redline Drawings documenting the locations/elevations of 2 constructed improvements signed and sealed by Registered Professional Land 3 Surveyor (RPLS) responsible for the work (refer to 01 71 23.16.01 — Attachment A 4 — Survey Staking Standards) . 5 2. Contractor shall submit the proposed as -built and completed redline drawing 6 submittal one (1) week prior to scheduling the project final inspection for City 7 review and comment. Revisions, if necessary, shall be made to the as -built redline 8 drawings and resubmitted to the City prior to scheduling the construction fmal 9 inspection. 10 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE 12 A. Construction Staking 13 1. Construction staking will be performed by the Contractor. 14 2. Coordination 15 a. Contact City and Developer's Project Representative at least one week in 16 advance notifying the City of when Construction Staking is scheduled. 17 b. It is the Contractor's responsibility to coordinate staking such that 18 construction activities are not delayed or negatively impacted. 19 3. General 20 a. Contractor is responsible for preserving and maintaining stakes. If City 21 surveyors or Developer's Project Representative are required to re -stake for 22 any reason, the Contractor will be responsible for costs to perform staking. If 23 in the opinion of the City, a sufficient number of stakes or markings have been 24 lost, destroyed disturbed or omitted that the contracted Work cannot take place 25 then the Contractor will be required to stake or re -stake the deficient areas. 26 B. Construction Survey 27 1. Construction Survey will be performed by the Contractor. 28 2. Coordination 29 a. Contractor to verify that horizontal and vertical control data established in the 30 design survey and required for construction survey is available and in place. 31 3. General 32 a. Construction survey will be performed in order to construct the work shown 33 on the Construction Drawings and specified in the Contract Documents. 34 b. For construction methods other than open cut, the Contractor shall perform 35 construction survey and verify control data including, but not limited to, the 36 following: 37 1) Verification that established benchmarks and control are accurate. 38 2) Use of Benchmarks to furnish and maintain all reference lines and grades 39 for tunneling. 40 3) Use of line and grades to establish the location of the pipe. 41 4) Submit to the City copies of field notes used to establish all lines and 42 grades, if requested, and allow the City to check guidance system setup prior 43 to beginning each tunneling drive. 44 5) Provide access for the City, if requested, to verify the guidance system and 45 the line and grade of the carrier pipe. 46 CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised February 14, 2018 017123-4 CONSTRUCTION STAKING AND SURVEY Page 4 of 8 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 6) The Contractor remains fully responsible for the accuracy of the work and correction of it, as required. 7) Monitor line and grade continuously during construction. 8) Record deviation with respect to design line and grade once at each pipe joint and submit daily records to the City. 9) If the installation does not meet the specified tolerances (as outlined in Sections 33 05 23 and/or 33 05 24), immediately notify the City and correct the installation in accordance with the Contract Documents. C. As -Built Survey 1. Required As -Built Survey will be performed by the Contractor. 2. Coordination a. Contractor is to coordinate with City to confirm which features require as - built surveying. b. It is the Contractor's responsibility to coordinate the as -built survey and required measurements for items that are to be buried such that construction activities are not delayed or negatively impacted. c. For sewer mains and water mains 12" and under in diameter, it is acceptable to physically measure depth and mark the location during the progress of construction and take as -built survey after the facility has been buried. The Contractor is responsible for the quality control needed to ensure accuracy. 3. General a. The Contractor shall provide as -built survey including the elevation and location (and provide written documentation to the City) of construction features during the progress of the construction including the following: 1) Water Lines a) Top of pipe elevations and coordinates for waterlines at the following locations: (1) Minimum every 250 linear feet, including (2) Horizontal and vertical points of inflection, curvature, etc. (3) Fire line tee (4) Plugs, stub -outs, dead-end lines (5) Casing pipe (each end) and all buried fittings 2) Sanitary Sewer a) Top of pipe elevations and coordinates for force mains and siphon sanitary sewer lines (non -gravity facilities) at the following locations: (1) Minimum every 250 linear feet and any buried fittings (2) Horizontal and vertical points of inflection, curvature, etc. 3) Stormwater — Not Applicable b. The Contractor shall provide as -built survey including the elevation and location (and provide written documentation to the City) of construction features after the construction is completed including the following: 1) Manholes a) Rim and flowline elevations and coordinates for each manhole 2) Water Lines a) Cathodic protection test stations b) Sampling stations c) Meter boxes/vaults (All sizes) CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised February 14, 2018 01 71 23-5 CONSTRUCTION STAKING AND SURVEY Page 5 of 8 1 d) Fire hydrants 2 e) Valves (gate, butterfly, etc.) 3 f) Air Release valves (Manhole rim and vent pipe) 4 g) Blow off valves (Manhole rim and valve lid) 5 h) Pressure plane valves 6 i) Underground Vaults 7 (1) Rim and flowline elevations and coordinates for each 8 Underground Vault. 9 3) Sanitary Sewer 10 a) Cleanouts 11 (1) Rim and flowline elevations and coordinates for each 12 b) Manholes and Junction Structures 13 (1) Rim and flowline elevations and coordinates for each 14 manhole and junction structure. 15 4) Stormwater — Not Applicable 16 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED 17 1.11 FIELD [SITE] CONDITIONS [NOT USED] 18 1.12 WARRANTY 19 PART 2- PRODUCTS 20 A. A construction survey will produce, but will not be limited to: 21 1. Recovery of relevant control points, points of curvature and points of intersection. 22 2. Establish temporary horizontal and vertical control elevations (benchmarks) 23 sufficiently permanent and located in a manner to be used throughout construction. 24 3. The location of planned facilities, easements and improvements. 25 a. Establishing final line and grade stakes for piers, floors, grade beams, parking 26 areas, utilities, streets, highways, tunnels, and other construction. 27 b. A record of revisions or corrections noted in an orderly manner for reference. 28 c. A drawing, when required by the client, indicating the horizontal and vertical 29 location of facilities, easements and improvements, as built. 30 4. Cut sheets shall be provided to the City inspector and Survey Superintendent for all 31 construction staking projects. These cut sheets shall be on the standard city template 32 which can be obtained from the Survey Superintendent (817-392-7925). 33 5. Digital survey files in the following formats shall be acceptable: 34 a. AutoCAD (.dwg) 35 b. ESRI Shapefile (.shp) 36 c. CSV file (.csv), formatted with X and Y coordinates in separate columns (use 37 standard templates, if available) 38 6. Survey files shall include vertical and horizontal data tied to original project 39 control and benchmarks, and shall include feature descriptions 40 PART 3- EXECUTION 41 3.1 INSTALLERS CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised February 14, 2018 01 71 23-6 CONSTRUCTION STAKING AND SURVEY Page 6 of 8 A. Tolerances: 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 The staked location of any improvement or facility should be as accurate as practical and necessary. The degree of precision required is dependent on many factors all of which must remain judgmental. The tolerances listed hereafter are based on generalities and, under certain circumstances, shall yield to specific requirements. The surveyor shall assess any situation by review of the overall plans and through consultation with responsible parties as to the need for specific tolerances. a. Earthwork: Grades for earthwork or rough cut should not exceed 0.1 ft. vertical tolerance. Horizontal alignment for earthwork and rough cut should not exceed 1.0 ft. tolerance. b. Horizontal alignment on a structure shall be within .0.1 ft tolerance. c. Paving or concrete for streets, curbs, gutters, parking areas, drives, alleys and walkways shall be located within the confines of the site boundaries and, occasionally, along a boundary or any other restrictive line. Away from any restrictive line, these facilities should be staked with an accuracy producing no more than 0.05ft. tolerance from their specified locations. d. Underground and overhead utilities, such as sewers, gas, water, telephone and electric lines, shall be located horizontally within their prescribed areas or easements. Within assigned areas, these utilities should be staked with an accuracy producing no more than 0.1 ft tolerance from a specified location. e. The accuracy required for the vertical location of utilities varies widely. Many underground utilities require only a minimum cover and a tolerance of 0.1 ft. should be maintained. Underground and overhead utilities on planned profile, but not depending on gravity flow for performance, should not exceed 0.1 ft. tolerance. B. Surveying instruments shall be kept in close adjustment according to manufacturer's specifications or in compliance to standards. The City reserves the right to request a calibration report at any time and recommends regular maintenance schedule be performed by a certified technician every 6 months. 1. Field measurements of angles and distances shall be done in such fashion as to satisfy the closures and tolerances expressed in Part 3.1.A. 2. Vertical locations shall be established from a pre -established benchmark and checked by closing to a different bench mark on the same datum. 3. Construction survey field work shall correspond to the client's plans. Irregularities or conflicts found shall be reported promptly to the City. 4. Revisions, corrections and other pertinent data shall be logged for future reference. 39 3.2 EXAMINATION [NOT USED] 40 3.3 PREPARATION [NOT USED] 41 3.4 APPLICATION 42 3.5 REPAIR / RESTORATION 43 A. If the Contractor's work damages or destroys one or more of the control 44 monuments/points set by the City or Developer's Project Representative, the monuments 45 shall be adequately referenced for expedient restoration. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised February 14, 2018 01 71 23-7 CONSTRUCTION STAKING AND SURVEY Page 7 of 8 1 1. Notify City or Developer's Project Representative if any control data needs to be 2 restored or replaced due to damage caused during construction operations. 3 a. Contractor shall perform replacements and/or restorations. 4 b. The City or Developer's Project Representative may require at any time a 5 survey "Field Check" of any monument or benchmarks that are set be verified 6 by the City surveyors or Developer's Project Representative before further 7 associated work can move forward. 8 3.6 RE -INSTALLATION [NOT USED] 9 3.7 FIELD [OR] SITE QUALITY CONTROL 10 A. It is the Contractor's responsibility to maintain all stakes and control data placed by the 11 City or Developer's Project Representative in accordance with this Specification. This 12 includes easements and right of way, if noted on the plans. 13 B. Do not change or relocate stakes or control data without approval from the City. 14 3.8 SYSTEM STARTUP 15 A. Survey Checks 16 1. The City reserves the right to perform a Survey Check at any time deemed 17 necessary. 18 2. Checks by City personnel or 3rd party contracted surveyor are not intended to 19 relieve the contractor of his/her responsibility for accuracy. 20 21 3.9 ADJUSTING [NOT USED] 22 3.10 CLEANING [NOT USED] 23 3.11 CLOSEOUT ACTIVITIES [NOT USED] 24 3.12 PROTECTION [NOT USED] 25 3.13 MAINTENANCE [NOT USED] 26 3.14 ATTACHMENTS [NOT USED] 27 28 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D. Johnson Added instruction and modified measurement & payment under 1.2; added 8/31/2017 M. Owen definitions and references under 1.3; modified 1.6; added 1.7 closeout submittal requirements; modified 1.9 Quality Assurance; added PART 2— PRODUCTS ; Added 3.1 Installers; added 3.5 Repair/Restoration; and added 3.8 System Startup. Removed "blue text"; revised measurement and payment sections for Construction 2/14/2018 M Owen Staking and As -Built Survey; added reference to selection compliance with TGC 2254; revised action and Closeout submittal requirements; added acceptable depth CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised February 14, 2018 01 71 23-8 CONSTRUCTION STAKING AND SURVEY Page 8 of8 measurement criteria; revised list of items requiring as -built survey "during" and "after" construction; and revised acceptable digital survey file format CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised February 14, 2018 017423-1 DAP CLEANING Page 1 of 4 1 SECTION 01 74 23 2 CLEANING 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Intermediate and final cleaning for Work not including special cleaning of closed 7 systems specified elsewhere 8 B. Deviations from this City of Fort Worth Standard Specification 9 1. None. 10 C. Related Specification Sections include, but are not necessarily limited to: 11 1. Division 0— Bidding Requirements, Contract Forms and Conditions of the Contract 12 2. Division 1— General Requirements 13 3. Section 32 92 13 — Hydro -Mulching, Seeding and Sodding 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Measurement and Payment 16 1. Work associated with this Item is considered subsidiary to the various Items bid. 17 No separate payment will be allowed for this Item. 18 1.3 REFERENCES [NOT USED] 19 1.4 ADMINISTRATIVE REQUIREMENTS 20 A. Scheduling 21 1. Schedule cleaning operations so that dust and other contaminants disturbed by 22 cleaning process will not fall on newly painted surfaces. 23 2. Schedule final cleaning upon completion of Work and immediately prior to final 24 inspection. 25 1.5 SUBMITTALS [NOT USED] 26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 27 1.7 CLOSEOUT SUBMITTALS [NOT USED] 28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 29 1.9 QUALITY ASSURANCE [NOT USED] 30 1.10 STORAGE, AND HANDLING 31 A. Storage and Handling Requirements 32 1. Store cleaning products and cleaning wastes in containers specifically designed for 33 those materials. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 017423-2 DAP CLEANING Page 2 of 4 1 1.11 FIELD [SITE] CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED] 3 PART 2- PRODUCTS 4 2.1 OWNER -FURNISHED FOR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 5 2.2 MATERIALS 6 A. Cleaning Agents 7 1. Compatible with surface being cleaned 8 2. New and uncontaminated 9 3. For manufactured surfaces 10 a. Material recommended by manufacturer 11 2.3 ACCESSORIES [NOT USED] 12 2.4 SOURCE QUALITY CONTROL [NOT USED] 13 PART 3- EXECUTION 14 3.1 INSTALLERS [NOT USED] 15 3.2 EXAMINATION [NOT USED] 16 3.3 PREPARATION [NOT USED] 17 3.4 APPLICATION [NOT USED] 18 3.5 REPAIR / RESTORATION [NOT USED] 19 3.6 RE -INSTALLATION [NOT USED] 20 3.7 FIELD [oR] SITE QUALITY CONTROL [NOT USED] 21 3.8 SYSTEM STARTUP [NOT USED] 22 3.9 ADJUSTING [NOT USED] 23 3.10 CLEANING 24 A. General 25 1. Prevent accumulation of wastes that create hazardous conditions. 26 2. Conduct cleaning and disposal operations to comply with laws and safety orders of 27 governing authorities. 28 3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in 29 storm or sanitary drains or sewers. 30 4. Dispose of degradable debris at an approved solid waste disposal site. 31 5. Dispose of nondegradable debris at an approved solid waste disposal site or in an 32 alternate manner approved by City and regulatory agencies. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 01 7423 -3 DAP CLEANING Page 3 of 4 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 6. Handle materials in a controlled manner with as few handlings as possible. 7. Thoroughly clean, sweep, wash and polish all Work and equipment associated with this project. 8. Remove all signs of temporary construction and activities incidental to construction of required permanent Work. 9. If project is not cleaned to the satisfaction of the City, the City reserves the right to have the cleaning completed at the expense of the Contractor. 10. Do not burn on -site. B. Intermediate Cleaning during Construction 1. Keep Work areas clean so as not to hinder health, safety or convenience of personnel in existing facility operations. 2. At maximum weekly intervals, dispose of waste materials, debris and rubbish. 3. Confine construction debris daily in strategically located container(s): a. Cover to prevent blowing by wind b. Store debris away from construction or operational activities c. Haul from site at a minimum of once per week 4. Vacuum clean interior areas when ready to receive finish painting. a. Continue vacuum cleaning on an as -needed basis, until Final Acceptance. 5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which may become airborne or transported by flowing water during the storm. C. Exterior (Site or Right of Way) Final Cleaning 1. Remove trash and debris containers from site. a. Re -seed areas disturbed by location of trash and debris containers in accordance with Section 32 92 13. 2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object that may hinder or disrupt the flow of traffic along the roadway. 3. Clean any interior areas including, but not limited to, vaults, manholes, structures, junction boxes and inlets. 4. If no longer required for maintenance of erosion facilities, and upon approval by City, remove erosion control from site. 5. Clean signs, lights, signals, etc. 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 017423-4 DAP CLEANING Page 4 of 4 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 01 77 19-1 DAP CLOSEOUT REQUIREMENTS Page 1 of 3 1 2 3 PART1- GENERAL 4 1.1 SUMMARY SECTION 01 77 19 CLOSEOUT REQUIREMENTS 5 A. Section Includes: 6 1. The procedure for closing out a contract 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0— Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division 1 — General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various Items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES [NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS 18 A. Guarantees, Bonds and Affidavits 19 1. No application for final payment will be accepted until all guarantees, bonds, 20 certificates, licenses and affidavits required for Work or equipment as specified are 21 satisfactorily filed with the City. 22 B. Release of Liens or Claims 23 1. No application for final payment will be accepted until satisfactory evidence of 24 release of liens has been submitted to the City. 25 1.5 SUBMITTALS 26 A. Submit all required documentation to City's Project Representative. