HomeMy WebLinkAboutContract 29320 AMENDMENT NO. 4
STATE OF TEXAS $ CITY SECRETARY CONTRACT NO. Z�9
(No M&C Needed)
COUNTY OF TARRANT $
WHEREAS, the City of Fort Worth (City) and Gutierrez, Smouse,
Wilmut & Associates, Inc. , (Engineer) made and entered into City
Secretary Contract No. 26802, (the Contract) which was authorized
by the City Council by M&C C-18597 on the 22nd day of May 2001;
and subsequently revised by three previous amendments; and
WHEREAS, the Contract involves engineering services for the
following project:
Engineering contract for the design of Sanitary Sewer
Rehabilitation Contract LXIII (63) .
WHEREAS, it has become necessary to execute Amendment No. 4
to said Contract to include an increased scope of work and revised
maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and
through their duly authorized representatives, enter into the
following agreement which amends the Contract:
1 .
Article I of the Contract is amended to include the
additional engineering services specified in a proposal letter
dated October 15, 2003 , a copy of which is attached hereto and
incorporated herein. The cost to City for the additional design
services to be performed by Engineer total $7, 229 . 00 .
2 .
Article II of the Contract is amended to provide for an
increase in the maximum fee to be paid to Engineer for all work
and services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall not
exceed the sum of $101, 845. 55 .
3 .
All other provisions of the Contract which are not expressly amended
herein shall remain in full force and effect.
EXECUTED on this the ��J day of 2003, in Fort
Worth, Tarrant County, Texas.
ATTEST: �b
--,r=Tact Authorization
Glo ' a Pearson, City Secretary _r
APPROVAL RECOMMENDED: APP ED:
- � - V
A. Douglas Rademaker, P.E. Marc A. O t
Director, Department of Assistant City Manager
Engineering
Gutierrez, Smouse, Wilmut & Associates, Inc.
ENGINEFgR/
J�
By:
Name: Gre Lens, P.E.
Proiect Manager
3950 Fossil Creek Blvd. , Ste 210
Fort Worth, TX 76137
APPROVED AS TO FORM AND LEGALITY:
Gary Stei erger
Assistant City Attorney
22266-6 '����b� �, l' :'.��►���
-2-
IL1kU
F . JX.
GSWW, Inc.
Civil/Environmental Engineers■Planners
Dallas■ Fort Worth■Midland■Austin
Predecessor Firms: Gutierrez,Smouse,Wilmut&Assoc.,Inc.
Washington&Associates,Inc.
October 15, 2003
City of Fort Worth
Department of Engineering
900 Monroe Street, 2nd Floor
Fort Worth, Texas 76102
Attention: Mr. Mike Domenech, P.E., Project Manager
Re: Supplemental Autorizabon Request No. 4,
CONTRACT LXIII, Sanitary Sewer Rehabilitation; Unit 1/DOE No. 3358 &
Unit 2/DOE No.3891, Sewer Project No. PS58-070580175510; GSW #1007-003
Mr. Domenech:
This letter is our formal request for Supplemental Authorization to be compensated for
additional engineering services as requested by the City.
Justification
In review of the existing L-483 backyard sewer main with City Staff, it has been
determined that the best solution to provide sufficient depth for the sanitary sewer
service to 2309 Edwin Street and minimize inconvenience to the downstream home
owners will be to construct a new 8-inch public sanitary sewer main from L-483R in
Mistletoe Drive east up Edwin Street for about 580 feet and then install 100 feet of new
sanitary sewer service line for 2309 Edwin Street. This new sewer main was not in the
original engineering contract scope or any of the previous amendments, therefore
additional surveying and engineering design will be required. GSW's contract with -the
MWBE surveyor is attached.
