HomeMy WebLinkAbout064126-CO2 - Construction-Related - Contract - McCarthy Building Companies, Inc.CSC No. 64126-CO2
FORT VVORT H City of Fort Worth
Change Order Request
Project Name: Water and Sanitary Sewer Replacement on Camp Bowie: Will Rogers - Part 4 City Sec No.: 64126
Project No.(s): 105062A I DOE No. N/A City Proj. No.: 105062-4
Project Description: Water and Sanitary Sewer Repalcement on Tower Dr from W. Lancaster Ave to Burnett Tandy Dr.
Conlractor:l McCarthy Building Companies, Inc. Change Order # 2 Dale: 8117/2026
City Project Mgr,I Preell KC I City Inspector: Pedro Hernandez
Phone Number: 817-392-5467 I Phone Number: 682-289-5735
Dept.
Original Contract Amount
Exlras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Dale
Water
Sewer
Paving
Totals
Contract Time
(Calender days)
$2,281,408.17
$1,527,265.60
$3,808,673.77
200
•$3,699.49
-$16,277.24
-$19,976.73
62
$2,277,708.68
$1 510,988.36
$3,788,697.04
262
Amount of Proposed Chancre Order
$0.00
$93135.16
$0.00
$93.135.16
134
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 1.92%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) $4,760,842.21
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Change Order No. 2 will provide for the replacement of approximately 200 linear feet of a deteriorated segment of an existing 10 -Inch PVC
sanitary sewer line that was encountered during construction of a 12 -Inch ductile Iron pipe on Burnett Tandy Drive. The change order also
Includes additional exploratory excavation to locate potential conflicts prior to sanitary sewer installation and the removal of additional existing
4 ft diameter manholes that were encounterd during construction.
Staff concurs with the contractor's request for an 134 additional calendar days for the change order.
ills understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Company Name
Contractor Name
Contractor Signature
Date
McCarthyBuilding Companies, Inc.
Mark Valdez
Mark Veldoz n
8/27/2026
I s clot
Date
Project Manager
Date
q---.7.Oj.b
Peet' C
8/27/2026
DIrectorS Water Dept)
Date
Co /ruction Supervisor (TPW Dept) .
Date
Christopher Harder (Sep 9. 2026 1603:44 CDT) v V'i
09/09/2026
/,t
9-- - z.C
Senior Assistant City Attorney
Date
Assistant City Manager
Dale
oer�
09/10/2026
09/16/2026
Council Action (If Required)
M&C Number I N/A M&C Date Approved
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT ZV()RTH City of Fort Worth
L1 = Change Order Additions
Project Name Water and Sanitary Sewer Replacement on Camp Bowie: Will Rogers - Part 4 I City Sec No.: 64126
Project No.(s): I 105062-4 DOE No. N/A City Proj. No.: 105062-Q
Project
Description
Water and Sanitary Sewer Repalcement on Tower Dr from W. Lancaster Ave to Burnett Tandy Dr.