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 017719-2 DAP CLOSEOUT REQUIREMENTS Page 2 of 3 1 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 2 1.7 CLOSEOUT SUBMITTALS [NOT USED] 3 PART 2- PRODUCTS [NOT USED] 4 PART 3- EXECUTION 5 3.1 INSTALLERS [NOT USED] 6 3.2 EXAMINATION [NOT USED] 7 3.3 PREPARATION [NOT USED] 8 3.4 CLOSEOUT PROCEDURE 9 A. Prior to requesting Final Inspection, submit: 10 1. Project Record Documents in accordance with Section 01 78 39 11 2. Operation and Maintenance Data, if required, in accordance with Section 01 78 23 12 B. Prior to requesting Final Inspection, perform fmal cleaning in accordance with Section 13 01 74 23. 14 C. Final Inspection 15 1. After final cleaning, provide notice to the City Project Representative that the Work 16 is completed. 17 a. The City will make an initial Final Inspection with the Contractor present. 18 b. Upon completion of this inspection, the City will notify the Contractor, in 19 writing within 10 business days, of any particulars in which this inspection 20 reveals that the Work is defective or incomplete. 21 2. Upon receiving written notice from the City, immediately undertake the Work 22 required to remedy deficiencies and complete the Work to the satisfaction of the 23 City. 24 3. Upon completion of Work associated with the items listed in the City's written 25 notice, inform the City, that the required Work has been completed. Upon receipt 26 of this notice, the City, in the presence of the Contractor, will make a subsequent 27 Final Inspection of the project. 28 4. Provide all special accessories required to place each item of equipment in full 29 operation. These special accessory items include, but are not limited to: 30 a. Specified spare parts 31 b. Adequate oil and grease as required for the first lubrication of the equipment 32 c. Initial fill up of all chemical tanks and fuel tanks 33 d. Light bulbs 34 e. Fuses 35 f. Vault keys 36 g. Handwheels 37 h. Other expendable items as required for initial start-up and operation of all 38 equipment 39 D. Notice of Project Completion CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 01 77 19-3 DAP CLOSEOUT REQUIREMENTS Page 3 of 3 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1. Once the City Project Representative finds the Work subsequent to Final Inspection to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet). E. Supporting Documentation 1. Coordinate with the City Project Representative to complete the following additional forms: a. Final Payment Request b. Statement of Contract Time c. Affidavit of Payment and Release of Liens d. Consent of Surety to Final Payment e. Pipe Report (if required) f. Contractor's Evaluation of City g. Performance Evaluation of Contractor F. Letter of Final Acceptance 1. Upon review and acceptance of Notice of Project Completion and Supporting Documentation, in accordance with General Conditions, City will issue Letter of Final Acceptance and release the Final Payment Request for payment. 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE -INSTALLATION [NOT USED] 3.7 FIELD [oR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 01 7823 - 1 DAP OPERATION AND MAINTENANCE DATA Page 1 of 5 1 SECTION 01 78 23 2 OPERATION AND MAINTENANCE DATA 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Product data and related information appropriate for City's maintenance and 7 operation of products furnished under Contract 8 2. Such products may include, but are not limited to: 9 a. Traffic Controllers 10 b. Irrigation Controllers (to be operated by the City) 11 c. Butterfly Valves 12 B. Deviations from this City of Fort Worth Standard Specification 13 1. None. 14 C. Related Specification Sections include, but are not necessarily limited to: 15 1. Division 0— Bidding Requirements, Contract Forms and Conditions of the Contract 16 2. Division 1 — General Requirements 17 1.2 PRICE AND PAYMENT PROCEDURES 18 A. Measurement and Payment 19 1. Work associated with this Item is considered subsidiary to the various Items bid. 20 No separate payment will be allowed for this Item. 21 1.3 REFERENCES [NOT USED] 22 1.4 ADMINISTRATIVE REQUIREMENTS 23 A. Schedule 24 1. Submit manuals in final form to the City within 30 calendar days of product 25 shipment to the project site. 26 1.5 SUBMITTALS 27 A. Submittals shall be in accordance with Section 01 33 00. All submittals shall be 28 approved by the City prior to delivery. 29 1.6 INFORMATIONAL SUBMITTALS 30 A. Submittal Form 31 1. Prepare data in form of an instructional manual for use by City personnel. 32 2. Format 33 a. Size: 8 1/2 inches x 11 inches 34 b. Paper 35 1) 40 pound minimum, white, for typed pages 36 2) Holes reinforced with plastic, cloth or metal 37 c. Text: Manufacturer's printed data, or neatly typewritten CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 017823-2 DAP OPERATION AND MAINTENANCE DATA Page 2 of 5 1 d. Drawings 2 1) Provide reinforced punched binder tab, bind in with text 3 2) Reduce larger drawings and fold to size of text pages. 4 e. Provide fly -leaf for each separate product, or each piece of operating 5 equipment. 6 1) Provide typed description of product, and major component parts of 7 equipment. 8 2) Provide indexed tabs. 9 f. Cover 10 1) Identify each volume with typed or printed title "OPERATING AND 11 MAINTENANCE INSTRUCTIONS". 12 2) List: 13 a) Title of Project 14 b) Identity of separate structure as applicable 15 c) Identity of general subject matter covered in the manual 16 3. Binders 17 a. Commercial quality 3 -ring binders with durable and cleanable plastic covers 18 b. When multiple binders are used, correlate the data into related consistent 19 groupings. 20 4. If available, provide an electronic form of the O&M Manual. 21 B. Manual Content 22 1. Neatly typewritten table of contents for each volume, arranged in systematic order 23 a. Contractor, name of responsible principal, address and telephone number 24 b. A list of each product required to be included, indexed to content of the volume 25 c. List, with each product: 26 1) The name, address and telephone number of the subcontractor or installer 27 2) A list of each product required to be included, indexed to content of the 28 volume 29 3) Identify area of responsibility of each 30 4) Local source of supply for parts and replacement 31 d. Identify each product by product name and other identifying symbols as set 32 forth in Contract Documents. 33 2. Product Data 34 a. Include only those sheets which are pertinent to the specific product. 35 b. Annotate each sheet to: 36 1) Clearly identify specific product or part installed 37 2) Clearly identify data applicable to installation 38 3) Delete references to inapplicable information 39 3. Drawings 40 a. Supplement product data with drawings as necessary to clearly illustrate: 41 1) Relations of component parts of equipment and systems 42 2) Control and flow diagrams 43 b. Coordinate drawings with information in Project Record Documents to assure 44 correct illustration of completed installation. 45 c. Do not use Project Record Drawings as maintenance drawings. 46 4. Written text, as required to supplement product data for the particular installation: 47 a. Organize in consistent format under separate headings for different procedures. 48 b. Provide logical sequence of instructions of each procedure. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 01 7823 -3 DAP OPERATION AND MAINTENANCE DATA Page 3 of 5 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 5. Copy of each warranty, bond and service contract issued a. Provide information sheet for City personnel giving: 1) Proper procedures in event of failure 2) Instances which might affect validity of warranties or bonds C. Manual for Materials and Finishes 1. Submit 5 copies of complete manual in final form. 2. Content, for architectural products, applied materials and finishes: a. Manufacturer's data, giving full information on products 1) Catalog number, size, composition 2) Color and texture designations 3) Information required for reordering special manufactured products b. Instructions for care and maintenance 1) Manufacturer's recommendation for types of cleaning agents and methods 2) Cautions against cleaning agents and methods which are detrimental to product 3) Recommended schedule for cleaning and maintenance 3. Content, for moisture protection and weather exposure products: a. Manufacturer's data, giving full information on products 1) Applicable standards 2) Chemical composition 3) Details of installation b. Instructions for inspection, maintenance and repair D. Manual for Equipment and Systems 1. Submit 5 copies of complete manual in final form. 2. Content, for each unit of equipment and system, as appropriate: a. Description of unit and component parts 1) Function, normal operating characteristics and limiting conditions 2) Performance curves, engineering data and tests 3) Complete nomenclature and commercial number of replaceable parts b. Operating procedures 1) Start-up, break-in, routine and normal operating instructions 2) Regulation, control, stopping, shut -down and emergency instructions 3) Summer and winter operating instructions 4) Special operating instructions c. Maintenance procedures 1) Routine operations 2) Guide to "trouble shooting" 3) Disassembly, repair and reassembly 4) Alignment, adjusting and checking d. Servicing and lubrication schedule 1) List of lubricants required e. Manufacturer's printed operating and maintenance instructions f. Description of sequence of operation by control manufacturer 1) Predicted life of parts subject to wear 2) Items recommended to be stocked as spare parts g. As installed control diagrams by controls manufacturer h. Each contractor's coordination drawings 1) As installed color coded piping diagrams CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 017823-4 DAP OPERATION AND MAINTENANCE DATA Page 4 of 5 1 i. Charts of valve tag numbers, with location and function of each valve 2 j. List of original manufacturer's spare parts, manufacturer's current prices, and 3 recommended quantities to be maintained in storage 4 k. Other data as required under pertinent Sections of Specifications 5 3. Content, for each electric and electronic system, as appropriate: 6 a. Description of system and component parts 7 1) Function, normal operating characteristics, and limiting conditions 8 2) Performance curves, engineering data and tests 9 3) Complete nomenclature and commercial number of replaceable parts 10 b. Circuit directories of panelboards 11 1) Electrical service 12 2) Controls 13 3) Communications 14 c. As installed color coded wiring diagrams 15 d. Operating procedures 16 1) Routine and normal operating instructions 17 2) Sequences required 18 3) Special operating instructions 19 e. Maintenance procedures 20 1) Routine operations 21 2) Guide to "trouble shooting" 22 3) Disassembly, repair and reassembly 23 4) Adjustment and checking 24 f. Manufacturer's printed operating and maintenance instructions 25 g. List of original manufacturer's spare parts, manufacturer's current prices, and 26 recommended quantities to be maintained in storage 27 h. Other data as required under pertinent Sections of Specifications 28 4. Prepare and include additional data when the need for such data becomes apparent 29 during instruction of City's personnel. 30 1.7 CLOSEOUT SUBMITTALS [NOT USED] 31 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 32 1.9 QUALITY ASSURANCE 33 A. Provide operation and maintenance data by personnel with the following criteria: 34 1. Trained and experienced in maintenance and operation of described products 35 2. Skilled as technical writer to the extent required to communicate essential data 36 3. Skilled as draftsman competent to prepare required drawings CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 01 7823 -5 DAP OPERATION AND MAINTENANCE DATA Page 5 of 5 1 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 2 1.11 FIELD [SITE] CONDITIONS [NOT USED] 3 1.12 WARRANTY [NOT USED] 4 PART 2- PRODUCTS [NOT USED] 5 PART 3- EXECUTION [NOT USED] 6 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D. Johnson 1.5.A.1 — title of section removed 4/7/2014 M.Domenech Revised for DAP Application CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 01 78 39 - 1 DAP PROJECT RECORD DOCUMENTS Page 1 of 4 1 2 3 PART1- GENERAL 4 1.1 SUMMARY SECTION 01 78 39 PROJECT RECORD DOCUMENTS 5 A. Section Includes: 6 1. Work associated with the documenting the project and recording changes to project 7 documents, including: 8 a. Record Drawings 9 b. Water Meter Service Reports 10 c. Sanitary Sewer Service Reports 11 d. Large Water Meter Reports 12 B. Deviations from this City of Fort Worth Standard Specification 13 1. None. 14 C. Related Specification Sections include, but are not necessarily limited to: 15 1. Division 0— Bidding Requirements, Contract Forms and Conditions of the Contract 16 2. Division 1 — General Requirements 17 1.2 PRICE AND PAYMENT PROCEDURES 18 A. Measurement and Payment 19 1. Work associated with this Item is considered subsidiary to the various Items bid. 20 No separate payment will be allowed for this Item. 21 1.3 REFERENCES [NOT USED] 22 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 23 1.5 SUBMITTALS 24 A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to 25 City's Project Representative. 26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 27 1.7 CLOSEOUT SUBMITTALS [NOT USED] 28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 29 1.9 QUALITY ASSURANCE 30 A. Accuracy of Records 31 1. Thoroughly coordinate changes within the Record Documents, making adequate 32 and proper entries on each page of Specifications and each sheet of Drawings and 33 other Documents where such entry is required to show the change properly. 34 2. Accuracy of records shall be such that future search for items shown in the Contract 35 Documents may rely reasonably on information obtained from the approved Project 36 Record Documents. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 017839-2 DAP PROJECT RECORD DOCUMENTS Page 2 of 4 1 3. To facilitate accuracy of records, make entries within 24 hours after receipt of 2 information that the change has occurred. 3 4. Provide factual information regarding all aspects of the Work, both concealed and 4 visible, to enable future modification of the Work to proceed without lengthy and 5 expensive site measurement, investigation and examination. 6 1.10 STORAGE AND HANDLING 7 A. Storage and Handling Requirements 8 1. Maintain the job set of Record Documents completely protected from deterioration 9 and from loss and damage until completion of the Work and transfer of all recorded 10 data to the final Project Record Documents. 11 2. In the event of loss of recorded data, use means necessary to again secure the data 12 to the City's approval. 13 a. In such case, provide replacements to the standards originally required by the 14 Contract Documents. 15 1.11 FIELD [SITE] CONDITIONS [NOT USED] 16 1.12 WARRANTY [NOT USED] 17 PART 2- PRODUCTS 18 2.1 OWNER -FURNISHED [OR] OWNER -SUPPLIED PRODUCTS [NOT USED] 19 2.2 RECORD DOCUMENTS 20 A. Job set 21 1. Promptly following receipt of the Notice to Proceed, secure from the City, at no 22 charge to the Contractor, 1 complete set of all Documents comprising the Contract. 23 B. Final Record Documents 24 1. At a time nearing the completion of the Work and prior to Final Inspection, provide 25 the City 1 complete set of all Final Record Drawings in the Contract. 26 2.3 ACCESSORIES [NOT USED] 27 2.4 SOURCE QUALITY CONTROL [NOT USED] 28 PART 3- EXECUTION 29 3.1 INSTALLERS [NOT USED] 30 3.2 EXAMINATION [NOT USED] 31 3.3 PREPARATION [NOT USED] 32 3.4 MAINTENANCE DOCUMENTS 33 A. Maintenance of Job Set 34 1. Immediately upon receipt of the job set, identify each of the Documents with the 35 title, "RECORD DOCUMENTS - JOB SET". CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 017839-3 DAP PROJECT RECORD DOCUMENTS Page 3 of 4 1 2. Preservation 2 a. Considering the Contract completion time, the probable number of occasions 3 upon which the job set must be taken out for new entries and for examination, 4 and the conditions under which these activities will be performed, devise a 5 suitable method for protecting the job set. 6 b. Do not use the job set for any purpose except entry of new data and for review 7 by the City, until start of transfer of data to final Project Record Documents. 8 c. Maintain the job set at the site of work. 9 3. Coordination with Construction Survey 10 a. At a minimum clearly mark any deviations from Contract Documents 11 associated with installation of the infrastructure. 12 4. Making entries on Drawings 13 a. Record any deviations from Contract Documents. 14 b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the 15 change by graphic line and note as required. 16 c. Date all entries. 17 d. Call attention to the entry by a "cloud" drawn around the area or areas affected. 18 e. In the event of overlapping changes, use different colors for the overlapping 19 changes. 20 5. Conversion of schematic layouts 21 a. In some cases on the Drawings, arrangements of conduits, circuits, piping, 22 ducts, and similar items, are shown schematically and are not intended to 23 portray precise physical layout. 24 1) Final physical arrangement is determined by the Contractor, subject to the 25 City's approval. 26 2) However, design of future modifications of the facility may require 27 accurate information as to the final physical layout of items which are 28 shown only schematically on the Drawings. 29 b. Show on the job set of Record Drawings, by dimension accurate to within 1 30 inch, the centerline of each run of items. 31 1) Final physical arrangement is determined by the Contractor, subject to the 32 City's approval. 33 2) Show, by symbol or note, the vertical location of the Item ("under slab", "in 34 ceiling plenum", "exposed", and the like). 35 3) Make all identification sufficiently descriptive that it may be related 36 reliably to the Specifications. 37 c. The City may waive the requirements for conversion of schematic layouts 38 where, in the City's judgment, conversion serves no useful purpose. However, 39 do not rely upon waivers being issued except as specifically issued in writing 40 by the City. 41 B. Final Project Record Documents 42 1. Transfer of data to Drawings 43 a. Carefully transfer change data shown on the job set of Record Drawings to the 44 corresponding final documents, coordinating the changes as required. 45 b. Clearly indicate at each affected detail and other Drawing a full description of 46 changes made during construction, and the actual location of items. 47 c. Call attention to each entry by drawing a "cloud" around the area or areas 48 affected. CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 017839-4 DAP PROJECT RECORD DOCUMENTS Page 4 of 4 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 d. Make changes neatly, consistently and with the proper media to assure longevity and clear reproduction. 2. Transfer of data to other Documents a. If the Documents, other than Drawings, have been kept clean during progress of the Work, and if entries thereon have been orderly to the approval of the City, the job set of those Documents, other than Drawings, will be accepted as final Record Documents. b. If any such Document is not so approved by the City, secure a new copy of that Document from the City at the City's usual charge for reproduction and handling, and carefully transfer the change data to the new copy to the approval of the City. 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE -INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP Application CITY OF FORT WORTH Cibolo Hills Parkway STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. 