HomeMy WebLinkAboutContract 45681 CITY SECREM
CITY OF FORT WORTH, TEXAS CONMCT NO.
STANDARD AGREEMENT FOR PROFESSIONAL SERVICES
This AGREEMENT is between the City of Fort Worth, a Texas home-rule municipality
(the "CITY"), and Halff Associates, Inc., authorized to do business in Texas, an independent
contractor ("Consultant"), for a PROJECT generally described as: City of Fort Worth Mapping
Activity Statement (MAS) #1 for FEMA Cooperating Technical Partners (CTP) FY13 Project.
Article
Scope of Services
(1) Consultant hereby agrees to perform as an independent contractor the services set
forth in the Scope of Services attached hereto as Attachment "A". These services
shall be performed in connection with City of Fort Worth Mapping Activity Statement
(MAS) #1 for FEMA Cooperating Technical Partners (CTP) FY13 Project.
(2) Additional services, if any, will be requested in writing by the City. City shall not pay
for any work performed by Consultant or its subconsultants, subcontractors and/or
suppliers that has not been ordered in writing. It is specifically agreed that
Consultant shall not be compensated for any alleged additional work resulting from
oral orders of any person.
Article II
Compensation
Consultant shall be compensated in accordance with the Fee Schedule shown in f
Attachment "B". Payment shall be considered full compensation for all labor, materials,
supplies, and equipment necessary to complete the services described in Attachment "A".
However the total fee paid by the City shall not exceed a total of $159,147 unless the City 1
and the Consultant mutually agree upon a fee amount for additional services and amend
this Agreement accordingly. r
i%
The Consultant shall provide monthly invoices to the City. Payment for services rendered
x
shall be due within thirty (30) days of the uncontested performance of the particular
services so ordered and receipt by City of Consultant's invoice for payment of same.
M
C-*)
M Acceptance by Consultant of said payment shall operate as and shall release the City from
�
all claims or liabilities under this Agreement for anything related to, done, or furnished in
CD connection with the services for which payment is made, including any act or omission of
the City in connection with such services.
-_
CR
City of Fort Worth,Texas
Standard Agreement for Professional Services
PMO Official Release Date:1/28/2013
R'"" � � '� ���
Page 1 of 8 r?i° F 1
CITY
ii
Article III
Term
Unless terminated pursuant to the terms herein, this Agreement shall be for a term of 365
days, beginning upon the date of its execution, or until the completion of the subject matter
contemplated herein, whichever occurs first.
Article IV
Independent Contractor
Consultant shall operate hereunder as an independent contractor, and not as an officer,
agent, servant, or employee of the City. Consultant shall have exclusive control of and the
exclusive right to control the details of its work to be performed hereunder and all persons
performing same, and shall be solely responsible for the acts and omissions of its officers,
agents, employees, contractors and subcontractors. The doctrine of respondent superior
shall not apply as between City and Consultant, its officers, agents, employees, contractors,
and subcontractors, and nothing herein shall be construed as creating a partnership or joint
venture between City and Consultant.
Article V
Professional Competence and Indemnification
(1) Work performed by Consultant shall comply in all aspects with all applicable local,
state and federal laws and with all applicable rules and regulations promulgated by
the local, state and national boards, bureaus and agencies. Approval by the City
shall not constitute or be deemed to be a release of the responsibility and liability of
Consultant or its officers, agents, employees, contractors and subcontractors for the
accuracy and competency of its services performed hereunder.
(2) In accordance with Texas Local Government Code Section 271.904, the
Consultant shall indemnify, hold harmless, and defend the City against
liability for any damage caused by or resulting from an act of negligence,
intentional tort, intellectual property infringement, or failure to pay a
subcontractor or supplier committed by the Consultant or Consultant's agent,
consultant under contract, or another entity over which the Consultant's
exercises control.
City of Fort Worth,Texas
Standard Agreement for Professional Services
PMO Official Release Date:1/28/2013
Page 2 of 8
Article VI
Insurance
(1) Consultant shall not commence work under this Agreement until it has obtained all
insurance required under this Article and the City has approved such insurance, nor
shall Consultant allow any subcontractor to commence work on its subcontract until
all similar insurance of the subcontractor has been so obtained and approval given
by the City; provided, however, Consultant may elect to add any subconsultant as
an additional insured under its liability policies.
Commercial General Liability
$1,000,000 each occurrence
$1,000,000 aggregate
Automobile Liability
$1,000,000 each accident (or reasonably equivalent limits of
coverage if written on a split limits basis). Coverage shall be
on any vehicle used in the course of the Project.
Worker's Compensation
Coverage A: statutory limits
Coverage B: $100,000 each accident
$500,000 disease - policy limit
$100,000 disease - each employee
(2) Additional Insurance Requirements
a. Except for employer's liability insurance coverage under Consultant's worker's
compensation insurance policy, the City, its officers, employees and servants shall
be endorsed as an additional insured on Consultant's insurance policies.
b. Certificates of insurance shall be delivered to the City of Fort Worth, Attention: the
respective Department Director (by name), 1000 Throckmorton, Fort Worth, TX
76102, prior to commencement of work.
c. Any failure on part of the City to request required insurance documentation shall
not constitute a waiver of the insurance requirements specified herein.
d. Each insurance policy shall be endorsed to provide the City a minimum thirty days
notice of cancellation, non-renewal, and/or material change in policy terms or
coverage. A ten days notice shall be acceptable in the event of non-payment of
premium.
City of Fort Worth,Texas
Standard Agreement for Professional Services
PMO Official Release Date:1/28/2013
Page 3 of 8
e. Insurers must be authorized to do business in the State of Texas and have a
current A.M. Best rating of A: VII or equivalent measure of financial strength and
solvency.
f. Other than worker's compensation insurance, in lieu of traditional insurance, City
may consider alternative coverage or risk treatment measures through insurance
pools or risk retention groups. The City must approve in writing any alternative
coverage.
g. Workers' compensation insurance policy(s) covering employees employed on the
Project shall be endorsed with a waiver of subrogation providing rights of recovery
in favor of the City.
h. City shall not be responsible for the direct payment of insurance premium costs
for Consultant's insurance.
L Consultant's insurance policies shall each be endorsed to provide that such
insurance is primary protection and any self-funded or commercial coverage
maintained by City shall not be called upon to contribute to loss recovery.
j. In the course of the Agreement, Consultant shall report, in a timely manner, to
City's officially designated contract administrator any known loss occurrence which
could give rise to a liability claim or lawsuit or which could result in a property loss.
k. Consultant's liability shall not be limited to the specified amounts of insurance
required herein.
I. Upon the request of City, Consultant shall provide complete copies of all
insurance policies required by these Agreement documents.
Article VII
Transfer or Assignment
City and Consultant each bind themselves, and their lawful successors and assigns, to this
Agreement. Consultant, its lawful successors and assigns, shall not assign, sublet or transfer
any interest in this Agreement without prior written consent of the City.
Article VIII
Termination of Contract
(1) City may terminate this Agreement for its convenience on 30 days' written notice.
Either the City or the Consultant for cause may terminate this Agreement if either
Party fails substantially to perform through no fault of the other and does not
City of Fort Worth,Texas
Standard Agreement for Professional Services
PMO Official Release Date:1/2812013
Page 4 of 8
commence correction of such nonperformance with 5 days of written notice and
diligently complete the correction thereafter
(2) If City chooses to terminate this Agreement under Article 8, upon receipt of notice of
termination, Consultant shall discontinue services rendered up to the date of such
termination and City shall compensate Consultant based upon calculations in Article
2 of this Agreement and Exhibit "B" attached hereto and incorporated herein.
(3) All reports, whether partial or complete, prepared under this Agreement, including
any original drawings or documents, whether furnished by the City, its officers,
agents, employees, consultants, or contractors, or prepared by Consultant, shall be
or become the property of the City, and shall be furnished to the City prior to or at
the time such services are completed, or upon termination or expiration of this
Agreement.
Article IX
Right to Audit
(1) Consultant agrees that the City shall, until the expiration of three (3) years after final
payment under this Agreement, have access to and the right to examine any directly
pertinent books, documents, papers and records of Consultant involving transactions
relating to this Agreement. Consultant agrees that the City shall have access during
normal working hours to all necessary facilities and shall be provided adequate and
appropriate workspace in order to conduct audits in compliance with the provisions of
this section. City shall give Consultant reasonable advance notice of intended audits.
(2) Consultant further agrees to include in all its subcontracts hereunder, a provision to
the effect that the subcontracting consultant agrees that the City shall, until the
expiration of three (3) years after final payment under the subcontract, have access
to and the right to examine any directly pertinent books, documents, papers and
records of such sub-consultant, involving transactions to the subcontract, and
further, that City shall have access during normal working hours to all sub-
consultant facilities, and shall be provided adequate and appropriate work space in
order to conduct audits in compliance with the provisions of this article. City shall
give Consultant and any sub-consultant reasonable advance notice of intended
audit.
(3) Consultant and sub-consultants agree to photocopy such documents as may be
requested by the City. The City agrees to reimburse Consultant for the cost of copies
at the rate published in the Texas Administrative Code in effect as of the time copying
is performed.
City of Fort Worth,Texas
Standard Agreement for Professional Services
PMO Official Release Date:1/28/2013
Page 5 of 8
Article X
Minority Business and Small Business Enterprise (MBE)(SBE) Participation
In accordance with the City's Business Diversity Enterprise Ordinance No. 20020-12-2011,
as amended, the City has goals for the participation of minority business enterprises and/or
small business enterprises in City contracts. Consultant acknowledges the MBE and SBE
goals established for this Agreement and its accepted written commitment to MBE and SBE
participation. Any misrepresentation of facts (other than a negligent misrepresentation)
and/or the commission of fraud by the Consultant may result in the termination of this
Agreement and debarment from participating in City contracts for a period of time of not less
than three (3)years.
Article XI
Observe and Comply
Consultant shall at all times observe and comply with all federal, state, and local laws and
regulations and with all City ordinances and regulations which in any way affect this
Agreement and the work hereunder, and shall observe and comply with all orders, laws
ordinances and regulations which may exist or may be enacted later by governing bodies
having jurisdiction or authority for such enactment. No plea of misunderstanding or ignorance
thereof shall be considered. Consultant agrees to defend, indemnify and hold harmless City
and all of its officers, agents and employees from and against all claims or liability arising out
of the violation of any such order, law, ordinance, or regulation, whether it be by itself or its
employees.
Article XII
Venue and Jurisdiction
If any action, whether real or asserted, at law or in equity, arises on the basis of any
provision of this Agreement, venue for such action shall lie in state courts located in
Tarrant County, Texas or the United States District Court for the Northern District of Texas
— Fort Worth Division. This Agreement shall be construed in accordance with the laws of
the State of Texas.
Article XIII
Contract Construction
The Parties acknowledge that each party and, if it so chooses, its counsel have reviewed
and revised this Agreement and that the normal rule of construction to the effect that any
ambiguities are to be resolved against the drafting party must not be employed in the
City of Fort Worth,Texas
Standard Agreement for Professional Services
PMO Official Release Date:1/28/2013
Page 6 of 8
interpretation of this Agreement or any amendments or exhibits hereto.
Article XIV
Severability
The provisions of this Agreement are severable, and if any word, phrase, clause,
sentence, paragraph, section or other part of this Agreement or the application thereof to
any person or circumstance shall ever be held by any court of competent jurisdiction to be
invalid or unconstitutional for any reason, the remainder of this Agreement and the
application of such word, phrase, clause, sentence, paragraph, section, or other part of this
Agreement to other persons or circumstances shall not be affected thereby and this
Agreement shall be construed as if such invalid or unconstitutional portion had never been
contained therein.
Article XV
Notices
Notices to be provided hereunder shall be sufficient if forwarded to the other Party by
hand-delivery or via U.S. Postal Service certified mail return receipt requested, postage
prepaid, to the address of the other Party shown below:
City of Fort Worth
Attn: Clair Davis, P.E., CFM
1000 Throckmorton
Fort Worth, Texas 76102
Consultant:
Halff Associates, Inc.
