HomeMy WebLinkAbout065244-CO1 - Construction-Related - Contract - McClendon Construction Company, Inc.CSC No. 65244-CO1
FORT WORTH.
City of Fort Worth
Change Order Request
Project Name Forest Hill Drive and Royal Crest Drive Intersection Improvements
Client Project #(s) 103308
Project
Paving and Traffic Signal Improvements
City Sec # 65244
Contractor McClendon Construction Company, Inc. Change Order #1 1 Date 8/10/2026
City Project Mgr. Keith Wright City Inspector Sergio Garcia
Dept.
TPW
Totals
Contract Time
(CD)
Original Contract Amount
$939,465.50
$939,465.50
180
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
$939,465.50
$939,465.50
180
Amount of Proposed Change Order
$48,898.00
$48,898.00
14
Revised Contract Amount
$988,363.50
$988,363.50
194
Original Funds Available for Change Orders
$0.00
Remaining Funds Available for this CO
$0.00
Additional Funding (if necessary)
$48,898.00
$48,898.00
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 5.20%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
$1,174,331.88
JUSTIFICATION (REASONS) FOR CHANGE ORDER
This change order awards the bid alternate to remove the hydrated -lime -treated subgrade from the proposed pavement section and use flexible base in its place. It also
provides additional traffic -control measures and construction phasing revisions to maintain safer and more reliable access through the Forest Hill Drive and Royal Crest
Drive intersection during construction.
The original traffic -control approach included a roadway and intersection closure with all traffic detoured around the construction area. Following coordination with the City,
the contractor, and the project team, this concept was reconsidered, and a more favorable approach was developed to maintain traffic through the project area while better
accommodating Uplift Ascend Preparatory School and Roger E. Souder Elementary School operations, local traffic, and peak -hour travel demands.
The revised approach will maintain two-way traffic during school drop-off and pick-up periods and daily peak traffic hours. One-way traffic control will be limited to off-peak
periods, with southbound traffic maintained through the construction area and northbound traffic detoured. All one-way traffic -control operations will be removed outside of
working hours. The revisions also include temporary pavement along the west side of the roadway and low -profile barriers within the construction area.
These improvements are beyond the traffic -control requirements included in the original bid documents and require additional temporary pavement, barriers, traffic -control
devices, labor, and associated construction coordination. The revised plan will reduce roadway closure impacts, improve access for the schools and surrounding
community, support safer traffic operations, and allow the contractor to complete the intersection improvements with less disruption to the traveling public.
We have compared these prices to recent bids and the TXDOT website and we believe they're reasonable. CSC 65439: N Tarrant Parkway and N Beach Street
Intersection Improvements (CPN103309); Flexible Base: CSC 62707 2024 Paving Improvements Unit Price Construction Contract (The Fain Group, Inc.); Barriers:
TxDOT's weighted average unit prices for bids let within the last three months were used to compare the proposed barrier prices against TxDOT bid item 512-7081: PTB
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full (both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below
acknowledges that he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and
reporting requirements.
I McClendon Construction Comoanv. Inc. I Dan McClendon 1 ,. qtr,≥ 109/09/2026 1
Inspector/Inspection Supervisor
Date
Project and Contract Compliance Manager
Date
09/09/2026
09/09/2026
Program Manager
Date
Senior Capital Project Officer
Date
09/11/2026
-j
09/15/2026
(Dept)
Date
Director, Contracting Department (Dept)
Date
PAW
09/18/2026-7
09/21/2026
na ,,
Date
Assista ager
Date
4lofec
—lu slay(s 21.20 con
09/21/2026
4�C?
10/02/2026
Council Action (if required)
ATTEST:
Jannette Goodall, City Secretary
FfORTn�Cd
p=jg a�9�0,
pqq�`g I'd
M&C Number M&C Date Approved I
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT WORTH City of Fort Worth
Change Order Additions
Project Name Forest Hill Drive and Royal Crest Drive Intersection Improvements I City Sec # I 65244
Client Project # I 103308
Contractorl McClendon Construction Company, Inc. PM Keith Wright Inspector Sergio Garcia
Change Order Submittal # 1 Date 8/10/2026
ADDITIONS
ITEM
DESCRIPTION
DEPT
Qty
Unit
Unit Cost
Total
BA-i -3
3211.0113Flexible Base, Type
W
850.00000000
SY
$34.00,
0 .