106104 Revised April 7, 2014 GC -4.02 Subsurface and Physical Conditions Page 1 of 1 GC -4.02 SUBSURFACE AND PHYSICAL CONDITIONS Cibolo Hills Parkway City Project No. 106104 UES,., May 9, 2025 GRBK Edgewood, LLC 5501 Headquarters Drive, Suite 300W Piano, Texas 75024 Attention. Mr. KD Weaver Re: Pavement Recommendations Cibolo Hills West Proposed Cibolo Hills Parkway Fort Worth, Texas UES Report No. W250053 -1 -real Environmental Geotechnical Engineering Materials Testing Field Inspections & Code Compliance Geophysicol Technologies Submitted herein arethe recommended pavement section forthe proposed Cibolo Hills Parkway. The proposed street is generally located about 2,445 ft west of the intersection of North Saginaw Boulevard and Cibolo Hills Parkway in Fort Worth, Texas. This study was authorized by Mr. Bobby Samuel on March 20, 2025 and performed in accordance with UES Professional Solutions, LLC Proposal No. 109354-2 dated March 18, 2025. This report is an extension of Report No. W250053- revi dated April 28, 2025. The purpose of this revision is to include recommendations for "Residential" and "Collector" roads per the client. We understand approximately 2,190 linear ft of Cibolo Hills Parkway is being constructed. We further understand that pavement recommendations in accordance with Paving Details Prepared by ILIA Engineering, Inc. ("Preliminary Document for the purpose of review", Sheets 45 through 50 dated Jan 2025) are desired. We understand the proposed streets within the subdivision could be classified as "Residential", "Collector" or "Arterial", as described in the referenced Paving Details. PURPOSE AND SCOPE The purpose of this geotechnical exploration is for UES PROFESSIONAL SOLUTIONS 44, LLC (UES) to evaluate for GRBK Edgewood, LLC (Client) some of the physical and engineering properties of subsurface materials at selected locations on the subject site with respect to formulation of appropriate geotechnical design parameters for the proposed pavement. The field exploration was accomplished by securing subsurface samples from widely spaced test borings performed across the expanse of the site. Engineering analyses were performed from results of the field exploration and results of laboratory tests performed on representative samples. 5058 Brush Creek Rd I Fort Worth, TX 761191 ph 817-496-5600 TearritlES.r om Also included are general comments pertaining to reasonably anticipated construction problems and recommendations concerning earthwork and quality control testing during construction. This information can be used to evaluate subsurface conditions and to aid in ascertaining construction meets project specifications. Recommendations provided in this report were developed from information obtained in test borings depicting subsurface conditions only at the specific boring locations and at the particular time designated on the logs. Subsurface conditions at other locations may differ from those observed at the boring locations, and subsurface conditions at the boring locations may vary at different times of the year. The scope of work may not fully define the variability of subsurface materials and conditions that are present on the site. The nature and extent of variations between borings may not become evident until construction. If significant variations then appear evident, our office should be contacted to re-evaluate our recommendations after performing on -site observations and possibly other tests. SUMMARY OF RECOMMENDATIONS Table A contains a summary of pavement section requirements for the proposed Cibolo Hills Parkway. TABLE A Summary of Pavement Section Requirements Street Classification Residential -Urban Collector Arterial PCC Pavement Thickness (in) 6 7l 10 28 -day Concrete Compressive Strength (psi) 3,600 Lime Stabilization Subgrade Depth (in) 6 8 Application Rate (lbs per sq yd) 32 42 Reinforcing Bar No. 3 4 Reinforcing Bar Spacing (in) 18 18 Further recommendations and analyses used to develop the summary in Table A are provided further in this report. FIELD EXPLORATION Subsurface conditions on the site were explored by drilling a total of five (5) test borings (Borings 68 through 72) drilled to a depth of about 10 ft. The borings were drilled in general accordance with ASTM Standard D 420 using standard rotary drilling equipment. The approximate location of each boring is shown on the attached Boring Location Plan, Figure 1. Subsurface types encountered during the field exploration are presented on the attached Log of Boring sheets (boring logs). These boring logs contain our Field Technician's and Engineer's interpretation of conditions believed to exist between actual samples retrieved. Therefore, the boring logs contain both factual and interpretive information. Lines delineating subsurface strata on the boring logs are approximate and the actual transition between strata may be gradual. LABORATORY TESTS Selected samples of the subsurface materials were tested in the laboratory to evaluate their engineering properties as a basis in providing recommendations for pavement sections design and earthwork construction. The following laboratory tests were performed to facilitate pavement section recommendations: • Moisture Content (ASTM D 2216) • Atterberg-Limits (ASTM D 4318) • Sulfate Content (TX -145-E Part II) • Lime Series (Plasticity Index vs. LimeContent) GENERAL SUBSURFACE CONDITIONS Based on geological atlas maps available from the Bureau of Economic Geology, published by the University of Texas at Austin, the project site lies within the Fort Worth Limestone and Duck Creek formation and the Kiamichi formations. These formations generally consist of limestone with marly (limey shale) seams and layers. The residual overburden clay soils in these formations are typically characterized by moderate to high shrink/swell potential. Subsurface conditions at geological interfaces can be highly variable as indicated on the attached boring logs. Subsurface conditions encountered in Boring 68 generally consisted of clay to a depth of about 6 ft below the ground surface underlain by shale extending to the 10 ft termination depth of the boring. Subsurface conditions encountered in 69 generally consisted of limestone extending to the 10 ft termination depth of the boring. Subsurface conditions encountered in Borings 70 and 72 generally consisted of clay to depths of about 8 ft and 2 ft, below the ground surface, respectively underlain by limestone extending to the 10 ft termination depth of the borings. Subsurface conditions encountered in Boring 71 generally consisted of clay extending to the 10 ft termination depth of the boring. The upper 8 ft of material encountered in Boring 71 was visually classified as fill material. Most of the materials encountered in the borings are considered relatively impermeable and are expected to have a relatively slow response to water movement. Therefore, several days of observation would be required to evaluate actual groundwater levels within the depths explored. Also, the groundwater level at the site is anticipated to fluctuate seasonally depending on the amount of rainfall, prevailing weather conditions and subsurface drainage characteristics. Free groundwater was encountered on drilling tools during drilling and immediately upon completion in Boring 68 at a depth of about 6 ft below the ground surface. It is common to encounter seasonal groundwater in fill material and from natural fractures within the clayey matrix, at the soil/rock (limestone/shale) interface and from fractures within the rock (limestone/shale), particularly during or after periods of precipitation. If more detailed groundwater information is required, monitoring wells or piezometers can be installed. Further information concerning subsurface materials and conditions encountered can be obtained from the boring logs in the Appendix. ENGINEERING ANALYSIS AND RECOMMENDATIONS Calculations used to determine the required pavement thickness are based only on the physical and engineering properties of the materials and conventional thickness determination procedures. Related civil design factors such as subgrade drainage, shoulder support, cross- sectional configurations, surface elevations, joint design and environmental factors will significantly affect the service life and must be included in preparati©n of the construction drawings and specifications but were not included in the scope of this study. Normal periodic maintenance will be required for all pavement to achieve the design life of the pavement system. Pavement Subgrade Preparation Based on review of the borings, we expect the pavement subgrade could consist of clay soils or similar onsite materials used for grading the site. In addition, the pavement subgrade could also consist of limestone in some areas depending on the given location along the alignment and grading requirements. Since the subgrade conditions and required treatments could vary along the proposed road alignment, UES should be retained to observe construction to verify conditions are as expected. Also, we should be provided with the final grading plan for review prior to construction to verify or modify in writing the recommendations contained in this report. The exposed clayey surface soils should be scarified to a depth of 6 inches and 8 inches for Residential and Collector/Arterial streets, respectively, and mixed with a minimum 32 and 42 lbs per sq yard of hydrated lime (by dry soil weight) in conformance with TxD0T Standard Specifications Item 260. The recommended application rate equates to about 7 percent based on a dry soil unit weight of 100 pcf. The results of lime series tests performed on representative clay samples are attached (Figure 2). We recommend lime stabilization procedures extend at least 1 ft beyond the edge of the pavement to reduce effects of seasonal shrinking and swelling upon the extreme edges of pavement. The soil -lime mixture should be compacted to at least 95 percent of the standard Proctor maximum dry density (ASTM D 698) and within the range of 0 to 4 percentage points above the mixture's optimum moisture content. In all areas where hydrated lime is used to stabilize subgrade soil, routine Atterberg-limit tests should be performed to verify the resulting plasticity index of the soil -lime mixture is at/or below 15. Lime stabilization of the pavement subgrade is not required where the pavement subgrade consists of limestone. In pavement areas where limestone is exposed after final subgrade elevation is achieved, on -site lime stabilized clay cuttings, on -site processed limestone cuttings, or flexible base material could be used as a leveling course (as needed) to provide a smooth surface for placement of the pavement, Mechanical lime stabilization of the pavement subgrade soil will not prevent normal seasonal movement of the underlying untreated materials. Pavement and other flatwork constructed at final grades could experience soil -related potential seasonal movements up to about 6 inches as discussed in the referenced foundation report (LIES Report No. W250053). California Bearing Ratio (CBR) tests were not performed for this specific project. However, based on our experience in the area and similar conditions, the CBR value for the natural clay soil is estimated to be about 2 to 3. Following improvement with lime, the CBR value for the lime stabilized clayey soils is expected to be at least 10. Existing fill was encountered in Boring 71 to the depth of 8 ft. It is not known if the existing fill on the site was placed under engineering supervision with compaction records. If compaction records for this existing cannot be obtained, it should be considered as uncontrolled fill. Any uncontrolled fill remained at the finished grade of the proposed arterial roadway subgrade may remain in place if proofroll is passed. Some levels of potential indeterminant settlement may occur due to the presence of uncontrolled fill, even when proofroll is passed. If the unknown indeterminant settlement risks are not acceptable, then considerations should be taken to remove and recompact the uncontrolled fill in accordance with Section "Fill Compaction" as discussed in this report. Portland Cement Concrete Pavement Section Using the 1993 AASHTO pavement design procedures (WinPAS computer), the following design parameters were used in analyses of the PCC pavement section. • Compressive strength of concrete 3,600 psi at 28 days • Modulus of Elasticity 4,000,000 psi • Modulus of Rupture 620 psi • Modulus of Subgrade Reaction* 280 pci • Load Transfer Co -efficient 3.0 ■ Drainage Coefficient 1.0 • Initial PSI 4.5 • Terminal PSI for 2.0 (Residential) 2.25 (Collector) 2.5 (Arterial) • Standard Deviation 0.39 • Reliability 85 percent *Subgrade prepared with lime stabilization, or graded limestone as discussed above. Using the Street Classification of "Residential" as described in accordance with Paving Details Prepared by LJA Engineering, Inc. ("Preliminary Document for the purpose of review", Sheets 45 through 50 dated Jan 2025it is estimated annual traffic volume will be about 35,000 Equivalent Single Axle Loads (ESALs) in one direction over a 25 -year design life with 0.5 percent annual traffic growth. Based on this, we estimate the cumulative ESALs over the design life of the Residential Urban Street pavement to be about 930,000. Using the Street Classification of '"Collector" as described in accordance with Paving Details Prepared by LJA Engineering, Inc. ("Preliminary Document for the purpose of review", Sheets 45 through 50 dated Jan 2025, the annual traffic volume will be about 100,000 Equivalent Single Axle Loads (ESALs) in one direction over a 25 -year design life with 1.5 percent annual traffic growth. Based on this, we estimate the cumulative ESALs over the design life of the pavement to be about 3,000,000. Using the Street Classification of "Arterial" as described in accordance with Paving Details Prepared by LJA Engineering, Inc. ("Preliminary Document for the purpose of review", Sheets 45 through 50 dated Jan 2025), the annual traffic volume will be about 300,000 Equivalent Single Axle Loads (ESALs) in one direction over a 30 -year design life with 2.5 percent annual traffic growth. Based on this, we estimate the cumulative ESALs over the design life of the pavement to be about 13,000,000. If the actual expected traffic volume is different than used for our analysis herein, our office should be provided with the actual expected traffic volume so that we can re-evaluate our recommendations. Based on the subgrade preparations recommended herein, the projected traffic volume and stated design parameters, a minimum 6 -inch section of Portland cement concrete is required for Residential Urban classified streets, a minimum 7Y2 -inch section of Portland cement concrete is required for Collector classified streets and a minimum 10 -inch section of Portland cement concrete is required for Arterial classified streets at this project. PCC should have a minimum 3,600 psi compressive strength at 28 days. The concrete section should be placed over a properly prepared subgrade as discussed herein. Concrete should be designed with 4.5 ± 1.5 percent entrained air. Reinforcing steel for concrete pavement and Joints and saw -cutting in concrete should be in accordance with Paving Details Prepared by LJA Engineering, Inc. ("Preliminary Document for the purpose of review", Sheets 45 through 50 dated Jan 2025. Drainage and Maintenance Routine maintenance, including sealing of cracks and joints should be performed over the life of the pavement. Adequate drainage should be provided to reduce seasonal variations in the moisture content of subgrade soils. Maintaining positive surface drainage throughout the life of the pavement is essential. Soluble Sulfates A total of four (4) samples obtained from the borings were tested for soluble sulfate concentrations (TxD0TTEX-145-E Part II). Results of the sulfate tests are summarized in Table B. TABLE B Soluble Sulfates Sample Boring Depth, Soluble Sulfate Material TypeNo. No. ft (ppm) 1 68 2-4 < 100 2 70 2-4 Brown CLAY 3 71 2-4 625 4 72 0-2 < 100 Based on the results of laboratory testing, the soluble sulfate content measured in the samples tested is considered relatively low (< 3,000 ppm). It should be noted that concentrations of soluble sulfates in soil are typically very localized and concentrations in other areas of the site could vary significantly. Therefore, it is recommended sulfate sampVing/testing be performed along the pavement subgrade during construction. During construction, experienced geotechnical personnel should make close observations for possible sulfate reactions. GENERAL CONSTRUCTION PROCEDURES AND RECOMMENDATIONS Variations in subsurface conditions could be encountered during construction. To permit correlation between test boring data and actual subsurface conditions encountered during construction, it is recommended a registered Professional Engineering firm be retained to observe construction procedures and materials, Some construction problems, particularly degree or magnitude, cannot be reasonably anticipated until the course of construction. The recommendations offered in the following paragraphs are intended not to limit or preclude other conceivable solutions, but rather to provide our observations based on our experience and understanding of the project characteristics and subsurface conditions encountered in the borings. Site Preparation and Grading Limestone was encountered within 4 ft of the ground surface in most of the borings. We expect limestone will be encountered during grading and general excavation at this site. From our experience, this limestone can be hard and difficult to excavate. Rock excavation methods (including, but not limited to rock teeth, rippers, jack hammers, or sawcutting) may be required to remove the limestone. Crushing equipment may be required to process this limestone if it is desired to use this material as compacted fill on the site. The contractor selected should have experience with excavation in hard limestone. All areas supporting pavement or areas to receive new fill should be properly prepared. • After completion of the necessary stripping, clearing, and excavating and prior to placing any required fill, the exposed subgrade should be carefully evaluated by probing and testing. Any undesirable material (organic material, wet, soft, or loose soil) still in place should be removed. • The exposed subgrade should be further evaluated by proof -rolling with a heavy pneumatic tired roller, loaded dump truck or similar equipment weighing approximately 25 tons to check for pockets of soft or loose material hidden beneath a thin crust of possibly better soil. • Proof -rolling procedures should be observed routinely by a Professional Engineer or his designated representative. Any undesirable material (organic material, wet, soft, or loose soil) exposed from the proof -roll should be removed and replaced with well -compacted material as outlined in the Fill Compaction section. • Prior to placement of any fill, the exposed subgrade should then be scarified to a minimum depth of 6 inches and recompacted as outlined in the Fill Compaction section. If fill is to be placed on existing slopes (natural or constructed) steeper than six horizontal to one vertical (6:1), the fill materials should be benched