Attn: Jessica D. Baker
1201 North Bowser Rd.
Richardson, Texas 75081
Article XVI
Headings
The headings contained herein are for the convenience in reference and are not intended
to define or limit the scope of any provision of this Agreement
City of Fort Worth,Texas
Standard Agreement for Professional Services
PMO Official Release Date:1/28/2013
Page 7 of 8
Article XVII
Counterparts
This Agreement may be executed in one or more counterparts and each counterpart shall,
for all purposes, be deemed an original, but all such counterparts shall together constitute
but one and the same instrument.
Executed and effective this the 13th day of May, 2014.
BY: BY:
CITY OF FORT WORTH ENGINEER
Halff Associates, Inc.
�.
Fernando Costa Jessica D. Baker
Assistant City Manager Authorized Agent/Team Leader
Date: he Date:
APPROVAL RECOMMENDED:
By:
Doug Wi M ig
Director, Transportation/Public Works
APPROVED AS TO FORM AND LEGALITY M&C No.: °
By: ". � M&C Date: � �
Assistant City Attorney
sE
ATTEST' „rbo[b� ,
, .
ca
L A..
Mary J. Kayser
City Secretary
t
i
City of Fort Worth,Texas
Standard Agreement for Professional Services
PMO Official Release Date:1/28/2013 � �
Page 8 of 8f
b m
MEN
E
April 23,2014
Mr. Clair Davis,P.E.,CFM
Floodplain Administrator
TPW Stormwater Management
City of Fort Worth
1000 Throckmorton
Fort Worth,Texas 76102
Re: Proposal for City of Fort Worth Mapping Activity Statement (MAS) #1 for FEMA
Cooperating Technical Partner (CTP) FY13 Project
Dear Mr. Davis:
Please find the attached fee proposal to assist the City of Fort Worth with the Mapping Activity
Statement (MAS) tasks for submittal to FEMA as part of the FY13 Cooperating Technical Partner
(CTP) Risk MAP Project.
Attached are the following documents:
• Attachment A—Proposed Scope of Work
• Attachment B—Proposed Fee Estimate
• Attachment C—Changes and Amendments to Standard Agreement
• Attachment D—Proposed Project Schedule
• Attachment E—City of Fort Worth FEMA MAS No. 1
This professional services contract requires a qualified team with FEMA project experience in order to
efficiently meet the FEMA technical requirements and schedule. Halff provides a team with significant
FEMA experience including over ten MAS assignments from other Texas CTPs in the past 5 years.
Halff assisted the City of Fort Worth with the preparation of the grant application for this project
where$154,197 will be funded by the CTP grant and$5,000 funded by the City of Fort Worth.
We appreciate your consideration of our team for this assignment. Please do not hesitate to contact
me if you have any questions or require additional information.
Sincerely,
HALFF ASSOCIATES, INC.
�x
i �aa
Jessica Baker,P.E.,CFM,PMP
Attachments
cc: T. Lynn Lovell,P.E., CFM
HALFF AS,SOCiATcs,Mr,
ATTACHMENT A
Proposed Scope of Work
City of Fort Worth
Mapping Activity Statement (MAS) #1
FEMA Cooperating Technical Partner (CTP) FY13 Risk MAP Project Execution
April 23,2014
PURPOSE
The City of Fort Worth has been and continues to be proactive in developing and maintaining
detailed floodplain information for multiple watersheds throughout the City. The purpose of this
proposed Scope of Work is to assist the City of Fort Worth with the tasks detailed in MAS No.1 for
submittal to FEMA.
The scope set forth herein defines the work to be performed by the ENGINEER in completing the
project. Both the CITY and ENGINEER have attempted to clearly define the work to be
performed and address the needs of the Project. Under this scope, "ENGINEER" is expanded to
include any sub-consultant, employed or contracted by the ENGINEER.
PROJECT ACTIVITIES
The FEMA study effort includes the following tasks. Details for each task are included in Attachment E
- City of Fort Worth Mapping Activity Statement No. 1.
• Task 1: Outreach
• Task 2: Perform Field Surveys—portion of task to be completed by SBE firm, Gorrondona&
Associates,Inc.
• Task 3: Develop Hydrologic Data (including independent QA/QC)
• Task 4: Develop Hydraulic Data (including independent QA/QC)
• Task 5: Perform Floodplain Mapping (including independent QA/QC)
• Task 6: Develop DFIRM Database
• Task 7: Develop Non-Regulatory Products
ENO
001111"m HALFF
NON PAGE 1 OF 1
ATTACHMENT B
Proposed Fee Estimate
City of Fort Worth
Mapping Activity Statement (MAS) #1
FEMA Cooperating Technical Partner (CTP) FY13 Risk MAP Project Execution
April 23, 2014
I. Compensation
A. The ENGINEER shall be compensated for personnel time, non-labor expenses, and subcontract
expenses in performing services enumerated in Attachment A as follows:
i. Personnel Time. Personnel time shall be compensated based upon hours worked directly in
performing the PROJECT multiplied by the appropriate Labor Category Rate for the
ENGINEER's team member performing the work.
Labor Category Rate as presented in the rate schedule table below is the rate for each labor
category performing the work and includes all direct salaries,overhead,and profit.
Labor Category Rates
$/hour
Principal in Charge $260.00
Project Manager $160.00
Senior QA/QC Engineer $180.00
Senior Professional Engineer $140.00
junior Professional Engineer $105.00
Engineer-in-Training I $95.00
Survey,RPLS $125.00
Survey,2 Man Crew $118.00
Survey,SIT $75.00
Senior GIS $110.00
junior GIS $75.00
Clerical $60.00
ii. Non-Labor Expenses. Non-labor expenses shall be reimbursed as Direct Expenses at invoice
or internal office cost.
Direct Expenses (non-labor)include,but are not limited to,mileage,travel and lodging expenses,
mail, supplies,printing and reproduction services, other direct expenses associated with delivery
of the work; plus applicable sales, use, value added, business transfer, gross receipts, or other
similar taxes.
iii. Subcontract Expenses. Subcontract expenses and outside services shall be reimbursed at cost
to ENGINEER plus a markup of ten percent(10%).
iv. Budgets. ENGINEER will make reasonable efforts to complete the work within the budget
and will keep the City informed of progress toward that end so that the budget or work effort
can be adjusted if found necessary.
ENGINEER is not obligated to incur costs beyond the indicated budgets, as may be adjusted,
nor is the City obligated to pay ENGINEER beyond these limits.
If ENGINEER projects, in the course of providing the necessary services, that the PROJECT
cost presented in Article 2 of this Agreement will be exceeded, whether by change in scope of
Me
"e"m HALFF
maim PAGE 1 OF 3
ATTACHMENT B
Proposed Fee Estimate
the project,increased costs or other conditions, the ENGINEER shall immediately report such
fact to the City and,if so instructed by the City, shall suspend all work hereunder.
When any budget has been increased, ENGINEER's excess costs expended prior to such
increase will be allowable to the same extent as if such costs had been incurred after the
approved increase.
B. The ENGINEER shall be paid monthly payments as described in Section II-Method of Payment.
II. Method of Payment
A. The ENGINEER shall be paid by the City based upon an invoice created on the basis of statements
prepared from the books and records of account of the ENGINEER, based on the actual hours and
costs expended by the ENGINEER in performing the work.
B. Each invoice shall be verified as to its accuracy and compliance with the terms of this Agreement by
an officer of the ENGINEER.
C. ENGINEER shall prepare and submit invoices monthly.
D. Payment of invoices will be subject to certification by the City that such work has been performed.
III.Summary of Total Project Fees
A. The tables below are a summary of the proposed project totals.
Firm Primary Responsibility Fee Amount %
Prime Consultant
Halff Associates,Inc. Execution of FEMA MAS $138,147 86.8%
Tasks
M/WBE Consultants
Gorrondona Associates, FEMA Surveys $21,000 13.2%
Inc.
Non-M/WBE Consultants
None
TOTAL $159,147 100%
Project Number& Name Total Fee SBE Fee SBE %
Mapping Activity Statement(MAS) # 1
FEMA Cooperating Technical Partner(CTP) $ 159,147 $21,000 13.2%
Risk MAP Project Execution
City SBE Goal= 13% Consultant Committed Goal= 13.2%
1 MEN
111111111110 HALFF
N PAGE 2 OF 3
ATTACHMENT B
Proposed Fee Estimate
B. The table below is a summary of the proposed fees per project activity.
Project Task Total Fee
per Task
Outreach $5,000
Perform Field Surveys—$21,000 to be completed by Gorrondona $51,000
Associates,Inc.
Develop Hydrologic Data and Perform Independent QA/QC $15,000
Develop Hydraulic Data and Perform Independent QA/QC $32,000
Perform Floodplain Mapping:Detailed Riverine and Perform $31,000
Independent QA/QC
Develop DFIRM Database $4,500
Develop Non-Regulatoiy Products $20,647
Total $159,147
miss rte
HALFF
PAGE 3 OF 3
ATTACHMENT "C"
CHANGES AND AMENDMENTS TO STANDARD AGREEMENT
Design Services for
City of Fort Worth Mapping Activity Statement (MAS) #1 Risk MAP Project
City Project No.
No revisions to the Standard Agreement.
City of Fort Worth,Texas
Attachment C
PMO Release Date:05.19.2010
Page 1 of 1
ATTACHMENT D
Proposed Project Schedule
City of Fort Worth
Mapping Activity Statement (MAS) #1
FEMA Cooperating Technical Partner (CTP) FY13 Risk MAP Project Execution
April 23, 2014
All tasks shall be completed following the scheduled outlined in Exhibit E - Mapping Activity
Statement No. 1.
Schedule subject to change following pending Change Request to be submitted by the City of Fort Irlorth.
The estimated project schedule is as follows:
Estimated Estimated
ACTIVITIES START END
DATE DATE
NOTICE TO PROCEED 3/24/2014
Outreach 8/1/2014 10/31/2014
Perform Field Surveys 3/24/2014 4/30/2014
Develop Hydrologic Data and Perform 3/24/2014 7/31/2014
Independent QA/QC
Develop Hydraulic Data and Perform 3/24/2014 7/31/2014
Independent QA/QC
Perform Floodplain Mapping: Detailed 3/24/2014 7/31/2014
Riverine and Perform Independent QA/QC
Develop DFIRM Database 3/24/2014 7/31/2014
Develop Non-Regulatory Products 8/1/2014 1 10/31/2014
U
mil, HALFF
01111010 PAGE 1 OF 1
f
ATTACHMENT E
FEEMAy.;
CITY OF FORT WORTH
COOPERATING TECHNICAL PARTNERS!
RISK MAP FLOOD STUDY MAPPING ACTIVITY
STATEMENT
Production
Mapping Activity Statement No. I
In accordance with the Cooperating Technical Partners (CTP)Partnership Agreement dated
November 19, 2012 between the City of Fort Worth,and the Federal Emergency Management
Agency(FEMA),this Mapping Activity Statement(MAS)No. 1 includes the following project
areas and production phases:
• Lower West Fork Trinity River HUC-8—Phase Two (Risk Identification&Assessment)
o Detailed Studies within the City of Fort Worth—24.1 stream miles
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 1 of 33
Contents
SECTION 1—OBJECTIVE AND SCOPE.....................................................................................3
Project Risk Identification and Mitigation ...............................................:.......................... 9
ProjectDocumentation...............................................................................................................9
PerformProject Outreach.................................................................................................... 10
Phase Two -Risk Identification and Assessment.............................................................. 12
DevelopTopographic Data.................................................................................................... 12
DevelopHydrologic Data..................................................................................................... 14
PerformField Survey...............................................................................................I............. 16
DevelopHydraulic Data........................................................................................................ 16
PerformFloodplain Mapping................................................................................................20
Develop Non-Regulatory Products.......................................................................................22
Phase Three-Regulatory Product Update(Support).....................................................23
Support to Post-Preliminary Map Production...............................
........................................
