HomeMy WebLinkAboutContract 29000 AMENDMENT NO. 3
f)r,
STATE OF TEXAS CITY SECRETARY CONTRACT NO. C>Q0ou
(No M&C Needed)
COUNTY OF TARRANT
WHEREAS, the City of Fort Worth (City) and LOPEZGARCIA Group,
(Engineer) made and entered into City Secretary Contract No.
26419, (the Contract) which was authorized by the City Council by
M&C C-18321 on the 31st day of October, 2000, and subsequently
amended by two previous amendments; and,
WHEREAS, the Contract involves engineering services for the
following project:
Risinger Road - Southside II Water Transmission Main
WHEREAS, it has become necessary to execute Amendment No. 3
to said Contract to include an increased scope of work and revised
maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and
through their duly authorized representatives, enter into the
following agreement which amends the Contract:
1.
Article I of the Contract is amended to include the
additional engineering services specified in a proposal letter
dated July loth, 2003 a copy of which is attached hereto and
incorporated herein. The cost to City for the additional design
services to be performed by Engineer total $10, 810 . 00
2 .
Article II of the Contract is amended to provide for an
increase in the maximum fee to be paid to Engineer for all work
and services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall not
exceed the sum of $197, 583 . 80 .
......... ..........
s",
3 .
All other provisions of the Contract which are not expressly amended
herein shall remain in full force and effect.
EXECUTED on this the A;� day of "--A
2003, in Fort Worth, Tarrant County, Texas .
ATTEST:
� ntract hut�:oriza►tion
" G1 ria Pearson qty Secretary
APPROVED:
AP
" PRO 7
: .
("
A. Douglas Rademaker, P.E. Marc Ott
Director, Department of Assistant City Manager
Engineering
LOPEZGARCIA
ENGINE
Name: Wendy Lopez, P.E.
LOPEZGARCIA Group
6850 Manhattan Blvd. , Ste 300
Fort Worth TX 76120
APPROVED AS TO FORM AND LEGALITY:
Gary Steinberger
Assistant City Attorney
ENGI.FRM(NO M&C)
-2- �
m
U,
July 10, 2003
Mr. Rakesh Chaubey, P.E.
Project Manager
City of Fort Worth - Engineering Department
Engineering Services Division
900 Monroe Street, Suite 201
Fort Worth, Texas 76102
RE: Additional Services (Paving Improvements, Traffic Control, SWPPP)
Risinger Road — Southside 11 Water Transmission Main
(Crowley Rd. to McCart Ave. Pump Station & Ground Storage Tank)
D.O.E. No. 2968
LGGROUP Project No. 201006.00
Amendment No. 3
Dear Mr. Chaubey:
This letter is in response to the City of Fort Worth's request to provide the following
additional services:
• Pavement improvement details (approx. 2 sheets)
• Traffic Control Plan and details (approx. 3 sheets)
• SWPPP
The additional fee to provide the above mentioned services is $10,810.00.
(See Attachments— Supplemental Fee Schedules).
If you have any questions or need additional information concerning this request, please
feel free to call me at(817) 446-1800.
Sincerely,
LOPEZGARCIA GROUP
Richard W. Albin, P.E.
Municipal Division Manager
RWAfbel
attaclunents
City of Fort Worth
Fee Schedule -Pavement Improvements
Contract No. C-18321
LGGROUP No. 201006.00
Amendment No. 3
7-10-03
LOPEZGARCIA GROUP
Direct Labor
Item Labor Category Hours Rate Labor Cost
002 Project Manager 4 $ 140.00 $ 560.00
05
0Civil Engineer-In-Training 16 $ 70.00 $ 1,120.00
007 CADIZ Technician
_ 32 $ 55.00 $ 1,760.00_
n
Subtotal for Direct Labor $ 3,440.00
Overhead(if applicable) Rate: 0.00% $ -
Professional Fee(if applicable) Rate: 0.00% $ -
Total Direct Labor $ 3,440.00
Direct Costs
Travel Description of travel: describe trip here
Unit of
Description Measure Quantity Rate Totals
Per diem for lodging Day 0 $ 59.00 $ -
Subtotal of Travel Costs $ -
Other Direct Costs
Unit of
Description Measure Quantity Rate Totals
Expendable field supplies Lump Sum 0 $ - $
Subtotal of Other Direct Costs $ -
Subcontractor Costs
Unit of
Description Measure Quantity Rate Totals
[other] Lump sum 0 $ - $ -
Subtotal of Subcontractor Costs $ -