into the existing slopes in such a manner as to provide a minimum bench width of five (5} ft. This should provide a good contact between the existing soils and new fill materials, reduce potential sliding planes, and allow relatively horizontal lift placements. Even if fill is properly compacted as recommended in the Fill Compaction section, fills in excess of about 10 ft are still subject to settlements over time of up to about 1 to 2 percent of the total fill thickness. This should be considered when planning or placing deep fills. Slope stability analysis of embankments (natural or constructed) and global stability analysis for retaining walls was not within the scope of this study. The contractor is responsible for designing any excavation slopes, temporary sheeting or shoring. Design of these structures should include any imposed surface surcharges. Construction site safety is the sole responsibility of the contractor, who shall also be solely responsible for the means, methods and sequencing of construction operations. The contractor should also be aware that slope height, slope inclination or excavation depths (including utility trench excavations) should in no case exceed those specified in local, state and/or federal safety regulations, such as OSHA Health and Safety Standard for Excavations, 29 CFR Part 1926, or successor regulations. Stockpiles should be place well away from the edge of the excavation and their heights should be controlled so they do not surcharge the sides of the excavation. Surface drainage should be carefully controlled to prevent flow of water over the slopes and/or into the excavations. Construction slopes should beclosely observed for signs of mass movement, including tension cracks near the crest or bulging at the toe. If potential stability problems are observed, a geotechnical engineer should be contacted immediately. Shoring, bracing or underpinning required for the project (if any) should be designed by a professional engineer registered in the State of Texas. Due to the nature of the clay soils found near the surface at most of the borings, traffic of heavy equipment (including heavy compaction equipment) may create pumping and general deterioration of shallow soils. Therefore, some construction difficulties should be anticipated during periods when these soils are saturated. Fill Compaction The following compaction recommendations pertain to general filling and site grading. The pavement subgrade should be prepared as discussed in the 'Pavement Subgrade Preparation' section. Clay soils with a plasticity index equal to or greaterthan 25 should be compacted to a dry density between 93 and 98 percent of standard Proctor maximum dry density (ASTIVI D 698). The compacted moisture content of the clays during placement should be within the range of +2 to +6 percentage points of the material's optimum moisture. Clay soils used for general fill with a plasticity index less than 25 should be compacted to a dry density of at least 95 percent of standard Proctor maximum dry density (ASTM D 698). The compacted moisture content of the clays during placement should be within the range of -1 to +3 percentage points of the material's optimum moisture. Clay soils used as filll should be processed and the largest particle or clod should be less than 6 inches prior to compaction. Processed limestone or other rock -like materials used as fill should be compacted to at least 95 percent of standard Proctor maximum dry density. The compacted moisture content of limestone or other rock -like materials used as fill is not considered crucial to proper performance, However, if the material's moisture content during placement is within 3 percentage points of optimum, the compactive effort required to achieve the minimum compaction criteria may be minimized. In general, processed limestone used as fill should have a maximum particle size of 6 inches. However, any processed limestone used as fill within 3, ft of the final pavement subgrade elevation should have a maximum particle size of 3 inches. A gradation of at least 40 percent passing a standard No, 4 sieve is recommended. Where mass fills are deeper than 10 ft, the fill/backfill below 10 ft should be compacted to at least 100 percent of standard Proctor maximum dry density (ASTM D-698) and within 2 percentage points of the material`s optimum moisture content. The portion of the fill/backfill shallower than 1Q ft should be compacted as outlined herein. Compaction should be accomplished by placing fill in about 8 -inch thick loose lifts and compacting each lift to at least the specified minimum dry density. Field density and moisture content tests should be performed on each lift.. In general site grading areas where final fill slopes will be four horizontal to one vertical (4:1) or steeper and greater than 5 ft in height, field density and moisture content tests should be performed on each lift. Utilities Where utility lines are deeper than 10 ft, the fill/backfill below 10 ft should be compacted to at least 100 percent of standard Proctor maximum dry density (ASTM D 698) and within —2 to +2 percentage points of the materials optimum moisture content. The portion of the fill/backfill shallower than 10 ft should be compacted as previously outlined. Density tests should be performed on each lift (maximum 12 -inch thick) and should be performed as the trench is being backfilled. Even if fill is properly compacted, fills in excess of about loft are still subject to settlements over time of up to about 1 to 2 percent of the total fill thickness. This should be considered when designing pavement over utility lines and/or other areas with deep fill. If utility trenches or other excavations extend to or beyond a depth of 5 ft below construction grade, the contractor or others shall be required to develop an excavation safety plan to protect personnel entering the excavation or excavation vicinity. The collection of specific geotechnical data and the development of such a plan, which could include designs for sloping and benching or various types of temporary sharing, is beyond the scope of this study. Any such designs and safety plans shall be developed in accordance with current OSHA guidelines and other applicable industry standards. Groundwater Groundwater was encountered in Boring 68 at a depth of about 6 ft below the ground surface. From our experience, shallow groundwater seepage could be encountered in excavations for foundations, utilities and other general excavations at this site. The risk of seepage increases with depth of excavation and during or after periods of precipitation. Standard sump pits and pumping may be adequate to control seepage on a local basis in clayey soils. In any areas where cuts are made, attention should be given to possible seasonal water seepage that could occur through natural cracks and fissures in the newly exposed stratigraphy. Also, the risk of seepage is increased where limestone is exposed in excavations and slopes or is near final grade. In these areas subsurface drains may be required to intercept seasonal groundwater seepage. The need for these or other dewatering devices should be carefully addressed during construction. Our office could be contacted to visually observe final grades to evaluate the need for such drains. LIMITATIONS Professional services provided in this geotechnical exploration were performed, findings obtained, and recommendations prepared in accordance with generally accepted geotechnical engineering principles and practices. The scope of services provided herein does not include an environmental assessment of the site or investigation for the presence or absence of hazardous materials in the soil, surface water or groundwater. UES, upon written request, can be retained to provide same. JES is not responsible for conclusions, opinions or recommendations made by others based on this data. Information contained in this report is intended forthe exclusive use of the Client (and their designated design representatives), and is related solely to design of the specific structures outlined on the cover page of this report. No party other than the Client (and their designated design representatives) shall use or rely upon this report in any manner whatsoever unless such party shall have obtained UES's written acceptance of such intended use. Any such third party using this report after obtaining UES's written acceptance shall be bound by the limitations and limitations of liability contained herein, including UES's liability being limited to the fee paid to it for this report. Recommendations presented in this report should not be used for design of any other structures except those specifically described in this report. In all areas of this report in which UES may provide additional services if requested to do so in writing, it is presumed that such requests have not been made if not evidenced by a written document accepted by UES. Further, subsurface conditions can change with passage of time. Recommendations contained herein are not considered applicable for an extended period of time after the completion date of this report. It is recommended our office be contacted for a review of the contents of this report for construction commencing more than one (1) year after completion of this report. Non- compliance with any of these requirements by the Client or anyone else shall release IDES from any liability resulting from the use of, or reliance upon, this report. Recommendations provided in this report are based on our understanding of information provided by the Client about characteristics of the project. If the Client notes any deviation from the facts about project characteristics, our office should be contacted immediately since this may materially alter the recommendations. Further, UES is not responsible for damages resulting from workmanship of designers or contractors and it is recommended the Owner retain qualified personnel, such as a Geotechnical Engineering firm, to verify construction is performed in accordance with plans and specifications. CLOSING All recommendations in the referenced geotechnical report remain unchanged unless specifically modified herein. We appreciate the opportunity to be of service. Please contact us with any questions or comments. Sincerely, UES PROFESSIONAL SOLUTIONS 44, LLC TBPE Firm No. 813 Elizabeth Gonsalez, Geotechnical Project Manager T•'' ")...•am Mohammadreza Keshavarz 138871... -r'..Cr Eh9S ' o S ;�� ► ''CNAte Attachments: Boring Location Plan — Figure 1 Mechanical Lime Series — Figure 2 WinPASAnalysis Result Log of Borings Key to Soil Symbols and Classifications Reza Keshavarz, Ph.D., P.E. Geotechnical Department Manager E OF) TILL WEST LLC �41218219520 R.T.C.T. / - /9 ,/ 'mss s s, r r - 7�w. ti* B-69 PROPOSE[ CIBOLO HIL PARKWAY ((H- EL HILL E T LL CHAPEL HILL WEST LLC C.C-a D218219520 R.T-C.T. PAVEMENT RECOMMENDATIONS I 4I CIBOLO HILLS WEST UEST, PROPOSED CIBOLO HILLS PARKWAY FORT WORTH, TEXAS UES PROJECT NO. W250053 -1 -REM I FIGURE 1 F M'OUNTA1N' E' I TI' MuL11FAMILY CPN 103516 APPROXIMATE [BORING LOCATION BORING LOCATION PLAN r4, UESII. Geotectrrw'ical • Construction Materials • ,Environmental • TBPE Firm No. 813 REPORT OF MECHANICAL LIME SERIES RESULTS Project No: W250053-1 Date: 05/06125 % Lime 0% 4°' 5°' 8% 10% PI 22 13 10 9 9 25 20 is d 10 5 0 I I I I h I I d I I I 0% 1% 2% 3% 4% 5% 6% 7% 8% 9% 10% 11% 12% Percent Dry Weight of Lime FIGURE 2 WinPAS PAS Pavement Thickness Design According to 1993 AASHTO Guide for Design of Pavements Structures American Concrete Pavement Association Rigid Design inputs Agency: City of Fort Worth Company: UES Professional Solutions, LLC Contractor: Project Description: Residential Pavement Analysis Location: Fort Worth, TX Rigid Pavement Design/Evaluation FCC Thickness 5.91 inches Load Transfer, J 3.00 Design ESALs 930,004 Mod. Subgrade Reaction, k 280 psifin Reliability 85.00 percent Drainage Coefficient, Cd 1.00 Overall Deviation 0.39 Initial Serviceability 4.50 Modulus of Rupture 620 psi Terminal Serviceability 2.00 Modulus of Elasticity 4,000,004 psi Modulus of Subarade Reaction (k-aalue) Determination Resilient Modulus of the Subgrade 0.0 psi Resilient Modulus of the Subbase 0.0 psi Subbase Thickness 0.00 inches Depth to Rigid Foundation 0.00 feet Loss of Support Value (0,1,2,3) 0.0 Modulus of Subgrade Reaction 280.00 psifin WinPAS PAS Pavement Thickness Design According to 1993 AASHTO Guide for Design of Pavements Structures American Concrete Pavement Association Rigid Design inputs Agency: City of Fort Worth Company: UES Professional Solutions, LLC Contractor: Project Description: Collector Pavement Analysis Location: Fort Worth, TX Rigid Pavement Design/Evaluation FCC Thickness 7.52 inches Load Transfer, J 3.00 Design ESALs 3,DOO,000 Mod. Subgrade Reaction, k 280 psifin Reliability 85.00 percent Drainage Coefficient, Cd 1.00 Overall Deviation 0.39 Initial Serviceability 4.50 Modulus of Rupture 620 psi Terminal Serviceability 2.25 Modulus of Elasticity 4,DOO,0O0 psi Modulus of Subarade Reaction (k-aalue) Determination Resilient Modulus of the Subgrade 0.0 psi Resilient Modulus of the Subbase 0.0 psi Subbase Thickness 0.00 inches Depth to Rigid Foundation 0.00 feet Loss of Support Value (0,1,2,3) 0.0 Modulus of Subgrade Reaction 280.00 psifin WinPAS PAS Pavement Thickness Design According to 1993 AASHTO Guide for Design of Pavements Structures American Concrete Pavement Association Rigid Design inputs Agency: City of Fort Worth Company: UES Professional Solutions, LLC Contractor: Project Description: Arterial Pavement Analysis Location: Fort Worth, TX Rigid Pavement DesigniEvaluation FCC Thickness 9.87 inches Load Transfer, J 3.00 Design ESALs 13,000,000 Mod. Subgrade Reaction, k 280 psifin Reliability 85.00 percent Drainage Coefficient, Cd 1.00 Overall Deviation 0.39 Initial Serviceability 4.50 Modulus of Rupture 620 psi Terminal Serviceability 2.50 Modulus of Elasticity 4,DOO,000 psi Modulus of Subgrade Reaction (k-aalue) Determination Resilient Modulus of the Subgrade 0.0 psi Resilient Modulus of the Subbase 0.0 psi Subbase Thickness 0.00 inches Depth to Rigid Foundation 0.00 feet Loss of Support Value (0,1,2,3) 0.0 Modulus of Subgrade Reaction 280.00 psifin 505R8rn5hcreek,Rd_ BORING NO 68 Sheet I JIi I I'acrd W6rih, Texas 7'6119 Phone. 817-446-5600 1 TM 1'ax: 817-49(-5608 PROJECT NO.: `251,0053-1 WWI4'. alphcif sWig aiM Client: GRBIC Edgewcod, LLC Location; Fort Worth, Texas Projects Cibolo Hills West Surface Elevation: Start Date: 411'112025 End Date: 411112025 West: Drilling Method: CONTINUOUS FLIGHT AUGER North: Hammer Drop (lbs 1 in): 140/30 GROUND WATER OBSERVATIONS m E - w On Rods (ft)_ 6 a i 'After C)r l ing� (ft;f: 6 7p{ 2 — f After Hours (R)m m co C C Z c Z) J CL a- 1-- MATERIAL DESCRIPTION Brown CLAY with limestone fragments 4.5+ 25 4.5+ 9 52 17 35 5 4.5+ 12 Y 6,0 Gray SHALE 10 10.0 10O 22 TEST BORING TERMINATED AT 24 FT 5' 15 20 25 30 35 505R8rn5hcreek,Rd_ BORING NO 69 JIi I I'acrd W6rih, Texas 76119 Phone. 817-446-5600 Sheet 1 i 1 TM 1'ax: 817-49(-5608 PROJECT NO.: `251,0053-1 WWI4'. alphcif sWig aiM Client: GRBIC Edgewcod, LLC Location; Fort Worth, Texas Projects Cibolo Hills West Surface Elevation: Start Date: 411'112025 End Date: 411112025 West: Drilling Method: CONTINUOUS FLIGHT AUGER North: Hammer Drop (Ibs 1 in): 140/30 GROUND WATER OBSERVATIONS I On Rods (ft): NONE VAfter Drillings (ft): DRY f After Hours (tt): MATERIAL DESCRIPTION p m `a C 4 yr R; C (I) E Ci J m� a- sn Tan LIMESTONE withclay seams and layers 5 1001 10 10.0 10p TEST BORING TERMINATED AT 10 FT 15 20 25 30 35 505R8rn5hcreek,Rd_ BORING NO 70 Sheet I JIi I I'acrd W6rih, Texas 76114 Phone. 817-446-5600 1 TM 1'ax: 817-49(-5608 PROJECT NO.: `251,0053-1 WWI4'. alphcif sWig aiM Client: GRBIC Edgewcod, LLC Location; Fort Worth, Texas Projects Cibolo Hills West Surface Elevation: Start Date: 411'112025 End Date: 411112025 West: Drilling Method: CONTINUOUS FLIGHT AUGER North: Hammer Drop (Ibs 1 in): 140/30 I GROUND WATER OBSERVATIONS On Rods (ft): NONE p `a E VAfter Grilling (ft): DRY >ff 4 yr f After Hours (ft): m C m� sn R; C (I) Ci J a- MATERIAL DESCRIPTION Brown CLAY 4.5+ 13 4.5+ 12 4.0 5 Tan and Gray CLAY with limestone fragments 4.5+ 12 4.5+ 12 33 13 20 0-1 5.0 Tan LIMESTONE with clay serns and layers 10 10.0 101 TEST BORING TERMINATED AT 10 FT 15 20 25 30 35 505R8rn5hcreek,Rd_ BORING NO 71 JIi I I'acrd W6rih, Texas 76119 Phone. 817-446-5600 1 TM 1'ax: 817-49(-5608 PROJECT NO.: `251,0053-1 WWI4'. alphcif sWig aiM Client: GRBIC Edgewcod, LLC Location; Fort Worth, Texas Projects Cibolo Hills West Surface Elevation: Start Date: 411'112025 End Date: 411112025 West: Drilling Method: CONTINUOUS FLIGHT AUGER North: Hammer Drop (Ibs 1 in): 140/30 I GROUND WATER OBSERVATIONS On Rods (ft): NONE p `a E VAfter Grilling (ft): DRY >ff 4 yr f After Hours (fty m C ; m� sn R C (I) Ci J a- MATERIAL DESCRIPTION Brown and Tan CLAY - FILL 4.5+ 13 4.5+ 18 49 15 34 5 4.5+ 5 42 15 27 0.0 4.0 15 8.0 Brown CLAY with limestone fragments 4.5+ 18 10 A 10.0 TEST BORING TERMINATED AT 10 FT 15 20 25 30 35 505R8rn5hcreek,Rd_ BORING NO 72 JIi I I'acrd W6rih, Texas 7'6114 Phone. 