11-6
0241.1100 Remove Asphalt Pvmt
TPW
277.00000000
SY
$16.50
$4,570.5U
111-8
3212.0302 2.5" Asphalt Pvmt Type D
TPW
277.00000000
SY
$27.00
$7,479.00
VII -1
3217.0102 6" SLD Pvmt Marking HAS (Y)
TPW
1,063.00000000
LF
$3.00
$3,189.00
VII -2
3217.0101 6" SLD Pvmt Marking HAS (W)
TPW
1,319.00000000
LF
$3.00
$3,957.00
VII -9
3217.2103 REFL Raised Marker TY II -A -A
TPW
30.00000000
EA
$12.00
CO -1-1
3211.0112 6" Flexible Base, Type D, OR -1 (Temporary Pavement)
TPW
277.00000000
SY
$45.00
$12,465.00
CO -1-2
Furnish, Install, Remove Traffic Barrier (Portable Water -Filled)
TPW
145.00000000
LF
$69.50
$10,077.50
Change Order Additions Page 2 of 5
Change Order Additions Page 3 of 5
FORT WORTH
City of Fort Worth
Change Order Deletions
Project Name Forest Hill Drive and Royal Crest Drive Intersection Improvements I City Sec # 65244
Client Project # 103308
Contractor McClendon Construction Company, Inc. PM Keith Wright Inspector Sergio Garcia
Change Order Submittal # 0 Date 8/10/2026
DELETIONS
ITEM
DESCRIPTION
DEPT
Qty
Unit
Unit Cost
Total
BA-1-i3BA-i-i
3211.0400Hydrated ime
TPW
20.0000000L
TN
$425.00
$8,500.00
BA -1-2
3211.0502 8" Lime Treatment
TPW
850.00000000
SY
$16.00
Lrrange order ueletions -'age 4 orb
Change Order Deletions Page 5 of 5
FORT WORTH.
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE: McClendon Construction Company, Inc.
Construction Contract — Change Order #1
M&C: 26-0325 CPN: 103308 CSO: 65244 DOC#: 1
Date: 9/8/2026
To:
Name
Department
Initials
Date Out
1.
Dan McClendon
Vendor - signature
"'
09/09/2026
2.
Tiffany Baltzgar
TPW - review
T
09/09/2026
3.
Keith Wright
TPW - signature
K�
09/09/2026
4.
Chad Allen
TPW - signature
Chad Allen
09/11/2026
5.
Lissette Acevedo
TPW - signature
c
09/15/2026
6.
Patricia Wadsack
TPW - signature
PL W
09/18/2026
7.
Lauren Prieur
TPW - signature
Lauren Ple
09/21 /2026
8.
Doug Black
Legal - signature
oolas Black
09/21/2026
9.
Jesica McEachern
CMO - signature
10/02/2026
10.
Jannette Goodall
CSO - signature
_ netteGoodall
10/02/2026
12.
TPW Contracts
TPW
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any
and all City Departments requesting City Manager's signature for approval MUST BE ROUTED
TO THE APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip,
Jay will review and take the next steps.
NEEDS TO BE NOTARIZED: ❑YES HNo
RUSH: ❑YES No SAME DAY: ❑YES No
ROUTING TO CSO: EYES ❑No
Action Required:
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File
Return To: TPWContracts(ci/FortWorthTexas.gov at ext. 7233 for pick up when completed.
Thank you!
NEXT DAY: ❑YES ❑No
❑ Attach Signature, Initial and Notary Tabs
FORT WORTH®
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: McClendon Construction Company, Inc.
Subject of the Agreement: Change Order No. 1 to CSC No. 65244, a Contract for the Forest Hill
Drive and Royal Crest Drive Intersection Improvements Project
M&C Approved by the Council? * Yes El No Ill
If so, the MSC must be attached to the contract.
Is this an Amendment to an Existing contract? Yes El No ❑■
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes N No ❑
If unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 9 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date:
Expiration Date:
If different from the approval date. If applicable.
Is a 1295 Form required? * Yes El No R
*If so, please ensure it is attached to the approving MSC or attached to the contract.
Project Number: If applicable. 103308
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 0 No 0
Contracts need to be routed for CSO processing in the following gorder:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be