HomeMy WebLinkAboutContract 29616 y CITY SECRETARY. CONTRACT NO . - AMENDMENT NO.2 STATE OF TEXAS $ CITY SECRETARY CONTRACT NO. 27845 (M&C Needed) COUNTY OF TARRANT S WHEREAS, the City of Fort Worth (City) and Wade and Associates Inc . , (Engineer) made and entered into City Secretary Contract No. 27845, (the Contract) which was authorized by the City Council by M&C C-19111 on the 4th day of June and; WHEREAS, the Contract involves engineering services for the following project: MAIN 286 AND CDSL32T DRAINAGE AREAS SANITARY SEWER EVALUATION STUDY AND IMPROVEMENTS WHEREAS, it has become necessary to execute Amendment No. 2 to said Contract to include an increased scope of work and revised maximum fee; NOW THEREFORE, City and Engineer, acting herein by and through their duly authorized representatives, enter into the following agreement which amends the Contract: 1. Article I, of the Contract is amended to include the additional engineering services specified in M&C C-19961, adopted by the City Council on 10th day of February, 2004, and further amplified in a proposal letter dated October 13th, 2003 , copies of which are both attached hereto and incorporated herein. The cost to City for the additional services to be performed by Engineer total $72, 359 . 00 . 2 . Article III, of the Contract is amended to provide for an increase in the maximum fee to be paid to Engineer for all work and services performed under the Contract, as amended, so that the total fee paid by the City for all work and services shall not exceed the sum of $1, 370, 155 . 00. RCVD NLNAL 3 . All other provisions of the Contract which are not expressly amended herein shall remain in full force and effect. EXECUTED on this the I day of 2004, in Fort Worth, Tarrant County, Texas. ATTEST: I Contract- authorization City Secretary Oae APPROVA RECOMME D: - PP V Dale A. Fissele P.E. Marc Ott - Director, Water Department Assistant City Manager Mark G. Wade, P.E. , President By: Name: APPROVED TO FORM AND LEGALITY: Assist nt City Attorney -2- v Pagel of 2 City of Fort Worth, Texas Mayor and Council Communication COUNCIL ACTION: Approved on 2/10/2004 DATE: Tuesday, February 10, 2004 LOG NAME: 60MAIN286 REFERENCE NO.: **C SUBJECT: Amendment No. 2 to the Engineering Agreement with Wade & Associates, Inc. for the Main 2E CDSL32T Drainage Areas Sanitary Sewer Evaluation Study and Improvements RECOMMENDATION: It is recommended that the City Council authorize the City Manager to execute Amendment No. Wade & Associates, Inc. for the Main 286 and CDSL32T Drainage Areas Sanitary Sewer Evaluation and Improvements, thereby increasing the amount of the agreement by $72,359, from $1,297,7 $1,370,155. DISCUSSION: On June 4, 2002 (M&C C-19111), the City Council authorized the City Manager to execute an engin( agreement with Wade & Associates, Inc. for the Sanitary Sewer Main 286 and CDSL32-T Drainage . Sanitary Sewer Study and Improvements. These mains are located near Bryant Irvin Road and IH southwest Fort Worth. On January 28, 2003 (M&C C-19448), the City Council authorized the City Manager to execute Amen( No. 1 in the amount of $298,915 for additional pipe cleaning, closed circuit television inspection (C and geographic information system (GIS) mapping. The original contract included approximately 13,000 linear feet of high priority sanitary replacement. Based on a field investigation conducted during the course of the study, it has be necessary to increase the amount of high priority sanitary sewer replacement. Within Amendment No. 2, the engineer will design an additional 2,646 linear feet of high priority sa sewer pipe rehabilitation and replacement, prepare additional temporary and permanent eas( documents, railroad