SECTION 2—Technical and Administrative Support Data Submittal...........................25
SECTION 3—PERIOD OF PERFORMANCE(for CTPs).........................................................25
SECTION4—FUNDING/LEVERAGE......................................................................................25
SECTION5—STANDARDS......................................................................................................27
SECTION 6—SCHEDULE and BUDGET................................................................................30
SECTION7—CERTIFICATIONS.............................................................................................. 30
SECTION 8—TECHNICAL ASSISTANCE AND RESOURCES..................................................31
SECTION9—CONTRACTORS.................................................................................................31
SECTION10—REPORTING....................................................................................................31
SECTION 11—PROJECT COORDINATION............................................................................. 32
SECTION 12—POINTS OF CONTACT(CTP)......................................................................... 33
i
i
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 2 of 33
SECTION 1-OBJECTIVE AND SCOPE
The objective of the Risk MAP Project documented in this CTP Production Mapping Activity Statement
(CTP-Production-MAS)is to document the project efforts to include a project specific scope of services
and deliverables for the mapping projects identified below:
• Lower West Fork Trinity River HUC-8—Phase Two(Risk Identification&Assessment)
o Detailed Studies within the City of Fort Worth—24.1 stream miles
Figure 1 shows the Study Streams for this Risk MAP Project. Please note,the updated of the regulatory
products(DFIRM panels and FIS Report)is not included with this MAS.
The City of Fort Worth participated in Phase One-Discovery as part of the North Central Texas Council
of Government(NCTCOG)efforts in the Lower West Fork Trinity HUC-8 Watershed during FY12. The
City of Fort Worth submitted flood risk mapping needs and mitigation actions identified/completed and
considers Phase One-Discovery complete.
All processes,service and deliverables prepared under this MAS must meet the requirements as defined
by Federal Emergency Management Agency's(FEMA's)Draft Risk MAP Operational Standards(which
is a compilation of the standards found in the previously issued volumes and appendices.of the Guidelines
and Specifications for Flood Hazard Mapping Partners as well as Procedure Memorandums) and any
updates or revisions thereto.
The Standards and other guidelines may be accessed from the FEMA Flood Hazard Mapping website at
htW ://www fema o� v/ctp-main/a iidelines-specifications-flood-hazard-mapping-partners. The Geospatial
Data Coordination Policy and the Geospatial Data Coordination Implementation Guide are located at
https://hazards.fema.gov under "Tools & Links." Mapping Partners must also coordinate with FEMA
Region 6 to assure that Regional Risk MAP Implementation Guidance is also followed.
Should scope or schedule require a modification,the CTPs should work through the change process by
submitting Special Problem Reports(SPR)to the appropriate Regional office.
Once released the Risk MAP Operational Standards will be available through the Knowledge Sharing Site
at: bIQ2://pm.riskmUcds.com/kss/default.qvx
Region 6 Risk MAP Implementation Guidance,Tools and Templates are available at:
hitp://pm.risknigpcds.com/FEMA REGIONS/REGIONVI/pages/Resources.aspx
Projects should be phased in alignment with the Outreach Framework,available at:
(htW://pm.riskmapcds.com/FENIA REGIONS/REGIONVI/Outreach%20Strategv/l/Framework.xlsx)
Historic Procedure Memos are available at:
htM://wvvw fema gov/cam-main/guidelines-specifications-flood-hazard-mapping-partners -
1
Operating Guidance(OGs)documents are available to assist CTPs and FEMA in Risk MAP
implementation and are not mandatory. Operational Guidance is available at:
htt :/hww fema gov/guidance-cooperating-technical-partners-program/operating --idance-documents
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 3 of 33
As the Draft Standards are finalized and expanded, it is expected that the CTP will remain in contact with
the FEMA POC to discuss the implementation of that updated or future standards on the existing project.
The CTP should provide an overview of the standards effect on current on-going projects. Effective dates
and retroactive issuance.memos will be reviewed jointly by FEMA and the CTP lead to determine the
need for a possible Change Request to modify scope,schedule and budget.
Phasing Risk MAP Project Production. In order to allow the flexibility required to move projects
from initiation(Discovery)to effective issuance,the Region has identified the following phases for
project funding:
• Phase One-Discovery
• To include Flood Risk Report,Flood Risk Map and Flood Risk Database
• Discovery and Discovery Close-Out meetings
• Phase Two-Risk Identification and Assessment
• Engineering and Risk MAP product development
• Project Kick-off,Flood Risk Review and Resilience meetings
• Phase Three-Regulatory Product Update
o Preparation of FIS and FIRM
o Panel Preparation,Preliminary and Effective Panel Issuance
o Consultation Coordination Officer's(CCO)Meeting
Deployment. In order to "deploy" a watershed study area, the following Risk MAP products
required:
• Flood Risk Report(based on Average Annualized Loss dataset)
• Flood Risk Map
• Flood Risk Database(based on the Average Annualized Loss dataset)
The following table outlines the required deliverable items for projects to count towards
deployment. Please refer to Table 1.1 in planning and preparation of all Risk MAP projects to
assure that the project investment will align with the required deliverables indicated by study
type below.
FYI CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 4 of 33
fi
Table 1.1—Risk MAP Deployment Definitions
Risk MAP Deployment Definition:
r r•.r
Required whendoingaflood_> - Refined analysis-
? __ engineering regulatorystudy, -Requiredwhendoing ! requiredforflooding " Watershed
Riverine 1 ✓ J endwhenamodemizedmap _afloodengineering lsourceswhereflgoddepth
i isavaliabietocampare regulatorystudy andanafysisgridswere : (HUGS)
changesto - produced
E i
RegmredshendoingaFlgod` Appllcableoniywhere j Refined analysis
beneficial.Guir.ancewil€ requiredforfloodin
engmeeringregulatorystddy_ g`
j ( j clarify and w Community
Coastal Atthe . r andwhena modemizedniap.- sourcesiyhereFlood depth, (CID)
Communi kuei _ t - P where coaztaidepth 3 - CID
�_ - isavailabletocom are grids addvalueandwifl andanalysisgridswere
changesto _ _ be required. ! ,produced
;Apply"Revised - Required xrfien doing a Flood Refined analysis
Analysis - engmeering'regulatorystudy Requiredwnendoing required for flooding; Project
Levee 3 Mapping % s� andwitenamodernaedmap afloodengmeenng sourceswhereflooddepthi t
Proceduresfor ( = Foot Footprint
Non•Acuedtted asavaila6le.tocompara_ regulatorystudy:; i endanalysisgridswar_e P
i Levees" changes to, :,' - I produced _
Required y,h a 6 doinga Fload'
angmeedngregujatorystddy, ! Project
Conversion Conversion 3
andwhen amodermzed-
tafamo i ! ua�adabletocompare ; Footprint
I [ Shangesto
In order to maintain the investment and production tracking databases, all projects identified in
the attached Mapping Activities Statement should also include a GIS file with the project
footprint. Either HUC-8 watershed, county or project FIRM panel areas for use in national roll
up and reporting required during each fiscal year. If the footprint of a project is modified, a
revised GIS foot print file shall be submitted with the Change Request documentation.
This Risk MAP Project will be completed by the following entities:
• City of Fort Worth
• Contractor(s)
In cooperation,the State CTP Lead and the FEMA Project Monitor will establish a Regional Project
Team(RPT). The RPT should be established at the onset of a project and at a minimum should include
the FEMA Project Monitor. As a project progresses, it may be deemed that other parties are necessary for
the successful delivery of Risk MAP within the project area. The RPT will be led by the CTP and meet
periodically throughout a project's lifecycle. The CTP is responsible for coordinating the activities
identified in this MAS No. 1. The FEMA Region should be provided with documentation identifying the
PMT membership and meeting schedule.
The Mapping Partner shall notify FEMA and all applicable parties of all meetings with community
officials, and other relevant meetings,at least two weeks prior to the meeting(with as much notice as
possible). FEMA and/or its contractor may or may not attend the community meetings.
I
FY1 33 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 5 of 33
Quality Program for Mapping Partners.City of Fort Worth is responsible for the implementation
of an independent Quality Assurance/Quality Control(QA/QC)plan for all assigned activities. The City
of Fort Worth will submit a Summary Report that describes and provides the results of all automated or
manual QA/QC review steps. The plan should include the process for all assigned activities.
It is expected that each CTP within the Region have in place a Quality Assurance/Quality Control
(QA/QC)plan. Independent QC review activities may be included in the costs associated with the
delivery of CTP data for tasks identified within the MAS. The City of Fort Worth will need to submit its
QC plan to the Regional Project Officer for approval.
Please note FEMA routinely performs periodic audits and overall study/project management reviews to
ensure study quality standards are being maintained. The City of Fort Worth will be responsible for
addressing any and all comments resulting from independent QA reviews,including re-submittal of
deliverables and products,to include these items passing all technical reviews. The City of Fort Worth
will submit Risk MAP products to FEMA's designated reviewer for QC prior to public issuance.
FEMA's Production and Technical Services(PTS)contractor remain responsible for National Quality
Control Review requirements in the preliminary and post-preliminary documentation reviews required to
assure due process is completed and appropriately documented as outlined in the Document Control
Procedure Manual and Procedure Memorandum 42. The City of Fort Worth will be responsible for
addressing any and all comments resulting from these National reviews,including re-submittal of
deliverables and products,to include these items passing all required reviews.
Data Availability.The Mapping Partner shall maintain an archive of all data submitted. All
supporting data must be retained for a minimum of three years from the date a funding recipient submits
its final expenditure report to FEMA.
Data Delivery. FEMA will provide download/upload capability for data submittals through the MIP
located at https://ha7-ards.fema.gov. As each activity is completed,the data must be submitted to the MIT
for validation by the FEMA Project Monitor.
Metadata is required for all activities in accordance with Appendix M,Data Capture Standards,dated
May 2013.
Mapping Information Platform (MIP) Projects: Two projects will be established for each Risk
MAP project area. The Regulatory(REG)project will track the production and delivery Regulatory
products(Flood Insurance Study Text and Flood Insurance Rate Maps),while the Risk MAP Products
(RMP)will track the project cost and progress of the non-regulatory products and services.
CTPs should note that projects obligated in the MIP only include FEMA dollars. CTPs should update the
MIP to inform FEMA of the FEMA dollars spent each month. Leverage costs,fees and data are entered
separately at the completion of the tasks,but are not included in the task dollars for project progress
reporting.
Leyerate.The MIP shall also be populated with appropriate leverage information regarding who paid
for the data provided and the amount of data used by the Risk MAP Project as the Scoping,Data
Development,Preliminary and Post Preliminary Management tasks are being completed. For future
review of leverage entries within the MIP,the CTP should document and include documentation outlining
leverage funds associated with the projects in the MAS within the Integrated Baseline Form. These funds
should be entered in the appropriate MIP Management task.
FYI CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 6 of 33
1
Earned Value Data Entry and the Maiming Information Platform (MIP): The MIP
Workflow is designed and used to track the Earned Value of on-going mapping projects. This .
information is automatically calculated by the MIP,using the Actual cost and schedule of work
performed,or"actuals"and comparing them to the expected cost and schedule of work performed,or
"baseline".
Once the FEMA Regional office has funded a project the CTP should prepare and deliver an Integrated
Baseline Form and submit the project schedule and task breakdown to the FEMA Region 6 MIP
Champion. FEMA will complete the"Obligate Project Funds"task in the MIP and inform the CTP of the
project availability for project progress tracking.
This step establishes the baseline for the project in the MIP,using the cost and schedule information for
each task as outlined in this document and agreed to at the completion of the scoping process.
The MIP study workflow allows City of Fort Worth to manage the status of these projects at a task level.
The cost and schedule information,updated by the City of Fort Worth for each contracted task,is
compared to the baseline established for those tasks. This information is rolled up to a project level and
monitored by the FEMA Region to assess progress and Earned Value.
Once the baseline has been established in the MIP,the City of Fort Worth shall input the performance and
actual cost to date for each contracted task for each project by the 250'of each month. This must be
completed at a minimum by every thirty days and at the completion of the task. When a task is
completed,including all QA/QC activities in this MAS plus the Quality Control Reviews established in
PM 42,the City of Fort Worth shall enter 100%complete,enter the actual completion cost,and the actual
completion date within the Manage Scoping task,as applicable. The"Manage"tasks will be open and
accepting updates for up to 90 days after the completion of the last producer task in each module.
Earned Value data entry involves updating cost,schedule and performance(physical percent complete)in
the MIP by the City of Fort Worth. The City of Fort Worth will maintain a Schedule Performance Index
(SPI)and Cost Performance Index(CPI)within a tolerable range(0.92 to 1.08)each monthly reporting
period.
