STANDARD AGREEMENT FOR ENGINEERING RELATED DESIGN SERVICES
This AGREEMENT is between the City of Fort Worth, a Texas home-rule
municipality (the "CITY"), and Dunaway Associates L.P., authorized to do business in
Texas, (the "ENGINEER"), for a PROJECT generally described as: Posada Drive
Connection.
Article I
Scope of Services
A. The Scope of Services is set forth in Attachment A.
Article II
Compensation
A. The ENGINEER's compensation shall be in the amount of$68,850.00 as set
forth in Attachment B.
Article III
Terms of Payment
Payments to the ENGINEER will be made as follows:
A. Invoice and Payment
(1) The Engineer shall provide the City sufficient documentation, including but
not limited to meeting the requirements set forth in Attachment D to this
AGREEMENT, to reasonably substantiate the invoices.
(2) The ENGINEER will issue monthly invoices for all work performed under this
AGREEMENT. Invoices are due and payable within 30 days of receipt.
(3) Upon completion of services enumerated in Article I, the final payment of
any balance will be due within 30 days of receipt of the final invoice.
City of Fort Worth,Texas ®��
Standard Agreement
ase D Engineering Related Design Services RECEIVED SEP ����j
PMO Official Release Date:1/28/2013 RECEIVED q n �o�� n j:��
Page 1 of 16 1 9 v t 1
(4) In the event of a disputed or contested billing, only that portion so contested
will be withheld from payment, and the undisputed portion will be paid. The
CITY will exercise reasonableness in contesting any bill or portion thereof.
No interest will accrue on any contested portion of the billing until mutually
resolved.
(5) If the CITY fails to make payment in full to ENGINEER for billings contested
in good faith within 60 days of the amount due, the ENGINEER may, after
giving 7 days' written notice to CITY, suspend services under this
AGREEMENT until paid in full. In the event of suspension of services, the
ENGINEER shall have no liability to CITY for delays or damages caused the
CITY because of such suspension of services.
Article IV
Obligations of the Engineer
Amendments to Article IV, if any, are included in Attachment C.
A. General
The ENGINEER will serve as the CITY's professional engineering
representative under this Agreement, providing professional engineering
consultation and advice and furnishing customary services incidental
thereto.
B. Standard of Care
The standard of care applicable to the ENGINEER's services will be the
degree of skill and diligence normally employed in the State of Texas by
professional engineers or consultants performing the same or similar
services at the time such services are performed.
C. Subsurface Investigations
(1) The ENGINEER shall advise the CITY with regard to the necessity for
subcontract work such as special surveys, tests, test borings, or other
subsurface investigations in connection with design and engineering
work to be performed hereunder. The ENGINEER shall also advise
the CITY concerning the results of same. Such surveys, tests, and
investigations shall be furnished by the CITY, unless otherwise
specified in Attachment A.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date:1128/2013
Page 2 of 16
(2) In soils, foundation, groundwater, and other subsurface investigations,
the actual characteristics may vary significantly between successive
test points and sample intervals and at locations other than where
observations, exploration, and investigations have been made.
Because of the inherent uncertainties in subsurface evaluations,
changed or unanticipated underground conditions may occur that
could affect the total PROJECT cost and/or execution. These
conditions and cost/execution effects are not the responsibility of the
ENGINEER.
D. Preparation of Engineering Drawings
The ENGINEER will provide to the CITY the original drawings of all plans in
ink on reproducible mylar sheets and electronic files in .pdf format, or as
otherwise approved by CITY, which shall become the property of the CITY.
CITY may use such drawings in any manner it desires; provided, however,
that the ENGINEER shall not be liable for the use of such drawings for any
project other than the PROJECT described herein.
E. Engineer's Personnel at Construction Site
(1) The presence or duties of the ENGINEER's personnel at a construction site,
whether as on-site representatives or otherwise, do not make the
ENGINEER or its personnel in any way responsible for those duties that
belong to the CITY and/or the CITY's construction contractors or other
entities, and do not relieve the construction contractors or any other entity of
their obligations, duties, and responsibilities, including, but not limited to, all
construction methods, means, techniques, sequences, and procedures
necessary for coordinating and completing all portions of the construction
work in accordance with the Contract Documents and any health or safety
precautions required by such construction work. The ENGINEER and its
personnel have no authority to exercise any control over any construction
contractor or other entity or their employees in connection with their work or
any health or safety precautions.
