HomeMy WebLinkAbout26-6365 - City Council - ResolutionRESOLUTION 26-6365
STATEMENT EXPRESSING OFFICIAL INTENT TO REIMBURSE
EXPENDITURES WITH PROCEEDS OF FUTURE DEBT FOR THE
MARY'S CREEK WATER RECLAMATION FACILITY
WHEREAS, the City of Fort Worth, Texas (the "City") is a home -rule municipality and
political subdivision of the State of Texas; and
WHEREAS, the City expects to pay expenditures in connection with the design, planning,
acquisition and construction of the Mary's Creek Water Reclamation Facility Project (the
"Project") prior to the issuance of obligations by the City in connection with the financing of the
Project from available funds; and
WHEREAS, the City finds, considers, and declares that the reimbursement of the City for
the payment of such expenditures will be appropriate and consistent with the lawful objectives of
the City and, as such, chooses to declare its intention, in accordance with the provisions of Section
1.150-2 of the Treasury Regulations, to reimburse itself for such payments at such time as it issues
obligations to finance the Project.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF FORT WORTH, TEXAS THAT:
1. The City reasonably expects debt, as one or more series of obligations,
may be issued or incurred by the City with an aggregate maximum principal amount
not to exceed $235,000,000.00 for the purpose of paying the aggregate costs of the
Proj ect.
2. All costs to be reimbursed pursuant hereto will be capital expenditures. No
obligations will be issued by the City in furtherance of this Statement after a date which is later
than 18 months after the later of (1) the date the expenditures are paid or (2) the date on which the
property, with respect to which such expenditures were made, is placed in service.
3. The foregoing notwithstanding, no obligation will be issued pursuant to this
Statement more than three years after the date any expenditure which is to be reimbursed is paid
4. This resolution shall be effective from and after its passage by the City Council.
Adopted this August 25, 2026.
ATTEST:
By:
Jannette S. Goodall, City Secretary
l F OOOOOA°°°�L a�
°
p o o'Q
� °° °°o TO
d°
�at1 nEXA`�oo�p
I�i�ll�4SL. :IUQU41111111K —.I4414III hi---- ---
j�., JJi). iii dad!! [ '
AV
Lhd�.l,�dlr
iIL
tP
FORT WORTH
MAYOR AND COUNCIL COMMUNICATION
7.1.8 WEBBER WATERWORKS, LLC CONSTRUCTION CONTRACT FOR MARY'S CREEK
WATER RECLAMATION FACILITY
DATE: 08/25/26 M&C FILE NUMBER: M&C 26-0822
DEPARTMENT: WATER
SUBJECT
(CD 3 and ETJ) Authorize Execution of a Contract with Webber Waterworks, LLC in the Amount
of $537,982,128.13 for the Mary's Creek Water Reclamation Facility Project, Adopt Resolution
Expressing Official Intent to Reimburse Expenditures with Proceeds of Future Debt, and Adopt
Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal Years 2026-
2030 Capital Improvement Program
RECOMMENDATION
It is recommended that the City Council:
1. Authorize execution of a contract with Webber Waterworks, LLC in the amount of
$537,982,128.13 for the Mary's Creek Water Reclamation Facility project;
2. Adopt the attached resolution expressing official intent to reimburse expenditures with
proceeds from future debt for the Mary's Creek Water Reclamation Facility Project; and
3. Adopt the attached appropriation ordinance adjusting appropriations in the Water and
Sewer Commercial Paper Fund by increasing appropriations in the Mary's Creek Water
Reclamation Facility project (City Project No. C01239) in the amount of $194,971,358.00
and decreasing appropriations in the Water & Sewer Commercial Paper project (City
Project No. UCMLPR) by the same amount, to effect a portion of Water's contribution to
the Fiscal Years 2026-2030 Capital Improvement Program.
DISCUSSION
The purpose of this Mayor and Council Communication (M&C) is to authorize execution of a
contract with Webber Waterworks, LLC in the amount of $537,982,128.13 for the construction of
the Mary's Creek Water Reclamation Facility (MCWRF). MCWRF is a 10 million gallon per day
(MGD) membrane bioreactor plant that will treat wastewater generated in the fast-growing
west Fort Worth area to an extremely high level prior to discharge into Mary's Creek.
Additionally, the new plant will provide reclaimed water to customers in west Fort Worth and
supplement the water supply through a collaborative project with the Tarrant Regional Water
District (TRWD) that will allow discharged MCWRF water to be conveyed to Eagle Mountain
Lake.
