FIRST AMENDMENT TO CITY SECRETARY CONTRACT NUMBER 65357
A COMMUNITY FACILITIES AGREEMENT BETWEEN
THE CITY OF FORT WORTH AND PMB TEAM RANCH DEVCO LLC
This FIRST AMENDMENT TO CITY SECRETARY CONTRACT NUMBER
65357 ("First Amendment") is made and entered into by and between the City of Fort Worth
("City"), a home -rule municipal corporation of the state of Texas, and PMB TEAM RANCH
DEVCO LLC ("Developer").
WHEREAS, the City and Developer entered into a Community Facilities Agreement
for the Construction of public infrastructure improvements for a Project known as Rockbrook
Offsite 24" WSIV Waterline, City Project Number 106272, City Secretary Contract Number
65357 ("CFA"); and
WHEREAS, on August 25, 2026, the City Council approved City participation in the
CFA in an amount up to $2,457,659.70 for the construction and oversizing of approximately
6,043 linear feet of water mains of various pipe sizes (Mayor and Council No. 26-0805); and
WHEREAS, City and Developer desire to amend the CFA to reflect the inclusion of
City participation.
NOW THEREFORE, City and Developer, acting herein by and through their duly
authorized representatives, enter into the following agreement, which amends City Secretary
Contract No. 65357:
1.
The CFA is amended to delete the following recital in its entirety:
WHEREAS, the City is not participating in the cost of the Improvements or Project;
and
OFFICIAL RECORD
2. CITY SECRETARY
The CFA is amended to add the following recitals: FT. WORTH, TX
WHEREAS, the City's participation in this Agreement shall be in an amount not to exceed
$2,457,659.70 for the City's portion of the cost of oversizing water mains; and
WHEREAS, the City Participation includes reimbursement to Developer in amounts not to exceed
$2,064,830.79 for construction costs, $3,683.23 for IPRC plan review fees, $249,464.25 for design services
costs, $1,768.67 for the CFA application fee, $42,300.00 for easement acquisition, and $61,944.92 for
City of Fort Worth, Texas
First Amendment to City Secretary Contract No. 65357
Page 1 of 5
material testing costs. The remaining City Participation in the amount of $33,667.84 shall not be paid to
Developer but will be used by City to pay for the City's portion of construction inspection service fees,
administrative material testing fees, and water lab testing fees; and
3.
Section 9 of the CFA is amended to incorporate subsection (h), which shall be and read
as follows:
(h) Developer shall ensure the contractors are paid the City's wage rates in effect
during construction of the Improvements.
4.
Section 36 of the CFA is amended in its entirety to be and read as set forth in Exhibit "A"
of this First Amendment.
5.
The CFA is amended to incorporate Section 37, which shall be and read as follows:
37.
City Participation; Fiscal Funding Limitation
(a) The City shall reimburse Developer in amounts not to exceed $2,064,830.79 for construction costs,
$3,683.23 for IPRC plan review fees, $249,464.25 for design services costs, $1,768.67 for the CFA
application fee, $42,300.00 for easement acquisition, and $61,944.92 for material testing costs. The
remaining City Participation in the amount of $33,667.84 shall not be paid to Developer but will
be used by City to pay for the City's portion of construction inspection service fees, administrative
material testing fees, and water lab testing fees. During construction of the Improvements,
Developer will receive applications for payment from Developer's contractors. Developer shall
verify that each application for payment is due and payable under the construction contracts
between Developer and the contractors and that the Improvements that are the subject of the
application for payment have been constructed. Developer shall submit payment requests to the
City, in the form of an invoice, no more frequently than one time per month to obtain
reimbursement of the City Participation (each a "Payment Request"). Each Payment Request shall
be delivered to the City utilizing the City's eBuilder software application and the spreadsheet
approved by the City. Each Payment Requested submitted by Developer shall be accompanied with
proof that: (1) Developer has paid the contractors for the amount included in the Payment Request;
and (2) an affidavit and lien release from the contractors indicating that Developer has paid the
contractors in full for the amount included in each Payment Request and the contractors have paid
all subcontractors and material suppliers in full. Developer must register as a vendor of the City in
order for the City Participation to be paid to Developer. The cost of any charge orders must be
agreed upon in writing by the parties and the party or parties benefitting from the change order
must pay the costs as outlined in the written change order signed by the parties. The City
Participation for construction costs was calculated as follows:
City of Fort Worth, Texas
First Amendment to City Secretary Contract No. 65357
Page 2 of 5
UNIT I: WATERIMPRO[E1fET-IS
Item Selection
CO?TLR4CIOR C1W
Bidlist item
Category
Item Description
UaiI of
Ali —
Bid
Quantity
Unit Price
Unit Valve
Unit Price
Unit Value
Cite
Partiripauo-n
I
Division_ 02_Existing_Conditions
Remove Fence
LF
75.0
$.10.00
5750.00
$50.00
$3.750.00
575000
2
Division 32 Exterior Im rnvements
Smooth Wire Fence. Metal Posts
LF
75.0
$20.00
$1.500.00
$25.38
$1.903.50
$1.500.00
3
Divisinn_33_Utilities
Cathodic Protection
LS
1.0
55500.00
55,500.00
$84,500.
