HomeMy WebLinkAbout062805-CO1 - Construction-Related - Contract - Ashton Dallas Residential, LLCDEVELOPER -AWARDED -PROJECT CHANGE ORDER
PROJECT NAME:
CATTLEMANS CROSSING LIFT STATION & FORCE MAIN
CHANGE
CONTRACT:
WATER, SEWER, PAVING, DRAINAGE, AND STREET LIGHT
ORDER No:
CFA#
CFA24-0126 I CITY PARTICIPATION:I YES
CITY PROJECT#
105377
CITY SECRETARY CONTRACT #
62805
1
FID #
30114-0200431-105377-E07685
X#
X-28067
FILE #
N/A
INSPECTOR: Hector Montoya Phone No: 682-215-9539
PROJECT MANAGER: Sandip Adhikari Phone No 682-432-5559
CSC No. 62805-CO1
REVIEWED
LBY Sandip Adhikari at 12:07 pm, Sep 08, 2026
CONTRACT UNIT
WATER
SEWER
DRAINAGE
PAVING
STREET LIGHTS
CONTRACT
Developer
Cost
City Cost
Developer Cost
City Cost
Developer
Cost
City Cost
Developer Cost
City Cost
Developer Cost
City Cost
DAYS
ORIGINAL CONTRACT
$0.00
$0.00
$996,166.94
$669,664.06
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
365
EXTRAS TO DATE
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
0
CREDITS TO DATE
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
0
CONTRACT TO DATE
$0.00
$0.00
$996,166.94
$669,664.06
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
365
AMOUNT OF PROP. CHANGE ORDER
$0.00
$0.00
$26,447.50
$5,837.20
$0.00
$0.00
$0.00
$0.00
$9.09
$0.00
14
REVISED CONTRACT AMOUNT
$0.00
$0.00
$1,022,614.44
$675,501.26
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
379
TOTAL REVISED CONTRACT AMOUNT PER
UNIT
$0.00
$1,698,115.70
$0.00
$0.00
$0.00
REVISED COST SHARE
Dev. Cost:
$1,022,614.44
City Cost:
$675,501.26
TOTAL REVISED CONTRACT
$1,698,115.70
You are directed to make the following changes in the contract documents:
UNIT 1A: SANITARY SEWER IMPROVMENTS FORCE
MAIN)
PAY ITEM #
CITY BID ITEM
QUANTITY
UNIT
ITEM DESCRIPTION
CFW Unit Price
UNIT PRICE
Developer Cost
City Cost
TOTAL
0241.2013
1
14
LF
0241.2013 Remove 8" Sewer Line
$ 55.00
$460.46
$309.54
$770.00
3301.0002
2
(4,585.00)
LF
3301.0002 POST -CCTV Inspection
$ 3.00
($8,225.49)
($5,529.51)
($13,755.00)
3331.3401
9
0.11
TON
3331.3401 Ductile Iron Sewer Fittings
$ 30,000.00
$1,973.40
$1,326.60
$3,300.00
3331.4205
13
5
LF
3331.4205 10" DIP Sewer Pipe
$ 200.00
$598.00
$402.00
$1,000.00
3339.0001
16
6.78
VF
3339.0001 Epoxy Manhole Liner
$ 500.00
$2,027.22
$1,362.78
$3,390.00
9999.0026
'25
6.78
VF
9999.0026 Prepare Manhole for Epoxy
Manhole Liner
$ 310.00
$2,101.80
$0.00
$2,101.80
0170.0101
'20
1
EA
0170.0101 Specified Remobilization
$ 7,500.00
$4,485.00
$3,015.00
$7,500.00
3305.0112
'21
1
EA
3305.0112 Concrete Collar for Manhole
$ 1,000.00
$598.00
$402.00
$1,000.00
9999.0027
26*
1
EA
9999.0027 Prepare site for Conc. Collar
$ 1,700.00
$1,700.00
$0.00
$1,700.00
3339.1101
'22
1
EA
3339.1101 5' Manhole (airtight)
$ 11,120.40
$6,650.00
$4,470.40
$11,120.40
9999.0028
•27
1
EA
9999.0028 Prepare site for 5' Manhole
(airtight)
$ 2,500.00
$2,500.00
$0.00
$2,500.00
3339.1103
'23
0.78
VF
3339.1103 5' Extra Depth Manhole
$ 250.00
$116.61
$78.39
$195.00
9999.0025
'24
4,585
LF
9999.0025 Force Main Pressure Testing
$ 2.50
$11,462.50
$0.00
$11,462.50
UNIT 1A: SANITARY
SEWER IMPROVMENTS
(FORCE MAIN)
$26,447.50
$5,837.20
$32,284.70
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Revised: 12-17-2018 Page 1
Docusign Envelope ID: D403700E-C833-89B5-807C-65E47093B5E9
Asterisk (*) indicates New Pay Item
REASONS FOR CHANGE ORDER 1.) The sanitary sewer section bid item, is for the force main improvements to reflect the excess in post-cctv inspection brought to our attention since the 147 LF of the 12" PVC Gravity
Pipe is the only pipe needing the inspection & cleaning. No plan revisions are required with this change order.
