HomeMy WebLinkAbout26-28767 - City Council - OrdinanceORDINANCE 26-28767
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER AND SEWER CAPITAL PROJECTS FUND
IN THE AMOUNT OF $5,660,817.00, TRANSFERRED FROM AVAILABLE
PAYGO FUNDS IN THE WATER AND SEWER FUND, FOR THE PURPOSE OF
FUNDING THE SANITARY SEWER REHABILITATION CONTRACT 116
PROJECT (CITY PROJECT NO. 102787); PROVIDING FOR A SEVERABILITY
CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF PRIOR
ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT HEREWITH;
AND PROVIDING AN EFFECTIVE DATE.
NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF
FORT WORTH, TEXAS THAT:
SECTION 1.
The budget of the City of Fort Worth for Fiscal Year 2025-2026, as enacted by Ordinance 27979-
09-2025, as amended, is hereby further amended by increasing estimated receipts and appropriations in the
Water and Sewer Capital Projects Fund in the amount of $5,660,817.00, transferred from available PayGo
funds in the Water and Sewer Fund, for the purpose of funding the Sanitary Sewer Rehabilitation Contract
116 project (City Project No. 102787).
SECTION 2.
Should any portion, section or part of a section of this ordinance be declared invalid, inoperative or
void for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way
impair the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions
shall be and remain in full force and effect.
SECTION 3.
This ordinance shall be cumulative of Ordinance No. 27979-09-2025 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions
of said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Douglas Black (Sep 28, 2026 17:33:11 CDT)
Douglas W. Black Jannette S. Goodall
Sr. Assistant City Attorney City Secretary
ADOPTED: September 15.2026
EFFECTIVE: September 15.2026
44d�l1:
1:t�
ao�°FORr��a
cLo A -O
Pvo 8X
0 oy
O T�
d OOOO
�at1 1EXPi
Ordinance No. 26-28767
Page 1 of I
MAYOR AND COUNCIL COMMUNICATION MAP
60SS RC 116 -WOODY
_ � �•�,� tiIii III I
U_
lily I��
DIbTRI(!fl18
1111
1 11 Fo
Woh
• 1
11� 5
i..L
MAA.w.uw�+
II
11 •
•
,•
• *LliI'
v 7-
Q � 0
I i 'rilk:' I m '_
•o- - - • � I' �� „ ilea
r¢ ac ta•
77l� 4.b 1 ii. YF r
ulo»F. iwn•}
1 .
_ I� Ii■ w • '
7 �r
F.
�r ��� �� -� .fie �•. ®__
0 0 1
MAYOR AND COUNCIL COMMUNICATION MAP
60SS RC 116 -WOODY
AMSPOKER AVE �
E MALTA AVE.-. ; '� • ^ � . � ",M .
_ HATHCOX AVE ;_'' •, 4'"?
N
wo o BRITTON AVE
w O
LL '-
EuGENEAvETTh
E ANTHONY ST JPRINCE ST
E SEMINARY OR
5 w sf GP _ e
Pte. +, z.. s . •' - .fir
AHARA
E PJ� A y .SAX
PURL ' ',.
:' �_ T � y � •�
1NP`�'
CARD 'PJ� • � -
E F 1
NpR '..�• — UGC, ,
` �; y'%, '�: t It-- x. s•}.�.—
• 4 � _
FORT WORTHo ,,�;, az.
ter..
MAYOR AND COUNCIL COMMUNICATION MAP
60SS RC 116 -WOODY
MAYOR AND COUNCIL COMMUNICATION MAP
60SS RC 116 -WOODY
Y
(-a'
W
U)
W
Ow
� R
11 � fY 1 :
•
-- rjatk.
•
" L ±JJ
E-LANCASTER'AVE '
p J w p.., : U) - Y I
VIRGIN IA LN
�
FORT WORTH®
MAYOR AND COUNCIL COMMUNICATION MAP
60SS RC 116 -WOODY
FORT WORTH.
MAYOR AND COUNCIL COMMUNICATION
7.1.32 WOODY CONTRACTORS, INC. CONSTRUCTION CONTRACT FOR SANITARY SEWER
REHABILITATION CONTRACT 116 PROJECT
DATE: 09/15/26 M&C FILE NUMBER: M&C 26-0895
DEPARTMENT: WATER
SUBJECT
(CD 8, CD 9, and CD 11) Authorize Execution of a Contract with Woody Contractors, Inc., in the
Amount of $4,980,914.30 for Sanitary Sewer Rehabilitation Contract 116 Project and Adopt
Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal Years 2026-
2030 Capital Improvement Program
RECOMMENDATION
It is recommended that the City Council:
1. Authorize execution of a contract with Woody Contractors, Inc., in the amount of
$4,980,914.30 for Sanitary Sewer Rehabilitation Contract 116 project; and
2. Adopt the attached appropriation ordinance increasing estimated receipts and
appropriations in the Water and Sewer Capital Projects Fund in the amount of
$5,660,817.00, transferred from available PayGo funds in the Water and Sewer Fund, for
the purpose of funding the Sanitary Sewer Rehabilitation Contract 116 project (City
Project No. 102787) and to effect a portion of Water's contribution to the Fiscal Years
2026-2030 Capital Improvement Program.