permits, highway permits, and storm water pollution prevention plans, and c additional sanitary sewer service re-route plans. This project is located in COUNCIL DISTRICTS 3 and 6. Wade & Associates, Inc. is in compliance with the City's M/WBE Ordinance by committing to an add 10% M/WBE participation on this Amendment No. 2. FISCAL INFORMATION/CERTIFICATION: The Finance Director certifies that funds are available in the current capit budget,as appropriated, Sewer Capital Projects Fund. http://www.cf\vnet.org/council_packet/Reports/mc_print.asp 2/20/2004 Page 2 of 2 TO Fund/Account/Centers FROM Fund/Account/Centers P171 531200 070171140030 $72,35� Submitted for City Manager's Office by: Marc Ott (8476) Originating Department Head: Dale Fisseler (8207) Additional Information Contact: Dale Fisseler (8207) �:7 r L��•1;SIC�.d..Y http://www.cfwnet.org/council_packet/Reports/mc_pnnt.asp 2/20/2004 WflDE _8c ASSOCIAT ES,_INC. 13 October, 2003 ATTN: Mr. Chris Harder, P.E. Planning and Engineering Division Fort Worth Water Department 1000 Throckmorton Street Fort Worth, Texas 76102 RE: Submission Contract Amendment No. 2, Main 286 and CDSL32-T Drainage Basins Sanitary Sewer Evaluation Study and Improvements Sewer Project No. P171-070171140030 WADE File No. 0206A Dear Mr. Harder: We have prepared a specific amendment request for additional engineering services that have been authorized on the above referenced project, including increased quantities of permits, easements, and right of entry documents in excess of budgeted amounts. In addition, this request also includes several items that are now being required by the Department of Engineering on construction projects including the preparation of detailed sewer service re-route plans as well as the preparation of storm water pollution prevention plans. 1. The first amendment item involves the increase in design footage on this project. The following describes in detail, the changes in the design footage that were incurred on a line by line basis: Nlairi/ UPMH DSMN Budgeted Design Comments Lateral -- -11W Lenth Length* M-196 109+ 93+00 1,638 2,134 Re-route (Main D) M-190 48+71 46+53BK 218 0 Abandoned M-190 51+11 48+71 240 1,016 Re-route (Main Q) L-3658 5+34 0+00 534 982 Re-route (Line R) L-3658 9+18 8+27 91 0 See above L-4374 35+81 28+02 779 789 Alta Mere Blvd. L-5328 6+11 0+00 611 0 Abandoned L-5329 3+33 0+00 333 793 1 Line F re-route in Irene L-6661 1+90 0+00 190 602 Replaced by Line E Consulting Engineers 6701 Brentwood Stair Road `�Fy7L'�• •� 1: i J,,-::� Fort Worth, Texas 76112 -� - 81 7 . 451 • 2820 FAX 817451 •2208 "1 Page 2 of 6 Mr. Chris Harder,P.E. October 13, 2003 M-211R 47+12 45+04 208 322 Continuity section added - Oak Manor Dr. h1-211R 51+89 48+15 374 378 Hillcrest Circle M-211 75+81 63+90 1,191 1,266 Includes replacement of L- 4534(75 LF) L-4526 1+48AHD 0+00 148 149 DSMH=M-211/64+43 L-4525 8+10E 2+48 562 740 Extended to Rothington St. for future maintenance L-3104 2+70 0+00 270 271 N1-186 205+37 210+99 338 340 L.5262 25+51 20+53 498 497 L-6072 14+47 11+13 400 517 Reroute to L-6077 L-6695 2+68 0+00 268 272 L-4901 6+32 0+00 632 795 Partial realignment & includes replacement of 60 LF of L-4898. L-5266 20+15E 12+52 763 889 L-5406 8+38E 8+22 14 0 L-5406 8+22 1+73 649 831 L-5406 1+73 0+00 173 0 L-5405 0+74 0+00 72 72 DSMH=M-190R/1+11 L-2862 4+70 3+32 135 138 L-2862 14+17 10+97 320 317 L-3269 3+10 0+00 310 0 Abandoned approx. 251 LF with Line T extension L-3269 7+50 3+10 440 440 L-3270 2+00 0+00 200 0 Abandoned approx. 