Change Order Request
Project Name Bomber Spur Trail Phase 1 City Sec # 64609
Client Project #(s) 104345
Construction of a shared use path from Calmont Ave. to US Route 377, including pedestrian crossings over Camp Bowie Blvd. and US Route 377
Contractorl McCarthy Building Companies, Inc. Change Order #1 9 Date 9/2/2026
City Project Mgr. Blaise Grissom City Inspector Sergio Garcia Pedroza
Dept.
PARD
Totals
Contract Time
(CD)
Original Contract Amount
$4,901,279.77
$4,901,279.77
215
Extras to Date
$41,512.98
$41,512.98
20
Credits to Date
$2,058.48
$2,058.48
Pending Change Orders (in M&C Process)
$4,940,734.27
$4,940,734.27
235
Contract Cost to Date
Amount of Proposed Change Order
$57,742.51
$57,742.51
10
Revised Contract Amount
$4,998,476.78
$4,998,476.78
245
Original Funds Available for Change Orders
$0.00
Remaining Funds Available for this CO
$0.00
Additional Funding (if necessary)
$57,742.51
$57,742.51
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 1.98%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
$6,126,599.71
JUSTIFICATION (REASONS) FOR CHANGE ORDER
This Change Order covers the following items: 1) Excavation for the construction of the headwall for Drainge Line A (project station 1132+63.51, LT 24.95') exposed two
previously buried and unknown concrete pipes that continue west under the adjacent commercial development for an unknown distance and terminate at the project station
mentioned previously. These pipes are presumed to be drainage pipes, based on visible water ponding around and in the pipes, and have a flow line elevation that is 18
inches below the flow line of Drainage Line A. In order to mitigate erosion concerns and allow for infiltration of water entering the project site from these pipes, the decision
was made to switch the rip rap material around Drainage Line A's headwall from 4 inches of poured concrete to 12 inches of stone. The City, project engineer, and contractor
are all in agreement that this is the best solution for this differing site condition. 2) During initial excavation for the drill shafts for the bridge support in the median of US 377
(project station 1077+03.62), an existing concrete substructure was discovered that is in conflict with the proposed locations of the drill shafts. In order to mitigate this conflict,
part of the substructure needs to be removed, the drill shaft locations adjusted, and an additional concrete cap constructed that spans between both drill shafts. The expanded
scope of work inside this median will require two additional weeks of traffic control. 3) In accordance with the City's Standard Specification 01 2975 and TxDOT's Standard
Specification Item 9, this Change Order will also provide PARD the ability to make Material on Hand (MOH) payment for the Handrail material to be incorporated into this
project and establish unit prices that will facilitate MOH payments.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full (both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges
that he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting
requirements.
Contractor's Company Name Contractor (Nam : Contract Signature
Date
McCarthyBuilding Companies, Inc. Peter Siggerud Peter Srtaerud
Y P 99 Peter Si erud0Se 8 2026 1503:18 D
Inspector/Inspection Supervisor
Date
Project and Contract Compliance Manager
Date
09/09/2026
' `n 'y,
09/08/2026
Program Manager
Date
Senior Capital Project Officer
Date
09/09/2026
09/09/2026
Assistant Director (Dept)
Date
Director, Contracting De a�rtment (Dept
Date
?mason(See 9.202613:36:18 CDT
Date
Assistant cityanL
Date
oee ia= 6ieek (See 10 2026 10 1O 20507:
09/10/2026
Tana Scu do
:off (Sep 11, 2026 18:21:03 CDT)
09/11/2026
Council Action (if required)
aAn
AofaRT up
F.......yad
ATTEST: a� o0o cc
Jannette Goodall, City Secretary �an�Ez asa4
M&C Number N/A M&C Date Approved N/A
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT WORTH City of Fort Worth
Change Order Additions
Project Name Bomber Spur Trail Phase 1 I City Sec # 64609
Client Project # I 104345
Contractor McCarthy Building Companies, Inc. PM Blaise Grissom Inspector®
Change Order Submittal # 0 Date 9/2/2026
ADDITIONS
ITEM
DESCRIPTION
DEPT
Qty
Unit
Unit Coet
Total
01-117
1IPRAP(STONECOMMON))DRY)(12IN)
PARD
39.0000000
CY
$392.6
$15,314.9
01-118
UTILITY EXPLORATION
PARD
1.00000000
LS
$5,330.38
01-119
EXCAVATION/DEMO OF EXISTING SUBSTRUCTURE
PARD
1.00000000
EA
$18,401.14
01-120
CLASS C CONCRETE (STRUCTURAL)
PARD
9.00000000
CY
$1,807.79
$16,270.11
01-121
BARRICADES, SI N , AND TRAFFIC TRAFFICHANDLING
PARD
0,50000000
MO
$42,969.01
01-122
TMA(STATIONARY)
PARD
10.00000000
DAY
$481.75
$4,817.50
01-123
DRILL SHAFT (36 IN)
PARD
60.00000000
LF
$607.92
01-124
RAIL (HANDRAIL)(TY E)(BASE BID)(FURNISH;
PARD
1,300.00000000
LF
$99.40
01-125
RAIL (HANDRAIL TY E) ADD ALT A BID FURNISH,
PARD
180.00000000
LF
$99.40
01-126
RAIL (HANDRAIL)(TY E)(ADD ALT B BID)(FURNISH;
PARD
140.00000000
LF
$99.40
01-127
RAIL HANDRAIL) TY E)(BASE BID IN TALL
PARD
1,300.00000000
LF
$30.60
01-128
RAIL (HANDRAIL)(TY E)(ADD ALT A BID)(INSTALL,
PARD
180.00000000
LF
$48.59
01-129
RAIL ANDRAIL (TY E) ADD ALT B BID (NSTALL
PARD
140.00000000
LF
$50.12
PARD
$334,664.75
Sub Total Additions
$334,664.7o
Change Order Additions Page 2 of 4
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name Bomber Spur Trail Phase 1 City Sec # 64609
Client Project # I 104345
Contractorj McCarthy Building Companies, Inc. PM Blaise Grissom Inspector®
Change Order Submittal # 9 Date 9/2/2026
DELETIONS
Change Order Deletions Page 3 of 4
M/SBE for this Change Order
M/SBE Sub
Type of Service
Amount for this CO
N/A
Total
$0.00
FORT WORTH®
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: McCarthy Building Companies, Inc.
Subject of the Agreement: Bomber Spur Trail Phase 1 - Change Order #9
M&C Approved by the Council? * Yes ❑ No
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes 8 No ❑ CSC 64609-CO9
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 9 No O
If unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No ® If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date:
If different from the approval date.
Expiration Date:
If applicable.
Is a 1295 Form required? * Yes ❑ No lI
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 104345
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 8 No ❑
Contracts need to be routed for CSO processing in the following order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.