Contractor I McCarthyBuilding Companies, Inc. Change Order:=2 Date: 811712026
City Project Mgr. I Preell KC I City Inspector I Pedro Hernandez
ADDITIONS
ITEM
DESCRIPTION
DEPT
Qty
Unit
Unit Cost
Total
1
2" DIP Sewer Lined with Protecto 401, CLSM Back ill
Sewer
74.00
LF
$561.82
$41,574.68
2
12" SDR-26 PVC Sewer Pipe, CLSM Backfll
Sewer
115,00
LF
$456.33
$52,477.95
3
10" DIP Sewer Lined with Protecto 401, CLSM Backfill
Sewer
3.00
LF
$512.75
$1,538.25
6
Trench Safety
Sewer
200.00
LF
$4.91
$982.00
7
4' Manhole
Sewer
4.00
EA
$10,391.23
$41,564.92
8
4' Extra Depth Manhole
Sewer
2.27
VF
$1,182.52
$2,684.32
13
Epoxy Manhole Liner for 4' Manhole
Sewer
11.70
VF
$597.40
$6,989.58
16
Post -CCTV Inspection
Sewer
197.00
EA
$2.45
$482.65
17
Manhole Vacuum Testing
Sewer
3,000
EA
$229.39
$688.17
18
Concrete Collar
Sewer
2.00
EA
$2,070.64
$4,141.28
21
6" Sewer Service, Reconnection
Sewer
2.00
EA
$4,629.50
$9,259.00
27
11" Conc Pvmt (no curb)
Sewer
11.00
SY
$200.00
$2,200.00
31
Remove Brick Pvmt
Sewer
48.00
SY
$130.00
$6,240.00
34
Remove Conc Pvmt
Sewer
55.55
SY
$11.00
$611.05
40
Additional Exploratory Excavation of Existing Utilities
Sewer
4.00
EA
$4,500.00
$18,000.00
4F
Remove Existing pipe
Sewer
751.00
LF
$47.25
$35,484.75
42
Remove Manhole
Sewer
4.00
EA
$2,700.00
$10,800.00
43
Demo Sidewalk
Sewer
1905.00
SF
$6.43
$12,249.15
44
Inlet and RCP removal
Sewer
1.00
EA
$7,425.80
$7,425.80
45
4' Dla Manhole (replacement)
Sewer
1.00
EA
$3,857.70
$3,857.70
46
4' Dla Manhole (Cored)
Sewer
1.00
EA
$1,155.00
$1,155.00
47
Cut and Restore Paving - Demo/Subgrade/HMA
Water
26.00
LF
$168.50
$4,381.00
Water
Sewer
$264,787.25
Paving
Page 1 of 1
FORT VV ORTH City of Fort Worth
rr--- Change
Z _ Order Deletions
Project Name Water and Sanitary Sewer Replacement on Camp Bowie: Will Rogers - Part 4 I City Sec No.: 64126
Project No.(s): 105062-4 I DOE No. N/A I City Proj. No.: 105062-4
Project Description Water and Sanitary Sewer Repalcement on Tower Dr from W. Lancaster Ave to Burnett Tandy Dr.
Contractor McCarthy Building Companies, Inc. Change Order: I I Date 8/17/2026
City Project Mgr. Preen KC I City Inspector: Pedro Hernandez
DELETIONS
ITEM
DESCRIPTION
DEPT
Qty
Unit
Unit Cost
Total
14
Epoxy Manhole Liner for 4' Drop Manhole(Warren Environmental
Sewer
7.00
VF
$597.39
$4,181.73
19
4" Sewer Service
Sewer
4.00
EA
$6,120.00
$24,480.00
20
4" Private Sewer Service
Sewer
364.00
LF
$150.00
$54,600.00
23
Sanitary Line Grouting
Sewer
7.00
CV
$1,557.89
$10,905.23
9a
4' Drop Manhole*
Sewer
1.00
EA
$16,302.61
$16,302.61
10a
4' Extra Depth Manhole (Drop Manhole)*
Sewer
1.00
VF
$1,182.52
$1,182.52
33
Construction Allowance
Sewer
1.00
LS
$60,000.00
$60,000.00
Page 1 of 1
Water
Sewer
$171,652.09
Paving
Deletions Sub Total
$171,652.09
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
/-e
Signature
Preeti KC
Name of Employee
Sr. Professional Engineer
Title
ooF FOFT��Yad
ATTEST: Ode e -1P
°aa °hEXPSo'o.>
09/17/2026
Jannette Goodall
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT WORTH®
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: McCarthy Building Companies, Inc.
Subject of the Agreement: Water and Sanitary Sewer Replacement on Camp Bowie: Will Rogers -Part 4
M&C Approved by the Council? * Yes 0 No
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes 8 No ❑ 64126-CO2
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 8 No 0
If unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *-Yes 0 No R If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date: 8/27/2026
If different from the approval date.
Expiration Date: N/A
If applicable.
Is a 1295 Form required? * Yes 0 No
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 105062-4
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes ® No ❑
Contracts need to be routed for CSO processing in the following order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
'`Indicates the information is required and if the information is not provided, the contract will be
returned to the department.