Non-Regulatory Projects in the MIP. The City of Fort Worth shall contact the Regional MIP
Champion lead to obtain the guidance document Risk MAP Products in the MIP which explains how
Non-Regulatory Products shall be submitted through the MIP. The guidance also explains how
performance will be tracked for Non-Regulatory Products—Flood Risk Report,Flood Risk Map and
Flood Risk Database. These tasks will be updated in the PJ P MIP project.
Contract Documentation Maintenance.The City of Fort Worth should alert the FEMA Regional
Project Monitor should a project require a modification to the scope,schedule or budget. The CTP shall
coordinate an update to the required contract and grant paperwork by submitting a completed Change
Request form to the Regional Point of Contact.
Change Request Form can be found online at:
liM2://pm riskingeds com/FEMA REGIONS/REGIONVI/Contractinc ProsramMgmt/Farms/Allltems.as
pY?RootFolder=%2fFEMA%5fREGIONS%2fREGIONVI%2fContractins%5fProaramMamt%2fl%2fCh
ange%20Requests&FolderCTID=&View=%7bC5BB33FB%2d5 I E3%2d460B%2dB418%2d50CB3 567C
892%7d
I
i
FYI CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 7 of 33
I
Other Requirements.The Project Officer,as needed;may request additional information on status
on an ad hoc basis.
The following tasks further define the scope and delivery requirements for each phase of production
project which are included in the Mapping Activities Statement.
Project Management
Responsible Mapping_Partner: City of Port Worth with Contractor(s)
Scope: Project Management is the active process of planning,organizing,and managing resources
toward the successful accomplishment of pre-defined project goals and objectives. The City of Fort
Worth will coordinate with the FEMA Regional Office with respect to Project Management activities and
technical mapping activities.
Project management costs should be determined by phase and included in the Integrated Baseline Form.
The project management costs of each phase will be included with an associated MIP task to allow the
Mapping Partners to report progress and invoice these project management fees. The project
management costs will be rolled up into the following project MIP tasks by phase:
• Phase One-Discovery
o Project management fees will be included in the MIP Scoping task
• Phase Two-Risk Identification and Assessment
o Project management fees will be included in the MIP Perform Floodplain Mapping task
• Phase Three-Regulatory Product Update
o Project management fees will be included in the MIP Post Preliminary Processing task
Standards: All Project Management work shall be performed in accordance with the standards specified
in Section 5 - Standards.
Deliverables:
• Monthly Earned Value data reporting through the MIP with variance explanations to support
management of technical mapping activities within specified timeframe,for both Regulatory and
Non-Regulatory Products;
• Management of SPI/CPI performance for an organization;
• Overall project QA/QC maintenance information,such as maintaining a QA/QC log and
providing a QA/QC approach to FEMA for review and approval;and
• Management of adherence to scope of work and quality of work for an organization.
J
I
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 8 of 33
i
Project Risk Identification and Mitigation
Responsible Mapping Partner: City of Fort Worth with Contractor(s)
Threats to the planned completion of a project may come from various sources.Risks should be identified
during the planning phase and monitored throughout the project so that potential impact can be assessed
and solution strategies developed and implemented as needed.
Risk identification and mitigation is required of all Cooperating Technical Partners,the Region looks to
work with its mapping partners throughout the project lifecycle in a proactive manner to identify project
risks and determine solutions that are cost-effective and efficient in implementation for all partners.
Project risks should be discussed quarterly with the FEMA Project Monitor.
Table 1.2—Project Risk Identification
o e � tee• � s • e
• o
Lack of Funding Low Study is not completed Secure funding prior to the
start of project
Project Documentation
Responsible Mapping Partner: City of Fort Worth with Contractor(s)
Scope: All FEMA projects require the documentation of the analysis,processes and engineering
judgment utilized during the preparation of a Flood Insurance Study. This information is included in a
series of Technical Study Data Notebooks(TSDNs)in Region 6. The requirements of these deliverables
are outlined below.
Standards: All Program Documentation shall be performed in accordance with the standards specified in
Section 5 -Standards.
Deliverables: The City of Fort Worth shall make the following products available to FEMA by uploading
the digital data to the MIP,in accordance with the schedule outlined in Section 6:
• The CTP will deliver intermediate TSDNs as each Data Development Task is completed.
TSDNs will be prepared for the following Manage Data Development Tasks:
o Topographic Data Development (Phase Two)
o Perform Field Survey(Phase Two)
o Develop Hydrologic Data(Phase Two).
o Develop Hydraulic Data(Phase Two)
o Floodplain Mapping(Phase Two)
o Risk MAP products(Phase Two)
o Base Map Acquisition (Phase Three)
o DFIRM Database(Phase Three)
c Flood Elevation Determination Document(FEDD)—Phase Three
1 FYI CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 9 of 33
l
i
• CTP will deliver the revised Flood Risk Report,Flood Risk Database and Flood Risk MAP ahead
of the Resilience meeting.
• These items will be delivered to the Region for future reference and use due to current
MIP upload limitations.
• Delivery reports should include two hard copies delivered to the Region
• Each hardcopy should include DVD(s)with all spatial data and mapping files used
throughout the Discovery Effort
• Delivery should include editable documents for future use
• The CTP will deliver each Intermediate TSDN in accordance with the Data Capture Standards
(DCS) outlined in the DRAFT Guidelines and Standards for Flood Risk Analysis and Mapping,
Appendix N, dated January 2012
• The CTP will review their deliveries to FEMA for completeness and certify each submittal as
being in accordance with the DCS outlined in the DRAFT Guidelines and Standards for Flood
Risk Analysis and Mapping,Appendix N, dated January 2012
o Once Appendix N is issued,the CTP will review and identify delivery items that may not
be included in the final delivery as they are delivering in accordance with the DRAFT
Guidance,dated January 2012.
• If the study is selected for Independent Verification and Validation(1V&V),the partner will be
provided a copy of the IV&V findings. If the findings indicate that items are not in accordance
with the DRAFT Guidelines and Standards for Flood Risk Analysis and Mapping,Appendix N,
dated January 2012,the partner will be held responsible for the delivery completion of the items
identified. The Region will work with the CTP partner to prepare a Corrective Action Plan as
required by FEMA-Headquarters.
Perform Project Outreach
(NOTE: The performance of outreach takes place throughout the life of the flood study project.A Project
Outreach Plan (POP)should be included in the Engagement Plan/Discovery Report.)
Responsible Mapping Partner: City of Fort Worth with Contractor(s)
Scope: This Risk MAP project will include at least one(1)in-person opportunities to engage
communities,build risk awareness,increase capabilities for risk communication, and stimulate mitigation
action at the local level.The overarching goal is to create a climate of understanding and ownership of the
mapping process at the State and local levels. Well-planned and executed community engagement can
reduce political stress,confrontation in the media, and public controversy,which can arise from lack of
information,misunderstanding,or misinformation. These outreach activities also can assist FEMA,the
Mapping Partner,and other members of the RPT in responding to congressional inquiries. The costs of
each of the meetings identified below should be rolled into the project tasks identified,the outreach costs
will not be tracked individually within the MIP.
The actual number of meetings will be determined based on the risk and need at the local level and
determined as part of developing the project-based communication plan. Provisions may be made for
remote access video/audio feeds for those that cannot attend in person.These opportunities consist of:
1 Protect Initiation Meetingf Coordination Call.This meeting will serve to introduce the
communities to the RPT,project scope and timeline,expectations for communities with risk
communication,methods and data to be used mapping efforts,and to answer any local questions about
f
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 10 of 33
the project. This can be held as an in-person meeting,webinar,or conference call. The costs
associated with these efforts shall be included in the MIP REG project—Scoping task.
Flood Risk Review Meeting.This meeting will serve.to provide communities with engineering
data and drafts of flood risk(non-regulatory)products, collect feedback,and revise as needed. It will
also provide FEMA the opportunity to show how the datasets and outreach tools can help communities
become more resilient by understanding risk data, communicating about risk,prioritizing mitigation
actions and improving mitigation plans,especially risk assessments and mitigation strategies. The
costs associated with these efforts shall be included in the MItP RMP project(Phase Two)—
Alluvial Fan(Outreach)task.
For all meetings,provisions should be made for remote access video/audio feeds for those RPT
members that cannot attend in person.
In addition to these meetings,in order to facilitate information sharing and a continuing dialogue between
the RPT and the community,the City of Fort Worth will provide communities with a regular status
reports outlining the current project status,key accomplishments to date,identified risks,if any, and next
steps including estimated next meeting date and meeting content(template to be provided from FEMA or
can be created by Mapping Partner).
These status reports will be provided to FEMA for review before electronic distribution. Project update
status reports will be distributed to communities at mid-points between each of the meetings,and between
the Final Meeting and effective date(for a total of four),to help introduce and prepare the communities
for upcoming discussions.
The City of Fort Worth will work with the Regional FEMA Office during the initiation of this activity to
develop the Engagement Plan to support the implementation of the mapping project. The Regional Office
will have access to many customizable outreach tools that have been developed for this process to support
each touch point that the Regional Project Team has with the community.
Standards: The primary guidance for Risk MAP Meetings is in OG-4-11:Risk MAP Meetings Guidance.
All communication with local governments will be done in accordance with 44 CFR Part 66.
Deliverables:The City of Fort Worth shall deliver the following to the FEMA Regional Project Officer in
accordance with the schedule outlined in Section 6—Schedule and include within the TSDN:
• Project update status reports for project communities.
• Delivery of all associated products to the Regional POC for upload to the RiskMAP6.com website for
the identified project areas
• Documentation of mitigation actions into the Action Tracker
FYI CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 11 of 33
Phase Two -Risk Identification and Assessment
Responsible Mapping Partner: City of Fort Worth with Contractor(s)
Scope: Phase two begins at the Project Kick-Off meeting and ends with the delivery of the Risk MAP
products at the Resilience Meeting with all participating parties. The emphasis of this phase is to deliver
the required and identified elements (products, services and technical assistance) within the selected
project areas to further the Awareness and Action metrics. In the Discovery Report the delivery of Risk
MAP throughout the Risk Identification and Assessment phase, has been identified by services and
deliverables from three possible project tracks.
Track 1—Risk Awareness &Mitigation Actions Track
Track 2—Data&Engineering
Track 3—Risk MAP Products
The objectives and elements included in the Internal Guidance for Risk MAP Conversion, dated October
19, 2010, shall be referenced and followed as directed by the FEMA Project Monitor. Furthermore, for
in-depth guidance, see the Regional Outreach Strategy for the delivery of the phase and tracks. The
following tasks may be included in the project work for Phase Two.
Note: Engineering analysis prepared during phase two may be included in a Phase Three effort for the
Regulatory Product Update effort in the future. If the engineering analysis prepared is used to update the
FIS and FIRM,the party whom produced the analysis is expected to assist FEMA(and its future mapping
partner)in responding to appeals and comments received during the 90-day appeal period.
Develop Topographic Data
Responsible Mapping Partner: City of Fort Worth with Contractor(s)
Scope:Topographic/elevation data may be new or existing. New is defined as data that will be flown and
processed for the areas specified in this MAS study areas according to the referenced specifications.
Existing topographic/elevation data (previously flown and/or processed) may be used to produce flood
studies and related products. However, if new data is not to be collected, the FEMA Region should be
consulted before leveraging the best available existing topographic to ensure acceptability for the
intended level of flood hazard study.
The City of Fort Worth shall obtain additional topographic data for the floodplain areas to be studied
including overbank areas. These data will be used for hydrologic analysis,hydraulic analysis, floodplain
boundary delineation and/or testing of floodplain boundary standard compliance. City of Fort Worth
shall gather availability, currency, and accuracy information for existing topographic data covering the
affected communities in this MAS. City of Fort Worth shall use topographic data for work in this MAS
only if it is better quality than that of the original study or effective studies. The Mapping Partner will
ensure that the FEMA Geospatial Data Coordination Policy and Implementation Guide is followed and
1 the data obtained or to be produced are documented properly as per those policies and guidelines.
I
FYI CTP-Production-MAS -City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 12 of 33
f
Requirements for leveraging existing xisting Topographic Data:
The City of Fort Worth shall use topographic data for the areas described in the Table 1.5 Summary of
Topographic Data table. The source of the topographic data must be listed as well. The City of Fort
Worth shall coordinate with other team members conducting field surveys as part of this MAS. Accuracy
for the topographic data shall be evaluated based on the current FEMA standards for flood hazard study
level of detail.