8T 7-446-56(70 1 TM 1'ax: 817-49(-5608 PROJECT NO.: `251,0053-1 WWI4'. alphcif sWig aiM Client: GRBIC Edgewcod, LLC Location; Fort Worth, Texas Projects Cibolo Hills West Surface Elevation: Start Date: 411'112025 End Date: 411112025 West: Drilling Method: CONTINUOUS FLIGHT AUGER North: Hammer Drop (lbs 1 in): 140/30 GROUND WATER OBSERVATIONS I On Rods (ft): NONE VAfter Drilling (ft): DRY f After Hours (fty MATERIAL DESCRIPTION p >ff m `a C 4 yr R ; C (I) E Ci J m� IL sn Brown CLAY with limestone fragments 4.5+ 12 2,0 Tan LIMESTONE with clay seams and layers 5 1401 10 10.0 1001 1' TEST BORING TERMINATED AT 10 FT 15 20 25 311 35 KEY TO SOIL SYMBOLS r/0 UEST,., AND CLASSIFICATIONS SOIL & ROCK SYMBOLS RELATIVE DENSITY OF COHESIONLESS SOILS (blowslt) (CH), High Plasticity CLAY VERY LOOSE 0 TO 4 (CL), Low Plasticity CLAY LOOSE MEDIUM 5 TO 10 11 TO 30 (SC), CLAYEY SAND DENSE VERY DENSE 31 TO 50 OVER 50 (SP), Poorly Graded SAND (SW), Well Graded SAND SHEAR STRENGTH OF COHESIVE SOILS (tsf) (Shit), SILTY SAND VERY SOFT LESS THAN 0.25 SOFT 0.25 TO 0.50 [liii® (ML), SILT FIRM 0.50 TO 1.00 STIFF 1.00 TO 2.00 (MH), Elastic SILT VERY STIFF 2.00 TO 4.00 ® HARD OVER 4.00 LIMESTONE RELATIVE DEGREE OF PLASTICITY (PI) SHALE/MARL LOW 4 TO 15 SANDSTONE MEDIUM 16 TO 25 HIGH 26 TO 35 c1 (GP), Poorly Graded GRAVEL VERY HIGH OVER 35 (GW), Well Graded GRAVEL (CC). CLAYEY GRAVEL RELATIVE PROPORTIONS (% (GM), SILTY GRAVEL (OL), ORGANIC SILT TRACE LITTLE 1 TO 10 11 TO 20 SOME 21 TO 35 (OH), ORGANIC CLAY AND 36 TO 50 SAMPLING SYMBOLS PARTICLE SIZE IDENTIFICATION (DIAMETER) ■SHELBY TUBE (3" OD except where BOULDERS 8.0" OR LARGER noted otherwise) COBBLES 3.0" TO 8.0" ®SPLIT SPOON (2" OD except where COARSE GRAVEL 0.75'" TO 3.0" noted otherwise) AUGER SAMPLE FINE GRAVEL COURSE SAND 5,0 mm TO 3.0" 2.0 mm TO 5.0 mm TEXAS CONE PENETRATION MEDIUM SAND FINE SAND 0.4 mm TO 5.0 mm 0,07 mm TO 0.4 mm ROCK CORE (2' ID except where SILT CLAY 0.002 mm TO 0,07 mm LESS THAN 0.002 mm noted othierwise) GR-0 1 60 00 Product Requirements Page 1 of 1 GR-01 60 00 PRODUCT REQUIREMENTS Cibolo Hills Parkway City Project No. 106104 CFW Lighting Approved Products List CFW Product Name Manufacturer Manufacturer Product Name & Description Residential -Standard MRT2470AB-Type 11, 36" or 60" Rise 2/Bolt 8' Arm, Makers Sales and Marketing, LLC Galvanized MRT2470AB-Type 11, 36" or 60" Rise 2/Bolt 8' Arm, Type 11 Pole Makers Sales and Marketing, LLC Black DB01373(page 1 of 6) -Shoe Base Pole Type 11, Valmont Industries, Inc Galvanized Makers Sales and Marketing, LLC Type 33B, 36" Rise Simplex 8' Arm, Galvanized Makers Sales and Marketing, LLC Type 33B, 36" Rise Simplex 8' Arm, Black Type 33B Arm Valmont Industries, Inc DB01373(page 4 of 6) -Single Arm Type 33B, Galvanized American Electric Lighting, ATBO-P101-Mvolt-R2-3K- Acuity Brands Lighting, Inc. M P -N L-P7-AO-RFD325607 American Electric Lighting, ATBO-P101-Mvolt-R4-3K- Acuity Brands Lighting, Inc. M P -N L-P7-AO-RFD325606 Residential Luminaire American Electric Lighting, ATB0-P101-Mvolt-R2-3K-BI< Acuity Brands Lighting, Inc. M P -N L-P7-AO-RFD325609 American Electric Lighting, ATB0-P101-Mvolt-R4-31<-BI< Acuity Brands Lighting, Inc. L-P7-AO-RFD325608 MP-NL-P7-AO-RFD325608 McFarland Cascade CREOSOTE 30/35 FOOT TIMBER POLE Timber Pole Bayou Forest Products 30-35' .80 CCA Green Timber Pole Makers Sales and Marketing, LLC Wood Pole Arm, 36" Rise Simplex 8' Arm, Galvanized Wood Pole Arm Makers Sales and Marketing, LLC Wood Pole Arm, 36" Rise Simplex 8' Arm, Black Valmont Industries, Inc DB01373(page 6 of 6) -Wood Pole Arm, Galvanized Arterial -Standard MRT33.585AB-Type 18, 36" or 60" Rise 2/Bolt 8' Arm, Makers Sales and Marketing, LLC Galvanized MRT33.585AB-Type 18, 36" or 60" Rise 2/Bolt 8' Arm, Type 18 Pole Makers Sales and Marketing, LLC Black DB01373(page 2 of 6) -Shoe Base Pole Type 18, Valmont Industries, Inc Galvanized Makers Sales and Marketing, LLC Type 33A, 60" Rise Simplex 8' Arm, Galvanized Makers Sales and Marketing, LLC Type 33A, 60" Rise Simplex 8' Arm, Black Type 33A Arm Valmont Industries, Inc DB01373(page 3 of 6) -Single Arm Type 33A, Galvanized American Electric Lighting, ATBO-P303-Mvolt-R2-31<- Acuity Brands Lighting, Inc. M P -N L-P7-AO-RFD322792 American Electric Lighting, ATBO-P303-Mvolt-R4-31<- Acuity Brands Lighting, Inc. M P -N L-P7-AO-RFD322794 Arterial Luminaire American Electric Lighting, ATB0-P303-Mvolt-R2-3K-BI< Acuity Brands Lighting, Inc. MP-NL-P7-AO-RFD322793 L-P7-AO-RFD322793 Acuity Brands Lighting, Inc. American Electric Lighting, ATB0-P303-Mvolt-R4-3K-BI< M P -N L-P7-AO-RFD322795 McFarland Cascade CREOSOTE 35/40 FOOT TIMBER POLE Timber Pole Bayou Forest Products 30-35' .80 CCA Green Timber Pole Makers Sales and Marketing, LLC Wood Pole Arm, 60" Rise Simplex 8' Arm, Galvanized Wood Pole Arm Makers Sales and Marketing, LLC Wood Pole Arm, 60" Rise Simplex 8' Arm, Black Valmont Industries, Inc DB01373 page 5 of 6) -Wood Pole Arm, Galvanized Decorative -Pedestrian Holophane, CLA 10.6(OAL)FT J20P07BK-MOD, AB -31-4 Washington 10' Pole Acuity Brands Lighting, Inc. RFD110736 Holophane, CLA14FT J20DMODC03BK RFD325026, AB - Washington 14' Pole Acuity Brands Lighting, Inc. 16-4 SPEC RFD325026 Holophane, WFCL3 P40 30K MVOLT FC3 NF BK AO PR7 Washington Luminaire Acuity Brands Lighting, Inc. FRGL RFD338699 Washington Globe Holophane, AWDE3 P40 30K MVOLT MS AL3 BK PR7 Luminaire Acuity Brands Lighting, Inc. AO RFD -315548 Oleander Type A Pole Acuity Brands Lighting, Inc. Holophane, PDA 12S5L20POBBK-MOD Oleander Type B Pole Acuity Brands Lighting, Inc. Holophane, PDA20S5L20P08BK-MOD Oleander Type B Arm Acuity Brands Lighting, Inc. Holophane, OHC 151N 2A TN BK Holophane, AUCL2 P40 30K AS BK L3 N P7 AO Oleander Luminaire Acuity Brands Lighting, Inc. RFD338741 Berry 12' Pole Acuity Brands Lighting, Inc. Holophane, RSA 12 50 G12 SC BK AB -26-4 RFD326400 Berry 20' Pole Acuity Brands Lighting, Inc. Holophane, PD20S5J20P11BK RFD338816 Berry Arm Acuity Brands Lighting, Inc. Holophane, VLC 271N 1A TN QSM BK Holophane, GPLF3 P40 30K MVOLT ASY QSM BK PR7 Berry Luminaire Acuity Brands Lighting, Inc. AO SH Banner Arms Acuity Brands Lighting, Inc. Holophane, BA-241N-2A-00-S4J-BL-075P-BK System Rigid Nonmetallic Schedule 80 Conduit, Meets UL 651 Cantex Inc. specifi cations and NEMA TC2, Rated for 90°C Cable, Sunlight Resistant, 10' Lengths and 20' lengths Rigid Nonmetallic Schedule 80 Electric Conduit, Meets UL 651 specifications, RUS listed, NEMA TC-2 and Heritage Plastics NEMA TC-3, Rated for 90°C Cable, Sunlight & Weather Conduit Resistant PVC Rigid Schedule 80 Conduit, Conforms to UL 651 Atkore-Heritage Plastics and NEMA TC 2, Sunlight Resistant, Listed for 90°C conductors or cable Schedule 80 PVC Rigid Nonmetallic Conduit, Extra Prime Conduit, Inc Heavy Wall EPC-80, Sunlight resistant, Rated for use with 90°C conductors, Meets UL651 Splice Kit With Connector NSi Industries, LLC Gel Stub Splice Kit with Connector, Easy -Splice, ESSLK Series Southwire Type XHHW-2 copper conductor, 600V TYPE XHHW-2 / RW90, copper conductor, Superslick Encore Wire Elite, 600V/1000V Encore Wire THHN / MTW / THWN-2 Copper conductor, 600V Copper Wire/Conductor Servicepro-X XHHW-2, 600/1,000 Volt Copper, CT Service Wire Co Rated XHHW-2 Low Smoke Halogen Free, Cross -linked Advanced Digital Cable Inc Polyethylene Insulated 14 AWG-750 MCM, 600 Volts, 90°C Dry and wet Aluminum Wire -Triplex Priority Wire & Cable, Inc Triplex Overhead Aluminum Conductor General Purpose, Midget Class MEN Fuses, Voltage Edison Rating: MEN - 250 VAC, Ampere Rating: 0.5 - 30 Amps, Interrupting Rating: 10,000 RMS Amps @ 125V Modular Ferrule Fuse Blocks for Midget Class and CC Edison Fuses Fuse & Fuse Holder In -line fuse holders for Single -Pole 13/32" x 1 1/2" Cooper Fuses HEB-AA Bussmann Series, HEB breakaway and non -breakaway EATON in -line fuse holders for UL 13/32" x 1- 1/2"supplemental fuses Bussmann Series, FNM 13/32" x 1-1/2" 250Vac time - EATON delay supplemental fuses Wire Joints for Copper Conductor, Cat No: 54615, Connector Thomas & Betts 54620, 54625 -TB, 54635, 54640, 54630 Electrol Systems, Inc TY A (120/240) 100(NS)AL(E)PS(U) Metered Pedestal 120-240V WE Manufacturing & Controls TY A 120/240 100(NS)AL(E)PS(U) Metered Pedestal 240- Electrol Systems, Inc TY A (240/480) 100(NS)AL(E)PS(U) WE Manufacturing & Controls TY A 240/480 100(NS)AL(E)PS(U) 480V Polymer Concrete, PHA132412X0002: TIER 22 (X) 22, MacLean Highline 5001bs Polymer Concrete, H -SERIES UNIT, H1730-24 TIER -22 - Oldcastle TXDOT 2x 1/2" CAPTIVE BOLT - 2x BRASS FLOATING Ground Box NUT Polymer Concrete, H -SERIES UNIT, H1324-24 TIER -15 - Oldcastle TXDOT 2x 1/2" CAPTIVE BOLT - 2x BRASS FLOATING NUT Split Bolt Connectors, Copper Split Bolts 2 Wire, N Kearneys NSi Industries, LLC Series Dark To Light, DLL Elite, Electronic Locking, Type Photocell Acuity Brands Lighting, Inc. Photocontrol, DLL -127 or DLL -480 Shorting Caps Acuity Brands Lighting, Inc. Dark To Light, Part # DSHORT SBK U Interim Products Residential Luminaire TRASTAR INC. DURA-STR10A-3K-120-3-GR-SCL Arterial Luminaire TRASTAR INC. DURA-STR25-3K-120-3-GR-SCL FORT WORTH, CITY OF FORT WORTH WATER DEPARTMENT STANDARD PRODUCT LIST Updated:2-26-26 Approval Spec No. Classsification Manufacturer Model No. National Spec Size Water & Sewer - Manholes & Bases/Components 33-39-10 (Rev 2/3/16) 07/23/97 3305 13 Urethane Hydrophilic Wotorstop Asahi Kogyo K.K. Adeka Ultra -Seal P-201 ASTM D2240/D412/D792 04/26/00 3305 13 Offset Joint for 4' Diam. MH Hanson Concrete Products Drawing No. 35-0048-001 04/26/00 3305 13 Profile Gasket for 4' Diam. MB. Press -Seal Gasket Corp. 250-4G Gasket ASTM C -443/C-361 SS MH 1/26/99 3305 13 FIDPE Manhole Adjustment Rings Ladtech Inc HOPE Adjustment Ring Traffic and Non -traffic area 5/13/05 3305 13 Manhole External Wrap Cannsa - CPS Wra idSeal Manhole Encapsulation System Water & Sewer - Manholes & Bases/Fiberglass 33-39-13 (1/8/131 1/26/99 3339 13 Fiberglass Manhole Fluid Containment Inc. Flowtite ASTM 3753 Non -traffic area 08/30/06 33 39 13 Fiberglass Manhole L.F. Manuleeturin Non -traffic area Water & Sewer - Manholes & Bases/Frames & Covers/Rectangular 33-05-13 (Rev 2/3/16) 3305 13 Manhole Frames and Covers I Western Iron Works, Bass & Hays Foundry 1001 24"x40" WD Water & Sewer - Manholes & Bases/Frames & Covers/Standard (Round) 33-05-13 (Rev 2/3/16) 3305 13 Manhole Frames and Covers Western Iron Works, Bass & Hays Foundry 30024 24" Dia. 3305 13 Manhole Frames and Covers McKinley Iron Works Inc. A 24 AM 24" Dia. 08/24/18 3305 13 Manhole Frames and Covers Neenah Foun R-1272 ASTM A40 & AASHTO M306 24" Dia. 08/24/18 3305 13 Manhole Frames and Covers Neenah Foundry NF 1274 ASTM A48 & AASHTO M306 30" Dia. 3305 13 Manhole Frames and Covers Sigma Corporation MH-144N 3505 13 Manhole Frames and Covers Sigma Corporation MH-143N 3305 13 Manhole Frames and Covers Pont-A-Mousson GTS-STD 24" dia. 3305 13 Manhole Frames and Covers Neenah Casting 24" dig. 10/31/06 3305 13 Manhole Frames and Covers Hin ed) Pewoeseal Hinged Ductile Iron Manhole ASTM A536 24" Dia. 7/25/03 3305 13 Manhole Frames and Covers Saint-Gobain Pipelines Pameex/nexus RE32-R8FS 30" Dia. 01/31/06 3305 13 30" Dia. MH Ring and Cover East Jordan Iron Works V1432-2 and V1483 Designs AASHTO M306-04 30" Dia. 11/02/10 3305 13 30" Dia. MH Ring and Cover Sigma Co ration MH1651 FWN & MHI 6502 30" Dia 07/19/11 3305 13 30" Dia. MH Ring and Cover Star Pipe Products MH32FTWSS-DC 30" Dia 08/10/11 3305 13 30" Dia. MH Ring and Cover Accucast 220700 Heavy Dutywith Gasket Ring 30" Dia 10/14/13 3305 13 30" Dia. MHRing and Cover (Biased & Lockable East Jordan Iron Works 30" ERGO XL Assembly with Cam Lock/MPIC/T-Gasket ASSHTO M105 & ASTM A536 30" Dia 06/01/17 3405 13 30" Dia. MH Ring and Cover Lockable) Cl SIP Industries 2280 (32" ASTM A 48 30" Dia. 12/05/23 3405 13 30" Dia. MH Ring and Cover Hinged & Lockable) Cl SIP Industries 4267 WT - Hinged (32") ASTM A 48 30" Dia. 09/16/19 3505 13 30" Dia. MH Ring and Cover Composite Access Products, L.P. CAP-ONE-30-FTW, Composite, w/ Lock w/o Fling 30" Din. 10/07/21 3405 13 30" Dia. MH Ring and Cover Trumbull Manufacturing 32(30") Frame and Cover 30" Dia. Water & Sewer - Manholes & Bases/Frames & Covers/Water Tight & Pressure Tight 33-05-13 (Rev 2/3/16) O 3305 13 Manhole Frames and Covers Pont-A-Mousson Pamti ht 24" Dia. • 3305 13 Manhole Frames and Covers Neenah Cawing 24" Dia. 3305 13 Manhole Frames and Covers Western Iron Works,Bass & Has Foundry 300-24P 24" Dia. 3305 13 Manhole Frames and Covers McKinley Iron Works Inc. WPA24AM 24" Dia. 03/08/00 3505 13 Manhole Frames and Covers Accucast RC -2100 ASTM A 48 24" Dia. 04/20/01 3305 13 Manhole Frames and Covers SIP Semm ore Industries Private Ltd. 300-24-23.75 Ring and Cover ASTM A 48 24" Dia. Water & Sewer - Manholes & Bases/Precast Concrete (Rev 1/8/13) 3339 10 Manhole, Precast Concrete Hydro Conduit Corp SPL Item #49 ASTM C 478 48" 3339 10 Manhole, Precast Concrete Wall Concrete Pie Co. Inc. ASTM C-443 48" 09/23/96 3339 10 Manhole. Precast Concrete Concrete Product Inc. 48" LD. Manhole w/ 32" Cone ASTM C 478 48" w/32" cone 12105/23 3339 10 Manhole, Precast Concrete The Turner Company 72" I.D. Manhole w/ 32" Cone ASTM C 478 72" 05/08/18 3339 10 Manhole, Precast Concrete The Turner Company 48", 60" I.D. Manhole w/ 32" Cone ASTM C 478 48", 60" 09/03/24 3339 10 Manhole, Precast Concrete Oldoastle Precast Inc. Manhole, 32" Opening and Flat top, (Na Transition Cones) ASTM C 478 48" to 84" I.D. 06/09/10 3339 10 Manhole, Precast Reinforced PetynoerlCoaoreto US Composite Pie Reinforced Polymer Concrete ASTM C-76 48" 10 72" 09/06/19 33 39 20 Manhole, Precast Concrete Forterra Pie and Precast 60" & 72" I.D. Manhole w/32" Cone ASTM C-76 60" & 72" 10/07/21 32 39 20 Manhole, Precast Concrete Forterea Pipe and Precast 48" I.D. Manhole w/32" Cone ASTM C-77 48" 10/07/21 33 39 20 Manhole Precast Reinforced PolymerPelymnrl Concrete Armorock 48" & 60" I.D. Manhole w/32" Cone 48" & 60" 10/07/21 33 39 20 Manhole, Precast lHt4seidl Polymer & PVC Geneva Pipe and Precast IPrudI Systems) 48" & 60" I.D. Manhole w/32" Cone 48" & 60" Non Traffic Areas 03/07/23 33 39 20 Manhole, Precast Concrete AmeriTex Pipe and Products, LLC 48" & 60" I.D. Manhole w/32" Cone ASTM C-478; ASTM C-923; ASTM CA43 03/07/23 33 39 20 Manhole, Precast Reinforced Polymer) Concrete P3 Polymers, RockHardse 48" & 60" I.D. Manhole w/32" Cone 04/28/07 Manhole, Precast Reinforced Polysoerl Concrete Amitech USA Meer Pol erete Pipe 02/04/26 33 39 20 Manhole Precast Concrete Thompson Pie Group 48" 60" 72" I.D. Manhole w/36" Cone Sewer -(WAC) Wastewater Access Chamber 33 39 40 12/29/23 333020 For use when Std.. MH cannot be Wastewater Access Chamber Ooiekstroant Solutions, Inc.. Type 8 Maintenace Shaft (Poopiti installed due to depth Water & Sewer - Manholes & Bases/Rehab Systems/Cementitious E1-14 Manhole Rehab Systems Quadex 04/23/01 EI-14 Manhole RehabSystems Standard Cement Materials, Inc. Reliner MOP El -14 Manhole Rehab Systems AP/M Permaf m 4/20/01 EI-14 Manhole Rehab System Strong Company Strong Seal MS2A Rehab System 5/12/03 El -14 Manhole Rehab System Liner Triplex Lining System MH r air product to stop infiltration ASTM D5813 08/30/06 General Concrete Repair FlexKrete Technologies Vinyl Polyester Repair Product Misc. Use ' From Original Standard Products List FORT WORTH, CITY OF FORT WORTH WATER DEPARTMENT STANDARD PRODUCT LIST Updated:2-26-26 Approval Spec No. Classsification Manufacturer Model No. National Spec Size Water & Sewer - Manholes & Bases/Rehab Systems/NonCementitious 05/20/96 EI-14 Manhole Rehab Systems Spraynog, Spray Wall Polyrcrrlbmno Coating ASTM D639/D790 12/14/01 Coating for Corrosion rotection Exterior ERTECH Series 20230 and 2100 )Asphn6c Emulsion) Structures Only 01/31/06 0/outings for Corrosion Protection Chesterton Are 791, SIHB, SI, S2 Acid Resistance Test Sewer Applications 8/28/2006 Coatings for Corrosion Protection Warren Environmental S-301 and M-301 Sewer Applications 03/19/18 33 05 16,3339 10, 33 3920 Coating for Corrosion otecdon Exterior Sherwin Williams RR&C Dampproofing Non-Fibered Spray Grade (Asphatic Emulsion) For Exterior Coating of Concrete Structures Only 02/04/26 Exterior Precast Joint Seat Wra p idseal Exterior Sealant Tape/Shrinkwrap Does not replace rubber gasket or Ram-Nek Water & Sewer - Manhole Inserts - Field Operations Use Only (Rev 2/3/16) 3305 13 Manhole Insert Knutson Enterprises Made to Order - Plastic ASTM D 1248 For 24" dia. 3303 13 Manhole Insert South Western Packaging Made to Order - Plastic ASTM D 1248 For 24" dia. 3305 13 Manhole Insert Noflow-Inflow Made to Order - Plastic ASTM D 1248 For 24" dia. 09/23/96 3303 13 Manhole Insert Southwestern Packing & Seals Inc. LifeSaver - Stainless Steel For 24" dia. 09/23/96 3305 13 Manhole Insert Southwestern Packing & Seals, Inc. TetherLok - Stainless Steel For 24" dia Water & Sewer - Pipe Casing Spacers 33-05-24 (07/01/13) 11/04/02 Steel Band Casing Spacers Advanced Products and Systems, Inc. Carbon Steel Spacers, Model SI 02/02/93 Stainless Steel Casing Spacer Advanced Products and Systems, Inc. Stainless Steel Spacer, Model SSI 04/22/87 Casing Spacers Cascade Waterworks Manufacturing Casing Spacers 09/14/10 Stainless Steel Casing Spacer Pipeline Seal and Insulator Stainless Steel Casing Spacer Up 10 48" 09/14/10 Coated Steel Casin Spacers Pipeline Seal and Insulator Coated Steel Casing Spacers Up to 48" 05/10/1 l Stainless Steel Casing Spacer Powerseal 4810 Powerehock Up 10 48" 03/19/18 Casing Spacers BWM SS -12 Casing Spaeer(Stainless Steel) 03/19/18 Casing Spacers BWM FB-12 Casing Spacer (Coated Carbon Steel) for Non_tressure Pipe and Grouted Casing 03/29/22 3305 13 Casing Spacers CCI Pipeline Systems CSC12, CSS12 09/03/24 3305 13 Casing Spacers Rani (Completely HDPE) Per Manufacturers Requirements (Sewer Applications Only) 8" - 12" (Sewer Only) Water & Sewer - Pipes/Ductile Iron 33-11-10(1/8/13) 33 11 10 Ductile Iron Pipe Griffin Pipe Products, Co. Super Bell-Tite Ductile Iron Pressure Pipe, AWWA C150, 0151 3" thou 24" 08/24/18 33 11 10 Ductile Iron Pipe American Ductile Iron Pipe Co. American Fastite Pipe (Bell Spigot) AWWA C150, CI5I 4" thou 30" 00/24/18 33 1 1 10 Ductile Iron Pipe American Ductile Iron Pipe Co. American Flex Ring (Restrained Joint) AWWA C 150, C 151 4" thou 30" " 33 11 10 Ductile Iron Pipe U.S. Pipe and Foundry Co. AWWA C) 50, C151 a 33 1110 Ductile Iron Pipe McWane Cast Iron Pipe Co. AWWA C150, 0151 Water & Sewer -Utility Line Marker (08/24/2018) Sewer - Coatings/Epoxy 33-39-60 (01/08/13) 02/25/02 Epoxy Lining System Sauereisen, Inc SewerGard 2l0RS LA County #210-1.33 12/14/01 '°.puxyLining Sexton, Ertoch Technical Coatings Ertech 2030 and 2100 Series. 04/14/05 Interior Ductile Iron Pi. a Coating Induron Protecto 401 ASTM B-117 Ductile Iron Pie Only 01/31/06 Coatings for Corrosion Protection Chesterton Arc 791 SIHB SI, S2 Acid Resistance Test Sewer Applications 8/28/2006 Coatings for Corrosion Protection Warren Environmental S-301 and M-301 Sewer Applications Sewer - Coatines/Polyurethane Sewer - Combination Air Valves 05/25/18 33-31-70 Air Release Valve AR.!. USA, Inc. D025LTP02 Com osite Body( 2" Sewer - Pipes/Concrete El -04 Conc. Pie, Reinforced Wall Concrete Pie Co. Inc. ASTM C 76 EI-04 Conc. Pie, Reinforced Uyxlro Conduit Corporation Class Ill T&G SPL Item #77 ASTM C 76 E1-04 Conc. Pie, Reinforced Hanson Concrete Products ASTM C 76 E1-04 Conc. Pipe, Reinforced Concrete Pie & Products Co. Inc. ASTM C 76 Sewer - Pipe Enlargment System (Method)33-31-23 (01/18/13) PIM System PIM Corporation Polyethylene PIM Corp., Piscam Way, N.J. Approved Prcviously McConnell systems MnLat Construction polyethylene Houston, Texas Approved Proxiocsly 'RS Systems Trenchless Roplucoment System Polyethylene Calgary. Canada Approved Proviously Sewer - Pipe/Fiberglass Reinforced/ 33-31-13(1/8/13) 7/21/97 3331 13 Cent. Cast Fiber lass FRP Hobas Pie USA, Inc. Hobas Pie on -Pressure ASTM D3262/D3754 03/22/10 33 31 13 Fiber lass Pi (FRP) Ameron Bondstrand RPM!' Pipe ASTM D3262ID3754 04/09/21 33 31 13 Glass -Fiber Reinforced Polymer Pi a (FRP) Thompson Pie Group Thomson Pipr Flowtite ASTM D3262/D3754 03/07/23 33 31 13 Fiberglass Pie (FRP) Future Pipe Industries Fiberstrcng FRP ASTM 03262, ASTM D3681, ASTM D4161, AWWA M45 09/03/24 33 31 13 Fiberglass Pipe (FRP) Superlit Borg Sanayi A.S. Superlit FRP ASTM D3262, ASTM D3517, ASTM 3754, AWWA C950 " From Original Standard Products List FORT WORTH,, CITY OF FORT WORTH WATER DEPARTMENT STANDARD PRODUCT LIST Updated:2-26-26 Approval Spec No. Classsification Manufacturer Model No. National Spec Size * From Original Standard Products List FORT WORTH[,, CITY OF FORT WORTH WATER DEPARTMENT STANDARD PRODUCT LIST Updated:2-26-26 Approval Spec No. Classsification Manufacturer Model No. National Spec Size Sewer - Pipe/Polymer Pipe 4/14/05 Polymer Modified Concrete Pipe Amitreh USA Meer Pol Crete Pipe ASTM C33, A276, F477 8" to 102", Class V 06/09/10 El -9 Reinforced Polymer Concrete Pipe US Composite Pipe Reinforced Polymer Concerto Pie ASTM C-76 Sewer - Pipes/HDPE 33-31-23(1/8/13) '-tigh-density potpedsylene pipe Phillips Driscopipe, e, Inc. O ticore Ductile Polyethylene Pipe ASTM D 1248 8" ligh-density potynthyleno pipo Plexco Inc. ASTM D 1248 8" High -density of eth lene pipe Polly Pipe, Inc. ASTM D 1248 8" °-Iigh-donsity polyethylene pipe CSR Hydro Conduit/Pi cline Syatooss McConnell Pipe Enlargement ASTM D 1248 Sewer - Pipes/PVC (Pressure Sewer) 33-11-12 (4/1/13) 12/02/11 33-11-12 DR -14 PVC Pressure Pipe Pipelife Jetstream PVC Pressure Pipe AWWA C900 4" then 12" 10/22/14 33-11-12 DR -14 PVC Pressure Pipe Royal Building Products Royal Seal PVC Pressure Pipe AWWA C900 4" then 12" Sewer — Pipes/PVC* 33-31-20 (7/1/13) 33-31-20 PVC Sewer Pipe J -M Manufacturin Co. Inc. JM Eagle) SDR-26 1PS1I5 ASTM D 3034 4" - 15" 12/23/97" 33-31-20 PVC Sewer Pipe Diamond Plastics Co oration SDR-26 PSI 15 ASTM D 3034 4" then 15" 33-31-20 PVC Sewer Pie Lamson V lon Pie SDR-26 (PSI 15) ASTM D 3034 4" then 15" 12/05/23 33-31-20 PVC Sewer Pipe Vin ltech PVC Pie SDR-26 PSI15 ASTM 03034 4" then 15" 12/05/23 33-31-20 PVC Sewer Pie Vinyttech PVC Pipe Gravity Sewer PS 115 ASTM F 679 18" 33-31-20 PVC Sewer Pie J -M Manufacturing Co Inc. JM Eagle) PS 115 ASTM P679 18" - 28" 05/06/05 33-31-20 PVC Solid Wall Pipe Diamond Plastics Corporation PS 115 ASTM F-679 18" to 48" 04/27/06 33-31-20 PVC Sewer Fittings Harco SDR-26 PS 115) Gasket Fittings ASTM D-3034, D-1784, etc 4" - 15" 33-31-20 PVC Sewer Fittings Plastic Trends, Inc.