584.500.00
$5.50000
4
Division_33_Utllities
Teench Safety
LF
5.580.0
52.00
811.160.00
$1.00
85..580.
$5,550.00
5
Divistun 33 Utilities
Utility Markers
LS
1.0
53,50000
03_50000
520600
5206O0
$20600
6
Division_33_Utililies
42" Casing By Other Than 6pen Cut
LF
479-0
01,280.
5613.120.00
51,600.
$766.400.00
$613,120.00
7
Division 33 Utilities
42" Casing By Open Cut
IF
137.0
$720.00
$98.640.00
$60000
882._' 00.00
882200.00
8
Division_33_Utilities
24" Water Carrier Pipe
I.F
604.0
5594.00
$358,776.00
5600.00
5362.400,00
535877600
9
Div.sson33 Utiutties
Ductilelron Water Fittengswl Restraint
TON
10_S93
$17.50000
$19067750
$972900
$10597800
$105.978.00
10
Division_33_Utilities
8"Water Pipe
LF
23.0
$54-00
$1.24200
$118.00
$'2,714.00
$1.242.00
Il
Division 33 Utilities
74" Water Pipe
LF
5420.0
$23250
$1'260.15000
523500
S1.?.73700.00
$1260,150.00
12
Division 33 Utilities
Comrection to Exisliag 24" Water Main
LA
1.0
$24,500.00
$_24.500.00
36,081..00
$6.081.00
$6,081.00
13
Division 33 Utilities
4" Combination Air Valve AssemblySor Waler
EA
1.0
$34,500.00
534,500.00
$24,767.00
$24.767.00
52476700
14
Division 33 Utilihesi
8" Gate Valve
EA
2.0
82,500.00
$5,000.00
82_,597.00
$5.,194.00
$5.000.00
15
Divisson_33Utilities
24" Gate Valve w1 Vault
EA
8.0
048.750.
$390.000.00
$43 82000
$350360.00
$350.560 00
16
Division_ 33_Utilites
Water Sampling Station
FA
6.0
$5500.00
$33,00000
$11,000.00
$66,000.00
$33.000.00
07
Division33 Utilities
8" Blow OffVaive
EA
3.0
$18.500.00
$55,500.00
520,064.00
$60.192.00
555.50000
18
Division_ 02_Esisting_Conditioes
24" Pressure Plug
EA
1.0
02,500.00
$2.500.00
5_'42800
52.428.00
02.428 00
09
Division 33 Utilities
Fire Etydrant
FA
1.0
53,500.00
03,500.00
516.87300
010.87300
$3,500.00
20
Division_34_Transportatron
Traffic Control
MO
4.0
$3,500.00
$14,000.00
3.250.0
$13..000.00
$13,000.00
Contractor total
53,107,465.50
$2,928,838.00
Cite Participation 70.5%
52,084,830.74
(b) Substantial completion of the Improvements shall occur after Developer's contractors notify the
City that the Improvements are constructed and ready for their intended use, the City and
Developer's contractors inspect the Improvements, and the City concurs that the Improvements are
substantially complete. This City will withhold 5% in retainage from each payment made to
Developer. Retainage shall be paid by City to Developer 60 days after the Improvements are
constructed and accepted by the City and Developer delivers an invoice to the City.
