HomeMy WebLinkAbout062401-CO1 - Construction-Related - Contract - McClendon Construction Company, Inc.CSC No. 62401-CO1
Foin''k Otvn I.
City of Fort Worth
Change Order Request
Project Name FY 2018 Railroad Safety Improvements Trinity Railway Express at Haltom Rd City Sec # 62401
Client Project #(s) 104003
Project Design of railroad safety improvements at the Haltom Rd Trin' Railway Express crossing, which consists of paving, signing, area li lighting andpaint stnping
Description 9 p p 9 p g9 9 p 9
Contractor McClendon Construction Company, Inc. Change Order# I Date 9/10/2026
City Project Mgr. I Paul D. Clutts, PE City Inspector Russell Rogers
Contract Time
Dept. TPW Totals (CD)
Original Contract Amount $891,052.50 $891,052.50 96
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date 1891.052.50 $891,052.50 96
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 0.00%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) $1,113,815.63
ER
This change order accounts for changes in the Traffic Control Plan since the project was originally bid that became necessary during the Street -Use permitting process. This
change order is specifically required by TxDOT since Federal -aid funds are being used for construction.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements.
Contractor's Company Name
Contractor Name Contract Si natur
Date
McClendon Construction Company, Inc.
Justin Blair Justin Blair (Sep 10, 202614:09:48 CDT)
Inspector/Inspection Supervisor
Date
Project and Contract Compliance ManageI
Date
09/10/2026
-
09/10/2026
M er
Date
Senior Capital Project Officer
Date
09/25/2026
09/30/2026
be .
Date
Director, Contracting De artme
Date
10/06/2026
_A7
10/06/2026
ssistant City Attorney
Date
Assistant City Manager
Date
oa g1 1 202611245/CDT
10/07/2026
L °t,'
10/19/2026
ion (if required)
M&C Number
FORT4nC
ATTEST: p;at;,o°std
�*aos Zd
Jannette Goodall, City Secretary°g* p
aann�6gaa
M&C Date Approved 0
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FOur'rWtii to City of Fort Worth
Change Order Additions
Project Name FY 2018 Railroad Safety Improvements Trinity Railway Express at Haltom Rd I City Sec # I 62401
Client Project # 104003
Contractor McClendon Construction Company, Inc. PM Paul D. Clubs, PE Inspector Russell Rogers
Change Order Submittal# 0 Date 9/10/2026
ADDITIONS
ITEM DESCRIPTION DEPT city Unit Unit Cost total
$0.00
TPW $0.00
Sub Total Additions $0.00
Change Order Additions Page 2 of 3
Flax r V4u a t, City of Fort Worth
Change Order Deletions
Project Name I FY 2018 Railroad Safety Improvements Trinity Railway Express at Haltom Rd I City Sec # 62401
Client Project# I 104003
Contractor McClendon Construction Company, Inc. PM Paul D. Clutts, PE Inspector Russell Rogers
Change Order Submittal# 1 )ate 9/10/2026
Change Order Deletions Page 3 of 3
c
H1ilON
H
o z rc m -orc�
a "
no mno
b LLL�i
3m3
n3
Wc
W s o
z
-
a m� w��+z
o m�m�'am
w
�
X
tsl
O,G
a�i � 2wrc�aF
o I�m
o <w S H H
<w m
133lS 1SL
�1
6�
!
+QFK'Z e
`MP 8 g
J
�
L
133N H18Z 3N'
£Bl AMH 31V1O
nS
O pQ
w�
oow
�o
p�o
�o
Nd Zt: 9ZOZ/ZZ/L :O3AVS 15V1
OMO(1IV13O) NVId NOO130 \S133HS\OVON W011VH IV 3NL\OOVO\rvO11VH-tl300HM-ZZ-OM-MdJ-LLZ9 LO L90\Old! MLi\ N 'NOUVJ0l
Wd ZT:E 9ZOZ/ZZ/L 3LV0 1015
NANVVVO 'SNINMVH AB O3llOld
104003-CNCO-FY CO -FY 2018 Railroad Safety
Improvements Trinity Railway Express at
Haltom Rd - Construction CO #1 Request
Final Audit Report 2026-09-14
Created: 2026-09-10
By: Andrea Munoz (Andrea.Munoz@fortworthtexas.gov)
Status: Canceled / Declined
Transaction ID: CBJCHBCAABAAolByl7HuHeYkLKZc6d6lv7FzGGAO83A2
"104003-CNCO-FY 2018 Railroad Safety Improvements Trinity
Railway Express at Haltom Rd - Construction CO #1 Request"
History
Li Document created by Andrea Munoz (Andrea.Munoz@fortworthtexas.gov)
2026-09-10 - 4:21:31 PM GMT- IP address: 204.10.90.100
Document emailed to LaKeshia Lynch (LaKeshia.Lynch@fortworthtexas.gov) for filling
2026-09-10 - 4:44:29 PM GMT
Document emailed to Justin Blair(jblair@mcclendonconstruction.com) for signature
2026-09-10 - 4:44:29 PM GMT
Document emailed to Russell Rogers (Russell.Rogers@fortworthtexas.gov) for signature
2026-09-10 - 4:44:29 PM GMT
Document emailed to Paul Clutts(Paul.Clutts@fortworthtexas.gov) for signature
2026-09-10 - 4:44:30 PM GMT
Email viewed by LaKeshia Lynch (LaKeshia.Lynch@fortworthtexas.gov)
2026-09-10 - 4:44:38 PM GMT- IP address: 51.54.38.120
`1 Email viewed by Russell Rogers (Russell.Rogers@fortworthtexas.gov)
2026-09-10 - 4:46:58 PM GMT- IP address: 166.198.250.120