2.)A new 5' manhole has been proposed 10' away from existing manhole as well as a residesign in the sewer. Manhole will connect to an existing Sanitary Sewer Gravity Main. This
change includes the necessary labor, materials, preparation to install, and fittings required to complete the revised connection. See page 7 of construction plan for revision.
RECOMMENDED:
Shield Engineering Group Ashton Dallas Residential L.L.C. Willco Underground
ro..�ea�er oeuagwaer:
By: '" By: By: Ii11.Idcac . 1 tsu 5
Name: Landon G. Geary Name: Daniel Satsky Name: Michael D. Osmus
Title: Project Manager Title: VP- Land Acquisition & Development Title:
APPROVAL RECOMMENDED: APPROVED: APPROVED AS TO FORM AND LEGALITY:
By:
CFW - Funding Department
✓•P!' 09/14/2026
CFW - Assistant City Manager
By: _.
09/16/2026
CFW - Assistant City Attorney
By:
Name: Suby Varughese Name: Jesica McEachern Name: Jessika Williams
Title: Engineering Manager Title: Assistant City Manager Title: Assistant City Attorney
09/15/2026
RECOMMENDED:
CFW - *Contract Compliance Manager ATTEST ��,eo�s * Contract Compliance Manager (Project Manager):
" 09/0612026 " - -u 09/1712026 By signing I acknowledge that I am the person responsible
By: "' By: for the monitoring and administration of this contract, include
ensuring all performance and reporting requirements.
Name: Sandie Adhikari Name: Jannette S. Goodall
Title: City Secretary
Title: Sr. Professional Engineer
M&C Number: N/A
M&C Date Approved: N/A
❑There are NO City Funds associated with this Contract
ID There are City Funds associated with this Contract
REVIEWED
By Sandip Adhikari at 12:07 pm, Sep 08, 2026
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Revised: 12-17-2018
Page 2
SANITARY SEWER SHEET KEY
NTS
LEGEND
NOTES:
PR OP SANITARY SEWER LINE
EXIST WATER LINE
1) ALL SANITARY SEWER LINES SHALL BE PVS DRI4, CLASS 305 PIPE UNLESS OTHERWISE NOTED ON THE PLANS. ALL SEWER UNES ARE B" UNLESS DETAILED OTHERWISE.
SEWER STUDY H:
2) THE EXISTENCE AND LOCATION OF UNDERGROUND UTILITIES ON THE DRAWING WERE DERIVED FROM AVAILABLE RECORDS AND SHALL BE CONSIDERED AS APPROXIMATE.
WSS-2021-1394
PROP SANITARY SEWER MANHOLE •
EXIST GATE VALVE
A'A
Dl CONTRACTOR SHALL BE RESPONSIBLE FOR FIELD VERIFYING EXISTING UTILITY LOCATIONS AS WELL AS HORIZONTALAND VERTICAL PLACEMENT.
4) CONTRACTOR SHALL IMMEDIATELY CONTACT THE ENGINEER OF ANY DISCREPANCIES.