DISCUSSION
The purpose of this Mayor & Council Communication (M&C) is to authorize execution of a
construction contract with Woody Contractors, Inc., in the amount of $4,980,914.30 for the
replacement of cast iron water and/or deteriorated sanitary sewer mains as indicated on the
following streets:
Street From To Scope of Work COUNCIL
DISTRICT
Tucker Street S. Virginia Luxton Street Water 8
Avenue
Berke Road Broadus Street Seminary Drive Water/ Sewer 8
1 of 4
FORT WORTH.
Pate Drive
Killian Street
Hardeman
Water/Sewer 11
Street
Briarwood Lane
Jenson Road
Wilson Road
Water/Sewer 11
Carter Park
400 feet South
400 feet North of
Water/Sewer 8
Drive
of Arrowwood
Broadus
Drive
Street/Carter
Park Drive
intersection
Alley between
260 feet North of
North 305 feet
Sewer 8
Berke Road and
Broadus Avenue
Sahara Place
Oakland
200 feet North of
North 900 feet
Sewer 11
Boulevard
Lancaster
Avenue
Easement South
170 feet North of
East 385 feet
Sewer 9
of Brown Drive
Oak Grove Road
Easement east
200 feet North of
North 700 feet
Sewer 11
of Sargent
Lancaster
Street
Avenue
Easement east
Avenue G
South 350 feet
Sewer 8
of Cobb Park
Drive
Easement South
612 feet South of
East 250 feet
Sewer 11
of Meadowbrook
the
Drive
Meadowbrook
Drive/Sargent
Street
Intersection
Easement North
200 feet North of
West 500 feet
Sewer 11
of Lancaster
the Lancaster
Avenue
Avenue/Oakland
Boulevard
intersection
2 of 4
FORT WORTH.
Additionally, asphalt pavement rehabilitation will be conducted on all the roadways curb to
curb subsequent to the water and sanitary sewer main replacement.
The project was advertised for bids on June 3, and June 10, 2026, in the Fort Worth Star -
Telegram. On July 2, 2026, the following bids were received:
Bidder
Woody Contractors, Inc.
William J. Schultz, Inc. dba
Circle C Construction
Company
Jackson Construction, Ltd.
Western Municipal
Construction of Texas, LLC
Blackrock Construction
Venus Construction Co, Inc
Amount
Time of Completion
$4,980,914.30 480 Calendar Days
$ 5,770,779.00
$5,997,008.55
$6,526,016.00
$ 6,615,287.50
$6,653,050.20
Small Business (SB) Goal - In accordance with the City's Small Business Ordinance, the City
has established a 30% Small Business goal for this solicitation/contract. Woody Contractors,
Inc. is a certified small business and has committed to 57% of the total contract award, thereby
meeting the requirements of the City's Small Business Ordinance.
In addition to the contract amount, $430,857.00 (Water: $179,268.00, Sewer: $251,589.00) is
required for project management, material testing, and inspection. Project contingencies are
provided in the amount of $249,045.00 (Water: $102,943.00; Sewer: $146,102.00).
The sanitary sewer component of this project is part of the Sanitary Sewer Overflow Initiative
Program of the Water Department. Approximately 2,756 linear feet of cast iron water pipe and
7,069 linear feet of sanitary sewer pipe will be removed/replaced or rehabilitated as part of this
project.
It is the practice of the Water Department to appropriate its Capital Improvement Program
(CIP) plan throughout the Fiscal Year, instead of within the annual budget ordinance, as
projects commence, additional funding needs are identified, and to comply with bond
covenants.
3 of 4
FORT WORTH.
Funding is budgeted in the Transfer to Water/Sewer account within the Water & Sewer
operating budget for the purpose of funding the Sanitary Sewer Rehabilitation Contract 116
project within the Water & Sewer Capital Projects Fund.
Appropriations for the Sanitary Sewer Rehabilitation Contract 116 project are as depicted below:
Fund
WAS Capital Projects
- Fund 56002
Project Total
Existing
Appropriations
$ 530,444.00
$ 530,444.00
*Numbers rounded for presentation purposes.
Additional
Appropriations
The project is located in COUNCIL DISTRICTS 8, 9 and 11.
This contract requires a Form 1295.
FISCAL INFORMATION/CERTIFICATION
$ 5,660,817.00
$ 5,660,817.00
Project Total*
$6,191,261.00
$6,191,261.00
The Director of Finance certifies that funds are currently available in the Water & Sewer Fund
and upon approval of the above recommendations and adoption of the attached
appropriation ordinance, funds will be available in the current capital budget, as appropriated,
in the W&S Capital Projects Fund for the SS Rehab Contract 116 project to support the execution
of the contract. Prior to an expense being incurred, the Water Department has the responsibility
of verifying the availability of funds.
SUBMITTED FOR CITY MANAGER'S OFFICE BY:
ORIGINATING BUSINESS UNIT HEAD:
ADDITIONAL INFORMATION CONTACT:
ATTACHMENTS
Jesica L. McEachern, # 5804
Chris Harder, # 5020
Dena Johnson, #
1. Map - Sewer Rehabilitation Contract 116 [7.1.32.7 - 5 pages]
2. Ordinance Approp (R2) - Sewer Rehabilitation Contract 116 [7.1.32.8 - 2 pages]
4 of 4