Subtotal of Direct Costs $ -
Professional Fee(if applicable) Rate: 0.00% $ -
Total Direct Costs $ -
Project Totals
Total Labor Costs $ 3,440.00
Total Direct Costs $ -
TOTAL DELIVERY ORDER COST $ 3,440.00
City of Fort Worth
Fee Schedule-Traffic Control Plans
Contract No. C-18321
LGGROUP No. 201006.00
Amendment No. 3
7-10-03
LOPEZGARCIA GROUP
Direct Labor
Item Labor Category Hours Rate Labor Cost
002 Project Manager 4 $ 140.00 $ 560.00
005 Civil Engineer-In-Training 16 $ 70.00 $ 1,120.00
007 CADD Technician 40 $ 55.00 $ 2,200.00_
Subtotal for Direct Labor $ 3,880.00
Overhead(if applicable) Rate: 0.00% $ -
Professional Fee(if applicable) Rate: 0.00% $ -
Total Direct Labor $ 3,880.00
Direct Costs
Travel Description of travel: describe trip here
Unit of
Description Measure Quantity Rate Totals
Per diem for lod ing Day 0 $ ..11 59.00 $
Subtotal of Travel Costs $ -
Other Direct Costs
Unit of
Description Measure Quantity Rate Totals
Expendable field supplies Lump Sum 0 $ - $ -
Subtotal of Other Direct Costs $ -
Subcontractor Costs
Unit of
Description Measure Quantity Rate Totals
[other] Lump sum 0 $ - $ -
Subtotal of Subcontractor Costs $ -
Subtotal of Direct Costs $ -
Professional Fee(if applicable) Rate: 0.00% $
Total Direct Costs $ -
Project Totals
Total Labor Costs $ 3,880.00
Total Direct Costs $ -
TOTAL DELIVERY ORDER COST $ 3,880.00
City of Fort Worth
Fee Schedule-SWPPP
Contract No. C-18321
LGGROUP No.201006.00
Amendment No. 3
7-10-03
LOPEZGARCIA GROUP
Direct Labor
Item Labor Category Hours Rate Labor Cost
002Project Manager 4 $ 140.00 $ 560.00
005 Civil Engineer-In-Training 8 $ 70.00 $ 560.00
_ ------ _ ......_
007 CADD Technician 24 $ 55.00 $ 1,320.00
_ _ _ -..._-.-
�, -Environmental Engineer -2 $ 105-00- $ 210.00
019 Environmental Engineer-I ri-Trainin12 $ 70.00 $ 840.00
Subtotal for Direct Labor $ 3,490.00
Overhead(if applicable) Rate: 0.00% $ -
Professional Fee(if applicable) Rate: 0.00% $
Total Direct Labor $ 3,490.00
Direct Costs
Travel Description of travel: describe trip here
Unit of
Description Measure Quantity Rate Totals
_ .... . ...... _..._._.
Per diem for lodging Day 0 $ 59.00 $ -
Subtotal of Travel Costs $ -
Other Direct Costs
Unit of
Description Measure Quantity Rate Totals
Expendable field supplies Lump Sum 0 $ - $
Subtotal of Other Direct Costs $ -
Subcontractor Costs
Unit of
Description Measure Quantity Rate Totals
[other] Lump sum 0 $ - $ -
Subtotal of Subcontractor Costs $ -
Subtotal of Direct Costs $ -
Professional Fee(if applicable) Rate: 0.00% $
Total Direct Costs $ -
Project Totals
Total Labor Costs $ 3,490.00
Total Direct Costs $ -
TOTAL DELIVERY ORDER COST $ 3,490.00
MEMORANDUM
TO: A. Douglas Rademaker, Director, DOE; and
Marc Ott, Assistant City Manager
FROM: Rakesh Chaubey, DOE
DATE: August 4`h, 2003 _
RE: DESIGN FEE AMENDMENT NO. 3 TO RISINGER ROAD -- SOUTHSIDE II
WATER TRANSMISSION MAIN
P160 060160140020
DOE 2968
The proposed amendment will allow Wendy Lopez and Associates, Inc. dba. LOPEZGARCIA
GROUP,to provide additional design and survey services to the project as requested by the City.
This amendment covers the cost of engineering work that is necessary for the following reasons:
v Preparation of Stormwater Pollution Prevention Plan (SWPPP), as now required by the Texas
Dept. of Environmental Quality
v Inclusion of extra work required (Traffic Control Plan &Pavement Improvements) which was
not a part of the original contract.
LOPEZGARCIA GROUP has submitted a fee in the amount of$10,810.00 for the additional work as
described above, thereby increasing the contract fee from $186,773.75 to $197,583.80. 1 believe this fee
is fair and reasonable for the additional work to be done. It is recommended that the request be approved.
Two previous amendments have been processed to this contract.
Please authorize additional fee by your signatures on the attached contract amendment forms.
Rakesh Chaubey
Attachment
Cc: Berdena Hamilton, Water Department
Dan Pepon, Water Department.