(2) Except to the extent of specific site visits expressly detailed and set forth in
Attachment A, the ENGINEER or its personnel shall have no obligation or
responsibility to visit the construction site to become familiar with the
progress or quality of the completed work on the PROJECT or to determine,
in general, if the work on the PROJECT is being performed in a manner
indicating that the PROJECT, when completed, will be in accordance with
the Contract Documents, nor shall anything in the Contract Documents or
the agreement between CITY and ENGINEER be construed as requiring
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date:1/28/2013
Page 3 of 16
ENGINEER to make exhaustive or continuous on-site inspections to
discover latent defects in the work or otherwise check the quality or quantity
of the work on the PROJECT. If the ENGINEER makes on-site
observation(s) of a deviation from the Contract Documents, the ENGINEER
shall inform the CITY.
(3) When professional certification of performance or characteristics of
materials, systems or equipment is reasonably required to perform the
services set forth in the Scope of Services, the ENGINEER shall be entitled
to rely upon such certification to establish materials, systems or equipment
and performance criteria to be required in the Contract Documents.
F. Opinions of Probable Cost, Financial Considerations, and Schedules
(1) The ENGINEER shall provide opinions of probable costs based on the
current available information at the time of preparation, in accordance
with Attachment A.
(2) In providing opinions of cost, financial analyses, economic feasibility
projections, and schedules for the PROJECT, the ENGINEER has no
control over cost or price of labor and materials; unknown or latent
conditions of existing equipment or structures that may affect operation
or maintenance costs; competitive bidding procedures and market
conditions; time or quality of performance by third parties; quality, type,
management, or direction of operating personnel; and other economic
and operational factors that may materially affect the ultimate
PROJECT cost or schedule. Therefore, the ENGINEER makes no
warranty that the CITY's actual PROJECT costs, financial aspects,
economic feasibility, or schedules will not vary from the ENGINEER's
opinions, analyses, projections, or estimates.
G. Construction Progress Payments
Recommendations by the ENGINEER to the CITY for periodic construction
progress payments to the construction contractor will be based on the
ENGINEER's knowledge, information, and belief from selective sampling
and observation that the work has progressed to the point indicated. Such
recommendations do not represent that continuous or detailed examinations
have been made by the ENGINEER to ascertain that the construction
contractor has completed the work in exact accordance with the Contract
Documents; that the final work will be acceptable in all respects; that the
ENGINEER has made an examination to ascertain how or for what purpose
the construction contractor has used the moneys paid; that title to any of the
work, materials, or equipment has passed to the CITY free and clear of liens,
claims, security interests, or encumbrances; or that there are not other
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date:1/28/2013
Page 4 of 16
matters at issue between the CITY and the construction contractor that
affect the amount that should be paid.
H. Record Drawings
Record drawings, if required, will be prepared, in part, on the basis of
information compiled and furnished by others, and may not always represent
the exact location, type of various components, or exact manner in which the
PROJECT was finally constructed. The ENGINEER is not responsible for
any errors or omissions in the information from others that is incorporated
into the record drawings.
I. Minority Business and Small Business Enterprise (MBE)(SBE)
Participation
In accord with the City of Fort Worth Business Diversity Ordinance No.
20020-12-2011, as amended, the City has goals for the participation of
minority business enterprises and/or small business enterprises in City
contracts. Engineer acknowledges the MBE and SBE goals established for
this contract and its accepted written commitment to MBE and SBE
participation. Any misrepresentation of facts (other than a negligent
misrepresentation) and/or the commission of fraud by the Engineer may
result in the termination of this Agreement and debarment from participating
in City contracts for a period of time of not less than three (3) years.
