HomeMy WebLinkAboutContract 29110-CO2A8 City of Fort Worth C9 Change Order Request COMRACTNO. �, -� it,� Change Order No. Date TPW Project No. Funding(FAC) 2 (Two) 8/13/14 FE 72 541350 002500100000 Facility and Project Description City Secretary Contract No. Energy Savings Performance Contract— JCI VII 29110-A8 ORIGINAL CONTRACT AMOUNT................................................................ $10,955,452 EXTRAS TO DATE..................................................................... $ 26,000 CREDITS TO DATE.................................................................... $ 0 CONTRACT COST TO DATE.................................................................................................. $ 10,981,452 AMOUNT OF PROPOSED CHANGE ORDER............................................................................ $ 36,857 REVISED CONTRACT AMOUNT............................................................................................. $ 11,018,309 ORIGINAL FUNDS AVAILABLE FOR CHANGE ORDERS............................................................ $ 100,000 REMAINING FUNDS AVAILABLE FOR CHANGE ORDERS......................................................... $ 74,000 ADDITIONAL FUNDING (IF NECESSARY)................................................................................ $ 36,857 IN ACCORDANCE WITH THIS CHANGE ORDER, THE CONTRACTOR SHALL: Provide all labor and materials as per attached Proposed Change Requests: Add three new ductless split systems for supplemental 24/7 cooling in two TV Control rooms and an adjacent server room on the 2nd floor of City Hall north of Council Chambers, add $36,857 ------------------------------------------------------------------------------------------------------------------------------ TOTAL ADD $36,857 s It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order Contractor's Name Johnson Controls Inc. (` Original Contract Time Additional Approved Time To Date Approved Contract Time To Date Additional Time For This Change Order 610 cd Ocd 610 cd 0 cd Contra r-Johnson Controls Inc Date Con ructio ger Date /I�+OZe t Architectural Services nager Date D#6,tQlrl Transportation and Public works Date Project Architect U Date Assistant khty Manager Date 44 r Date 1, rn Council Action If Required) y d ❑ Approved ❑ Disapproved ssist n�k city fit ❑ Other i Distribution i F ruc t i ID C IVE® AW 0qP 0 $ e�� 9 f g 0 � � ��oi�or oil WORTH, r �w TPW Facilities Management Division � ,°� 00 er Sic 00000 Change Order Form(12 O Johnson Controls,Inc. f/ 7461 Airport Freeway Richland Hills,Texas 76118 Johnson Tel.:(817)548-2200(Office) Controls (817)548-2201(Fax) August 11, 2014 Mr. Sam Gunderson City of Fort Worth Transportation & Public Works 401 W 13th Street Fort Worth, TX 76102 Ref: JCI ESPC Phase VII Subject: City Hall —TV Control Room Ductless Split Systems Dear Sam, JCI has developed the following scope of work for City consideration: Scope of Work I Cost Two 2 new 1-ton &one 1 new 3-ton ductless split systems. 1 $36,857 Scope of Work: • Two (2) new 1-ton high-efficiency cooling-only ductless split systems to serve Control Rooms A & B (24/7 area) • One (1) new 3-ton high-efficiency cooling-only ductless split systems to serve the Server Room (24/7 area) • Refrigerant piping • Condensate piping and pumps • Roofing work • Condensing unit concrete pads • Two (2) new 2'x 2'access doors to allow access above hard ceilings Benefits: • Provides additional cooling for Control Rooms &Server Room • Allows Central Plant to be shutdown during most nighttime &weekend hours Exclusions: • Asbestos abatement • Electrical • Metasys controls • TAB If you have any questions, please give me a call at 817-480-6953. Regards, r Harry Romine, P.E. Account Manager. Johnson Controls, Inc. Page 2 f