1 of 4
FORT WORTH
Construction of the project was advertised for bid on April 29 and May 6, 2026 in the Fort
Worth Star -Telegram. On July 9, 2026 the following proposals were received. The proposals
were evaluated based on pre -established criteria specified in the solicitation.
Bidder
Webber
Waterworks,
LLC
Thalle
Construction
Co, Inc
Walsh Group
Bid Amount
$ 537,982,128.13
$ 576,527,017.43
$607,890,518.00
Cost
Evaluation
(70 points)
70.0
65.3
61.9
Experience
with Similar
Projects
(10 points)
8.2
6.5
8.7
Project
Approach
and
Schedule
(20 points)
18.5
16.3
17.4
Total
96.7
88.0
Webber Waterworks, LLC, submitted the highest-ranking proposal based upon the identified
pre -established criteria.
In addition to the contract cost, $2,013,995.00 is required for project management and
inspection and $1,613,946.00 is provided for project contingency.
Available cash within the Water and Sewer portfolio and the City's portfolio along with the
appropriation authority authorized under the Callable Commercial Paper Program (CP) will
be used to provide interim financing for this project until debt is issued. Once debt associated
with this project is sold, bond proceeds will be used to reimburse the Water and Sewer
portfolio and the City's portfolio in accordance with the attached Reimbursement Resolution.
Under federal law, debt must be issued within approximately three years in order for these
expenses to be reimbursable. Adoption of the attached resolution does not obligate the City
to sell bonds but preserves the ability of the City to reimburse itself from tax-exempt bond
proceeds.
It is the practice of the Water Department to appropriate its Capital Improvement Program
(CIP) plan throughout the Fiscal Year (FY), instead of within the annual budget ordinance, as
projects commence, additional funding needs are identified, and to comply with bond
covenants.
2 of 4
FORT WORTH
Funding is budgeted in the Commercial Paper Project within the W&S Commercial Paper Fund
and in the Mary's Creek Reclamation Facility project within the W&S WIFIA Revenue Bond Fund
for the purpose of funding the Mary's Creek Water Reclamation Facility.
Funding for the Mary's Creek Water Reclamation Facility project is depicted below:
Existing
Additional
Fund
Appropriations
Appropriations
Project Total*
Sewer Capital
$6,691,576.09
$0.00
$6,691,576.09
Legacy - Fund 59607
Water & Sewer Bond
$857,415.00
$0.00
$857,415.00
2017A — Fund 56011
W&S Rev Bonds
$2,143,498.00
$0.00
$2,143,498.00
Series 2023 - Fund
56021
W&S Rev Bonds
$20,473,700.00
$0.00
$20,473,700.00
Series 2024 - Fund
56022
W&S WIFIA Revenue
$346,638,712.57
$0.00
$346,638,712.57
Bond - Fund 56027
W&S Rev Bond 2026B
$1,870,060.00
$0.00
$1,870,060.00
— Fund 56026
W&S Commercial
$0.00
$194,971,358.00
$194,971,358.00
Paper - Fund 56032
Project Total
$378,674,961.66
$194,971,358.00
$573,646,319.66
Small Business Enterprise: A Small Business goal is not assigned to this contract because a
waiver has been approved by the department's Assistant City Manager in accordance with
the City's Small Business Ordinance.
The project is located in COUNCIL DISTRICT 3 and Extraterritorial Jurisdiction (ETJ).
This contract requires a Form 1295.
FISCAL IN FORMATION/CERTIFICATION
The Director of Finance certifies that funds are currently available in the Commercial Paper
project within the W&S Commercial Paper Fund and in the W&S WIFIA Revenue Bond Fund, as
previously appropriated, and upon approval of the above recommendations and adoption of
the attached appropriation ordinance, funds will be available in the W&S Commercial Paper
Fund and the W&S WIFIA Revenue Bond Fund for the Mary's Creek Water Reclamation Facility
3 of 4
FORT WORTH
project to support the execution of the contract. Prior to any expense being incurred, the
Water Department has the responsibility to validate the availability of funds.
SUBMITTED FOR CITY MANAGER'S OFFICE BY:
ORIGINATING BUSINESS UNIT HEAD:
ADDITIONAL INFORMATION CONTACT:
ATTACHMENTS
Jesica L. McEachern, # 5804
Chris Harder, #5026
Suzy Abbe, #8209
1. Map - Mary's Creek Water Reclamation Facility [7.1.8.1 - 1 page]
2. Resolution (R2) - Mary s Creek Water Reclamation Facility [7.1.8.2 - 1 page]
3. Ordinance Appropriation (R3) - Mary's Creek Water Reclamation Facility [7.1.8.4 - 2
pages]