J. Right to Audit
(1) ENGINEER agrees that the CITY shall, until the expiration of five (5) years
after final payment under this contract, have access to and the right to
examine and photocopy any directly pertinent books, documents, papers
and records of the ENGINEER involving transactions relating to this
contract. ENGINEER agrees that the CITY shall have access during normal
working hours to all necessary ENGINEER facilities and shall be provided
adequate and appropriate work space in order to conduct audits in
compliance with the provisions of this section. The CITY shall give
ENGINEER reasonable advance notice of intended audits.
(2) ENGINEER further agrees to include in all its subconsultant agreements
hereunder a provision to the effect that the subconsultant agrees that the
CITY shall, until the expiration of five (5) years after final payment under the
subcontract, have access to and the right to examine and photocopy any
directly pertinent books, documents, papers and records of such
subconsultant, involving transactions to the subcontract, and further, that the
CITY shall have access during normal working hours to all subconsultant
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date:1/28/2013
Page 5 of 16
facilities, and shall be provided adequate and appropriate work space, in
order to conduct audits in compliance with the provisions of this article
together with subsection (3) hereof. CITY shall give subconsultant
reasonable advance notice of intended audits.
(3) ENGINEER and subconsultant agree to photocopy such documents as may
be requested by the CITY. The CITY agrees to reimburse ENGINEER for
the cost of copies at the rate published in the Texas Administrative Code in
effect as of the time copying is performed.
K. INSURANCE
(1) ENGINEER'S INSURANCE
a. Commercial General Liability — the ENGINEER shall maintain
commercial general liability (CGL) and, if necessary, commercial
umbrella insurance with a limit of not less than $1,000,000.00 per each
occurrence with a $2,000,000.00 aggregate. If such Commercial General
Liability insurance contains a general aggregate limit, it shall apply
separately to this PROJECT or location.
i. The CITY shall be included as an insured under the CGL, using
ISO additional insured endorsement or a substitute providing
equivalent coverage, and under the commercial umbrella, if any.
This insurance shall apply as primary insurance with respect to
any other insurance or self-insurance programs afforded to the
CITY. The Commercial General Liability insurance policy shall
have no exclusions by endorsements that would alter or nullify:
premises/operations, products/completed operations, contractual,
personal injury, or advertizing injury, which are normally contained
within the policy, unless the CITY approves such exclusions in
writing.
ii. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the commercial general
liability or commercial umbrella liability insurance maintained in
accordance with this agreement.
b. Business Auto — the ENGINEER shall maintain business auto liability
and, if necessary, commercial umbrella liability insurance with a limit of
not less than $1,000,000 each accident. Such insurance shall cover
liability arising out of "any auto", including owned, hired, and non-owned
autos, when said vehicle is used in the course of the PROJECT. If the
engineer owns no vehicles, coverage for hired or non-owned is
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date:1/28/2013
Page 6 of 16
acceptable.
i. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the business auto liability or
commercial umbrella liability insurance obtained by ENGINEER
pursuant to this agreement or under any applicable auto physical
damage coverage.
c. Workers' Compensation —ENGINEER shall maintain workers
compensation and employers liability insurance and, if necessary,
commercial umbrella liability insurance with a limit of not less than
$100,000.00 each accident for bodily injury by accident or $100,000.00
each employee for bodily injury by disease, with $500,000.00 policy limit.
i. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by workers compensation and
employer's liability or commercial umbrella insurance obtained by
ENGINEER pursuant to this agreement.
d. Professional Liability — the ENGINEER shall maintain professional
liability, a claims-made policy, with a minimum of $1,000,000.00 per
claim and aggregate. The policy shall contain a retroactive date prior to
the date of the contract or the first date of services to be performed,
whichever is earlier. Coverage shall be maintained for a period of 5 years
following the completion of the contract. An annual certificate of
insurance specifically referencing this project shall be submitted to the
CITY for each year following completion of the contract.