(Westlake) (indicted PVC Sewer Main Fittings ASTM D 3034 3/19/2018 3531 20 PVC Sewer Pipe Pi elite Jet Stream SDR 26 (PS 115) ASTM F679 18"- 24" 3/19/2018 33 31 20 PVC Sewer Pie Pipelife Jet Stream SDR 26 ASTM D3034 4"- 15" 3/29/2019 3331 20 Gasketed Fittings (PVC) GPK Products, Inc. SDR 26 ASTM D3034 4"- 15" 10/21/2020 3331 20 PVC Sewer Pie NAP( Westlake) SDR26 ASTM 03034 4" - 15" 10/22/2020 3331 20 PVC Sewer Pie Sanderson Pipe Corp. SDR 26 ASTM 03034 4"- 15" 10/21/2020 33 31 20 PVC Sewer Pie NAPCO(Westlake) SDR 26 PS 115 ASTM F-679 18"- 36" 2/4/2026 33 31 20 PVC Sewer Pipe Hawk Plastics Corp. SDR 26 ASTM 03034 4"- l5" ' From Original Standard Products List FORT WORTH,, CITY OF FORT WORTH WATER DEPARTMENT STANDARD PRODUCT LIST Updated:2-26-26 Approval Spec No. Classsification Manufacturer Model No. National Spec Size Water - Appurtenances 33-12-10 (07/01/13) 09/03/24 33-12-10 Double Strap Saddle Ford Meter Box Co., Inc. 202B I "-2" SVC, op to 16" Pipe 01/18/18 33-12-10 Double Strap Saddle Romac 202NS Nylon Coated AWWA C800 1"-2" SVC, ap to 24" Pipe 08/28/02 Double Strap Saddle Smith Blair #317 Nylon Coated Double Strap Saddle 07/23/12 33-12-10 Double Strop Service Saddle Mueller Company DR2S Double SS Strop DI Saddle AWWA C800 1"-2" SVC UP 10 24" Pipe 03/07/23 33-12-10 Double Strap Service Saddle Powerseal 3450AS, locl. Corp. Stop, Dbl Strap, Stainless NSF ANSI 372 1"-2" SVC, up to 24" Pipe 10/27/87 Curb Stops -Boll Meter Valves McDonald 6100M,6100MT & 61OMT 3/4" and I" 10/27/87 Cub Stops -Ball Meter Valves McDonald 4603B, 4604B, 6100M, 610OTM and 6101M I /4" and 2" 5/25/2018 33-12-10 Curb Stops -Ball Meter Valves Ford Meter Box Co. Inc. FB600-7NL, FB1600-7-NL, FV23-777-W-NL, L22-77NL AWWA 0800 2" 5/25/2018 33-12-10 Curb Slops -Ball Meter Valves Ford Motor Box Co. Inc. FB600-6-NL, FB1600-6-NL, FV23-666-W-NL, L22-66NL AWWA 0800 1-1/2" 5/25/2018 33-12-10 Cub Stops -Ball Meter Valves Ford Meter Box Co., Inc. FB600-4-NL, FB1600-4-NL, Bl1-044-WR-NL, B22444-WR-NL, L28-44NL AWWA C800 1" 5/25/2018 33-12-10 Cub Stops -Bull Meter Valves Mueller Co., Ltd. B -25005N, B -24277N-3, B -20200N-3, H- 15000N, , H -1552N, H142276N AWWA C800, ANSF 61, ANSI/NSF 372 2" 5/25/2018 33-12-10 Curb Stops -Boll Meter Valves Mueller Co. Ltd. B-25000N,B-20205N-3, B -24277N -3,H- 15005N, H -14276N H -15525N AWWA 0800, ANSF 61, ANSI/NSF 372 1-1/2" 5/25/2018 33-12-10 Curb Slops -Ball Meter Valves Mueller Co., Ltd. B -25000N, B -20200N -3,H -15000N, H- 15530N AWWA C800, ANSF 61, ANSI/NSF 372 01/26/00 Coated Tapping Saddle with Double SS Straps JCM Industries Inc. #406 Double Band SS Saddle 1 "-2" Taps on ap to 12" 0/5/21/12 33-12-25 Tapping"apping Sleeve Coated Steel) JCM Industries, Inc. 412 Tapping Sleeve ESS Ass/WA C-223 Up to 30" w/12" Out 03/29/22 33-12-25 "repine Sleeve Coated or Stainless Stroll JCM Industries, Inc. 415 Tapping Sleeve AWWA C-223 Concrete Pie Only 05/10/11 Tapping Sleeve Stainless Stroll Powerseal 3490AS )Flange) & 3490MJ 4"-8" and 16" 02/29/12 33-12-25 Tapping Sleeve Coated Steel Romac FTS 420 AWWA C-223 U pta 42" w/24" Out 02/29/12 33-12-25 "'upping Sleeve Stainless Steel) Romac SST Stainless Steel AWWA C-223 Up 10 24" w/12" Om 02/29/12 33-12-25 "Upping Sleeve (Stainless Steel) Romac SST III Stainless Steel AWWA C-223 Up to 30" w/12" Oct 05/10/11 Joint Repair Clamp Powerseal 3232 Bell Joint Re air Clam 4" 10 35" Plastic Meter Box w/Com osite Lid DFW Plastics Inc. DFW37C-12-IEPAF FTW Plastic Meter Box so/Composite Lid DFW Plastics Inc. DFW39C-12-1EPAF FTW 08/30/06 Plastic Meter Box w/Com osite Lid DFW Plastics Inc. DFW65C-14-IEPAF FTW Class "A" Concrete Meter Box Bass & Hays CMB37-B12 1118 LID -9 Concrete Meter Box Bass & Hays CMB-18-Dual 1416 LID -9 Concrete Meter Box Bass & Has CMB65-B65 1527 LID -9 Water - Bolts, Nuts, and Gaskets 33-11-05 (01/08/13) None Water - Combination Air Release 33-31-70 (01/08/131 a El -II Combination Air Release Valve GA Industries, Inc. Empire Air and Vacuum Valve, Model 935 ASTM A 126 Class B, ASTM A 1" & 2" E1-11 Combination Air Release Valve Multiples Manufacturing Co. Crispin Air and Vacuum Valves, Model Na. I /2", 1" & 2" EI-11 Combination Air Release Valve Valve and Primer Corp. APCO #143C #145C and #147C I ". 2" & 3" Water - Dry Barrel Fire Hydrants 33-12-40 (01/15/14) 10/01/87 E-1-12 '3ry Barrel Fire Hrant American-DarlingValve Drawing Nos, 90-18608 94-18560 AWWA C-502 03/31/88 E-1-12 Dry Barrel Fire Hydrant American Dueling Valve Shop Drawing No. 94-18791 Ass/WA C-502 09/30/87 E-1-12 Dry Barrel Fire Hydrant Clow Corporation Shop Drawing No, D-19895 AWWA C-502 01/12/93 E-1-12 Dry Barrel Fire Hydrant American AVK Company Model 2700 AWWA C-502 08/24/88 E-1-12 Dry Barrel Fire H drent Clow Corporation Drawings D20435, D20436 820506 AWWA C-502 E-1-12 Dry Barrel Fire Hant ITT Keanedy Valve Shop Drawing No. D-80783FW AWWA C-502 09/24/87 E-1-12 Dry Barrel Fire Hydrant M&H Valve Company Shop Drawing No. 13476 AWWA C-502 10/14/87 E-1-12 0ry Barrel Fire Hydrant Mueller Company Shop Drawings No. 6461 A-423 Centurion AWWA C-502 01/15/88 EI-12 Dry Barrel Fire H drent Mueller Company Shop Drawing FH-12 A-423 Super Centurion 200 AWWA C-502 10/09/87 E-1-12 Dry Barrel Fire Hant U.S. Pipe & Faun Shop Drawing No. 960250 AWWA C-502 09/16/87 E-1-12 DryBserol Fire Hydrant American Flow Control )AFC) Watereus Pacer WB67 AWWA C-502 08/12/16 33-12-40 Dry Barrel Fire Hydrant EJ lEast Jordan Iron Works) WaterMaster 5CD250 Water - Meters 02/05/93 E101-5 Detector Check Meter Ames Company Model 1000 Detector Check Valve AWWA C550 4" - 10" 08/05/04 Magnolia Drive Vertical Turbine Hersey Magnetic Drive Vertical AWWA 0701 Class 1 3/4" - 6" ' From Original Standard Products List FORT WORTH,, CITY OF FORT WORTH WATER DEPARTMENT STANDARD PRODUCT LIST Updated:2-26-26 Approval Spec No. Classsification Manufacturer Model No. National Spec Size Water - Pipes/PVC (Pressure Water) 33-31-70 01/08/13 12/05/23 33-11-12 PVC Pressure Pipe Vinyltech PVC Pipe DR14 AWWA C900, AWWA C605, ASTMD1784 4"-16" 12/05/23 33-1.1-12 PVC Pressure Pipe Vin ltech PVC Pipe DRIB AWWA C900, AWWA C605, ASTMD1784 l6-18" 09/03/24 33-11-12 PVC Pressure Pipe Northern Pipe Products DR14 AWWA C900, AWWA C605, ASTM DI 784 4"-16" 09/03/24 33-11-12 PVC Pressure Pipe Northern Pipe Products 01518 AWWA C900, AW WA C605, ASTMD1784 16-18" 3/19/2018 331112 PVC Pressure Pipe Pi elite Jet Stream DR14 AWWA C900 4"-12" 3/19/2018 331112 PVC Pressure Pipe Pi elite Jet Stream DR18 AWWA C900 16-24" 5/25/2018 33 11 12 PVC Pressure Pie Diamond Plastics Corporation DR 14 AWWA C900 4"-12" 5/25/2018 33 11 12 PVC Pressure Pipe Diamond Plastics Co ration DR 18 AWWA C900 l6"-24" 12/6/2018 33 11 12 PVC Pressure Pipe J -M Manufacturing Co., Inc d/b/a JM Eagle DR 14 AWWA C900-16 UL 1285 ANSI/NSF 61 FM 1612 4"-28" 12/6/201% 33 1 1 12 PVC Pressure Pipe J -M Manufacturing Co., Inc d/b/a JM Eagle DR 18 AWWA C900-16 UL 1285 ANSJMSF 61 FM 1612 l6"-24" 9/6/2019 33 11 12 PVC Pressure Pipe Underground Solutions Inc. DR14 Fusible PVC AWWA C900 4" - 8" 9/6/2019 331112 PVC Pressure Pipe NAPCO(Westlake) DRI 8 AWWA C900 16"- 24" 9/6/2019 33 1112 PVC Pressure Pipe NAPCO(Westlake) DR14 AWWA C900 4"- 12" 9/6/2019 33 1112 PVC Pressure Pipe Sanderson Pipe Corp. DR14 AWWA C900 4"- 12" Water - Pipes/Valves & Fittinps/Ductile Iron Fittings 33-11-11 (01/08/13) 07/23192 EI-07 Ductile loon Fittings Star Pipe Products, Inc. Mechanical Joint Fittings AWWA C153 & CI 10 E 1-07 Ductile Iron Fittings Griffin Pie Products, Co. Mechanical Joint Fittings AWWA C 110 E1-07 Ductile Jean Fittings McWene/T ler Pi Union Utilities Division Mechanical Joint Fittings, SSB Class 350 AWWA C 153, C 110, C III 08/11/98 E 1-07 Ductile Iron Fittings Sigma, Co. Mechanical Joint Fittings, SSB Class 351 AWWA C 153, C 110, C 112 02/26/14 EI-07 MJ Fittings Accucast Class 350 C-153 MJ Fittings AWWA C153 4"-12" 05/14/98 EI-07 Ductile Iron Joint Restraints Ford Meter Box Co./Uni-Flan Uni-Flange Series 1400 AWWA CII I/C153 4" to 36" 05/14/98 E1-24 PVC Joint Restraints Ford Meter Box Co./Uni-Flan a Uni-Flange Series 1500 Circle -Lock AS/WA Cl I I/C153 41024" 11/09/04 E1-07 Ductile Iron Joint Restraints One Bolt, Inc. One Bolt Restrained Joint Fitting A'S/WA C I 11/C 116/C 153 4" to 12" 02/29/12 33-11-11 Ductile Iron Pipe Mechanical Joint Restraint EBAA Iron, Inc. Megalug Series 1100 (for DI Pipe) A'S/WA Cl 11/Cl 16/C153 4" to42" 02/29/12 33-11-11 PVC Pipe Mechanical Joint Restraint EBAA Iron, inn. Megalug Series 2000 (for PVC Pipe) AWWA C I I 1/Cl 16/C 153 4" to 24" 08/05/04 E1-07 Mechanical Joint Retainer GlandaPVC Sigma. Co. Sigma One-Lok SLC4 - SLCI0 AWWA CII I/C153 4"to 10" 03/06/19 33-11-I1 Mechanical Joint Retainer GlandsPVC Sigma, Co. Sigma One-Lok SLCS4 - SLCS12 AWWA CIlI/C153 4" to 12" 08/05/04 E1-07 Mechanical Joint Retainer Glands PVC Si to Co. Sigma One-Lok SLCE A'S/WA Cl I I/C153 12" to 24" 08/10/98 E1-07 MJ Finings(DIP)Sigma, Co. Sigma One-Lok SLDE AWWA C153 4" - 24" 10/12/10 P1-24 Interior Restrained Joint System S & B Techncial Products Bulldog System) Diamond Lok 21 & JM Eagle ASTM F-1624 4" 10 12" 04/07/69 Interior Restrained Joint System Huller Hydrogrip-R ASTM D395, D412, D471, D573, D883, D1149, D1229, D1349, D1414, D1415, D1566, F913 4'-12" 08/16/06 E1-07 Mechanical Joint Fittings SIP Industries Scram ore Mechanical Joint Fittings AWWA 1/153 4" 1024" 11/07/16 33 -I1 -I I Mechanical Joint Retainer Glands Star Pipe Products Inc. PVC Stargrip Series 4000 ASTM A536 AWWA CI l l 11/07/16 33-11-11 Mechanical Joint Retainer Glands Star Pipe Products, Inc. DIP Stargrip Series 3000 ASTM A536 AWWA CIII l 03/19/18 33-I 1-11 Mechanical Joint Retainer Glands SIP Industries Scram or EZ Grip Joint Restraint (EZD) Black For DIP ASTM A536 AWWA C111 3"-48" 03/19/18 33-11-11 Mechanical Joint Retainer Glands SIP Industries(Saesmporr) EZ Grip Joint Restraint (EZD) Red for C900 DR14 PVC Pipe ASTM A536 AWWA Cl II 4"-12" 03/19/18 33-11-11 Mechanical Joint Retainer Glands SIP Industries(Serampore) EZ Grip Joint Restraint (EZD) Red for C900 DR18 PVC Pipe ASTM A536 AWWA CIII I 16-24" * From Original Standard Products List FORT WORTH,, CITY OF FORT WORTH WATER DEPARTMENT STANDARD PRODUCT LIST Updated:2-26-26 Approval Spec No. Classsification Manufacturer Model No. National Spec Size Water - Pipes/Valves & Fittines/Resilient Seated Gate Valve* 33-12-20 (05/13/15) Resilient Wedged Gate Valve w/no Gears American Flow Control Series 2500 Grassing #94-25247 16" 12/13/02 Resilient Wedge Gate Valve American Flow Control Series 2530 and Series 2536 AWWA 0515 30" and 36" 08/31/99 Resilient Wedge Gate Valve American Flow Control Series 2520 & 2524 SD 94-20255) AWWA C515 20" and 24" 05/18/99 Resilient Wedge Gate Valve American Flow Control Series 2516 SD 94-20247) AWWA C515 16" 10/24/00 E1-26 Resilient Wedge Gate Valve American Flow Control Series 2500 Ductile Iron) AWWA 0515 4" to 12" 08/05/04 Resilient Wedgo Gate Valve American Flow Control 42" and 48" AFC 2500 AWWA C515 42" and 48" 05/23/91 El -26 Resilient Wedge Gate Valve American AVK CompanyCompaey American AVK Resilient Sealed GV AWWA C509 4" to 12" 01/24/02 E1-26 Resilient Wedge Gate Valve American AVK Company 20" and smaller E1-26 Resilient Seated Gate Valve Kennel 4" - 12" E1-26 Resilient Seated Gate Valve M&H 4"- 12" EI-26 Resilient Seated Gate Valve Mueller Co. 4" - 12" 11/08/99 Resilient Wedge Gate Valve Mueller Co. Series A2361 SD 6647) AWWA C515 16" 01/23/03 Resilient Wedge Gate Valve Mueller Co. Series A2360 for 18-24" SD 6709) AWWA C515 24" and smaller 05/13/05 Resilient Wedge Gate Valve Mueller Co. Mueller 30" & 36", C-515 AWWA (.515 30" and 36" 01/31/06 Resilient Wedge Gate Valve Mueller Co. Mueller 42" & 48", C-515 AWWA C515 42" and 48" 01/28/88 E1-26 Resilient Wedge Gate Valve Clow Valve Co. AWWA C509 4"- 12" 10/04/94 Resilient Wedge Gate Valve Clow Valve Co. 16" RS GV (SD D-20995) AWWA C515 16" 11/08/99 E1-26 Resilient Wedge Gate Valve Clow Valve Co. Clow RW Valve SD D-21652) AWWA C515 24" and smaller 11/29/04 Resilient Wedge Gate Valve Clow Valve Co. Clow 30" & 36" C-515 AWWA C515 30" and 36"Note 3) 11/30/12 Resilient Wedge Gate Valve Clow Valve Co. Clow Valve Model 2638 AWWA C515 24" to 48" (Note 3 05/08/91 El -26 Resilient Seated Gate Valve Stnckham Valves & Fittings AWWA C 509, ANSI 420 - stem, 4" - 12" El -26 Resilient Seated Gate Valve U.S. Pipe and Foundry Co. Menoseal 250, re meements SPL #74 3" to 16" 10/26/16 33-12-20 Resilient Seated Gate Valve EJ lEast Jordan Iron Works) EJ FlowMaster Gate Valve & Boxes Remove Marc. 225 MR 2-4-26 Water - Pipes/Valves & Fittings/Rubber Seated Butterfly Valve 33-12-21 (07/10/14) El -30 Rubber Seated Butterfly Valve HenryPratt Co. AWWA C-504 24" El -30 Rubber Seated Butterfly Valve Mueller Co. AWWA C-504 24"and smaller 1/11/99 E1-30 Rubber Seated Butterfly Valve Dezurik Valves Co. AWWA C-504 24" and larger 06/12/03 E1-30 Valmatic American Butterfly Valve Valmatie Valve and Manufacturing Corp. Valmatic American Butterfly Valve. AWWA C-504 Up 10 84" diameter 04/06/07 El -30 Rubber Seated Butterfly Valve M&H Valve M&H Style 4500 & 1450 AWWA C-504 24" 10 48" 03/19/18 33 1221 Rubber Seated Butterfly Valve G. A. Industries Golden Anderson) AWWA C504 Butterfly Valve AWWA C-504 30-54" 09/03/24 33 1221 Rubber Seated Butterfly Valve American AVK Company AWWA C504 Butterfly Valve Class 250B AWWA C-504 24" - 48" 02/04/26 331221 Rubber Seated Butterfly Valve Mueller Water Products Pratt XR-75W/Segmented Seats AWWA C-504 24"- 54" Water -Polyethylene Encasement 33-11-10 (01/08/13) 05/12/05 El -13 Polyethylene Encasment Flexsol Paekagieg Fulton Enterprises AWWAC105 8 mil LLD 05/12/05 E1-13 Polyethylene Encasment Mountain States Plastics (MOF( and AEP Ind. Standard Hardware AWWA C105 8 mil LLD 05/12/05 El -13 Polyethylene Encasment AEP Industries Bultvtraeg by Cowtown Bolt & Gasket AWWA 0105 8 mit LLD 09/06/19 33-I1-11 Polyethylene Encasment Northtown Products Inc. PE Encasement for DIP AWWA C105 8 mil LLD Water - Sampling Station 03/07/23 33 1250 Water Sampling Station Kupferle Foundry Company Eclipse, Number 08, 12 -inch Depth of Bury As shown in spec. 33 12 50 Water - Automatic Flusher 10/21/20 Automated Flashing System Mueller Hdroguard HG6-A-IN-2-BRN-LPRR(Portable) HGZ-A-IN--2-PVC-018-LPLG(Permanent 04/09/21 Automated Flushing System Kupferle Foundry Company Eclipse #9800we 04/09/21 Automated Flushing System Kupferle Foundry Company Eclipse #9700 (Portable) The Fort Worth Water Department's Standard Products List has been developed to minimize the submittal review of products which meet the Fort Worth Water Department's Standard Specifications during utility construction projects. When Technical Specifications for specific products, are included as pan ofthe Construction Contract Documents, the requirements ofthe Technical Specification will override the Fort Worth Water Department's Standard Specifications and the Fort Worth Water Department's Standard Products List and approval of the specific products will be based on the requirements of the Technical Specification whether or not the specific product meets the Fort Worth Water Department's Standard Specifications or is on the Fort Worth Water Department's Standard Products Yellow Highlight indicates recent changes a From Original Standard Products List FORT WORTH. CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT STANDARD PRODUCTS LIST AS OF 08/01/2026 !1!!!!!! Attention: Mix Desiens do not supersede CFW Snecifications !!!!!!!!!! Concrete C1jSidewalk, ADA Rams, Driveways, Curb/Gutter, Median Pavement) 1/14/2026 32 13 13 Mix Design AM Corp 1071 3600 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 20 Mix Design American Concrete Company 30CAF029 3000 psi 3-5" Slump; 3-6% Air 4/3/2025 32 13 20 Mix Design Big Town Concrete 2211 3000 psi 3-5" Slump; 3-6% Air 7/16/2025 32 1320 Mix Design Big Town Concrete 22113 With 30% Slag 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 1320 Mix Design Borneo Texas 30U l01AG 3000 psi 3-5" Slump; 3-6% Air 4/1/2024 32 13 20 Mix Design Bumco Texas 30U500BG 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 20 Mix Design Carder Concrete FWCC502001 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 1320 Mix Design Carder Concrete FWCC502021 3500 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 20 Mix Design Chisholm Trail Redi Mix C13020AE 3000 psi 3-5" Slump; 4.5-7.5% Air 4/28/2025 32 1320 Mix Design Chisholm Trail Redi Mix CT6020A 3600 psi 3-5" Slump; 3-6% Air 7/20/2026 32 13 20 Mix Design Chisholm Trail Redi Mix CT5020A With 20% Fly Ash 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 20 Mix Design City Concrete Company 30HA2011 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 20 Mix Design Cow Town Redi Mix 253-W 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 20 Mix Design Cow Town Redi Mix 250 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 1320 Mix Design Cow Town Redi Mix 350 3000 psi 3-5" Slump; 3-6% Air 1/29/2024 32 13 20 Mix Design Estrada Ready Mix R3050AEWR 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 1320 Mix Design Holcim/ Amrize 1261 3000 psi 3-5" Slump; 3-6% Air 9/23/2024 32 13 20 Mix Design Holcim/ Amrize 5177 3000 psi 3-5" Slump; 3-6% Air 5/8/2025 32 13 20 Mix Design Holcim/ Amrize 530WA-T1 3000 psi 3-5" Slump; 3-6% Air 4/7/2023 32 1320 Mix Design Liquid Stone C301D 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 1320 Mix Design Martin Marietta R2136214 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 20 Mix Design Martin Marietta R2136014 3000 psi 3-5" Slump; 3-6% Air 4/1/2023 32 1320 Mix Design Martin Marietta 36Nl4 3000 psi 3-5" Slump; 3-6% Air 6/1/2023 32 13 20 Mix Design Martin Marietta R2136R20 3000 psi 3-5" Slump; 3-6% Air 6/1/2023 32 13 20 Mix Design Martin Marietta R2136N20 3000 psi 3-5" Slump; 3-6% Air 11/2/2022 32 13 20 Mix Design Martin Marietta 41 924 4000 psi 3-5" Slump; 3-6% Air 4/7/2023 32 1320 Mix Design Martin Marietta 36K14 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 1320 Mix Design Martin Marietta R2131314 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 1320 Mix Design Martin Marietta R2132214 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 1320 Mix Design Martin Marietta D9490SC 3000 psi 3-5" Slump; 4.5-7.5% Air 5/9/2025 32 1320 Mix Design Martin Marietta 36R14 3000 psi 3-5" Slump; 3-6% Air 10/4/2023 32 13 20 Mix Design NBR Ready Mix CLS A-YY 3000 psi 3-5" Slump; 3-6% Air 10/4/2023 32 13 20 Mix Design NBR Ready Mix CLS A -NY 3000 psi 3-5" Slump; 3-6% Air 7/10/2023 32 1320 Mix Design Gsburn 30A50MR 3000 psi 3-5" Slump; 3-6% Air 1/18/2023 32 13 20 Mix Design Ra id Redi Mix RRM5020A 3000 psi 3-5" Slump; 3-6% Air 1/24/2023 32 13 20 Mix Design Ra id Redi Mix RRM5525A 3600 psi 3-5" Slump; 3-6% Air 1222/2025 32 1320 Mix Design Ra id Redi Mix 3250AL With 50% Slug 3000 psi 3-5" Slump; 3-6% Air 10/24/2024 32 1320 Mix Design SRM Concrete 30850 With 20% Fly Ash 3000 psi 3-5" Slump; 3-6% Air 10/24/2024 32 1320 Mix Design SRM Concrete 30350 3000 psi 3-5" Slump; 3-6% Air 10/18/2024 32 13 20 Mix Design SRM Concrete 30050 With 20% Fly Ash 3000 psi 