City of Fort Worth also shall update the topographic maps and/or DEMs for the subject flooding sources
using the data collected under this Topographic Data Development process and via field surveys. In
addition, City of Fort Worth shall address all concerns or questions regarding the topographic data
development that are raised by City of Fort Worth during the independent QC review,or during the PM
42 defined Validation Process.
The City of Fort Worth will utilize existing TNRIS topographic data that has been used for other FEMA
studies in Tarrant County.
Table 1.5—Summary of Topographic Data
" •e • e °' e 0
0 Oee �s • "• 0 "6
• - ee
Lower West 1.2 ft
Fork Trinity Existing vertical TNRIS TNRIS None
River HUC- 2009
8 Watershed
Standards: All Topographic Data Development work shall be performed in accordance with the standards
specified in Section 5 -Standards.
Deliverables: City of Fort Worth shall make the following products available to FEMA by uploading the
digital data to the MIP in accordance with the schedule outlined in Section 6—Schedule:
• Documentation in overall TSDN Report summarizing terrain methodology and results;
• Support documentation and Certification of Work;
• Where paper documentation is required by State Law for Professional certifications,the Mapping
Partner may submit the paper in addition to a scanned version of the paper for the digital record.
Please coordinate with the Regional and/or State representative to verify state reporting
requirements.
• CTP will perform Quality Assurance and Quality Control(QA/QC)review and provide
• A Summary Report that describes the findings of the independent QA/QC review;
• Confirmation of update(s)made to the NDEP; -
• Recommendations to resolve any problems that are identified during the independent
QA/QC review;and
FYI CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 13 of 33
1
Develop hydrologic Data
Responsible Mapping Partner: City of Fort Worth with Contractor(s)
Scone: City of Fort Worth shall perform hydrologic analyses for approximately 22.4 square miles of
drainage area for the flooding source(s)identified in Table 1.6. The City of Fort Worth shall calculate
peak flood discharges for the 10-,4-,2-, 1-and 0.2-percent-annual-chance events using the HEC_HMS
computer program as defined in Table 1.7. These flood discharges will be the basis for subsequent
Hydraulic Analyses performed under this Mapping Activity Statement No. 1.
If GIS-based modeling is used, City of Fort Worth shall document automated data processing and
modeling algorithms, and provide the data to FEMA to ensure these are consistent with FEMA standards.
Digital datasets(such as elevation,basin,or land use data)are to be documented and provided to FEMA
for approval before performing the hydrologic analyses to ensure the datasets meet minimum
requirements. If non-commercial(i.e.,custom-developed)software is used for the analysis,then City of
Fort Worth shall provide full user documentation,technical algorithm documentation, and the software to
FEMA for review before performing the hydrologic analyses.
Table 1.6—Summary of Hydrologic Analysis
aeo e e •
P ® "e a s e•
CF-3C(Warner Channel) Approximate HEC-HMS 0.6
SC-7A(Upper) Xavier Channel Approximate HEC-HMS 0.3
Unnamed Tributary to Sycamore Approximate HEC-HMS 0.9
Creek(Marlboro)
CF-3A (Upper Willow) Approximate HEC-HMS 1.3
Unnamed Tributary to Marys
Creek (Royal Creek,trib is Approximate HEC-HMS 0.6
between US377 and Old
Benbrook Road)
MSC-2 Approximate HEC-HMS 0.7
Ed ecliff Branch Approximate HEC-HMS 4.5
Stream EB-1 and EB-IA Approximate HEC-HMS 0.9
(Ed ecliff Tribs)
Unnamed Tributary to Kings Approximate HEC-HMS 0.8
Branch Broadmoor
Se bold Creek Approximate HEC-HMS 1.0
Menefee Creek(Trib to WF-5) Approximate HEC-HMS 0.9
Glenwood Creek(Stream SC-2) Approximate HEC-HMS 1.6
Dunbar Creek(Stream WC-1) Approximate HEC-HMS 1.5
Wildcat Branch Approximate HEC-HMS 1.7
Summer Creek Approximate HEC-HMS 1.1
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 14 of 33
Standards: All Hydrologic Analyses work shall be performed in accordance with the standards specified
in Section 5 -Standards.
Deliverables: City of Fort Worth shall make the following products available to FEMA by uploading the
digital data to the MIP-so that FEMA and its future Mapping Partners can access the data to respond to
inquiries. These items should be delivered in accordance with the schedule outlined in Section 6 -
Schedule.
• Digital copies of all hydrologic modeling (input and output) files for the 10-, 4-, 2-, 1- and 0.2-
percent-annual-chance events;
o Watersheds should be studied in their,entirety
■ Detailed Streams require the 10-,4-,2-, 1-and 0.2-percent-annual-chance events
to be analyzed
• All required GIS layers meeting specifications outlined for S_XS and S_WTR_LN
o All required attributes should be included in each of the data sets
o S_XS should include station locations for all cross-sections
• S_WTR_LN should include all stream centerlines used for modeling purposes.
• Additionally, S_WTR_LN should include any profile baselines used in production
• Digital versions of all backup data used in the analysis including work maps;
• For GIS-based modeling,deliverables shall include all input and output data, and GIS
data layers;
• GIS-based modeling approach still requires a work map to be delivered for future use.
• Metadata file;
• Digital versions of draft text for inclusion in the FIS report;
• Digital Summary of Discharges Tables presenting discharge data for the flooding sources for
which hydrologic analyses were performed;
• Format Hydrology Database or Data Delivery consistent with the Data Capture Standards(DCS)
of all return periods;
9 A Summary Report that describes and provides the results of all automated or manual QA/QC
review steps taken during the preparation of the FIRM as outlined in the approved QA/QC Plan;
• Where paper documentation is required by State Law for Professional certifications,the Mapping
Partner may submit the paper in addition to a scanned version of the paper for the digital record.
Please coordinate with the Regional and/or State representative to verify state reporting
requirements; and
• Summary of the hydrologic analysis for each study area in Table 1.6 Summary of Hydrologic
Analysis.
0 CTP will perform Quality Assurance and Quality Control(QA/QC)review and provide
o A Summary Report that describes the findings of the independent QA/QC review;
o Confirmation of update(s)made to the NDEP;
o Recommendations to resolve any problems that are identified during the independent
QA/QC review;and
• TSDN,as outlined in the Project Documentation section of this Mapping Activities Statement
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 15 of 33
i
j
Perform Field Survey
Responsible Mapping Partner: City of Fort Worth with Contractor(s)
Scope: To supplement any field reconnaissance conducted during the Project Discovery phase of this
project, City of Fort Worth shall conduct a detailed field reconnaissance of the specific study area to
determine conditions along the floodplain(s), types and numbers of hydraulic and/or flood-control
structures, apparent maintenance or lack thereof of existing hydraulic structures, locations of cross
sections to be surveyed, and other parameters needed for the hydrologic and hydraulic analyses.
The City of Fort Worth shall conduct field surveys, including obtaining channel and floodplain cross
sections, identifying or establishing temporary or permanent bench marks, and obtaining the physical
dimensions of hydraulic and flood-control structures. If appropriate, the City of Fort Worth shall also
identify items needed for coastal analyses including land cover, vegetation types, housing, dunes, beach
nourishment, and coastal structures. The City of Fort Worth also shall coordinate with other entities that
are involved in the Topographic Data Development process regarding ongoing activities and deliverables.
Standards: All Field Survey work shall be performed in accordance'with the standards specified in
Section 5 - Standards.
Deliverables: The City of Fort Worth shall make the following products available to FEMA by uploading
the digital data to the MIP, in accordance with the schedule outlined in Section 6:
• A report summarizing the findings of the field reconnaissance;
• Maps and drawings that provide the detailed survey results;
• Survey notebook containing cross section and structure data;
• Documentation of the horizontal and vertical datum;
• Digital versions of draft text for inclusion in the FIS report;
• Digital survey data consistent with the Data Capture Standards(DCS);
• Metadata file complying with the NFIP Metadata Profiles Specifications;
• Support documentation and Certification of Work;
• TSDN,where appropriate;
• Where paper documentation is required by State Law for Professional certifications,the Mapping
Partner may submit the paper in addition to a scanned version of the paper for the digital record.
Please coordinate with the Regional and/or State representative to verify state reporting
requirements; and
• A Summary Report that describes and provides the results of all automated or manual QA/QC
review steps taken during the preparation of the FIRM as outlined in the approved QA/QC Plan.
Develop Hydraulic Data
Responsible Mapping Partner: City of Fort Worth with Contractor(s)
Scope: City of Fort Worth shall perform hydraulic analyses as described in Tables 1.7.The modeling will
include the 10-,4-,2-, 1-and 0.2-percent-annual-chance events based on peak discharges computed under
Hydrologic Analyses. The hydraulic methods used for this analysis will include base level and enhanced
level hydraulic modeling. The base level will use an automated hydraulic model,and use the best
available elevation data. It will not include field surveys,floodways,or mapped BFEs.The enhanced
level may include field surveys,floodways,and the 10-,4-,2-, 1-and 0.2-percent-annual-chance events,
using methods described in Table 1.7.
I
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 16 of 33
The Mapping Partner shall use the cross-section and field data collected during Field Survey and the
topographic data collected during the Topographic Data Collection,when appropriate,to perform the
hydraulic analyses. The hydraulic analyses will be used to establish flood elevations and regulatory
floodways for the subject flooding sources.
The City of Fort Worth shall use the FEMA CHECK-2 or CHECK-RAS checking program to verify the
reasonableness of the hydraulic analyses. To facilitate the independent QA/QC review,City of Fort
Worth shall provide explanations for unresolved messages from the CHECK-2 or CHECK-RAS program,
as appropriate. In addition,the City of Fort Worth shall address all concerns or questions regarding the
hydraulic analyses that are raised by City of Fort Worth during the independent QA/QC review.
The City of Fort Worth shall document automated data processing and modeling algorithms for GIS-
based modeling and provide the data to FEMA for review to ensure these are consistent with the
standards outlined above. Digital datasets are to be documented and provided to FEMA for approval
before performing the hydraulic analyses to ensure the datasets meet minimum requirements. If non-
commercial(i.e.,custom-developed)software is used for the analyses,then City of Fort Worth shall
provide full user documentation,technical algorithm documentation,and software to FEMA for review
before performing the hydraulic analyses.
Any flooding sources associated with a levee that are mapped as providing protection on effective FIRMs,
but will not meet certification requirements for the new FIRMS,will require revised hydraulic analysis.
The revised analysis should meet all of FEMA's related Program and Working standards. Historic
Reference Materials—G&S Appendix C, PMs 34,43, 51, 52, 53,59,and 63.
i
i
i
1
i
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 17 of 33
I
Table 1.7—NVUE Summary and Summary of Hydraulic Data
1 CF-3C(Warier Modernized Unknown Approximate Detailed 0.6
Channel)
2 SC-7A(Upper) Modernized Unknown Approximate Detailed 0.4
Xavier Channel
Unnamed
3 Tributary to Modernized Unknown Approximate Detailed 1.3
Sycamore Creek
(Marlboro)
4 CF-3A (Upper Modernized Unknown Approximate Detailed 1.3
Willow)
Unnamed
Tributary to
Marys Creek
5 (Royal Creek, Modernized Unknown Approximate Detailed 1.2
trib is between
US377 and Old
Benbrook Road)
6 MSC-2 Modernized Unknown Approximate Detailed 2.4
7 Edgecliff Modernized Unknown Approximate Detailed 4.4
Branch
Stream EB-1
8 and EB-IA Modernized Unknown Approximate Detailed 1.1
(Edgecliff
Tribs)
Unnamed
9 Tributary to Modernized Unknown Approximate Detailed 0.9
Kings Branch
Broadmoor)
10 Se bold Creek Modernized Unknown Approximate Detailed 2.2
11 Menefee Creek Modernized Unknown Approximate Detailed 1.3
(Trib to WF-5)
Glenwood
12 Creek(Stream Modernized Unknown Approximate Detailed 1.4
SC-2)
13 Dunbar Creek Modernized Unknown Approximate Detailed 1.6
Stream WC-1)
14 Wildcat Branch Modernized Unknown Approximate Detailed 2.8
15 Summer Creek Modernized Unknown Approximate Detailed 1.2
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 18 of 33
Base Flood Elevations
It is the requirement of the Region to produce and provide Base Flood Elevations (through all hydraulic
methods selected for a project either through Automated Approximate (when possible), Enhanced
Approximate,Limited Input,Limited Detail or Detailed Study) for all project areas studied. If the above
project listed has not completed Phase One Production—Discovery prior to execution of this task order,
the Regional Project Monitor will identify project areas and study mileage at the conclusion of.the
Discovery Phase and request an updated scope and cost estimate for that project prior to proceeding into
Phase Two.