EXIST SANITARY SEWER LINE ;s
EXIST FIRE HYDRANT
y.— —
5) ALL VERTICAL AND HORIZONTAL FITTINGS AND VALVESO AL BE DESIGNED WITH RETRAINED JOINTS IN ADDITION TO CONCRETE THRUSTS OAK 65 ANCHOR TEES OR
EX SANITARY SEWER LINE
ANCHOR COUPLINGS SHOULD BE USED TO SECURE ALL BRANCH VALVES TO FITTINGS. TABLE 5-2 INCLUDES THE MINIMUM LENGTHS OF PIPE TO BE RETRAINED FOR B -INCH
EXIST SANITARY SEWER MANHOLE O—
PROP GATE VALVE M
(BY OTHERS)
AND 12 -INCH PVC SEWER MAINS. DCM-5.6.1
B) RADIUS OF CURVATURE JO DEFLECTION- MINIMUM RADIUS OF CURVE AND MAXIMUM DEFLECTION ANGLE OF PIPE JOINTS WILL BE RESTRICTED TO 10% OF
MANUFACTURER'S RECOMMENDATION, AFTER WHICH THE USE OF HORIZONTAL OR VERTICAL BENDS WILL BE REQUIRED. NO BENDING OF PIPE ALLOWED. OCM-S R I
7) ODOR CONTROL UNIT SHALL BE LOCATED WITHIN THE PUBLIC RIGHT-OF-WAY(ROW) AND OUTSIDE OF ALL PAVEMENT UNITS. REFER TO PLAN SYMBOL AND CALLOUT FOR
'CONTRACTOR IS RESPONSIBLE TO
APPROXIMATE LOCATION.
COORDINATION WITH COFW S PLAN
SS FM -I A l,)S.20
OPERATIONS DEPARTMENT PRIOR TO
\ ENO 80
1-_'ILEE (ATLLEMAN'S(RUSSINCi 'IASE H
REGIONAL LIFT STATION
END
CONSTRUCTION WORK
s\'STE CASING
1111E_7
CAUTION
XVIT. PROTECTO
S FM 1 STA 1 89
SS FM 1 STA 2 5000
EXISTING UTILITIES
A COATING
IN TALL.
INSTA OSFM ST ],39.16
THE CONTRACTOR IS RESPONSIBLE FOR IDENTIFYING
INS (ILL'
0000 HORZB ND
1-10 ATEVALVE&B X INSTALL:
LOCATING ALL UNDERGROUND UTILITIES PRIOR TO
HOR2BENp=45°0'0°
N. 033089.20
053065.20
N703113].11 -' HE BEND 0°42'40"
CONSTRUCTION. ALL INFORMATION SHOWN IN THERE
N ]033 5.18
E
E 230 89922 N ]03352].1
PLANS IS BASED ON BEST AVAILABLE REFERENCE E 23028&185
DOCUMENTS. DATA PROVIDED BV UTILITY OWNERS,&
_ E 2303194.4
PHYSICAL APPURTENANCES OBSERVED IN THE FIELD.
15' X 25'
0°C900 DR-25PVCSSFM
THE CONTRACTOR IS RESPONSIBLE FOR REVIEWING
AND VERIFYING ALL SUCH INFORMATION.
CEIVING PIT -
WARNING!II
- - - -
- - _ --
15 S S.E. BY SEPARATE INS-- - - - --_
EXISTING GAS
g
SEPARATE INST. 30 PIPELINE EASEMENT
20 PIPELINE EASEMENT
INST. SO. D208131709
INST. NO.
O.P.R.T.C.T.
0.17M
O.P.RC.T. .T.C.T.
SS FM STA 0-30.4]
I00
OW
-1
BEGIN20"STEEL CASIN
SSFM-1 STA0+15.19
FORT WORTH AND
- -
-
WITH TO
491 COATING
INSTALL: ,
11°W'00'HORZ BEND DENVER R.R. COMPANY
9A1
N 7032987 b3
N7032978:81 (100 RIGHT—OF—WAY)
aas 1
EX 21" GRAVITY SS
(DESIGN BY BURGES
BATES ASTON ROAD (40' RIGHT—OF—WAY)
&NIPLE INC.) r,
CPN 105385 X-27fifi1
.__ .... .�.....
