HomeMy WebLinkAbout26-28755 - City Council - OrdinanceORDINANCE 26-28755
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER AND SEWER CAPITAL PROJECTS FUND
IN THE AMOUNT OF $297,496.00, TRANSFERRED FROM AVAILABLE PAYGO
FUNDS WITHIN THE WATER AND SEWER FUND, FOR THE PURPOSE OF
FUNDING THE WATER/SANITARY SEWER REPLACEMENT CONTRACT
2020, WSM-M PROJECT (CITY PROJECT NO. 103413); PROVIDING FOR A
SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF
PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF
FORT WORTH, TEXAS THAT:
SECTION 1.
The budget of the City of Fort Worth for Fiscal Year 2025-2026, as enacted by Ordinance 27979-
09-2025, as amended, is hereby further amended by increasing estimated receipts and appropriations in the
Water and Sewer Capital Projects Fund in the amount of $297,496.00, transferred from available PayGo
funds within the Water and Sewer Fund, for the purpose of funding the Water/Sanitary Sewer Replacement
Contract 2020, WSM-M project (City Project No. 103413)
SECTION 2.
Should any portion, section or part of a section of this ordinance be declared invalid, inoperative or
void for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way
impair the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions
shall be and remain in full force and effect.
SECTION 3.
This ordinance shall be cumulative of Ordinance No. 27979-09-2025 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions
of said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Douglas V� �$fack�'�
Sr. Assistant City Attorney
ADOPTED: September 15, 2026
EFFECTIVE: September 15.2026
aOR
j6O°
Jannette S. Goodall i� o o d
City Secretary V o o = d
X 000 0
00000
zi �EXAS�<55�1',d
Ordinance No. 26-28755
Page 1 of 1
— 'if IN � it
1
'
I � T�..
IFRLU if tin
ry -, i' i h
R
NO
L
FORT WORTH®
MAYOR AND COUNCIL COMMUNICATION
7.1.20 VENUS CONSTRUCTION COMPANY, INC. WATER AND SEWER CONTRACT CHANGE
ORDER 4
DATE: 09/15/26 M&C FILE NUMBER: M&C 26-0789
DEPARTMENT: WATER
SUBJECT
(CD 8) Authorize Execution of Change Order No. 4 in the Amount of $297,494.95.00 to a
Contract with Venus Construction Company, Inc., for a Revised Contract Amount of
$10,400,495.70 for the Water and Sanitary Sewer Replacement Contract 2020, WSM-M Project
and Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal
Years 2026-2030 Capital Improvement Program
RECOMMENDATION
It is recommended that the City Council:
1. Authorize execution of Change Order No. 4 in the amount of $297,494.95 and an
additional 180 days to City Secretary Contract No. 62014, a contract with Venus
Construction Company, Inc., for the Water and Sanitary Sewer Replacement Contract
2020, WSM-M project for a revised contract amount of $10,400,495.70; and
2. Adopt the attached appropriation ordinance increasing estimated receipts and
appropriations in the Water and Sewer Capital Projects Fund in the amount of
$297,496.00, transferred from available PayGo funds within the Water and Sewer Fund,
for the purpose of funding the Water and Sanitary Sewer Replacement Contract 2020,
WSM-M project (City Project No. 103413) and to effect a portion of Water's contribution
to the Fiscal Years 2026-2030 Capital Improvement Program.
DISCUSSION
The purpose of this Mayor and Council Communication (M&C) is to approve execution of
Change Order No. 4 in the amount of $297,494.95 to a construction contract with Venus
Construction Company, Inc., for the Water & Sanitary Sewer Replacement Contract 2020,
WSM-M project (City Project No. 103413).
On August 13, 2024, by M&C 24-0683, the City Council authorized a construction contract with
Venus Construction Company, Inc., in the amount of $10,103,000.75 for the Water & Sanitary
Sewer Replacement Contract 2020, WSM-M project (City Secretary Contract No. 62014).
The contract was subsequently revised by three change orders as follows:
1of3
FORT WORTH®
Change Order No. 1 with a net total of $0.00 administratively authorized July 15, 2025, that
provided for the installation of two additional manholes to accommodate two 6-inch service
lines that were encountered during construction; Change order No. 2 with a net total of $0.00
administratively authorized September 22, 2025, that provided for additional concrete
flatwork on Rondo Dr. to replace broken curb and gutter and revise elevations to ensure
positive drainage flow: Change order No. 3 with a net total of $0.00 administratively
authorized February 08, 2026, that provided for the installation of 160 LF of 8-inch water line
by other than open cut in lieu of open cut installation, due to conflict with an existing 92-
inch storm drain on Harvey Ave, Powell Ave and Evans Ave.
Change Order No. 4 will primarily provide additional quantities of concrete flatwork on
Jessamine Street, Powell Street, Harvey Street, E. Davis Street and Evans Ave to facilitate the
pulverization and asphalt overlay process of all five streets subsequent to water and sewer
line installation.
It is the practice of the Water Department to appropriate its Capital Improvement Program
(CIP) plan throughout the Fiscal Year, instead of within the annual budget ordinance, as
projects commence, additional funding needs are identified, and to comply with bond
covenants.
Funding is available in the Transfer to Water/Sewer account within the Water and Sewer
Fund for the Water Department for the purpose of funding the W&SS REPL Contract 2020
WSM-M project.
Appropriations for the W&SS REPL Contract 2020 WSM-M project are as depicted below:
Fund
W&S Capital Projects
Fund 56002
General Capital
Projects Fund 30100
Project Total
Existing
Appropriations
$11,037,043.00
$623,958.00
$11,661,001.00
*Numbers rounded for presentation purposes.
The project is located in COUNCIL DISTRICT 8.
This contract requires a Form 1295.
FISCAL INFORMATION/CERTIFICATION
Additional
Appropriations
$297,496.00
$ 0.00
$297,496.00
Project Total*
$11,334,539.00
$623,958.00
$11,958,497.00
The Director of Finance certifies that funds are currently available in the Water & Sewer Fund,
and upon approval of the above recommendations and adoption of the attached
appropriation ordinance, funds will be available in the current capital budget, as
2 of 3
FORT WORTH®
appropriated in the WAS Capital Projects Fund for the W&SS REPL Contract 2020 WSM-M
project to support the execution of the change order. Prior to any expense being incurred, the
Water Department has the responsibility of verifying the availability of funds.
SUBMITTED FOR CITY MANAGER'S OFFICE BY: Jesica L. McEachern, # 5804
ORIGINATING BUSINESS UNIT HEAD: Chris Harder, # 5020
ADDITIONAL INFORMATION CONTACT: Preeti KC, # 5467
ATTACHMENTS
1. 602020 WSMMC 0 4- VENUS [7.1.20.1 - 1 page]
2. ORD APP 60WSSC20WSMMC04 VENUS 56002 A026 R2 [7.1.20.6 - 1 page]