3-5" Slump; 3-6% Air 1/9/2026 32 1320 Mix Design SRM Concrete 36822 With 20% Fly Ash 3600 psi 3-5" Slump; 3-6% Air 9/9/2022 32 1320 Mix Design Tarrant Concrete FW5025A 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 1320 Mix Design Tarrant Concrete CP5020A 3000 psi 3-5" Slump; 3-6% Air 10/10/2022 32 13 20 Mix Design Tarrant Concrete TCFW5020A 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 1320 Mix Design Tarrant Concrete FW5525A2 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 1320 Mix Design Titan Reudy Mix 3020AE 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 1320 Mix Design True Grit Redi Mix 0250.230 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 20 Olin Design True Grit Redi Mix 0250.2301 3000 psi 3-5" Slump; 3-6% Air 11/17/2025 32 1320 Mix Design True Grit Redi Mix 450.230 With 30% Slug 3000 psi 3-5" Slump; 3-6% Air Class CIP Inlets Manholes, Junction Boxes, Encasement, Blocking, Collars, (Spread Footing Pedestal Pole Foundations —Reference Detail 34 41 10-D605A 9/9/2022 32 13 13 Mix Design American Concrete Company 40CNF065 4000 psi 3-5" Slump; 0-3% Air 9/9/2022 32 13 13 Mix Design Bumco Texas 40U500BG 4000 psi 3-5" Slump; 3-6% Air 8/21/2025 33 13 13 Mix Design Bumco Texas 36U500BG 1" 20% MRWR AIR (Lighting and Signal Footing Foundation) 3600 psi 3-5" Slump; 3-6% Air 4/8/2026 03 3000 xDesign Design umco Texas 30U500BG 4000 psi 3-5" Slump; 3-6% Air 4/28/2025 34 13 13 xDesign Design hisholm Trail Redi Mix CT6020A 3600 psi 3-5" Slump; 3-6% Air 4/28/2025 35 13 13 Mix Design Chisholm Trail Redi Mix CTFW5520A 3600 psi 3-5" Slump; 3-6% Air 4/28/2025 36 1313 Mix Design Chisholm Trail Redi Mix CTFW6020A 4000 psi 3-5" Slump; 3-6% Air 8/4/2025 37 1313 Mix Design Chisholm Trail Redi Mix CTFW5020A 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 xDesign Design ow Town Redi Mix 2/5-2 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 1313 Mix Design Cow Town Redi Mix 55 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 nDesign Design ow Town Redi Mix 255 3500 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Cow Town Redi Mix 270 5000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Cow Town Redi Mix 370 5000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 1313 Mix Design Cow Town Redi Mix 353 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 nDesign Design ow Town Redi Mix 257 3600 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Cow Town Redi Mix 357 3600 psi 3-5" Slump; 3-6% Air 5/7/2025 32 13 13 nDesign Design ow Town Redi Mix 265-42 4200 psi 3-5" Slump; 3-6% Air 3/3/2026 03 3000 --Design strada Ready Mix R3555AESC 3500 psi 3-5" Slump; 3-6% Air Page 1 of 7 FORT WORTH CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT STANDARD PRODUCTS LIST AS OF 08/01/2026 !!!!!!!! Attention: Mix Designs do not supersede CFW Specifications !!ll!!!!1 1 ... Class CIP Concrete (Continues) 5/26/2026 03 3000 Mix Design Chisholm Trail Redi Mix CT60A 4000 psi 3-5" Slump; 3-6% Air 2/7/2025 32 13 13 Mix Design Holcim/ Amrize 1701 4000 psi 3-5" Slump; 3-6% Air 2/7/2025 32 13 13 Mix Design Holcim/ Amrize 1551 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Holcim/ Amrize 5409 4000 psi 3-5" Slump; 3-6% Air 8/14/2025 321313 Mix Design Holcim/ Amrize 540WA-Tl With 20% Fly Ash and 30% Slag 4000 psi 3-5" Slump; 3-6% Air 4/27/2023 32 13 13 Mix Design Liquid Stone C361DNFA 3600 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Martin Marietta R2141230 4000 psi 3-5" Slump; 3-6% Air 8/4/2023 32 13 13 Mix Design Martin Marietta R2141R24 4000 psi 3-5" Slump; 3-6% Air 1.1/20/2023 32 13 13 Mix Design Martin Marietta R21461833 4000 psi 3-5" Slump; 3-6% Air 11/20/2023 32 13 13 Mix Design Martin Marietta R2146K33 4000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Martin Marietta R2142233 3600 psi 3-5" Slump; 4.5-7.5% Air 9/9/2022 32 13 13 Mix Design Martin Marietta R2136224 3600 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Martin Marietta R2141233 3600 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Martin Marietta R2146038 4500 psi 3-5" Slump; 3-6% Air 10/24/2024 321313 Mix Design Martin Marietta R2146K34 4000 psi 3-5" Slump; 3-6% Air 5/5/2025 32 13 13 Mix Design Martin Marietta R2146R35 4000 psi 3-5" Slump; 3-6% Air 5/5/2025 33 13 13 Mix Design Martin Marietta R2146K35 4000 psi 3-5" Slump; 3-6% Air 5/5/2025 33 13 13 Mix Design Martin Marietta R2146N33 4000 psi 3-5" Slump; 3-6% Air 9/12/2023 321313 Mix Design NBR Read Mix CLS PI-YY 4000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design NBR Ready Mix TX C-YY 3000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design NBR Ready Mix TX C -NY 3000 psi 3-5" Slump; 3-6% Air 4/30/2026 32 13 13 Mix Design NBR Ready Mix CLS C-YY 3600 psi 3-5" Slump; 3-6% Air 4/30/2026 32 13 13 Mix Design NBR Ready Mix CLS C -NY Straight Cement 3600 psi 3-5" Slump; 3-6% Air 1/18/2023 32 13 13 Mix Design n Rapid Redi Mix RRM5320A 3000 psi 3-5" Slump; 3-6% Air 1/18/2023 32 13 13 Mix Design Ra id Redi Mix RRM6020ASS 4000 psi 3-5" Slump; 3-6% Air 10/24/2024 32 13 13 Mix Design SRM Concrete 40350 4000 psi 3-5" Slump; 3-6% Air 10/24/2024 32 13 13 Mix Design SRM Concrete 40850 4000 psi 3-5" Slump; 3-6% Air 9/16/2024 321313 Mix Design SRM Concrete 35050 3500 psi 3-5" Slum; 3-6% Air 4/28/2025 32 13 13 Mix Design SRM Concrete 36850 3600 psi 3-5" Slump; 3-6% Air 11/24/2025 03 3000 Mix Design Sum Concrete 45852 4500 psi 3-5" Slump; 4.5-7.5% Air 2/27/2026 32 13 13 Mix Design SRM Concrete 35850 With 20% Fly Ash 3500 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Tarrant Concrete FW5320A 3000 psi 3-5" Slump; 3-6% Air 10/10/2022 32 13 13 Mix Desi g Tarrant Concrete TCFW6025A2 4000 psi 3-5" Slump; 3-6% Air 2/25/2026 32 13 13 Mix Design True Grit Redi Mix 450.230CIP With 30% Slag 3000 psi 3-5" Slump; 3-6% Air Class C Drilled Shaft for Traffic Signal Pole Foundations Reference Detail 31 41 10-D605 8/21/2025 321313 Mix Design Bumco Texas 40U502BG 120% HRWR AIR 3600 psi 6-8"Slump; 3-6%Air 7/20/2026 32 13 13 Mix Design Chisholm Trail Redi Mix CT6520MR-67 With 4500 psi 5-7" Slump, 0-3% Air 6/21/2023 32 13 13 Mix Design Cow Town Redi Mix 360 -DS 3600 psi 5.5-7.5" Slump; 3-6% Air 3/12/2026 32 13 13 Mix Design Cow Town Redi Mix 360-2DS 3600 psi 5.5-7.5" Slump; 11-3% Air 10/30/2024 32 13 13 Mix Design Estrada Ready Mix R36575AEWR 3600 psi 5.5-7.5" Slump; 3-6% Air 9/11/2025 32 13 13 Mix Design Gonzalez Brothers P6020LA 3600 psi 5.5-7.5" Slump; 3-6% Air 12/5/2022 32 13 13 Mix Design Holcim/ Amrize 1822 3600 psi 5.5-7.5" Slump; 0-3% Air 9/9/2022 32 13 13 Mix Design Holcim/ Amrize 1859 4000 psi 5.5-7.5" Slump; 3-6% Air 1/14/2026 32 13 13 Mix Design City Concrete Company 36LA20H-MR With 20% Fl28% Fly Ash 3600 psi 5.5-7.5" Slump; 3% Air 4/7/2023 32 1313 Mix Design Liquid Stone C361DHR 3600 psi 5.5-7.5" Slump; 3-6% Air 6/27/2023 321313 Mix Design Martin Marietta U2146N41 3600 psi 5-7"Slump; 3-6%Air 6/27/2023 32 13 13 Mix Design Martin Marietta U2146K45 3600 psi 5-7" Slump; 3-6% Air 5/9/2025 32 1313 Mix Design Martin Marietta U2146R41 3600 psi 5-7" Slump; 3-6% Air 8/22/2024 32 13 13 Mix Design NBR Ready Mix 1351(2524 3600 psi 5.5" Slump; 3-6% Air 8/22/2024 32 13 13 Mix Design NBR Ready Mix. 135KO524 3600 psi 5.5" Slump; 3-6% Air 5/6/2026 32 13 13 Mix Design SRM Concrete 40351 4000 PSI STRT COMMERCIAL SP AIR 4000 psi 5.5-7.5" Slump; 3-6% Air Class C eadwalls, Wing walls, Culverts) 4/8/2026 03 3000 Mix Design Borneo Texas 36U500BC With 20% Fly Ash 3600 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Carder Concrete FWCC602001 4000 psi 3-5" Slump; 3-6% Air 2/24/2026 03 3000 Mix Design Chisholm Trail Redi Mix CT7020A With 20% Fly Ash 5000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design CilyConcrete Company 40LA201 I 4000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Cow Town Redi Mix 260-2 3600 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Cow Town Redi Mix 360-1 3600 psi 3-5" Slump; 3-6% Air 9/9/2022 32 1313 Mix Design Cow Town Redi Mix 260-1 3600 psi 3-5" Slump; 3-6% Air 8/11/2025 32 13 13 Mix Design Cow Town Redi Mix 275 With 20% Fly Ash 5000 psi 4-6" Slump; 3-6% Air 8/11/2025 32 13 13 Mix Design Cow Town Redi Mix 375 5000 psi 4-6" Slump: 3-6% Ar 1/29/2024 32 13 13 Mix Design Estrada Ready Mix R3655AEWR 3600 psi 3-5" Slump; 3-6% Air 9/9/2022 32 1313 Mix Design GCH Concrete Services GCH4000 4000 psi 3-5" Slump; 3-6% Air 4/12023 32 13 13 Mix Design Martin Marietta 310LBP 3600 psi 3-5" Slump; 4-7% Air 8/30/2023 32 13 13 Mix Design Martin Marietta R2141R30 4000 Psi 3-5" Slump; 3-6% Air Page 2 of 7 FORT WORTH. CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT STANDARD PRODUCTS LIST AS OF 08/01/2026 !1!!!!!! Attention: Mix Desiens do not supersede CFW Snecifeotions !!!!!!!!!! 1' Class C Concrete continues 9/9/2022 32 13 13 Mix Design Martin Marietta R2146035 4000 psi 3-5" Slump; 3-6% Air 3/10/2026 03 30 00 Mix Design NBR Ready Mix TX-C-YY 3600 psi 3-5" Slump: 3-6% Air /I0/2026 03 3000 Mix Design NBR Ready Mix TX -C -NY 3600 psi 3-5" Slump: 3-6% Air 9/9/2022 32 13 13 Mix Design SRM Concrete 40050 4000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design SRM Concrete 35022 With 20% Fl Ash 3600 psi 3-5" Slump; 3-6% Air 3/6/2026 03 30 00 Mix Design SRM Concrete 45350 4500 psi 3-5" Slump; 3-6% Air 5/26/2026 03 3000 Mix Design SRM Concrete 36322 3600 PSI NCTCOG STRT CLASS C 3600 psi 3-5" Slump; 3-6% Air 6/15/2026 03 3000 Mix Design SRM Concrete 36822 With 20% Fly Ash 3600 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Tarrant Concrete FW6020A2 4000 psi 3-5" Slump; 3-6% Air 2/26/2026 03 3000 Mix Design True Grit Redi Mix 455.230C With 30% Slog 3600 psi 3-5" Slump; 3-6%% Au Class P (Machine Placed Pavinu) 6/4/2026 32 13 13 Mix Design Amrize/ Hocim 540LWA-Tl With 20% Slag 4000 psi 1-3" Slump: 3-6% Air 4/3/2025 32 13 13 Mix Design Bi g Town Concrete 45!! 3600 psi 1-3" Slump; 3-6% Air 4/3/2025 32 13 13 Mix Design Bi Town Concrete 4411 3600 psi 1-3" Slump; 3-6% Air 6/30/2025 321313 Mix Design Big Town Concrete 5211 With 20% Fly Ash 4000 psi I-3" Slum; 3-6%, Au 1-3" Sit 6/30/2025 30 13 13 asDesign Design Town Concrete 5311 4000 psi 1-3" Slump; 3-6% Air 9/30/2025 30 13 13 nsDesign Design umco Texas 40U553BG 1"20% MRWR AIR 4000 psi 1-3" Slump; 3-6% Air 9/9/2022 321313 Mix Design Carder Concrete FWCC552091 3600 psi 1-3"Slump; 3-6%Air 9/9/2022 32 13 13 Mix Design Carder Concrete FWCC602091 4000 psi 1-3" Slump; 3-6% Air 11/6/2025 32 13 13 Mix Design Chisholm Trail Redi Mix CT5520AMP With 20% Fly Ash 3600 psi 1-3" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Ci Concrete Company 36LA2011 3600 psi 1-3" Slump; 3-6% Air 9/9/2022 33 13 13 Mix Design Cow Town Redi Mix 257-M 3600 psi 1-3" Slump; 3-6% Air 11/14/2022 32 13 13 Mix Design Cow Town Redi Mix 357-M 3600 psi 1-3" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Cow Town Redi Mix 260-M 4000 psi 1-3" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design ow Town Redi Mix 360-M 4000 psi 1-3" Slump; 3-6% Air 2/6/2024 32 13 13 Mix Design Estrada Ready Mix TD3655AEWR 3600 psi 1-3" Slump; 3-6% Air 5/12/2025 32 13 13 Mix Desi g Holcim/ Antrize 1703 4000 psi 1-3" Slump; 3-6% Air 10/3/2025 32 13 13 Mix Design Holcim/ Amrize 5405 With 20%Fl FlyAsh 4000 psi 1-3" Slump; 3-6% Air 8/4/2023 32 13 13 Mix Design Martin Marietta/ Quilcrete Q214IR27 4000 psi 1-3" Slump; 3-6% Air 11/2/2022 32 13 13 Mix Design Martin Marietta/ Quilrete Q214IK30 4000 psi 1-3" Slump; 3-6% Air 5/5/2025 32 13 13 Mix Design Martin Marietta/ Quikrete Q214IN27 4000 psi 1-3" Slump; 3-6% Air 1/23/2026 32 13 13 Mix Design Martin Marietta/ Quikrete Q2146K33 4000 psi 1-3" Slump: 3-6% Air 7/30/2026 32 13 13 Mix Design Martin Marietta/ . ete - 2146833 4000 psi 1-3" Slump: 3-6% Air 10/4/2023 32 13 13 Mix Design NBR Ready Mix TX C SF-YY 3600 psi 1-3" Slump; 3-6% Air 10/4/2023 32 13 13 Mix Design NBR Ready Mix TX C SF -NY 3600 psi 1-3" Slump; 3-6% Air 12/22/2025 32 13 13 Mix Design Rapid Redi Mix 4050AL With 50% Slag 4000 psi 1-3" Slump; 3-6% Air 10/24/2024 32 13 13 Mix Design SRM Concrete 40068 4000 psi 1-3" Slump; 3-6% Air 10/24/2024 32 13 13 Mix Design SRM Concrete 40825 4000 psi 1-3" Slump; 3-6% Air 9/16/2024 32 13 13 Mix Design SRM Concrete 40025 With 20% F1' Ash 4000 psi 1-3" Slump; 3-6% Air 10/18/2024 32 13 13 Mix Design SRM Concrete 35023 3600 psi I-3" Slump; 3-6% Air 6/5/2025 32 13 13 Mix Design SRM Concrete 40324 4000 psi 1-3" Slump; 3-6% Air 7/212025 1313 Mix Design SINACOLA 24011-4000MP 20% With 20% Fl Ash 4000 psi 1-3" Slump; 3-6% Air 7/21/2025 32 13 13 Mix Design SWACOLA 24011-4000MP Straight Cement 4000 psi 1-3"Slump; 3-6% Air 2/3/2026 32 13 13 Mix Design Sunrise Redi Mix 1451 4000 psi I-3" Slump: 3-6% Air 9/9/2022 32 13 13 Mix Design Tarrant Concrete FW5520AMP 3600 psi I-3" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design True Grit Redi Mix 0255.2301 3600 psi 1-3" Slump; 3.5-6.5% Air 9/9/2022 32 13 13 Mix Design True Grit Redi Mix 0260.2302 4000 psi 1-3"Slump; 3.5-6.5% Air 6/17/2025 32 13 13 Mix Design Tme Grit Redi Mix 460.230M 4000 psi 1-3" Slump; 3-6% Air 623/2025 32 13 13 Mix Design Tme Grit Redi Mix 360.230M 4000 psi 1-3" Slump; 3-6% Air 1/2/1900 32 13 13 Mix Design Tme Grit Redi Mix 455.230M With 30% Slag 3600 psi 1-3" Stump; 3-6% Air Class H (Hand Placed Paving, Vallev Gutter) 9/9/2022 32 13 13 Mix Design American Concrete Company 45CAF076 4500 psi 3-5" Slump; 3-6% Air 5/2/2023 32 13 13 Mix Design Big D Concrete CMI4520AE 4500 psi 3-5" Slump; 3-6% Air 4/3/2025 32 13 13 Mix Design Big Town Concrete 6211 4500 psi 3-5" Slump; 3-6% Air 4/3/2025 32 13 13 Mix Design Big Town Concrete 6311 4500 psi 3-5" Stump; 3-6% Air 4/5/2025 32 13 13 Mix Design Big Town Concrete 6017 4500 psi 3-5" Slump; 3-6% Air 7/16/2025 32 13 13 Mix Design Big Town Concrete 62113 With 30% Slag 4500 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Burnco Texas 45U500BG 4500 psi 3-5" Slump; 3-6% Air 9/302025 33 13 13 Mix Design Bumco Texas 45U100AG 4000 psi 3-5" Stump; 3-6% Air 9/9/2022 32 13 13 Mix Design Carder Concrete FWCC602021 4500 psi 3-5" Slump; 3-6% Air 4/28/2025 32 13 13 Mix Design Chisholm Trail Redi Mix CTFW6520A 4500 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design City Concrete Company 45NA20B 4500 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Cow Town Redi Mix 265 4500 psi 3-5" Stump; 3-6% Air 9/92022 32 13 13 Mix Design Cow Town Redi Mix 365 4500 psi 3-5" Slump; 3-6% Air 1/29/2024 32 13 13 Mix Design Estrada Ready Mix R4560AEWR/ 4500 psi 3-5" Slump; 4-6% Air 9/9/2022 32 13 13 Mix Design GCH Concrete Services GCH4500 4500 psi 3-5" Slump; 3-6% Air 10/4/2024 32 13 13 Mix Design Holcim/ Amrize 5507 4500 psi 3-5" Slump; 3-6% Air Page 3 of 7 FORT WORTH. CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT STANDARD PRODUCTS LIST AS OF 08/01/2026 !!!!!!!! Attention: Mix Desiens do not supersede CFW Specifications 111!!!!!!! 11511. 1' Class H Concrete continues 9/9/2022 321313 Mix Design Holcim/Amrize 1851 4500 psi 3-5"Slump; 3-6% Air 5/8/2025 32 13 13 Mix Design Amrize/ Hocim 545WA-Tl 4500 psi 3-5" Slump; 3-6% Air 4/5/2025 32 13 13 Mix Design Liquid Stone C451D 4500 psi 3-5" Slump; 3-6% Air 11/2/2022 32 13 13 Mix Design Martin Marietta R2146N35 4500 psi 3-5" Slump; 3-6% Air 8/4/2023 32 13 13 Mix Design Martin Marietta R2146R36 4500 psi 3-5" Slump; 3-6% Air 11/2/2022 32 13 13 Mix Design Martin Marietta R2146N36 4500 psi 3-5" Slump; 3-6% Air 5/22/2023 32 13 13 Mix Design Martin Marietta R2146K37 4500 psi 3-5" Slump; 3-6% Air 12/22/2023 321313 Mix Design Martin Marietta R2146R44 4500 psi 3-5"Slump; : 3-6% Air 12/22/2023 32 1313 Mix Design Martin Marietta R2146K44 4500 psi 3-5" Slump; 3-6% Air 11/15/2022 32 1313 Mix Design Martin Marietta R2146P36 4500 psi 3-5" Slump; 3-6% Air 11/152022 32 13 13 Mix Design Martin Marietta R2146K36 4500 psi 3-5" Slump; 3-6% Air 9/9/2022 321313 Mix Design Martin Marietta R2147241 4500 psi 3-5"Slump; 4.5-7.5% Air 9/9/2022 321313 Mix Design Martin Marietta R2146236 4500 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Martin Marietta R2146036 4500 psi 3-5" Slump; 3-6% Air 9/92022 32 13 13 Mix Design Martin Marietta R2146242 4500 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Martin Marietta R2146042 4500 psi 3-5" Slump; 3-6% Air 6/3/2025 32 13 13 Mix Design Martin Marietta R2146K43 4500 psi 3-5" Slump; ; 3-6% Air 1/29/2026 32 13 13 Mix Design Martin Marietta R2146R43 4500 psi 3-5" Slump; 3-6% Air 10/4/2023 32 13 13 Mix Design NBR Ready Mix CLS P2-YY 4500 psi 3-5" Slump; 3-6% Air 10/4/2023. 32 13 13 Mix Design NBR Ready Mix CLS P2 -NY 4500 psi 3-5" Slump; 3-6% Air 7/10/2023 321313 Mix Design Osborn 45A60MR 4500 psi 3-5" Slump; 3-6% Air 1/24/2023 32 13 13 Mix Design Raid Redi Mix RRM6320AHP 4500 psi 3-5" Slump; 3-6% Air 12/22/2025 32 13 13 Mix Design Ra id Redi Mix 4550AL With 50% Slag 4500 psi 3-5" Slump; 3-6% Air 10/24/2024 32 13 13 Mix Design SRM Concrete 45350 4500 psi 3-5" Slump; 3-6% Air 10/24/2024 32 13 13 Mix Design SRM Concrete 45850 With 20% Fly Ash 4500 psi 3-5" Slump; 3-6% Air 10/18/2024 321313 Mix Design SRM Concrete 45050 4500 psi 3-5" Slum; 3-6% Air 7/21/2025 321313 Mix Design SINACOLA 24011-4500HP 20% With 20% FlAsh 4500 psi 3-5"Slump; 3-6%Air 7/21/2025 32 13 13 Mix Design SINACOLA 24011-4500BP Straight Cement 4500 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Tarrant Concrete FW6020AHP 4500 psi 3-5" Slump; 3-6% Air 9/9/2022 321313 Mix Design Tarrant Concrete FW60ABP 4500 psi 3-5"Slump; 3-6%Air 9/9/2022 32 13 13 Mix Design Tarrant Concrete TCFW6020AHP 4500 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Titan Ready Mix TRC4520 4500 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design True Grit Redi Mix 0260.2301 4500 psi 3-5" Stump; 3-6% Air 9/9/2022 32 1313 Mix Design n True Grit Redi Mix 0265.2301 4500 psi 3-5" Slump; 3.5-6.5% Air 9/9/2022 32 13 13 Mix Design True Grit Redi Mix 270.230 4500 psi 3-5" Slump; 3-6% Air 6/12/2025 32 13 13 Mix Design True Grit Redi Mix 465.23014 With 30% Slag 4500 psi 3-5" Slump: 3-6% Air 6/23/2025 32 13 13 Mix Design True Grit Redi Mix 365.230H 4500 psi 3-5" Stump: 3-6% Air 10/9/2024 32 13 13 Mix Design Wildcatter 4520AI 4500 psi 3-5" Slump; 3-6% Air Class HES High Farly Strength Paving) 9/9/2022 32 13 13 Max Design Bi D Concrete 14500AE 4500 psi 3-5"Slump; 3%,Air 12/10/2025 32 13 13 Mix Design Bumco Texas 70UI00AG I day average comp strength >4000 psi 7000 psi 3-5" Slump; 3-6% Air 11/18/2025 32 13 13 Mix Design Chisholm Trail Redi Mix CTTX70AHES 2600 @24 hex and/or 3000 @72hrs;4500@28 days 3-5" Slump; 3-6% Air 2/24/2026 32 13 13 Max Design Chisholm Tmil Redi Mix CT75AHES 3000 psi @ 24 hours and 5000 psi @ 28 days 3-5" Slump; 3-6% Air 5/26/2026 32 13 13 Max Design Chisholm Trail. Redi Mix CT65A 4500 psi @ 24 hours 3-5"Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Cow Town Redi Mix 370-INC 4500 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Cow Town Redi Mix 375 -NC 5000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Cow Town Redi Mix 370 -NC 4500 psi -5" Slump; 3-6% Air 1/18/2023 32 13 13 Max Design Cow Town Redi Mix 380 -NC 4500 psi 3-5"Slump; 3-6% Air 1/29/2024 32 13 13 Mix Design Estrada Ready Mix 4575AESC 4500 psi / 3000 psi @3 days 3-5" Slump; 3-6% Air 9/9/2022 321313 Mix Design Holcim/Amrize 2125 5000 psi 3-5"Slump; 3-6%Air 1/24/2023 32 13 13 Mix Design Liquid Stone C451DHR-A 4500 psi 3-5" Slump; 3-6% Air 4/7/2023 32 13 13 Mix Design Martin Marietta R2161K70 6000 psi / 3000 psi @ 24hrs. -5" Slump; 3-6% Air 6/17/2026 32 13 13 Mix Design SINACOLA Class HES 3200psi 24hrs With l0% Fly Ash 3200psi 24hrs 1-5" Slump; 3-6% Air 2/10/2023 32 13 13 Mix Design SRM Concrete 50310 5000 psi 3-5" Stump; 3-6% Air 2/7/2025 32 