WHEREAS, the City of Fort Worth (City) and Dunaway
Associates, Inc . , (Engineer) made and entered into City Secretary
Contract No. 27650, (the Contract) which was authorized by the
City Council by M&C C-19049 on the 16th day of April, 2002, and
subsequently revised by seven previous amendments; and
WHEREAS, the Contract involves engineering services for the
following project:
Sanitary Sewer Rehabilitation Contract LV (55) .
WHEREAS, it has become necessary to execute Amendment No. 8
to said Contract to include an increased scope of work and revised
maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and
through their duly authorized representatives, enter into the
following agreement which amends the Contract:
1.
Article I of the Contract is amended to include the
additional engineering services specified in a proposal letter
dated January 31, 2005, a copy of which is attached hereto and
incorporated herein. The cost to City for the additional design
services to be performed by Engineer total $24, 674 . 00 .
2 .
Article II of the Contract is amended to provide for an
increase in the maximum fee to be paid to Engineer for all work
and services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall not
exceed the sum of $658, 657 .42 .
02-07-05P02' : 20 RCV0 ORIGINAL
3 .
All other provisions of the Contract which are not expressly amended
herein shall remain in full force and effect.
EXECUTED on this the day of 2005, in Fort
Worth, Tarrant County, Texas.
ATTEST: LLULdw�el
P�\(�,� • Contract Authorizatic;,
Marty Hendri , City Secretary Date
APPROVAL RECOMMENDED: APPROVED: j
f
A. Douglas Rademaker, P.E. Marc A. , Ott '
Director, Department of Assistant City Manager
Engineering
Dunaway Associates, Inc .
ENGINE!
By:
Name: Brian S . Darby, P.E.
Associate
1501 Merrimac Circle, Ste 100
Fort Worth, TX 76137
APPROVED AS TO FORM AND LEGALITY:
4
Gary Steinberger
Assistant City Attorney
-2-
DunawayEngineers
lanners
Surveyors
Associates, L.1 Landscape Architects
DAI No. 2001223
January 31, 2005
Mr. Mike Domenech, P,E,
Project Manager
City of Fort Worth
Department of Engineering
Fort Worth, Texas 76102
Reference: Amendment No. 8-Revised
Sanitary Sewer Rehabilitation
Contract LV (55)
Sewer Project No. PS 58-070580175100
D.O.E. Project No. 3569
Dear Mr. Domenech:
Dunaway Associates, Inc. is pleased to present this Amendment No. 8 for the following
additional services that are beyond our original scope of services.
Part 1 (M-17)
• Split Contract 55, Part 1 (M-17) plans, specifications, and opinion of probable
construction costs into 3 separate construction units for separate advertisement dates.
• Re-design of 1,240 LF of sanitary sewer line for adequate flow capacity due to project
split and maintain connection between existing sewer system and phased proposed
sewer system.
• Additional design of 325 LF of sanitary sewer line for temporary connection between
existing sewer system and phased proposed sewer system.
• Coordination with City and Pate Engineers for design &scheduling.
• Additional pre-construction assistance for 2 extra construction units.
a Bidding assistance—2 additional
o Pre-construction conferences—2 additional
o Public meetings—2 additional
o Final inspections—2 additional
tw
• Reimbursibles ��1 �a 1;
q
1501 Merrimac Circle•Suite 100•Fort Worth,Texas 76107
Tel:817.335.1121•Metro:817.429.2135•Fax:817.335.7437
www.dunawayassociates.com
• Amendment No. 8
January 31, 2005
Page 2
A summary of the proposed budget for this revised amendment is as follows:
Basic Fee
Part 1
Split C-55 Part 1 M-17 plans, specs, &cost estimate $ 8,000.00
Re-design of 1,240 LF of sewer $ 6,200.00
Design of 325 LF of sewer $ 3,250.00
Coordination $ 2,000.00
Pre-construction assistance $ 4,000.00
Reimbursables 1,224.00
TOTAL PROPOSED AMENDMENT $ 24,674.00
A summary of the total project is as follows:
Contract Description Fee
Original Contract Design of 21,396 LF of Sewer Improvements $315,790.12
Amendment No. 1 Design of 6,576 LF of Sewer Improvements $86,307.50
Amendment No.2 Storm Drain TxDot permit,&CCTV of storm drain $22,270.0
Amendment No. 3 Design, re-route plans,easements,&SWPPP $123,659.30
Amendment No.4 Design of 1,125 LF of Sewer Improvements,TxDOT $24,865.9
permit and easements.
Amendment No. 5 Design of 1,822 LF of Sewer Improvements&TROE's $24,682.60
Amendment No.6 Revise Contract 55 Part 1 plans $24,000.00
Amendment No. 7 Revise Contract 55 Part 2 plans $12,408.00
Amendment No. 8 Split Contract 55 Part 1(M-17) into 3 consturction units. $24,674.0
TOTAL PROJECT $ 658,657.42
Please review the enclosed information and do not hesitate to call me if you have any
questions or require additional information regarding this proposal.