HomeMy WebLinkAboutContract 29007-A4 AMENDMENT NO. 4
STATE OF TEXAS 8 CITY SECRETARY CONTRACT NO. 00_1 - AL4
(No M&C Required)
COUNTY OF TARRANT 8
WHEREAS, the City of Fort Worth (City) and TranSystems
Corporation Consultants (Engineer) made and entered into City
Secretary Contract No. 29007 , (the Contract) which was authorized
by the City Council by M&C C-19678 on the 29th day of July
2003 ; and subsequently revised by three (3) previous
amendment; and
WHEREAS, the Contract involves engineering services for the
following project:
Replacement of South Shore Sanitary Sewer Main 253
WHEREAS, it has become necessary to execute Amendment No.
four (4) to said Contract to include an increased
scope of work and revised maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and
through their duly authorized representatives, enter into the
following agreement which amends the Contract:
1.
Article I of the Contract is amended to include the
additional engineering services specified in a proposal letter
dated January 18, 2011 , a copy of which is attached hereto and
incorporated herein. The cost to City for the additional design
services to be performed by Engineer total $ 7,415. 00
2 .
Article II of the Contract is amended to provide for an
increase in the maximum fee to be paid to Engineer for all work
and services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall not
exceed the sum of $ 1,026,891. 00
OFFI0141 RECOnD�;
CI Y f CRETARY
3.
All other provisions of the Contract which are not expressly amended
herein shall remain in full force and effect.
EXECUTED on this the day of , 2011, in Fort Worth,
Tarrant County, Texas.
ATTEST: p , 000000000 /�
Marty Hendrix o o x�
City Secretary Q*0 00 0°
Ay
000000
APPROVAL RECOMMENDED: APPROVED:
S. Frank Crumb, P.E. Fernando Costa
Director, Water Department Assistant City Manager
TranSystems Corporation Consultants �iC) (' UI �
ENGINEER �-�-a--�_,....��
Y•
Name: Raul Pena III, P.E. , Principal
500 W. 7t' St. Suite 1100
Fort Worth, Texas 76102
APPROVED TO FORM AND LEGALITY:
Assistant City Attorney
-2- OF 1 0 R D:
rx
r
i
January 18, 2011
Madelene Rafalko, P.E.
Water Department
City of Fort Worth
1000 Throckmorton Street
Fort Worth, TX 76102-6311
RE: Amendment 4 of M-253 Replacement
City Project No. 29007, DOE 4027
Dear Madelene,
TranSystems (TSC) appreciates the opportunity to provide additional services with respect to the above
referenced project. We have prepared this amendment request for services regarding engineering and
permitting.
1. Hydraulic Report $3,063
The pipe laid for M-252 Part I construction contract was found to differ from the contract
documents. The Water Department with the assistance of TSC reviewed the results. TSC
assistance included:
• Review trends of slope and capacity from as-builts data.
• Simulate flow conditions and determine the magnitude of a surcharging and characteristics of
hydraulic jump.
• Provide a brief letter report explaining the finding
• Attend meetings(3)
2. Parks and Community Services Department(PACSD)Application $4,352
During the design phase, Mallard Cove Park was developed along the proposed sewer alignment.
TSC assistance for a permit application and coordination included the following:
• Standard application form, review of park plans, aerial exhibit of site with local parcels, misc
exhibits, existing features and utilities.
• Specification and plan coordination
• Meetings (11)
i. TSC Site Visits(2)—Application review, re-staking and tree locations
ii. Site Visits with PACSD Project Manager and Water Dept(2)
iii. Site Visit with PACSD Manager and Water Dept
iv. Site Visit with Field Operations(only)
v. PACSD Advisory Board Public Meeting at Haws Athletic Center
vi. Meetings at PACSD with Water Dept. (2)
vii, Meetings with PACSD at City Hall (2)
Total Fee Amendment 4 $7,415
i
G:IFW021 01551ProjecbMgmAContracts\Amedment 4W253 amendment 4 121510.doc
Summary of the Contract and Amendments
Original Contract $ 890,335.00
Amendment 1 $ 35,243.00 Archeology Study
Amendment 2 $ 77,344.00 Reuse Water Line Layout,Survey, Other Meetings
Amendment 3 $ 23,969.00 Pump Station Alternative Report
Amendment 4 $ 7,415.00 Hydraulic Report and PACSD Application
$1,026,891.00 Contract Total
TSC has performed some of the above work to expedite the project and keep the project moving toward
completion. If you have any questions or require additional information please give me a call.
Sincerely,
TranSystems Corporation Consultants
Kent Lunski, P.E.
Project Manager
Cc. Craig Schellbach, Municipal Team Leader
2
G:I FW021 0155IProjectMgmt\Contracts\Amedment 41M253 amendment 4121510.doc
City of Fort worth
M-253 Sewer Rehabilitation
Amendment 4
Breakout of Services
18-Jan-11
Rates
E4 E3 T4
170 125.86 103.45 Total
1. Hydraulic Report
Review asbuilt information and review trends in data for exhibits 1 4 0 $ 673
Calculate hydraulic jump and surcharging 2 4 0 $ 843
Letter report 4 0 $ 503
Location,and flow exhibits 2 4 $ 666
Meetings(3) 3 0 $ 378
Subtotal $ 3,063
2. Park and Community Services Department Application
Application 4 4 $ 917
Specification and plan coordiantion 4 2 $ 710
Meeting(9)and Site Visits 2 20 2 $ 2,724
Subtotal $ 4,352
Total $ 7,415