235 LF with Line T extension L-3270 7+00 2+00 500 480 L-3658 13+73 11+29 244 244 Addressed by Line R L-3965 14+84 14+50 34 41 L-4500 2+86 0+00 286 277 Done- emergency design Line T 0+00 7+17 0 717 Extends from L-4164, Sta. 2+45 in Clayton Rd, to intercept L-3269 &L-3270 Totals: 13,663 16,309 Shaded lines are being designed by LTS From the table above, the net increase in design footage is 2,646 LF. The additional footage at the unit price for design of $14.79/LF yields a total net fee increase of $39,134.00. The items below specifically describe the project locations with significant design changes Ilk Wade & Associates, Inc. G e ��.1/rs 'ti ., Consulting Engineers Page 3 of 6 Mr. Chris Harder, P.E. October 13, 2003 • The total design footage for the M-196 area sewer improvements was increased from 2,772 LF to 3,529 LF due to the final alignment of the sewer main re- routing that was approved. In addition, the proposed reroute required the extensions of Line E and Line F to fully serve the overall project area which resulted in the abandonment and/or replacement of L-5008, L-6661, and L-5329. • The total design footage for the M-190 area sewer improvements was increased- from ncreasedfrom 1,327 LF to 2,242 LF due to the final alignment of the sewer main re- routing that was approved for M-190 and L-3658. This project includes the replacement of the existing L-3658 from Sta. 8+27 to 5+34 which is needed for upstream grade in order to clear storm sewers in the shopping center parking lot. Additionally, M-190 was rerouted to Pelham St. and approximately 330 LF of L- 3273 will be replaced as part of this project to provide sufficient grade across Camp Bowie Blvd. • The total design footage for the Luther Lake area improvements to L-4901 and L-5266 was increased from 1,395 LF to 1,684 LF due to the final alignment and improvements for these sewer lines. Due to the complex nature of these location and close proximity to existing homes, much of these lines will be constructed using pipe reaming technology. There is also a significant amount of sewer line relocations by open cut and by other than open cut. Because of existing grade problems on the downstream end of the L-5266 replacement, the next segment of line from Sta. 12+52 to 10+80 was included in the project. Additionally, the replacement of 60 LF of L-4898 was also included in order to improve the grade for L-4901 and to clear the storm sewer in Brants Ln. • The total design footage for L-6072 was increased from 400 LF to 517 LF due to the flow reversal and reroute of L-6072 to L-6077 along Wilmington Dr. Additionally, this reroute will replace L-6073 in Wilmington Dr. • The total design footage for L-4525 was increased from 562 LF to 740 LF so that the line extends to Rothington St. for improved sewer line maintenance. • The inclusion of proposed Line T, north from Clayton Rd. along Wellington Rd., increased the total design footage from 486 LF to 717 LF. Line T intercepts L- 3269 and L-3270 and abandons the downstream portions of both L-3269 and L- 3270. 2. Another item that must be included in this amendment pertains to service reroutes for the large number of re-aligned project locations that have been discussed previously. The existing contract does not cover expenses for the detailed presentation of service re-routes that are being required by the City at this time. Therefore, we proposed a flat rate fee of$150 per service re-route and/or property. This is a reduced fee from what we charged for this task under the design portion of the Village Creek Contract. We also have determined that the number of easements, right of entry (ROE) documents, and permits will exceed the budgeted amounts for this project. The contract authorized 2 permanent easements, 8 ROE's, and ue to the 11�;MiLl lj_'A Z.EO i Wade & Associates, Inc. Consulting Engineers Page 4 of 6 Mr. Chris Harder, P.E. October 13, 