The additional costs are summarized below:
• Additional surveying for 8-inch sewer main in Edwin St.
by A.N.A. Consultants, L.L.0 (MWBE firm) $ 2,040.00
• Additional design for 8-inch sewer main in Edwin Street $ 5,189.00
TOTAL FOR PROPOSED AMENDMENT NO. 4 FEE $ 7,229.00
3950 Fossil Creek Boulevard,Suite 210, Fort Worth,Texas 76137 . 817.306.1444 . 817.306.1555 Fax . www.gsw-inc.com
City of Fort Worth October 15,2003 Paye 2
Unit 11DOE#3358& Unit 21DOE#3891
PROJECT FEE DETAILS
Contract Item Description Fee
Original Contract Contract LXIII San. Sewer Rehab $ 67,704.00
Amendment No. 1 Additional Survey & Easements $ 14,557.55
Amendment No. 2 Sanitary Sewer Lateral L-558
Redesign $ 8,765.00
Amendment No. 3 Design of Sewer Services $ 3,590.00
Amendment No. 4 Edwin Street Sewer Design $ 7,229.00
TOTAL PROJECT FEE $101.845.55
If you have any questions or need additional information concerning this request, please
call me.
Respectfully submitted
Gutierrez, Smouse, Wilmut & Assoc., Inc.
Gregory . D' in P.E.
Associat d ct Manager
Enclosures
\\Sery r2k\$Documents\CORRESPONDENCaGSWW Itr-2003\101503-IGWD-1007-003-amend4¢rev.doc
I
I
CITY OF FORT WORTH
AMENDMENTS, CHANGE ORDERS or EXTRA WORK
CONTRACT COMPLIANCE MEMORANDUM
THIS FORM MUST BE ATTACHED TO THE ROUTING "M & C"BEFORE LEGAL
AND CITY MANAGER APPROVAL
To: Tony Sholola
(underline appropriate ote) Project Manager Buyer Department Director
From: Rachel Ortega `� 6104
M1WBE Office Staff y Extension
Date: October 28, 2003
In the Amount of $7,229.00 DOE 3358
Project Number
Project/Bid: Amendment No. 4 for the Design of Contract LX111 (63), Sanitary
Sewer Rehabilitation
Compliance with the City's M/WBE Ordinance as it relates to amendments, which
exceed ten precent (10%) of the original contract amount has been achieved by one
of the following methods:
a). is in compliance with the City's MAMBE Ordinance by committing to an additional
0% M/WBE participation on this Amendment/Change Order No._
b). GSWW, Inc. is in compliance with the City's M/WBE Ordinance by committing to an
additional 28 % M/WBE participation on this Amendment/Change Order No. 4 . The
City's goal on this amendment, change order or extra work is 12 %.
c), is in compliance with the City's M/WBE Ordinance by documenting good faith effort.
The City's goal on this amendment, change order or extra work is 0 %.
d). is in compliance with the City's M/WBE Ordinance by approval of a waiver request
of the M/WBE requirement. The City's goal on this amendment, change order or extra
work is 0 %.
05/11/99
r
FORT WORTH
MEMORANDUM
TO: A. Douglas Rademaker, Director DOE and
Marc A. Ott, Assistant City Manager
FROM: Miguel A. Domenech, P.E.
DATE: November 7, 2003
RE: DESIGN FEE AMENDMENT NO. 4 TO SANITARY SEWER REHABILI-
TATION CONTRACT LXIII (63), DOE NO. 3358, WATER PROJECT NO.
PS58-070580175510
The proposed amendment will allow Gutierrez, Smouse, Wilmut & Associates, Inc.,
(GSWA)•to provide additional survey and design on the project as requested by the City.
Subsequent to completing design of the project, it has been determined that lateral L-483
needs to be deepened in order to provide trouble free sanitary sewer service to residences lo-
cated on Edwin Street. A new 8-inch sanitary sewer main is proposed from L-483R in Mis-
tletoe Drive east up Edwin Street for about 580 linear feet along with 100 linear feet of new
sanitary sewer service line.
Gutierrez, Smouse, Wilmut & Associates, Inc., has requested a fee of$7,229.00 for the addi-
tional services to be provided thereby increasing the contract fee from $94,616.55 to
$101,845.55. I believe this fee is fair and reasonable for the additional services that were pro-
vided.
Please authorize this additional design fee by your signatures on the attached contract
amendment form.
cc: Tony Sholola, P.E., Program Manager
Berdena Hamilton, Water Department
Dan Pepon, Water Department
MEMO 7642
F ENGINEERING DEPARTMENT
THE CITY OF FORT WORTH * 1000 THROCKMORTON STREET * FORT WORTH, TEXAS 76102-6311
(817) 871-7941 * Fax (817) 871-7854
Printed on recycled pape.