City of Fort Worth CITY MWARYW
Change Order Request Col .T Ct Non 14/SS a71[� :j--
Change Order No. Date TPW Project No. Funding(FAC)
1 (one) 18/20/11 GC04 539120 0246000
Facility and Project Description City Secretary Contract No.
Install Replacement Chillers Fort Worth Convention Center 41552
ORIGINAL CONTRACT AMOUNT................................................................ $ 658,066
EXTRASTO DATE..................................................................... $ 0
CREDITSTO DATE.................................................................... $ 0
CONTRACTCOST TO DATE..................................................................................................
$ 658
AMOUNT OF PROPOSED CHANGE ORDER................................................... ...................... $ 7,507
REVISEDCONTRACT AMOUNT............................................................................................. $ 55 73 66
ORIGINAL FUNDS AVAILABLE FOR CHANGE ORDERS............................................................ $ 57,434
REMAINING FUNDS AVAILABLE FOR CHANGE ORDERS......................................................... $ 49,927
ADDITIONAL FUNDING (IF NECESSARY)................................................................................ 0
IN ACCORDANCE WITH THIS CHANGE ORDER, THE CONTRACTOR SHALL:
Provide all labor and materials as per the attached PCR:
Furnish and install new 10 inch check valve and chiller pump insulation ADD $ 7,507.00
Total Add $ 7,507.00
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time
and money)for all costs arising out of or incidental to,the above Change Order
Contractor's Name
Johnson Controls Inc.
Original Cut-ad Time Additlonal Approved Time To Date Approved Control Time To Date Additional Time For Thls Change Order
170 cd 0 cd 170 cd 0 cd
Contractor-Johnson Controls,Inc Date IZM
Date
O n i t /!
Choi,Architectural Services Division Date D or,T nsportatlon and Public works Date
Yzs/-xv cow
Project Architect at Date
C'
Date -Required)
NO M&C R QUIRED
File 16.0 .4
• U
C c
Piojea men
W A r t y Hendrix, City gam, P .4 rot=1?�� `� 43 J J T OFFICIAL RECORD i ICY
�a CITY SECRETARY
TPW Facilities Managsmenfblant� y
FT WORTH, TX
Change Order Form(12/19/01) --
Y
9'
I
Johnson Controls—Building Efficiency ,
7461 Airport Freeway Johnson
�
Richland Hills,TX 76118
Phone:866-589-9413 Controls
FAX: 866-621-0399
August 22,2011
City of Fort Worth
Public Events Department
Fort Worth Convention Center
120 Houston Street
Fort Worth,Texas 76102
Re: Fort Worth Convention Center Chiller Plant Upgrade
Subject: Change Order Add for Check Valve Installation
Johnson Controls is pleased to propose a price of SEVEN THOUSAND FIVE HUNDRED SEVEN
DOLLARS AND NO CENTS($7,507.00)plus any applicable sales tax for the following scope of work.
Scope:
1. Furnish and install one 10"Check Valve on existing chilled water pump.
2. Two weld neck flanges
3. One Bolt and Gasket Set
4. Thermal Insulation for check valve,piping,and existing pump.
Exclusions:
1. Overtime Labor
Thank you for this opportunity to be of service.
This proposal is hereby accepted and Johnson Controls is authorized to This proposal valid 30 days past:
proceed with the work;subject,however,to credit approval by Johnson August 22, 2011
Controls,Inc.,Milwaukee,Wl.
Alternate Number Accepted
JOHNSON CONTROLS, INC.
Purchaser-Company Name
Signature Signature
Name: Name:Ted Godawski
Title: Title: Senior Account Executive
Date:
(Important:This Proposal incorporates by reference the attached Johnson Controls Terms and Conditlons.)
Page 1