- -- - 40 ROW
Ste.. -
SS FM -1 STA-0,0350
.. - f�
211N GRAVITY-MAIMBFA 27+372₹ -� -- -
X 12°SSFM
- - - - -I
BURGES300
15 X
LAUNCHING
MH
WITH CONCRETE COLLARS (DESIGN BY
WITH CONCRETECOLLARS
02
URN 104300 X-27681
PIT
PER 330517, HYDRAULIC BURGES & NIPLE INC.)
SLIDE, &EPDXY MIT LINER CPN: 104385, X-27661
N703295 `
E23029954x SS FM -I
wEXI
BATESrFORTWORTH&DE
VET
O'PIPELIN
PFILESCALE:
AST
NROADCOMPANY(10O.O.W.)
ROWIINSTNO.
EASEMEN
HORZ1"=40(4
VERT. 1'=4q�
�I
�Wy
_
all
F
l"aa
Fm
l
ii:
Z
855
U
.855
asB
Bse
\
—
EXISTGR
UND
845
I 15' X 25'
845
RECEIVIN
PIT
30,3.3'
5
14 LF 10"P
1
LF1o" rY
j
145LF
20
@ GDR -25010%
STEEL CA NR
U.
9%
9 LF 10" CV
I, 05-25 PVC 0.10%
940
10"DI
840
LF1 "PV
85LF 10"
C900, DR -2
PVC@0.10%
40 LF
@0.10'
100
LF 10" DI
W PRTOTECTIVE
ARRIER PIPE
C ATING@0.10%
835
15' X
LAUNCHING
0' I
IT
I,U)
PROTECTIV
LF 10"
835
5 LFF 10"
VC 84F10"PVC
)PRO ECTIVE
OATIN @0.10%
Cc S FM-
@
.10%
u'i
B e
�
m
$
'I 8+,
830
TPIPE
ELEVATION
$
$
REVISIONS
DESCRIPTION
fElEN . a • s lIaSM!P00
I , SHIELD
ENGINEERING GROUP
iBIB NBM 4F11 W9 iBIU FIRM a10,9BB90
0 40 BO 120
GRAPHIC SCALE IN FEET
REVIEWED
BySaaclpAdMFaNal4:54pm,Au9 03,2010
OS 106 59. CORNER OF P101 REM CREEK TRZJL NM9s5s COO ED SOLOS BLUE OAIUEMOUTCCBOI
COPED EA LATHE TOFF 00 01 MFrz,FI.EAs610tH
OFF OCR ORUOR 01000 EASTUORFTwN USA
ABLVD Env. ,8869 U
CR01000 PT 910
CKKH100RRME0M MARCRAILROAD AND 501 FR Ua O0
°,a1o�m NORTH THE 6101 SN ITaNOF US HIGHWAY 1, ABUA
NOOB F cAsre T LI-
ELEL ROOM 0L.
Z
0
CRY PMOJECTH 156977 ig0P000RTAR-4Z
FILEMX-22067 I�—
CITY OF FORT WORTH, TEXAS LL
WATER DEPARTMENT
Z
CATTLEMANS CROSSING 0
LIFT STATION & FORCE MAIN 0
Cl)
SANITARY SEWER FORCE MAIN
7OF 17
PLAN & PROFILE FM -1
DESIGNED: LM SCALE: (GATE:
BRAWN: MAR 1'=40' AUG 2520
FORT WORTH®
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: Ashton Dallas Residential L.L.C.
Subject of the Agreement: Cattleman's Crossing Force Main & LiftStation - Change Order 1
Field constraints lead to plan revisions. Plan revision triggered project cost adjustments. Change order is prepared to
adjust this cost.
M&C Approved by the Council? * Yes ❑ No
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes 8 No ❑ 62805
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 9 No ❑
If unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 8 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date: 2/17/2025
If different from the approval date.
Expiration Date: 2/16/2027
If applicable.
Is a 1295 Form required? * Yes ❑ No 0
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 105377
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 8 No 0
Contracts need to be routed for CSO processing in the following order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.