(c) In the event no funds or insufficient funds are appropriated and budgeted or are otherwise
unavailable by any means whatsoever in any fiscal period for payments due under this Agreement,
then the City will immediately notify Developer of such occurrence and this Agreement shall be
terminated on the last day of the fiscal period for which appropriations were received without
penalty or expense to the City of any kind whatsoever, except to the portions of annual payments
herein agreed upon for which funds shall have been appropriated.
6.
a. All other provisions of City Secretary Contract Number 65357 which are not expressly
amended herein, shall remain in full force and effect.
b. All terms in this First Amendment that are capitalized, but not defined, shall have the
meanings ascribed to those terms in City Secretary Contract Number 65357.
[SIGNATURES ON FOLLOWING PAGE]
City of Fort Worth, Texas
First Amendment to City Secretary Contract No. 65357
Page 3 of 5
IN TESTIMONY WHEREOF, the City and Developer have executed this First
Amendment to be effective on the date signed by the City's Assistant City Manager.
CITY OF FORT WORTH DEVELOPER
PMB TEAM RANCH DEVCO LLC,
A Texas limited liability company
Jesica McEachern By: PMB Team Ranch Manager LLC,
Assistant City Manager A Texas limited liability company,
Its Manager
Date: 09/29/2026
Recommended by:
Dwayne Hollars
Sr. Contract Compliance Specialist
Development Services
Approved as to Form & Legality:
Jessika Williams
Assistant City Attorney
M&C No. 26-0805
Date: 8/25/2026
Form 1295: 2026-1485099
4 nvan
Lp
f�pt R
ATTEST:
Pvo �=d
A aaQygz4saa
Jannette S. Goodall
City Secretary
City of Fort Worth, Texas
First Amendment to City Secretary Contract No. 65357
Page 4 of 5
Taylor aird (Sep 17, 2026 10:49:18 CDT)
K. Taylor Baird
Manager
Date: 09/17/2026
Contract Compliance Manager:
By signing, I acknowledge that I am the
person responsible for the monitoring and
administration of this contract, including all
performance and reporting requirements.
Kandice Merrick
Contract Compliance Manager
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
EXHIBIT A
36.
Cost Summary Sheet
Project Name: Rockbrook Offsite 24" WSIV Waterline
CFA No.: 26-0070 City Project No.: 106272
Items
A. Water and Sewer Construction
1. Water Construction
2. Sewer Construction
Water and Sewer Construction Total
IPRC No.: 25-0124
Developer's Cost City's Cost Total Cost
$ 1,042,634.71 $2,064,830.79 $ 3,107,465.50
$ - $ - $
$ 1,042,634.71 $2,064,830.79 $ 3,107,465.50
B. TPW Construction
1. Street
$
- $
- $ -
2. Storm Drain
$
- $
- $ -
3. Street Lights Installed by Developer
$
- $
- $ -
4. Signals
$
- $
- $ -
TPW Construction Cost Total
$
- $
- $ -
Total Construction Cost (excluding the fees)
Estimated Construction Fees:
C. Construction Inspection Service Fee
D. Administrative Material Testing Service Fee
E. Water Testing Lab Fee
F. Material Testing
G. Design Services
H. IPRC Plan Review Fees
I. CFA Application Fee
J. Easement Acquisition
Total Estimated Construction Fees:
TOTAL PROJECT COST
$ 1,042,634.71 $ 2,064,830.79 $ 3,107,465.50
$
12,445.31
$
29,742.19
$
42,187.50
$
1,463.44
$
3,497.36
$
4,960.80
$
179.21
$
428.29
$
607.50
$
-
$
61,944.92
$
61,944.92
$
104,385.75
$
249,464.25
$
353,850.00
$
1,541.21
$
3,683.23
$
5,224.44
$
740.08
$
1,768.67
$
2,508.75
$
17,700.00
$
42,300.00
$
60,000.00
$ 138,455.00 $ 392,828.91 $ 531,283.91
$ 1,181,089.71 $ 2,457,659.70 $ 3,638,749.41
Financial Guarantee Amount
Bond = 100% $ 3,107,465.50 I X
City of Fort Worth, Texas
First Amendment to City Secretary Contract No. 65357
Page 5 of 5
FORT WORTH.