Table 1.8—Hydraulic Study Approaches
Flood Insurance Rate'Map A A _AE AE AE
Flood insurance Study': = " "
Flood Insurance Study Profile}BFE = Proviaedto
Community
Flood Risk Repor[&_Map
Flootl.Risk,Database
;Changes Since last FIRM "
,FioodRlskAssessment{HAZUS) AAt: AAt 'tfiAL-+New)- '(AAL�Newj �{AAL+New)
Singie,Flood Frequency Depth Grrd Provided tc
1�Annual_Chance = _ Community
(' )
'< 5
fvluibple Fldod Frequency Depth:Gnds ` t ,
u.- —
Preas of M tigatlon IrferasttEn ancedt —
Addltlonal Enhanced,pata Set{sj s, $
Terrain Data 10M/30M 10M DEMsor UDAR LIDAR LIDAR
DEMsorLIDAR LIDAR -
No Field Survey No Field Survey
• No Field Survey Auto H&H •.Auto H&H Limited Feld Field Survey
Auto H&H Survey
•X sections adjusted X sections adjusted - Detailed H&H
Associated'Engineering Level Xsection not -.Auto H&tt
near structures only nearstructures,onig adjust coons.
adjusted AilXsecBons
•Dam Structures 3r0 party Structure adjusted
-No,tructures adjusted
entered Data i;3ndgejCulvertj _
Standards: All Hydraulic Data work shall be performed in accordance with the standards specified in
Section 5 -Standards.
Deliverables: City of Fort Worth shall make the following products available to FEMA by uploading the
digital data to the MIP so that City of Fort Worth can access it for an independent QA/QC review in
accordance with the schedule outlined in Section 6-Schedule.
• Digital hydraulic modeling(input and output)files;
• For Detailed Study Streams the 10-,4-,2-, 1-and 0.2-percent-annual-chance events will
be analyzed
• Digital profiles for all streams studied
• FEMA RASPLOT program or similar software should be utilized to prepare the digital
profiles;
• For Detailed Study Streams the 10-,2-, 1-and 0.2-percent-annual-chance events will be
included on the profile
• PDF and editable GIS or CAD files should be delivered
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 19 of 33
l
• Digital tables with range of Manning's"n"values;
• Digital Floodway Data Tables for each flooding source that is compatible with the FIRM
database;where applicable
• For GIS-based modeling,deliverables include all input and output data, GIS data'layers,and final
products in the format of the FIRM database structure;
• Depth grids for all studied streams for all frequencies as required;
• For Detailed Study Streams depth grids for the 10-,4-,2-, 1-and 0.2-percent-annual-
chance events shall be delivered
• Metadata file;
• Explanations for unresolved messages from the CHECK-2 or CHECK-RAS program, as
appropriate;
• Digital versions of all backup data used in the analyses;
• Digital versions of draft text for inclusion in the FIS report;
• Format Hydraulic Database or Data Delivery consistent with the Data Capture Standards(DCS);
• A Summary Report that describes and provides the results of all automated or manual QA/QC
review steps taken during the preparation of the FIRM as outlined in the approved QA/QC Plan;
• Where paper documentation is required by State Law for Professional certifications,you shall
submit the paper in addition to a scanned version of the paper for the digital record. Please
coordinate with the Regional and/or State representative to verify reporting requirements for your
state;
• Appropriate leverage information includes who paid for the data and the amount of data used by
the Risk MAP Project;and
• CTP will perform Quality Assurance and Quality Control(QA/QC)review and provide
• A Summary Report that describes the findings of the independent QA/QC review;
• Confirmation of update(s)made to the NDEP;
• Recommendations to resolve any problems that are identified during the independent
QA/QC review; and
• TSDN,as outlined in the Project Documentation section of this Mapping Activities Statement
Perform Flood lain Mapping
Responsible Mapping Partner: City of Fort Worth with Contractor(s)
Scope for Enhanced Riverine or Coastal Analysis: The City of Fort Worth shall delineate the 1-and 0.2-
percent-annual-chance floodplain boundaries and the regulatory floodway boundaries(if required)and
any other applicable elements for the flooding sources for which hydrologic,enhanced hydraulic, and/or
coastal analyses were performed. The City of Fort Worth shall incorporate all new or revised hydrologic,
hydraulic,and/or coastal modeling and shall use the topographic data acquired under Develop
Topographic Data to delineate the floodplain and regulatory floodway boundaries on a digital work map.
The City of Fort Worth shall incorporate the results of all effective Letters of Map Change(LOMCs)for
all affected communities on the FIRM and provide to the appropriate PTS the required submittals for
incorporation into the National Flood Hazard Layer(NFHL). Also,the City of Fort Worth shall address
all concerns or questions regarding Floodplain Mapping that are raised by the City of Fort Worth during
the independent QA/QC review.
FYI CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 20.of 33
The City of Fort Worth shall capture flood hazard engineering and/or mapping data quality issues
encountered during this activity in the CNMS data model for the area of interest. These issues will be
entered as"Requests"or"Needs"in the CNMS data model based on the nature of the deficiency
encountered. Detailed information on performing this task can be found in the relevant standards
specified in Section 5-Standards.
Standards: All floodplain mapping work shall be performed in accordance with the standards specified in
Section 5—Standards. The Mapping Partner will perform self-certification audits for the Floodplain
Boundary Standards for all flood hazard areas and submit this FBS certification with the Perform
Floodplain Mapping TSDN.
The City of Fort Worth will complete all required activities related to levees in accordance with the
Program and Working Standards.
Deliverables: Upon completion of floodplain mapping for all flooding sources in this project,the City of
Fort Worth shall make the following products available to FEMA by uploading the digital data to the MIP
so that the City of Fort Worth can access it for the independent QA/QC review in accordance with the
schedule outlined in Section 6—Schedule.
• A metadata file complying with the NFIP Metadata Profiles Specifications,must accompany the
compliant digital data;
0 Support documentation and Certification of Work,
• Seamless digital floodplain layer meeting specifications for S_XS, S_FLD_HAZ_AR and
S_FLD_HAZ_LN
• All required attributes should be included in each of the data sets
• S_XS should include water surface elevations
• Digital work map showing the 1-and 0.2-percent-annual-chance floodplain boundary
delineations,regulatory floodway boundary delineations,cross sections,BFEs,flood insurance
risk zone designation labels,gutters,PFD,coastal high hazard areas,LiMWA and all applicable
base map features,
0 Floodplain Boundary Standards(FBS)Certification Report and Back Up Data to support FBS
j findings.(Historic Procedure Memorandum No. 3 8—Implementation of Floodplain Boundary
Standards)
• Identification of the Letters of Map Change a CTP has reviewed and incorporated and superseded
by the engineering analysis performed in the Phase Two efforts.
j o Catalog of cases reviewed and entered into the SOMA tool at www.hazards.fema.eov
o Documentation of the last date of LOMC incorporation
• Floodplain Overlay Maps for the Flood Risk Review and Resilience Meetings to be held in Phase
Two. Floodplain Overlay Maps are prepared to review the current effective floodplain and the
newly prepared engineering results.
• A Summary Report that describes and provides the results of all automated or manual QA/QC
review steps taken during the preparation of the FIRM as outlined in the approved QA/QC Plan;
• An explanation for the use of existing topography for the studied reaches,if appropriate;
• Written summary of the analysis methodologies;
• Digital versions of draft FIS report,Floodway Data Tables and updated profiles including all
profiles and tables converted appropriate daturn, as well as any other necessary items for the
finalization of the preliminary FIS;
• If automated GIS-based models are applied,all input data,output data, intermediate data
processing products,and GIS data layers shall be submitted consistent with the DCS; and
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 21 of
I
• Where paper documentation is required by State Law for Professional certifications,the Mapping
Partner may submit the paper in addition to a scanned version of the paper for the digital record.
Please coordinate with the Regional and/or State representative to verify state reporting
requirements.
• CTP will perform Quality Assurance and Quality Control(QA/QC)review and provide
o A Summary Report that describes the findings of the independent QA/QC review;
o Confirmation of update(s)made to the NDEP;
o Recommendations to resolve any problems that are identified during the independent
QA/QC review; and
• TSDN, as outlined in the Project Documentation section of this Mapping Activities Statement
Develop Non-Regulatory Products
Responsible Mapping Partner: City of Fort Worth with Contractor(s)
Scope: Risk assessment data and analyses are defined as processes for analyzing or evaluating the risk
associated with a hazard, and using that information to make informed decisions on the appropriate ways
to reduce the impacts of the hazard on people and property. As part of the Risk MAP Program, non-
regulatory Flood Risk Products shall be developed for study areas.
During Phase Two,the CTP will update the previously created Flood Risk Products (Flood Risk Report,
Flood Risk Map and Flood Risk Database)to include the findings of the engineering analysis performed.
In accordance with Procedure Memorandum 65 - Guidance for Additional Enhanced Dataset Definitions
and Flood Risk Database Standards, the Mapping Partner will prepare Flood Risk Assessment with a
combination of the new engineering analysis and the larger scale AAL dataset. The tables and risk
assessment calculations within the Flood Risk Report (FRR), Flood Risk Map (FRM) and Flood Risk
Database(FRD)will be updated to reflect these changes.
Furthermore,the Mapping Partner may produce the following additional Risk MAP datasets during Phase
Two as identified below:
• Areas of Mitigation Interest(AOMI);
• Multi-Frequency Depth Grids(Limited Detail and Detailed Study areas)
• Percent Annual Chance Grid
• 3 0-Year Annual Chance Grid
The Mapping Partner will develop the following Flood Risk Datasets, as identified in Table 1.9. Flood
Risk Assessment Datasets shall be incorporated into the standard Flood Risk Products. Please note,
Changes Since Last FIRM(CSLF)will be prepared and delivered in Phase Three.
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 22 of 33
Table 1.9—Risk Assessment Product Development Table
n- x Mr., n� a .. � t ' � �;..�;�,.r��' .�,#x. -;.:. ..mac _�.._.�
Standards: All Risk MAP work shall be performed in accordance with the standards specified in Section
5 -Standards. Please contact the Regional POC to obtain draft appendices.
FEMA's Operating Guidance document OG 6-11 - User Guidance for Flood Risk Datasets and Products
is available from the following website:http:/Jvr v.fema. ov/plan/prevent/thm/o. main.shtm.
Additionally,the CTPs should consult Procedure Memorandum 65 -Guidance for Additional Enhanced
Dataset Definitions and Flood Risk.
The Mapping Partner shall contact the MIP Champion to obtain the guidance document Risk MAP
Products in the MIP (March 4, 2011)which explains how Non-Regulatory Products shall be submitted
through the MIP.
Deliverables:The following products,for those communities identified in Table 1.4 will be made
available to FEMA and uploaded to the MIP as appropriate:
• Revised and Updated Flood Risk Report,Flood Risk Map,and Flood Risk Database;
• Flood Depth and Analysis Grids as listed in Table 1.9
• Preliminary Changes Since Last Firm(CSLF)for the New Detailed Study Streams as listed in
Table 1.9
Phase Three -Regulatory Product Update (Support)
Responsible Mapping Partner: City of Fort Worth with Contractor(s)
Scope: Phase Three encompasses the update of the Regulatory Flood Insurance Rate Map
(FIRM) and Flood Insurance Study(FIS)report. This phase is to update the regulatory FIS and
FIRM information prepared in phase two.