2003 large number of instruments needed (see table below), we have reduced our unit fee for TxDOT permits from$1,000 to $500 and permanent easements from $700 to $500 in order to lessen the fiscal impact to the City. :blain/ Service Permanent ROE Permits Lateral Re-routes Easements Documents . M-196 4 2 7 2 - TxDOT Permits & (Main D) 1 RR Permit M-190 0 0 2 1 —TxDOT Permits (Main Q) L-3658 1 1 6 Permitted w/Main Q (Line R) L-4374 0 0 3 1 —TxDOT Permit L-5328 & 1 1 3 L-5329 (Line F) L-6661 & 2 1 3 Permitted w/Main D L-5008 (Line E) M-21 IR 0 0 1 M-211 0 0 21 L-4526 0 0 3 L-4525 2 0 16 L-3104 0 2 4 1 - RR Permit M-186 0 0 2 L-5262 0 0 3 L-6072 3 1 10 1 —TxDOT Permit L-6695 0 0 2 1 —TxDOT Permit L-4901 3 2 8 L-5266 7 7 11 L-5406 1 0 6 L-5405 0 0 1 L-2862 0 1 4 L-2862 0 1 4 L-3269 3 2 10 (including portion to be abandoned) L-3270 2 2 12 (including portion to be abandoned) L-3965 1 0 3 L-4500 2 0 2 Totals: 32 23 147 Wade & Associates, Inc. Consulting Engineers Page 5 of 6 Mr. Chris Harder, P.E. October 13, 2003 The total additional expense associated with these items is $29,225.00 and are itemized below: Service re-routes: (32) @ $150/ea. _ $4,800.00 Additional TxDOT Permits: (5) @ $500/ea. _ $2,500.00 Additional RR Permits: (1) @ $1,000/ea. _ $1,000.00 Additional Permanent Easements: (21) @ $500.00/ea. _$10,500.00 Additional ROE Documents: (139) @ $75/ea. _ $10,425.00 3. The final amendment item is to cover expenses associated with the preparation of Storm Water Pollution Prevention Plans (SW3Ps). Due to the diverse locations of all of these project sites, it is difficult to determine the exact number of reports that will have to be prepared for this project. At this time, we are assuming that a minimum of two reports will be needed, although more may be necessary. We are seeking $2,000 per SW3P report, for a.total cost of$4,000.00. A summary table of all of the amendment items and costs associated with Contract Amendment No. 2 are as follows: Amendment Item Description Quantities Unit Prices Total Costs Additional Design Footage 2,646 LF $14.79 $39,134.00 Service Re-route Design 32 Ea $150.00 $4,800.00 Additional TxDOT Permits 5 Ea $500.00 $2,500.00 Additional RR Permits 1 Ea $1,000.00 $1,000.00 Additional Permanent Easements 21 Ea $500.00 $10,500.00 Additional ROE Documents 139 Ea $75.00 $10,425.00 SW3P Report Preparation 2 Ea $2,000.00 $4,000.00 TOTAL AMENDMENT FEE: $72,359.00 Therefore, we are requesting Contract Amendment No. 2 to the Main 286 & CDSL32-T Agreement in the amount of $72,359.00. This amendment represents approximately a five and one half percent (5.58%) increase in the total contract value. For your convenience, a summary of the total project fees are as follows: Contract Item Fee Original Contract Amount $ 998,881.00 Amendment No. 1 $ 298,915.00 Amendment No. 2 $ 72,359.00 Revised Contract Value $ 1,370,155.00 Wade & Associates, Inc. Consulting Engineers Li Page 6 of 6 Mr. Chris Harder, P.E. October 13, 2003 We realize that this is a large amendment request and it comes at a difficult time for the City due to funding concerns. We have tried to thoroughly note the items this amendment covers and hopefully provided reasonable and sufficient justifications for the recovery of these costs. We would be pleased to discuss this matter in greater detail at your convenience. Please do not hesitate to contact me should you have questions or need any background information concerning this matter. Thank you for your time and consideration. WAD & TES, INC. kris B oks, P ASSOC, Project ana r CC: Peter Fu, P.E., FWWD, City of Fort Worth Dan Hegwald, P.E., Senior Associate, WADE Mark Wade, P.E., President, WADE Wade & Associates, Inc. Consulting Engineers