13 13 Mix Design SRM Concrete 40326 4500 psi / 3000 psi @3 days 3-5" Slump; 3-6% Air 2/3/2026 32 13 13 Mix Design Sunrise Redi Mix 1477 3 day average comp strength>3000 psi 5500 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Tarrant Concrete FW6520AMR 4500 psi / 3000 psi @3 days 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Tarrant Concrete FW7520AMR 4500 psi / 3000 psi @3 days 3-5" Stump; 3-6% Air 3/30/2026 32 13 13 Mix Design True Grit Redi Mix 370.230HES 4500 psi / 3000 psi @24 hex 3-5" Slump; 3-6% Air Class S (Bridt?e Slabs. Ton Slabs of Direct Traffic Culverts. ADnroach Slabs) 2/24/2026 03 3000 Mix Design Chisholm Trail Redi Mix CT7020A With 20% FlyAsh 5000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Cow Town Redi Mix 260 4000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Cow Town Redi Mix 360 4000 psi 3-5" Slump; 3-6% Air 9/9/2022 32 13 13 Mix Design Cow Town Redi Mix 365-STX 4000 psi 3-5" Slump; 3-6% Air 7/28/2026 32 13 13 Mix Design Cow Town Redi Mix 273 With 20% Fly Ash 5000 psi 3-5" Slump; 3-6% Air 1/29/2024 32 13 13 Mix Design Estrada Ready Mix R4060AEWR 4000 psi 4-6" Slump; 3-6% Air 5/3/2023 32 13 13 Mix Design Martin Marietta M7842344 4000 psi 3-5" Slump; 4.5-7.5% Air 4/1/2023 32 13 13 Mix Design Martin Marietta R2146P33 4000 psi 3-5" Stump; 3-6% Air Page 4 of 7 FORT WORTH- CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT STANDARD PRODUCTS LIST AS OF 08/01/2026 !!!!!!!! Attention: Mix Desiens do not sunersede CFW Snecifications !!!!!!!!!! Class S Concrete continues 8/18/2025 32 13 13 Mix Design Martin Marietta 61 OLBT 4000 psi 3-5" Slump; 3-6% Air 4/15/2024 32 13 13 Mix Design NBR Ready Mix TX S -NY 4000 psi 3-5" Slump; 3-6% Air 4/15/2024 32 13 13 Mix Design NBR Ready Mix TX S-YY 4000 psi 3-5" Slump; 3-6% Air 4/5/2025 32 13 13 Mix Design SRM Concrete 40850 With 20% Fly Ash 4000 psi 3-5" Slump; 3-6% Air 4/5/20?5 32 13 13 Mix Design SRM Concrete 40350 4000 psi 3-5" Slump; 3-6% Air 3/6/2026 03 3000 Mix Design SRM Concrete 45350 4500 psi 3-5" Slump; 3-6% Air 5/5/20?3 32 13 13 Mix Design SRM Concrete D100008553CB 4000 psi 3-5" Slump; 3-6% Air /8/2026 03 30 00 Mix Design True Grit Redi Mix 460.230S 35% Slag, AEA, Class S Concrete 4000 psi 3-5" Stump; 3-6% Air Concrete Base Trench Repair 4/1/2023 0334 16 Mix Design Borneo Texas IOYH50BF 1000 psi Flowable; 8.5-11.5% Air 9/9/2022 03 34 16 Mix Design Burnco Texas 08Y450BA 800 psi 5-7" Slump; 3-6% Air 12/19/2025 0334 16 Mix Design Cow Town Redi Mix 330-58 750 psi 5.5-8.5" Slump; 5-15% 9/30/2025 0334 16 Mix Design Martin Marietta YN81O001 750 psi 8-12" Slump; 5-10% Air 12/26/2025 03 34 16 Mix Design SRM Concrete 915 750 psi Flowable; 3-6% Air Controlled Low Strength Material (Flowable Fill) 2/7/2025 03 3413 Mix Design Bunten Texas OIY69OBF 100 psi Flowable; 9.5-11.5% Air 5/19/2025 033413 Mix Design Bunten Texas OIZ180AF 100 psi Flowable; 9.5-11.5% Air 11/18/2025 033413 Mix Design Bumco Texas OIZ401BF SAND 25% MRWR 17% AIR FLOW FILL 100 psi Flowable; 174-/-l.5% air 9/9/2022 03 3413 Mix Design Carder Concrete FWCC359101 50-150 psi 3-5" Slump; 8-12% Air 9/9/2022 03 3413 Mix Design Carder Concrete FWFF237501 50-150 psi Flowable; 8.5-11.5% Air 8/4/2025 03 34 13 Mix Design Chisholm Trail Redi Mix CT150FF 50-150 psi Flowable; 7-9.0% Air 12/26/2025 03 3413 Mix Design Chisholm Trail Redi Mix CTFWCLSM 100-150 psi 5-7" slump; 8.5-11.5% Air 9/9/2022 3413 Mix Design Cilv Concrete Company 11-350-FF 50-150 psi Flowable; 8-12% Air 9/9/2022 03 3413 Mix Design Cow Town Redi Mix 9 70 psi 7-9" Slump; 8-11% Air 4/30/2026 03 3413 Mix Design Cow Town Redi Mix 9-S Flowable fill/ Straight Cement 70 psi 6-12" Slump; 5-15% Air 9/9/2025 03 3413 Mix Design Cow Town Redi Mix I 0 Min 50 psi Min 9" Slump; 10-20% Air 5/12/2025 033413 Mix Design Holcim/ Amrize 3741 100 psi Flowable; 12.0-24.0% Air 8/4/2025 03 34 13 Mix Design Holcim/ Antrize 901 100 psi 9-11" Slump; 10-30% Air 8/14/2025 03 34 13 Mix Design Holcim/ Amrize 904 150 psi 9-11" Slump; 10-30% Air 2/27/2026 03 34 13 Mix Design Holcim/ Amrize 3747 150 psi Flowable; 12.0-24.0% Air 9/11/2025 033413 Mix Design Martin Marietta FLOW25A 150 psi 8"-12" Slum; 10% Air 10/4/2023 03 34 13 Mix Design NBR Ready Mix FTW FLOW FILL 150 psi 7-10" Slump; 8-12% Air /30/2026 03 3413 Mix Design NBR Ready Mix FO000022 150 psi 8.5-12" Slump; 10%-20% Air 2/7/2025 03 34 13 Mix Design SRM Concrete 910 150 psi Flowable; 8-12% Air 12/26/2025 3413 Mix Design SRM Concrete 900 100 psi Flowable; 10-30% Air 9/9/2022 033413 Mix Design Tarrant Concrete FWFF150CLSM 50-150 psi Flowable; 8-12% Air 4/8/2026 03 34 13 Mix Design True Grit Redi Mix FF420.230CS CISM Flowable Fill, 100% Concrete Sand 150 psi Flowable; 8-12% Air 4/8/2026 03 34 13 Mix Design True Grit Redi Mix FF420.230MS CLSM Flowable Fill, 100% Manufactured Sand 150 psi Flowable; 8-12% Air Concrete Rip Rap 4/1/2023 31 3700 Mix Design Martin Marietta R2141030 4000 psi 3-5" Slump; 3-6%Air 4/1/2023 31 3700 Mix Design Martin Marietta R2146033 4000 psi 3-5" Slump; 3-6% Air 7/29/2026 31 3700 Mix Design SRM Concrete 20900 2000 psi 7 -IS" Stomp; 0-4.5% Air Cement- Stabilized Sand (CSS) 11/21/2025 330510 Mix Design Burnco Texas 04Z500BA SAND 20% MRWR 17% AIR FLOW FILL 250 psi Flowable; 15.5-18.5% Air 7/7/2026 33 05 10 Mix Design ARCOSA 010 6% Cement with Ave 108 psi @7 days 165 psi Grout 4/24/2026 Mix Design Bumco Texas FMG75 Pipe Collars Grout 3000 psi 7"-10" Slump; 2.0% Air 5/26/2026 Mix Design Cow Town Redi Mix O8 Grout for Stone Ripmp 3000 psi 5"-1 t" slump 6/17/2026 Mix Design SRM Concrete 30900 Fine Grout 3000 psi 7-10" Slump; 0-4.5%Air Cellular Grout 4/22/2026 33 05 10 Mix Design SRM Concrete CC0090CG Cellular Grout 300 psi Flowable; >50% Air 7/23/2026 33 05 10 Mix Design Superior 965-55-500 With SRM grout mix of 5000 psi @28 dus 500 psi Flowable As halt Pavin 9/9/2022 32 12 16 Mix Design Austin Asphalt FT5BI17965 FT5B117965 PG64-22 Type B Fine Base 9/9/2022 321216 Mix Design Austin Asphalt FTIBI39965 FTIBI39965 PG64-22 Type B Fine Base 9/9/2022 32 12 16 Mix Design Austin Asphalt FTIB117.2 FTIB117.2 PG64-22 Type B Fine Base 5/1/2024 32 12 16 Mix Design "ynolds Asphalt 340 -DG -B P 340 -DO -B PG64-22 Type B Base Course 9/9/2022 32 12 16 Mix Design Reynolds Asphalt 1112B 1112B PG64-22 Type B Fine Base 9/9/2022 32 12 16 Mix Design Reynolds Asphalt 1612B 1612B PG64-22 Type B Fine Base 4/4/2025 32 12 16 Mix Design Reynolds Asphalt 2315B 2315B PG64-22 Type B Fine Base 4/13/2026 32 12 16 Mix Design Reynolds Asphalt 2409B 3076_DG-B_SAC B P064-22_RAP 19.8% RAP/Binder 4/13/2026 321216 Mix Design Reynolds Asphalt 2525D 341_DG-D_PG70-22 Virgin 0% RAP 12/5/2022 33 12 16 Mix Design Sunntount Paving 3076BV6422 3076BV6422 PG62-22 Type B Fine Base 9/9/2022 32 12 16 Mix Design Sunmount Paving 341-BRAP6422ERG 341-BRAP6422ERG PG64-22 Type B Fine Base 5/7/2026 32 12 16 Mix Design Texas Materials 202DI 031500 SP -D SAC B 70-22 R (2-215122-25) — 344 -SP -D 14.2% RAP/ Binder 9/9/2022 32 12 16 Mix Design TXBIT 37-211305-20 37-211305-20 PG64-22 Type B Fine Base 9/9/2022 32 12 16 Mix Design TXBIT 44-211305-17 44-211305-17 PG64-22 Type B Fine Base 9/9/2022 32 12 16 Mix Design TXBIT 211305 (1757) 211305 (1757) PG64-22 Type B Fine Base 9/9/2022 32 12 16 Mix Design TXBIT 64-224125-1S PG 64-224125-18 PG70-22 Type D Fine Surface /1/2024 32 12 16 Mix Design TXBIT 344 MAC -SP -D 70-22XR 344 MAC -SP -D 70-22XR SAC A -R Type D Fine Surface 5/7/2026 32 12 16 Mix Design TXBIT 202D2031500 SP -D SAC A 70-22 R (1-215120-25) SS -3077 -SP -D 13.8% RAP/Binder Page 5 of 7 FORT WORTH. CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT _- STANDARD PRODUCTS LIST AS OF 08/01/2026 !! Attention: Mix Desiens do not supersede CFW Snecificatinns !!!!!!!!!! 1 Detectable Warning Surface 9/9/2022 32 13 20 DWS - Pavers Pine Hall Brick (Winston Salem, NC) Tactile Pavers 9/9/2022 32 13 20 DWS - Pavers Western Brick Co. (Houston, TX) Detectable Warning Pavers 9/9/2022 32 13 20 DWS - Composite Armor Tile 9/9/2022 32 13 20 DWS - Composite ADA Solutions (Wilmington, MA) Heritage e Brick CIP Composite Paver 4/7/2023 32 13 20 DWS - Pavers ADA Solutions (Wilmington, MA) Detectable Warning Pavers 10/16/2025 32 13 20 DWS - Pavers EQUALTILE E t ualTile Brick Pattern Wet -Set Replaceable 10/16/2025 32 13 20 DWS - Pavers EQUALTILE E ualTile Cast -In -Place Replaceable 4/13/2026 32 13 20 DWS Tuffile Inc Polymer Surface applied detectable warning s 4/13/2026 32 13 20 DWS Tuffile Inc Galvanized steel Surface applied detectable warnings 4/13/2026 32 13 20 DWS TutTile Inc Polymer wet set detectable warnings for cast in place 4/13/2026 32 13 20 DWS TutTile Inc Galvanized steel wet set detectable warnings for cast in place 4/13/2026 32 13 20 DWS Tuffile Inc Cast iron wet set detectable warnings for cast in place Silicone .joint Sealant 9/9/2022 32 13 73 Joint Sealant Dow 890SL 890SL - Cold Applied, Single Component, Silicone Joint Sealant ASTM D5893 9/9/2022 32 13 73 Joint Sealant Tremco 900SL 900SL - Cold Applied, Single Component, Silicone Joint Sealant ASTM D5893 9/9/2022 32 13 73 Joint Sealant Pecora 300SL 300SL - Cold Applied, Single Component. Silicone Joint Sealant ASTM D5893 9/9/2022 32 13 73 Joint Sealant Crafco RoadSaver Silicone RoadSaver Silicone - Cold Applied, Single Component, Silicone Joint Sealant ASTM D5893 Utility Trench Embedment Sand 9/9/2022 33 05 10 Embedment Sand Silver Creek Materials Utility Embedment Sand ASTM C33 9/9/2022 33 05 10 Embedment Sand Crouch Materials Utility Embedment Sand ASTM C33 9/9/2022 33 05 10 Embedment Sand F and L Dirt Movers Utility Embedment Sand ASTM C33 9/9/2022 33 05 10 Embedment Sand F and L Dirt Movers Utility Embedment Sand ASTM C33 9/9/2022 33 05 10 Embedment Sand Tin Top Martin Marietta Utility Embedment Sand ASTM C33 Storm Sewer - Manholes & Races/Frames & Covers/Standard (Rmmd) 33-05-13 9/28/2018. 33 05 13 Manholc Frames and Covers AccuCast (Govind Steel Company, LTD) MHRC #220605 MHRC #220605 Size - **24" Dia.) ASTM A48 AASHTO M306 9/28/2018 33 05 13 Manhole Cover Neenah Foundry NF -1274-T91 NF -1274-T91 (Size - 32" Dia.) ASTM A48 AASHTO M306 9/28/2018 33 05 13 Manhole Frames and Covers Neenah Foundry NF -1743 -LM (Hinged) NF -1743 -LM (Hinged) (Size - 32" Dia.) ASTM A48 AASHTO M306 9/28/2018 33 0513 Manhole Frame Neenah Foundry NF -1930-30 NF -1930-30 (Size - 32.25" Dia.) ASTM A48 AASHTO M306 9/28/2018 33 05 13 Manhole Frames and Covers Neenah Foundry R -1743-13V R-1743-HV (Size - 32" Dia.) ASTM A48 AASHTO M306 2/13/2026 33 05 13 Round Manhole lid and frame Neenah Foundry Pan number 101560 and 12940110 Size- 24" Dia clear opening AASHTO M306 H-20 4/3/2019 33 05 13 Manhole Frames and Covers SIP Industries ++ 2279ST 2279ST (Size - 24" Dia.) ASTM A48 AASHTO M306 4/3/2019 33 05 13 Manhole Frames and Covers IS Industries -H- 2280ST 2280ST (Size - 32" Dia.) ASTM A48 AASHTO M306 10/8/2020 33 05 13 Manhole Frames and Covers EJ ( Formally East Jordan Iron Works) EA033 Z2/A NJ 1033 Z2/A (Size - 32.25" Dia.) ASTM A536 AASHTO M306 3/8/2024 33 05 13 Curb Inlet Covers SIP Industries ++ 2296T 2296T (Size - ***24" Dia.) ASTM A48 AASHTO M306 6/18/2024 33 0513 Curb Inlet Covers SIP Industries ++ 2279STN 2279STN (Size - 24" Dia.) ASTM A48 AASHTO M306 **Note: All new development and new installation manhole lids shall meet the minimum 30 -inch opening requirement as specified in City Specification 33 0513. Any smaller opening sizes will only be allowed fu r existing manholes that require replacement frames and covers Storm Sewer - Inlet & Structures 33-05-13 10/8/2020 33 4920 Curb inlets Footman FRT-10x3-405-PRECAST** Size - 10' X 3' ASTM C913 10/8/2020 33 4920 Curb Inlets Farterra FRT-10x3-406-PRECAST** (Size - 10' X 3') ASTM C913 10/8/2020 33 4920 Curb Inlets Forterra FRT-10x4.5-407-PRECAST** Size - 10' X 4.5') ASTM C913 10/8/2020 33 4920 Curb Inlets Forterra FRT-10x4.5-420-PRECAST** (Size - 10' X 4.5') ASTM C913. 10/8/2020 33 39 20 Manhole Forterra FRT-4X4-409-PRECAST-TOP (Size - 4' X 4') ASTM C913 10/8/2020 33 3920 Manhole Forterra FRT-4X4-409-PRECAST-BASE (Size - 4' X 4') ASTM C913 10/8/2020 33 3920 Manhole Forterra FRT-5X5-410-PRECAST-TOP Size - 5' X 5' ASTM C913 10/8/2020 33 3920 Manhole Forterra FRT-5X5-41 0 -PRECAST -BASE Size - 5' X 5') ASTM C913. 10/8/2020 33 3920 Manhole Forterra FRT-6X6-41 1 -PRECAST -TOP (Size - 6' X 6') ASTM C913 10/8/2020 33 3920 Manhole Forterra FRT-6X6-41 1 -PRECAST -BASE (Size - 6' X 6') ASTM C913 3/19/2021 33 4920 Curb Inlets Thompson Pipe Group TPG-IOX3-405-PRECAST INLET'* (Size - 10' X 3') ASTM 615 3/19/2021 33 4920 Curb Inlets Thompson Pipe Group TPG-15X3-405-PRECAST INLET** (Size - 15' X 3) ASTM 615 3/19/2021 33 4920 Curb Inlets Thompson Pipe Group TPG-20X3-405-PRECAST INLET** (Size - 20' X 7') ASTM 615 3/ 19/2021 33 3920 Manhole Thompson Pipe Group TPG-4X4-409-PRECAST TOP (Size - 4' X 4') ASTM 615 3/19/2021 33 3920 Manhole Thompson Pipe Group TPG-4X4-409-PRECAST BASE (Size - 4' X 4') ASTM 615 3/19/2021 33 3920 Manhole Thompson Pipe Group TPG-4X4-412-PRECAST 4 -FT RISER (Size - 4' X 4') ASTM 615 3/19/2021 33 3920 Manhole Thompson Pipe Group TPG-5X5-410-PRECAST TOP (Size - 5' X 5') ASTM 615 3/ 19/2021 33 3920 Manhole Thompson Pipe Group TPG-5X5-410-PRECAST BASE (Size - 5' X 5') ASTM 615 3/ 19/2021 33 3920 Manhole Thompson Pipe Group TPG-5X5-412-PRECAST 5 -FT RISER (Sire -S 5 X 5') ASTM 615 3/19/2021 33 3920 Manhole Thompson Pipe Group TPG-6X6-411-PRECAST TOP (Size - 6'X 6') ASTM 615 3/19/2021 33 3920 Manhole Thompson Pipe Group TPG-6X6-4I 1 -PRECAST BASE (Size - 6' X 6') ASTM 615 3/19/2021 33 3920 Manhole Thompson Pipe Group TPG-6X6-412-PRECAST 6 -FT RISER (Si- - 6' X 6') ASTM 615 Page 6 of 7 FORT WORTH. CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT STANDARD PRODUCTS LIST AS OF 08/01/2026 !1!!!!!! Attention: Mix Desiens do not supersede CFW Snecifleations !!!!!!!!!! 1 Starrrr Surer... 3/19/2021. 33 3920 Manhole Thompson Pipe Group TPG-7X7-411-PRECAST TOP (Size - 7' X 7') ASTM 615 3/19/2021 33 3920 Manhole Thompson Pipe Group TPG-7X7-411-PRECAST BASE (Size -7' X 7') ASTM 615 /19/2021 33 3920 Manhole Thompson Pipe Group TPG-7X7-412-PRECAST 4 -FT RISER (Size -7' X 7') ASTM 615 3/19/2021 33 3920 Manhole Thompson Pipe Group TPG-8X8-411-PRECAST TOP (Size - 8' X 8') ASTM 615 3/19/2021. 33 3920 Manhole Thompson Pipe Grasp TPG-8X8-411-PRECAST BASE (Size - 8' X 8') ASTM 615 3/19/2021 33 3920 Manhole Thompson Pipe Grasp TPG-8X8-412-PRECAST 5 -FT RISER (Size - 8' X 8') ASTM 615 3/19/2021 33 4920 Drop Inlet Thompson Pipe Group TPG-4X4-408-PRECAST INLET (Size - 4' X 4') ASTM 615 /19/2021 33 4920 Drop Inlet Thompson Pipe Grasp TPG-5X5-4O8-PRECAST INLET (Size -5' X 5' ASTM 615 3/19/2021 33 4920 Drop Inlet Thom son Pipe Group TPG-6X6-408-PRECAST INLET (Size - 6' X 6') ASTM 615 8/28/2023 33 4910 Manhole Oldcastle Precast 4' x 4' Stacked Manhole (Size - 4' X 4') ASTM C478 8/28/2023 33 4910 Manhole Oldcastle Precast 5' x 8' Storm Junction Box (Size -S 5 X 8') ASTM C478 8/28/2023 33 4910 Manhole Oldcastle Precast 4'x 4' Storm Junction Box (Size - 4' X 4') ASTM C478 8/28/2023 33 4910 Manhole Oldcastle Precast 5'x5' Storm Junction Box (Size - 5' X 5') ASTM C478 8/28/2023 33 4910 Manhole Oldcastle Precast 6' x 6' Storm Junction Box (Size -6' X 6') ASTM C478 8/28/2023 33 4910 Manhole Oldcastle Precast 8's 8' Storm Junction Box Base (Size - 8' X 8') ASTM C478 8/28/2023 33 4910 Manhole Oldcastle Precast 5'x 8' Storm Junction Box Base (Size -S 5' X 8') ASTM C478 8/28/2023 33 4910 Manhole Rinker Materials Reinforced 48" Diameter Spread Footing Manhole (Size - 4' X 4') ASTM C433 /21/2028 34 49 10 Manhole Rinker Materials 4'0"x4'-0" Reinforced Maximum Pipe connection 036" /21/2026 3449 10 Manhole Rinker Materials SO"x5'-0" Reinforced Maximum Pipe connection 048" /21/2026 34 4910 WYE Inlet Rinker Materials 5'O"x5'-0" Reinforced Maximum Pipe connection 048" 8/28/2023 33 3920 Curb Inlet 10 'x3' Riser Thom son Pipe Group Inlet Riser (Size -3 FT) ASTM C913-16 8/28/2023 33 3920 Curb Inlet 15 x 3' Riser Thom son Pipe Group Inlet Riser (Size -5 FT) ASTM C913-16 8/28/2023 33 3920 Curb Inlet 20's 3' Riser Thompson Pipe Group Inlet Riser (Size -3 FT) ASTM C913-16 1/12/2024 33 4920 Drop Inlet AmeriTex Pipe &Products Drop Inlet 4' X 4') ASTM C913. 1/12/2024 33 4920 Drop Inlet AmeriTex Pipe &Products Drop Inlet (5' X 5' ASTM 0913 1/19/2024 33 4920 Manhole AmeriTex Pipe &Products Precast 4'x4' Storm Junction Box ASTM C913 /19/2024 33 4920 Manhole AmeriTex Pipe &Products Precast 5'x5' Storm Junction Box ASTM C913 1/19/2024 33 4920 Manhole AmeriTex Pipe &Products 5' Precast Transition MH (41st/Hon the tap of 5' JB ASTM C913. 1/19/2024 33 4920 Manhole AmeriTex Pipe &Products Precast 6'x6' Storm Junction Box ASTM C913 1/19/2024 33 4920 Manhole AmeriTex Pipe &Products 6' Precast Transition MH (4' MH on the top of 6' JB ASTM C913 1/19/2024 33 4920 Manhole AmeriTex Pipe &Products Precast 8'x8' Storm Junction Box ASTM C913 1/19/2024 33 4920 Manhole AmeriTex Pipe &Products 'Precast Transition MH 4' MH on the top of 8' JO) ASTM C913. 1/19/2024 33 4920 Manhole AmeriTex Pipe &Products T e C Storm Drain Manhole on Box 4' MH.on the top of RCB ASTM C913 /16/2024 33 4920 Curb Inlets AmeriTex Pipe &Products ] 0x3 Precast**(Size 10' x 3' ASTM C9t3 /16/2024 33 4920 Curb Inlets AmeriTex Pie &Products 15x3 Precast**Size 15's 3' ASTM C913 ^-/vote: rte -cast mien are approved/or roe surge t portion l me srrucrure (dawn) only. stage a portion J tae structure are required ro de cast m place. lye exceptions retain requirement soda ae auowea. Storm Sewer - Pines & Boxes 33-05-13 4/9/2021 33 4113 Storm Drain Pipes Advanced Drainage Systems, Inc. (ADS) ADS HP Storm Polypropylene (PP) Pipe Size - 12" - 60") ASTM F2881 & AASHTO M330 8/28/2023 33 4110 Storm Drain Pipes Rinker Materials Reinforced Concrete Pipe e Tongue and Groove Joint Pipe (Size - 21" or larger) ASTM C76, C655 8/28/2023 33 4110 Culvert Box Rinker Materials Reinforced Concrete Box Culvert (Sze - Various) ASTM C789, C850 /21/2026 33 4110 Reinforced Concrete Pipe Rinker Materials Tongae and Groove —Straight Wall (Size -Various) ASTM C76, C655 5/21/2026 33 4110 Reinforced Concrete Pipe Rinker Materials Tangue and Groove —WSize-Various ASTM C76, C655 5/21/2026 33 4110 Reinforced Concrete Pipe Rinker Materials Tonue and Groove —Bend (Size -Various) ASTM C76, C655 5/21/2026 33 4110 Reinforced Concrete Pipe Rinker Materials Tonue and Groove —Bend (Size -Various) ASTM C76, C655 5/21/2026 33 4110 Reinforced Concrete Pipe Rinker Materials Tongac and Grease —Straight Wall —Tee. Vertical/ Horizontal .Size -Various ASTM C76, C655 5/2112026 33 4110 Reinforced Concrete Pipe Reducers Rinker Materials Tongue and Groove —Option 2 (Size-Varieius) ASTM C76, C655 10/12/2023 33 4110 Storm Drain Pipes AmeriTex Pipe &Products Reinforced Concrete Pipe Tongue and Groove Joint Pie* (Size - 15" or larger) ASTM C76, C506 10/12/2023 34 4110 Culvert Box AmeriTex Pie &Products Reinforced Concrete Box Culvert (size - Various)) I ASTM C1433,C1577 10/18/2023 35 4110 Storm Drain Pipes es The Turner Co. Reinforced Concrete Pipe e Tongue and Groove Joint Pie* (Size - 15" or larger) ASTM C76, C506 10/18/2023 33 4110 Culvert Box The Turner Co. Reinforced Concrete Box Culvert (size - Various) I ASTM CI433,CI577 4/12/2024 33 4110 Storm Drain Pipes Thompson Pipe Group Reinforced Concrete Pipe Tongue and Groove Joint Pie* (Size Various) ASTM C76, C506 6/25/2024 33 4110 Culvert Box Oldcastle Reinforced Concrete Box Culvert I ASTM C 1433,C 1577 6/252024 33 4110 Storm Drain Pipes Oldcastle Reinforced Concrete Pipe Tongue and Groove Joint Pipe* (Size Various) ASTM C76, C506 Removed due to slump value revision by the supplier Monthly New Entire,. Page 7 of 7