MAYOR AND CO NCIL CO NICATJON
7.5.3 RO BROOK OFF -SITE WATER LINE OVERSIZING AGREEMENT CK
DATE: 08/25/26 M&C FILE NUMBER: M&C 26-0805
DEPARTMENT: TER
SUBJECT
(CD 3) Authorize Execution of a Community Facilities Agreement with City Participation in an
Amount Up to $2,457,659.70 with PMB Team Ranch Devco, LLC for the Construction of
Approximately 6,043 Linear Feet of Oversized Water Mains of Various Pipe Sizes for Anticipated
Future Growth in Southwest Fort Worth, Adopt Resolution Expressing Official Intent to Reimburse
Expenditures from Proceeds of Future Debt Project, and Adopt Appropriation Ordinance to Effect
a Portion of Water's Contribution to the Fiscal Years 2026-2030 Capital Improvement Program
RECO NDATION
It is recommended that the City Council:
1. Authorize execution of a Community Facilities Agreement with City participation in an
amount up to $2,457,659.70 with PMB Team Ranch Devco, LLC for the construction of
approximately 6,043 linear feet of oversized water mains of various pipe sizes for
anticipated future growth in southwest Fort Worth;
2. Adopt the attached resolution expressing official intent to reimburse expenditures with
proceeds of future enterprise fund debt for the Community Facilities Agreement-
Rockbrook Off -Site 24 -inch Water Line; and
3. Adopt the attached appropriation ordinance adjusting estimated appropriations in the
Water and Sewer Commercial Paper Fund by decreasing estimated appropriations in
the Commercial Paper project (City Project No. UCMLPR) in the amount of $2,767,385.00
and increasing estimated appropriations in the Community Facilities Agreement Bucket
programmable project (City Project No. P00001) by the same amount for the purpose of
funding the Community Facilities Agreement- Rockbrook Off -Site 24 -inch Water Line
project (City Project No. 106272) and to effect a portion of Water's contribution to the
Fiscal Years 2026-2030 Capital Improvements Program.
DISCUSSION
The purpose of this Mayor and Council Communication (M&C) is to authorize execution of a
Community Facilities Agreement (CFA) with PMB Team Ranch Devco, LLC (Developer) with City
participation in amount up to $2,457,659.70.
1 of 4
FORT WORTH.
Developer is constructing the Rockbrook development project located south of Interstate -
Highway (IH) 20 and along Farm to Market Road (FM) 2871. The Developer is required to extend
the water line to serve the proposed development. The Water Department is requesting to
oversize approximately 4,161 linear feet (LF) of water line from 12 -inches to 24 -inches and 1,882
LF from 8 -inches to 24 -inches for anticipated future growth in the area. The Rockbrook Off -
Site 24 -inch Water Line project is assigned City Project No. 106272 and Accela System Record
Infrastructure Plan Review Center (IPRC) 25-0124.
In accordance with Chapter 212, Subchapter C of the Texas Local Government Code, the City's
participation in the contract is exempt from competitive bidding requirements because the
contract is for oversizing public improvements being constructed by the Developer, the
Developer will execute a performance bond to cover the total project cost, including all of the
City's cost participation, and the City's cost participation will be determined in accordance with
the City's CFA unit price ordinance.
The City's cost participation in the oversizing of the water line is estimated to be an amount up
to $2,457,659.70 as shown in the table below. Payments to the Developer are estimated to be:
$2,064,830.79 for construction costs, $3,683.23 for IPRC Plan Review Fees, $1,768.67 for the CFA
Application fee, $42,300.00 for Easement Acquisition, $61,944.92 for material testing costs and
$249,464.25 for design services costs. The remaining City Participation in the estimated
amount of $33,667.84 will cover the City's portion of inspection fees, administrative material
testing fees, and water lab testing fees. An additional $309,724.62 in contingency funds will
cover the City's portion of any change orders.
The following table shows the cost -sharing breakdown for the project between all parties:
Public Improvements
Developer
Cost
City Cost
Total Cost
Water Improvements
$1,042,634.71
$2,064,830.79
$3,107,465.50
Contingency
$0.00
$309,724.62
$309,724.62
Construction Fees
A. Construction Inspection Fee
$12,445.31
$29,742.19
$42,187.50
B. Admin Material Testing Fee
$1,463.44
$3,497.36
$4,960.80
C. Water Lab Fee
$179.21
$428.29
$607.50
D. Material Testing Cost- City's cost
$0.00
$61,944.92
$61,944.92
E. Design Services
$104,385.75
$249,464.25
$353,850.00
F. IPRC Plan Review Fees
$1,541.21
$3,683.23
$5,224.44
G. CFA Application Fee
$740.08
$1,768.67
$2,508.75
2 of 4
FORT WORTH.