Document e -signed by Russell Rogers (Russell.Rogers@fortworthtexas.gov)
Signature Date: 2026-09-10 - 4:53:39 PM GMT - Time Source: server- IP address: 166.198.250.120 - Signature Appearance Selected:
MOBILE_DRAW
FORTWORTH.Powered by
I Adobe
Acrobat Sign
=) Email viewed by Paul Clutts(PauI.Clutts@fortworthtexas.gov)
2026-09-10 - 4:54:54 PM GMT- IP address: 204.10.90.100
Document e -signed by Paul Clutts (Paul.Clutts@fortworthtexas.gov)
Signature Date: 2026-09-10 - 4:55:58 PM GMT - Time Source: server- IP address: 204.10.90.100 - Signature Appearance Selected: IMAGE
I Email viewed by Justin Blair(jblair@mcclendonconstruction.com)
2026-09-10 - 6:55:05 PM GMT- IP address: 47.37.93.50
fro Document e -signed by Justin Blair(jblair@mcclendonconstruction.com)
Signature Date: 2026-09-10 - 7:09:48 PM GMT - Time Source: server- IP address: 47.37.93.50 - Signature Appearance Selected: TYPE
1_i , Form filled by LaKeshia Lynch (LaKeshia.Lynch@fortworthtexas.gov)
Form filling Date: 2026-09-11 - 2:25:16 PM GMT - Time Source: server- IP address: 204.10.90.100 - Signature Appearance Selected: TYPE
'.. Document emailed to Chad Allen (Chad.Allen@fortworthtexas.gov) for signature
2026-09-11 - 2:25:19 PM GMT
Document declined by Chad Allen (Chad.Allen@fortworthtexas.gov)
Decline reason: Paul, we need to route this with the TxDOT change order attached and the revised plan sheets attached. I will send you an
example.
2026-09-14 - 8:55:49 PM GMT- IP address: 208.184.124.181
FORTWORTHPowered by
Adobe
Acrobat Sign
FORT WORTH®
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE:
M&C:
FY 2018 Railroad Safety Improvements Trinity Railway
Express at Haltom Rd — Construction CO #1 Request
CPN: 104003 CSO: 62401 DOC#: 1
Date:
To:
Name
Department
Initials
Date Out
1.
LaKeshia Lynch
TPW - initial
09/11/2026
2.
Justin Blair
Vendor - initial
?
09/10/2026
3.
Russell Rogers
TPW - initial
R�•
09/10/2026
4.
Paul Clutts
TPW - initial
09/10/2026
5.
Chad Allen
TPW - initial
Chad Allen
09/25/2026
6.
Lissette Acevedo
TPW - initial
A
09/30/2026
7.
Patricia Wadsack
TPW AD - initial
PLW
10/06/2026
8.
Lauren Prieur
TPW Director - initial
.a 9 p feur
10/06/2026
9.
Doug Black
Legal - initial
DouglasBlack
10/07/2026
10.
Jesica McEachern
CMO - initial
CA
10/19/2026
11.
Jannette Goodall
CSO - initial
10/20/2026
12.
TPW Contracts
TPW
CC: Program Manager, Sr. CPO, TPW BSPAP Recon Team, TPW Records Room, TPW Contracts
ALSO List: Bus Sppt: LaKeshia Lynch; Prg Mgr: Chad Allen; Sr CPO: Lissette Acevedo
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all
City Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, Jay will review and
take the next steps.
NEEDS TO BE NOTARIZED: ❑YES No
RUSH: RYES No SAME DAY: ❑YES [I]No NEXT DAY: [I]YES ❑No
ROUTING TO CSO: ❑YES ❑No
Action Required:
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Return To: Please notify TPWContracts(afortworthtexas.gov for pickup when complete. Call ext.
7233 or ext. 8363 with questions. Thank you.
FORT WORTH®
City Secretary's Office
Contract Routing & Transmittal Slip
Contractor's Name: McClendon Construction Company, Inc.
Subject of the Agreement:
This change order accounts for changes in the Traffic Control Plan since the project was originally bid that
became necessary during the Street -Use permitting process. This change order is specifically required by TxDOT
since Federal -aid funds are being used for construction.
M&C Approved by the Council? * Yes ❑ No 8
If so, the M&C must be attached to the contract.
Is this an Amendment to an Existing contract? Yes ❑ No 8
If so, provide the original contract number and the amendment number.
Is the Contract "Permanent"? *Yes 0 No 0
If unsure, see back page for permanent contract listing.
Is this entire contract Confidential? *Yes ❑ No 0 If only specific information is
Confidential, please list what information is Confidential and the page it is located.
Effective Date:
Expiration Date:
If different from the approval date. If applicable.
Is a 1295 Form required? * Yes ❑ No 0
*If so, please ensure it is attached to the approving M&C or attached to the contract.
Project Number: If applicable. 104003
*Did you include a Text field on the contract to add the City Secretary Contract (CSC)
number? Yes 8 No ❑
Contracts need to be routed for CSO processing in the following order:
1. Katherine Cenicola (Approver)
2. Jannette S. Goodall (Signer)
3. Allison Tidwell (Form Filler)
*Indicates the information is required and if the information is not provided, the contract will be
returned to the department.