Support to Post-Preliminary leap Production
Responsible Mapping Partners: City of Fort Worth with Contractor(s)
Scope: If another Mapping Partner is selected to prepare the Phase Three—Regulatory Products Update,
i the CTP whom produced the Hydrology,Hydraulics and Floodplain Mapping tasks will support FEMA
and its Mapping Partners in response to Appeal and Comments received during the Statutory 90-Day
Appeal and Comment period.
1
FYl3 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 23 of 33
This activity consists of responding to appeals and comments received from the communities and
residents within the project area. The City of Fort Worth will be responsible for:
• Coordination with the Phase Three Mapping Partner to review the incoming Appeals and
Comments associated with the Hydrology,Hydraulics and Floodplain Mapping submittals.
• The CTP will be responsible for a coordinated review effort with the Phase Three
Mapping Partner to prepare suggestions for appeal and comment incorporation.
• The CTP shall review the draft FIS text sections submitted during the production of the
Hydrology,Hydraulics or Floodplain Mapping tasks to identify areas of required update
to incorporate the incoming appeal or comment.
• The CTP shall review the Hydrologic or Hydraulic modeling submitted during the
production of the Hydrology,Hydraulics or Floodplain Mapping tasks to identify areas
of required update to incorporate the incoming appeal or comment.
• Conference calls should be held at the close of the appeal period to allow the review of
all appeals and comments received.
• The Phase Three Mapping Partner will be responsible for the update of the Hydrology,
Hydraulics and/or Floodplain Mapping tasks to resolve the incoming appeal or comment.
o The Phase Three Mapping Partner should provide copies of the appeal and comments
received and provide at least 10 business days for CTP review and comment.
• The CTP should prepare an Addendum/Memorandum to document the suggested amendments to
the FIS,and modeling as well as the TSDNs submitted during the production of the Hydrology,
Hydraulics or Floodplain Mapping tasks for upload to the M1P.
• CTP should indicate a number of hours,appeals and comments that will be supported for the
project areas prepared in Phase Two efforts.
I
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
f Mapping Activity Statement No. 1 24 of 33
SECTION 2—Technical and Administrative Support Data Submittal
The Project Team members for this Risk MAP Project that have responsibilities for activities included in
this MAS No. 1 shall comply with the data submittal requirements summarized below and in appropriate
Procedure Memorandums.
All supporting documentation for the activities in this MAS shall be submitted according to Appendix M,
and will include a flood elevation determination docket(FEDD)folder. Where Technical Support Data
Notebook(TSDN)format is used,such shall be submitted in accordance with Section 2—Technical and
Administrative Support Data Submittal.Table 2.1 Mapping Activities and Applicable TSDN Sections
indicates the sections of the TSDN that apply to each mapping activity. Submittals must be made to the
appropriate PTS for a review of required materials. As needed,the CTP will work with the PTS to ensure
that all required documents are included in the TSDN and will respond to requests from the PTS for
additional information.
If any issues arise that could affect the completion of an activity within the proposed scope or budget,the
responsible Mapping Partner shall complete a Change Request(CR)as soon as possible after the issue is
identified. The Mapping Partner should coordinate with their FEMA Project Monitor and prepare the
Change Requests forms for submittal to FEMA. The SPR is to describe the issue and propose possible
resolutions.For additional information on Change Requests,please review Region 6's change request
materials on the SharePoint site:
hM2://pm.riskmapeds.com/FENIA REGIONS/REGIONVI/pages/Resotu-ces aspx?RootFolder=%2fFEMA
%5 fREGIONS%2fREGIONVI%2fContracting%5fProgramMamt%2fl%2fChange%20Requests&Folder
CTID=&View=%7b6A68FOD9%2dB338%2d4671%2d9508%2d55880608B908%7d
Please refer to Procedure Memorandum 62—TSDN and FEDD File Protocol for Mapping Projects.
Intermediate TSDNs are expected in Region 6 and should be uploaded to the MIP at the time of
data delivery for each mapping task. The TSDNs required are outlined in the Project
Documentation section of this MAS.
SECTION 3—PERIOD OF PERFORMANCE(for CTPs)
The mapping activities outlined in this MAS will be completed as specified in the Agreement Articles of
the Cooperative Agreement. The Mapping Activities may be terminated at the option of FEMA or City of
Fort Worth in accordance with the provisions of the Partnership Agreement dated November 19,2012. If
these mapping activities are terminated, all products produced to date must be returned and updated into
the MIP and the remaining funds from uncompleted activities,provided by FEMA for this MAS,will be
returned to FEMA.
Note: Grants awarded for CTPs expire three years from issuance date.
SECTION 4—FUNDING/LEVERAGE
FEMA is providing funding, in the amount of$154,147,to City of Fort Worth for the completion of this
Risk MAP Project. The City of Fort Worth shall provide any additional resources required to complete
the assigned activities for this Risk MAP Project. During the discovery process, additional needs may be
identified. Activities associated with any additional needs would be performed based on availability of
additional funds. The leverage listed below includes in-kind services and blue book values for acquired
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 25 of 33
information(i.e.base map data,hydrologic and hydraulic analyses,etc.). These values should also be
reported in the MIP by the appropriate task owner. The current Blue Book(3.0)is dated September 2011
and can be downloaded from FEMA's Information Resource Library at
h!W://www fema goy/plan/�revent/fhpVcV info.shtm#4.The City of Fort Worth shall complete Table 4.1
Contribution and Leverage.
Table 4.1—Contribution and Leverage
B 0
•
Outreach $5,000 $0 0% $5,000
Perform Field Surveys $46,000 $262,000 85% $308,000
Develop Hydrologic Data
and Perform Independent $15,000 $65,000 81% $80,000
QA/QC
Develop Hydraulic Data and
Perform Independent $32,000 $80,000 71% $112,000
QA/QC
Perform Floodplain
Mapping:Detailed Riverine $31,000 $10,000 24% $41,000
and Perform Independent
QA/QC
Develop DFIRM Database $4,500 $0 0% $4,500
Develop Non-Regulatory $20,647 $0 0% $20,647
Products
Total $154,147 $417,000 73% $571,147
i
Include Reference to Integrated Baseline Form -See attached Fort Worth FY13 IBF
Prepare the Integrated Baseline Foam for the tasks identified within this Mapping Activities
Statement,please include:
o FEMA Contribution
o Partner Contribution(in Leverage Rows for each project phase)
o Total Project Cost
Final leverage dollars or units shall be entered as applicable within the Manage Data Development task in
the MIP workflow. Leverage data shall be an estimate of available leverage data at the time the MAS is
prepared and shall be further defined in the Discovery Report.
FYI CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 26 of 33
SECTION 5-STANDARDS
All work completed under this MAS must meet the requirements as defined by FEMA's Draft Risk MAP
Operational. Standards (which is a compilation of the standards found in the previously issued volumes
and appendices of the Guidelines and Specifications for Flood Hazard Mapping Partners as well as
Procedure Memorandums) and any updates or revisions thereto. Details regarding the previous source of
the relevant standards for activities completed in the MAS are provided in Tables 5.1 Applicable
Standards for Project Activities and 5.2 Project Activities and Applicable Portions of FEMA Guidelines
and Specifications. Information on the original volume and appendix of the G&S referenced for each
mapping activity are summarized in Table 5.2 for convenience. All mapping partners working on a Risk
MAP Project are responsible for complying with all appropriate requirements in FEMA's Draft
Operational Standards and any supporting technical references and guidance documents.
The Standards and other guidelines may be accessed from the FEMA Flood Hazard Mapping website at
htW://www fema gov/ctp-main/Quidelines-specifications-flood-hazard-mapping=partners. The Geospatial
Data Coordination Policy and the Geospatial Data Coordination Implementation Guide are located at
https://hazards.fema.gov under"Tools&Links."
FYI CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 27 of 33
Table 5.1—Applicable Standards for Project Activities
Activities
tN0 _ C :-
k�
O
Du
4
_ m - c cca o ca o y> A
o
m
R
N
Ap dit'able Standards o c Q c r a
O 8
.0. v ¢ m L m °� o� a p
> m a y
Me
13 N
Z M A
a of a a a N
II. 3 4-s
FEMA's Draft Risk AMP Operational X X X X X X X X X X X X X X X X X
Standards
Guidelines and Specifications for
Flood Hazard Mapping Partners and
Procedure Memorandums(Replaced X . X X X X X X X X X X X X X X X X
and Superseded by FEMA Draft Risk
MAP Operational Standards)
FEMA's Geospatial Data
Coordination Policy and X X X
Coordination Implementation Guide
Engineer Manual 1110-2-1003,
Hydrographic Surveys(USACE), X X
January 1,2002
'Numerical Models Accepted by
X X X X X X
FEMA for NFIP Usage,"Updated X
April 2003
w
NFIP Metadata Profile Specifications X X X X X X X X X
Document Control Procedures X X X X
Manual
44 Code of federal Regulations Parts X X X X X X X X X X X X X X X X
65, 66 and 67
Data SharingAgreement R R R R R R R
i
R—.4s Required for use of third party data
I
1
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 28 of 33
Table 5.2—Project Activities and Applicable Portions of FEMA's previous volumes of Guidelines
and Specifications
u` AMA Ems. , i f, 9 ."?I"-r1m �,' }t
i.. ';> {,,ir''f_'res� E - 1'•t �rt. ?
,�4 � � t = }�_ 4sFra 2 APP11cab eoluSne� e- con/ ubsec on,
Volume 1
Outreach Appendix I
OG 4-11: Risk MAP Meetings Guidance
Appendices N and O(draft) September 2011
PM 59 and 65
OG 1-11:Risk MAP Guidance for Incorporating
Mitigation Planning Technical Assistance and
Training into Flood Risk Projects
OG 2-11: Operating Guidance for Creation of Risk
Develop Non-Regulatory Products MAP Products
OG 3-11: Communicating Flood Risk with Risk
MAP Datasets and Products
OG 6-11: User Guidance for Flood Risk Datasets
and Products
Develop Non-Regulatory Products
"Risk MAP Products in the MIP"(March 4,2011)
FYI CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 29 of 33
SECTION 6—SCHEDULE and BUDGET
The activities documented in this MAS No. 1 shall be completed in accordance with Table 6.1 Mapping
Activities Schedule, which should drive the schedule within the MIP. If changes to this schedule are
required,the responsible Mapping Partner shall coordinate with FEMA and the PMT in a timely manner.
Table 6.1 MagEing Activities Schedule
e • e•
Outreach *Contractor(s) 8/1/2014 10/31/2014 $5,000
Perform Field Surveys *Contractor(s) 10/1/2013 4/30/2014 $308,000
Develop Hydrologic Data and Perform Independent *Contractor(s) 10/1/2013 7/31/2014 $80,000
QA/QC
Develop Hydraulic Data and Perform Independent *Contractor(s) 10/1/2013 7/31/2014 $112,000
QA/QC
Perform Floodplain Mapping: Detailed Riverine and *Contractor(s) 10/1/2013 7/31/2014 $41,000
Perform Independent QA/QC
Develop DFIRM Database *Contractor(s) 10/1/2013 7/31/2014 $4,500
Develop Non-Regulatory Products *Contractor(s) 8/1/2014 10/31/2014 $20,647
TOTAL COST $571,147
*City of Fort Worth will act as project manager to the contractor(s).
Include Reference to Integrated Baseline Form-See attached Fort Worth FY13 IBF
• Prepare the Integrated Baseline Form to identify the schedule for the tasks identified within this
Mapping Activities Statement,please include:
• Activity
• Responsible Partners)
o Cost
The City of Fort Worth shall update the MIP workflow tasks with schedule and cost information within
60 days once funds are awarded.
SECTION 7—CERTIFICATIONS
The Mapping Partner shall follow all Quality Management Standards included in FEMA's Draft Risk
MAP Operational Standards. These include,however are not limited to the completion of all required:
• Quality Compliance Checks;
• Standardized Checklists;
• Self-Certification Reports; -
• Documentation of all standards utilized within a Data Development task;
• Documentation of any exceptions(with appropriate exception approval);
• Citation of any know areas of non-compliance;
• Data Capture Standards;
• Floodplain Boundary Standard Report; and
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 30 of 33
• Any other documentation requirements identified within.
i SECTION 8-TECHNICAL ASSISTANCE AND RESOURCES
Project Team members may obtain copies of FEMA-issued LOMCs,archived engineering backup data,
and data collected as part of the mapping needs assessment and/or CNMS process from FEMA and/or
your Regional Project Officer.