H. Easement Acquisitions
$17,700.00
$42,300.00
$60,000.00
Total Cost
$1,181,089.71
$2,767,384.32
$3,948,474.03
The reimbursement of the City participation is not a lump sum amount and may be less than
the stated amount depending upon the actual quantities and unit prices from the Notice of
Final Completion package, commonly referred to as the Green Sheet package.
It is the practice of the Water Department to appropriate its Capital Improvement Program
(CIP) plan throughout the Fiscal Year (FY), instead of within the annual budget ordinance, as
projects commence, additional funding needs are identified, and to comply with bond
covenants. The actions in the M&C will appropriate funds in support of the Water's portion of
the City of Fort Worth's Fiscal Years 2026-2030 CIP.
Available cash within the Water and Sewer portfolio and the City's portfolio along with the
appropriation authority authorized under the Callable Commercial Paper Program (CP) will be
used to provide interim financing for this project until debt is issued. Once debt associated with
this project is sold, bond proceeds will be used to reimburse the Water and Sewer portfolio and
the City's portfolio in accordance with the attached Reimbursement Resolution. Funding is
available in the Commercial Paper project within the Water & Sewer Commercial Paper Fund
for the purpose of funding the CFA- Rockbrook 24 -inch Water Line - offsite project.
Funding for the CFA- Rockbrook 24 -inch Water Line - offsite is as depicted in the table below:
Existing
Additional
Fund
Appropriations
Appropriations
Project Total
W&S Commercial
Paper - Fund 56032
$0.00
$2,767,385.00
$2,767,385.00
Total
$0.00
$2,767,385.00
$2,767,385.00
This project is located in COUNCIL DISTRICT 3.
FISCAL INFORMATION/CERTIFICATION
The Director of Finance certifies that funds are currently available in the Commercial Paper
project within the W&S Commercial Paper Fund and upon approval of the above
recommendations and adoption of the attached appropriation ordinance, funds will be
available in the W&S Commercial Paper Fund for the CFA-Rockbrook-24 WL - offsite project
3 of 4
FORT WORTH.
to support the execution of the agreement. Prior to an expense being incurred, the Water
Department has the responsibility of verifying the availability of funds.
SUBMITTED FOR CITY MANAGER'S OFFICE BY: Jesica L. McEachern, # 5804
ORIGINATING BUSINESS UNIT HEAD: Christopher Harder, #5020
ADDITIONAL INFORMATION CONTACT: Suby Varughese, #8009
Elynn Ray, #7856
ATTACHMENTS
1. Map - Rockbrook Water Line Oversizing [7.5.3.1 - 1 page]
2. Ordinance Appropriation (R3) - Rockbrook Water Line Oversizing [7.5.3.2 - 2 pages]
3. Resolution R 2 Rockbrook Water Line Oversizing [7.5.3.4 - 1 page]
4. CONFIDENTIAL - FID Table - Rockbrook Water Line Oversizing [7.5.3.6 - 1 page]
5. CONFIDENTIAL - Project Budget Summary - Rockbrook Water Line Oversizing [7.5.3.7 - 1
page]
6. CONFIDENTIAL - Funds Availability - Rockbrook Water Line Oversizing [7.5.3.8 - 1 page]
7. CONFIDENTIAL - Form 1295 Certificate - PMB Team Ranch Devco [7.5.3.9 - 1 page]
4 of 4
FORT WORTH.
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: PMB TEAM RANCH DEVCO LLC
Subject of the Agreement:
CFA - Amendment
M&C Approved by the Council? * Yes 8 No 0
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes 8 No ❑ 65357
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 8 No ❑
If unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 8 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date:
If different from the approval date.
Expiration Date:
If applicable.
Is a 1295 Form required? * Yes 8 No 0
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 106272
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 8 No ❑
Contracts need to be routed for CSO processing in the following order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.