General technical and programmatic information can be downloaded from the FEMA website at
http://-vvww.fema.goy/plan/prevent/fhm/frm soft.shtin. Specific technical and programmatic support may
be provided through FEMA and/or its contractor; such assistance should be requested through the FEMA
Project Officer specified in Section 12—Points of Contact.
i
Project Team members also may consult with the FEMA Regional Project Officer to request support in
the areas of selection of data sources,digital data accuracy standards,assessment of vertical data
accuracy,data collection methods or subcontractors,and GIS-based engineering and modeling training.
I
Please contact the Regional POC to obtain the most recent version of the Risk MAP Timeline and Risk
MAP Process Path.
Assistance with the MIP may be requested at miphelp @riskmapeds.com
SECTION 9-CONTRACTORS
The City of Fort.Worth intends to use the services of Contractors for this Risk MAP Project. The City of
Fort Worth shall ensure that the procurement for all contractors used for this Risk MAP Project complies
with the requirements of 44 CFR 13.36.
Part 13 may be downloaded in PDF or text format from the United States Government Printing Office
website at http://www.access.gpo.gov/nara/efr/waisidx_04/44cfrl3_04.html.
F
3
f
SECTION 10-REPORTING
t
Financial Reporting: Because funding has been provided to the City of Fort Worth by FEMA, financial
reporting requirements for will be in accordance with Cooperative Agreement Articles. The City of Fort
Worth shall also refer to 44 CFR 13.41.
f
The City of Fort Worth shall communicate with communities throughout the life of each project.
Continued'engagement is necessary and appropriate and will build upon the relationships established or
enhanced during Discovery and provide transparency into the Risk MAP process.This may occur through
r monthly or quarterly updates or project status calls with community leaders, project websites including
updates at several milestones or along a specific timeline, or other methods.
The City of Fort Worth shall provide financial reports to the FEMA Regional Project Officer and
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 31 of 33
Assistance Officer in accordance with the terms of the signed Cooperative Agreement for this MAS.
Status Reporting; Status reports will be submitted on a quarterly basis in accordance with the financial
reporting submittals. The City of Fort Worth shall refer to 44 CFR 13.4 to obtain minimum requirements
for status reporting. The Project Officer,as needed,may request additional information on status.
The City of Fort Worth may meet with FEMA and/or its contractor up to bi-weekly,or more frequently if
needed,to review the progress of the project in addition to the quarterly financial and status submittals.
These meetings will alternate between FEMA's Regional Office,the City of Fort Worth office,and
conference calls,as necessary.
Earned Value Data Entry:
The City of Fort Worth will update the Earned Value Status on the MIP workflow monthly,in
coordination with the submittal of the Monthly Progress Report.
SECTION 11-PROJECT COORDINATION
Throughout the project, all members of the Regional Project Team will coordinate, as necessary,to ensure
the products meet the technical and format specifications required and contain accurate,up-to-date
information. Coordination activities may include: -
• Meetings,teleconferences,and video conferences with FEMA and other Regional Project Team
members as needed;
• Telephone conversations with FEMA and other Regional Project Team members on an ad hoc
basis,as required;
0 E-mail,facsimile transmissions,and letters,as required.
FY13 CTP-Production-MAS - City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 32 of 33
I
SECTION 12--POINTS OF CONTACT(CTP)
The points of contact for this Risk MAP Project are Ronald Wanhanen,PE,the FEMA Regional Project
Officer;Clair Davis,PE,CFM,the Project Manager for the City of Fort Worth;or subsequent personnel
of comparable experience who are appointed to fulfill these responsibilities. When necessary,any
additional FEMA assistance should be requested through the FEMA Regional Project Officer.
Each party has caused this MAS to be executed by its duly authorized representative.
Clair Davis,PE,CFM Date
Project Manager
City of Fort Worth
Ronald Wanhanen,PE Date
Regional Project Officer
Federal Emergency Management Agency,Region VI
I
I
FY13 CTP-Production-MAS -City of Fort Worth(Version 2.0)
Mapping Activity Statement No. 1 33 of 33
M&C Review Pagel of3
Official site of the City of Fort Worth,Texas
CITY COUNCIL AGENDA
. 1JRT IVORTlt
COUNCIL ACTION: Approved on 5/13/2014 - Ordinance Nos. 21236-05-2014 & 21237-05-2014
DATE: 5/13/2014 REFERENCE NO.:**C-26796 LOG NAME: 20FEMACTP13-
14AMENDMENT
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: Amend Mayor and Council Communication C-26381 Increasing the Grant Application
Amount with the Federal Emergency Management Agency from $150,000.00 to
$154,147.00 for the Cooperating Technical Partners Program to Produce Flood
Insurance Rate Maps and Related Information, Authorize Execution of a Professional
Services Contract and Adopt Appropriation Ordinances (ALL COUNCIL DISTRICTS)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize the amendment of Mayor and Council Communication C-26381 increasing the grant
application amount with the Federal Emergency Management Agency from $150,000.00 to
$154,147.00 for the Cooperating Technical Partners program;
2. Authorize the use of$422,000.00 from the Stormwater Utility Fund as an in-kind match for this
Agreement;
3. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in
the Grants Fund in the amount of$4,147.00;
4. Authorize the execution of a Professional Services Agreement with Halff Associates, Inc., for an
amount not to exceed $159,147.00 for the Cooperating Technical Partners program Mapping
Services; and
5. Adopt the attached supplemental appropriation ordinance increasing appropriations in the
Stormwater Utility Fund and decreasing the unreserved, undesignated fund balance in the amount of
$5,000.00.
DISCUSSION:
Since November, 2012, the City of Fort Worth has been participating with the Federal Emergency
Management Agency (FEMA) as a Cooperating Technical Partner (CTP). Through CTP, FEMA
provides funds to participating communities in order to update Special Flood Hazard Areas shown on
Flood Insurance Rate Maps (FIRM's) according to a Mapping Activity Statement (MAS) prepared by
the City that is updated annually.
On August 6, 2013, (M&C C-26381) the City Council approved the application for and acceptance of
a grant from the Federal Emergency Management Agency, in the amount up to $150,000.00, for the
Cooperating Technical Partners program to provide funding to produce flood insurance rate maps
and other flood hazard information for 15 local streams. FEMA has notified the Transportation and
Public Works Department that an additional $4,147.00 of grant funding is available from the FEMA
Fiscal Year 13 budget for the CTP Program. This Mayor and Council Communication authorizes the
additional grant amount of$4,147.00 for a total grant of$154,147.00.
All of the streams selected for mapping updates with this grant are unstudied approximate flood
zones or have outdated studies that need to be revised. Updating FIRM's through CTP provides
http://apps.cfivnet.org/council_packet/mc_review.asp?ID=19067&counciIdate=5/13/2014 6/4/2014
M&C Review Page 2 of 3
benefits to Fort Worth residents by developing the most accurate flood zone limits and base flood
elevations so that the lowest possible flood insurance premiums are available. FEMA benefits by
leveraging recent City-sourced stream studies to provide up-to-date flood risk analyses for accurate
FIRM's. City regulatory capabilities benefit from improved digital mapping products, and new non-
regulatory flood risk products enhance information and outreach efforts. Local QA/QC of the updated
FIRM's ensure that mapping errors are eliminated prior to official publication.
FIRM updates through CTP for these 15 streams will result in savings of Stormwater Utility funds of
approximately $375,000.00 compared to regular FEMA Letter of Map Revision (LOMR) process
expenses, assuming a conservative estimate of$25,000.00 per stream.
The in-kind services match for this grant is based upon qualifying portions of previously-completed
open channel studies in the amount of$417,000.00. An additional $5,000.00 is being contributed to
the match in order to provide on-ground survey for bridge and culvert structures, bringing the total in-
kind contribution to $422,000.00. The total funding available for mapping and additional services is
$159,147.00.
Halff Associates, Inc., has provided the specialized technical services associated with FEMA's CTP
program to the City of Dallas for four years and to the City of Grand Prairie for 13 years. Halff
Associates, Inc., proposes to perform the specified CTP services for a lump sum fee of
$159,147.00. Staff has determined the proposed cost to be reasonable for the scope of services
proposed, and exactly matches the MAS and awarded grant funds as required by FEMA.
M/WBE Office - Halff Associates, Inc., is in compliance with the City's BDE Ordinance by committing
to an additional 13.2 percent SBE participation on this contract. The City's goal on this contract is 13
percent.
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies that upon approval of the above
recommendations, receipt of the grant and adoption of the attached appropriation ordinance, funds
will be available in the Fiscal Year 2014 operating budget, as appropriated, of the Grants Fund.
TO Fund/Account/Centers FROM Fund/Account/Centers
GR76 451583 020446670000 4147.00 GR76 531200 020446670010 $154,147.00
GR76 531200 020446670010
$4,147.00 4.5) PE69 531200 0209207 $5,000.00
?)
GR76 488279 020446670000 $422,000.00
GR76 533280 020446670020 $422,000.00
5) PE69 531200 0209207 $5,000.00
Submitted for City Manager's Office by: Fernando Costa (6122)
Originating Department Head: Douglas W. Wiersig (7801)
Additional Information Contact: Cindy Robinson (7947)
http://apps.cAvnet.org/council_packet/mc_review.asp?ID=19067&councildate=5/13/2014 6/4/2014
M&C Review Page 1 of 2
Official site of the City of Fort Worth,Texas
CITY COUNCILAGENDA FORT WORTH
COUNCIL ACTION: Approved on 8/6/2013 -Ordinance No. 20855-08-2013
DATE: 8/612013 REFERENCE NO.: C-26381 LOG NAME: 20FEMACTP13-14
CODE: C TYPE: NON-CONSENT PUBLIC NO
NO
SUBJECT: Authorize Application for and Acceptance of, if Awarded, a Grant from the Federal
Emergency Management Agency in the Amount Up to $150,000.00 for the Cooperating
Technical Partners Program to Manage Flood Plain Boundaries and Adopt Appropriation
Ordinance (ALL COUNCIL DISTRICTS)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize the application for and acceptance of, if awarded, a grant from the Federal Emergency
Management Agency in the amount up to $150,000.00 for the Cooperating Technical Partners Program;
2. Authorize the execution of a contract with the Federal Emergency Management Agency for the
Cooperating Technical Partners Program to manage flood plain boundaries for the period October 1, 2013
through September 30, 2014, upon receipt of the grant; and
3. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Grants Fund in the amount up to $150,000.00, subject to receipt of the grant.
DISCUSSION:
The purpose of this Mayor and Council Communication is to authorize a grant application to the Federal
Emergency Management Agency (FEMA) for the Cooperating Technical Partners (CTP) Program to
provide funding to produce flood insurance rate maps and other flood hazard information for 15
streams. The purpose of the CTP Program is to provide an innovative approach between FEMA and local
communities that have the capability to become active participants in the FEMA flood hazard mapping
program. Communities that participate in the CTP Program collaborate directly with FEMA in maintaining
up-to-date flood hazard maps and flood hazard information. The overall outcome of this effort will be more
timely development of accurate floodplain maps, leading to savings in flood insurance premiums to many
Fort Worth residents. Staff estimates that this specific effort could save up to a total of$200,000.00 per
year in flood insurance premiums.
FEMA has notified the City of Fort Worth that funds are available for the CTP Program. The Storm Water
Management Division of the Transportation and Public Works Department will administer the CTP Program.
This program serves ALL COUNCIL DISTRICTS.
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies that upon approval of the above recommendations,
receipt of the grant and adoption of the attached appropriation ordinance, funds will be available in the
Fiscal Year 2014 operating budget, as appropriated, of the Grants Fund.
TO Fund/Account/Centers FROM Fund/Account/Centers
GR76 451583 020450670000 $150,000.00
GR76 5XXXXX 020450670010 $150,000.00
Submitted for City Manager's Office by:
http://apps.cfwnet.org/council_packet/me review.asp?ID=18 8 15&councildate=8/6/201 3 6/19/2014
M&C Review Page 2 of 2
Fernando Costa (6122)
Originating Department Head: Douglas W. Wiersig (7801)