(2) GENERAL INSURANCE REQUIREMENTS
a. Certificates of insurance evidencing that the ENGINEER has obtained all
required insurance shall be delivered to the CITY prior to ENGINEER
proceeding with the PROJECT.
b. Applicable policies shall be endorsed to name the CITY an Additional
Insured thereon, as its interests may appear. The term CITY shall
include its employees, officers, officials, agents, and volunteers as
respects the contracted services.
c. Certificate(s) of insurance shall document that insurance coverage
specified in this agreement are provided under applicable policies
documented thereon.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date:1/28/2013
Page 7 of 16
d. Any failure on part of the CITY to request required insurance
documentation shall not constitute a waiver of the insurance
requirements.
e. A minimum of thirty (30) days notice of cancellation or material change in
coverage shall be provided to the CITY. A ten (10) days notice shall be
acceptable in the event of non-payment of premium. Notice shall be sent
to the respective Department Director (by name), City of Fort Worth,
1000 Throckmorton, Fort Worth, Texas 76102.
f. Insurers for all policies must be authorized to do business in the State of
Texas and have a minimum rating of AV or greater, in the current A.M.
Best Key Rating Guide or have reasonably equivalent financial strength
and solvency to the satisfaction of Risk Management.
g. Any deductible or self insured retention in excess of $25,000.00 that
would change or alter the requirements herein is subject to approval by
the CITY in writing, if coverage is not provided on a first-dollar basis. The
CITY, at it sole discretion, may consent to alternative coverage
maintained through insurance pools or risk retention groups. Dedicated
financial resources or letters of credit may also be acceptable to the
CITY.
h. Applicable policies shall each be endorsed with a waiver of subrogation
in favor of the CITY as respects the PROJECT.
i. The CITY shall be entitled, upon its request and without incurring
expense, to review the ENGINEER's insurance policies including
endorsements thereto and, at the CITY's discretion; the ENGINEER may
be required to provide proof of insurance premium payments.
j. Lines of coverage, other than Professional Liability, underwritten on a
claims-made basis, shall contain a retroactive date coincident with or
prior to the date of the contractual agreement. The certificate of
insurance shall state both the retroactive date and that the coverage is
claims-made.
k. Coverages, whether written on an occurrence or claims-made basis,
shall be maintained without interruption nor restrictive modification or
changes from date of commencement of the PROJECT until final
payment and termination of any coverage required to be maintained after
final payments.
1. The CITY shall not be responsible for the direct payment of any
insurance premiums required by this agreement.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date:1/28/2013
Page 8 of 16
m. Sub consultants and subcontractors to/of the ENGINEER shall be
required by the ENGINEER to maintain the same or reasonably
equivalent insurance coverage as required for the ENGINEER. When
sub consultants/subcontractors maintain insurance coverage,
ENGINEER shall provide CITY with documentation thereof on a
certificate of insurance.
L. Independent Consultant
The ENGINEER agrees to perform all services as an independent
consultant and not as a subcontractor, agent, or employee of the CITY.
M. Disclosure
The ENGINEER acknowledges to the CITY that it has made full disclosure
in writing of any existing conflicts of interest or potential conflicts of interest,
including personal financial interest, direct or indirect, in property abutting the
proposed PROJECT and business relationships with abutting property cities.
The ENGINEER further acknowledges that it will make disclosure in writing
of any conflicts of interest that develop subsequent to the signing of this
contract and prior to final payment under the contract.
N. Asbestos or Hazardous Substances
(1) If asbestos or hazardous substances in any form are encountered or
suspected, the ENGINEER will stop its own work in the affected portions
of the PROJECT to permit testing and evaluation.
(2) If asbestos or other hazardous substances are suspected, the CITY may
request the ENGINEER to assist in obtaining the services of a qualified
subcontractor to manage the remediation activities of the PROJECT.
O. Permitting Authorities - Design Changes
If permitting authorities require design changes so as to comply with
published design criteria and/or current engineering practice standards
which the ENGINEER should have been aware of at the time this
Agreement was executed, the ENGINEER shall revise plans and
specifications, as required, at its own cost and expense. However, if design
changes are required due to the changes in the permitting authorities'
published design criteria and/or practice standards criteria which are
published after the date of this Agreement which the ENGINEER could not
have been reasonably aware of, the ENGINEER shall notify the CITY of
such changes and an adjustment in compensation will be made through an
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date:1/28/2013
Page 9 of 16
amendment to this AGREEMENT.
P. Schedule
ENGINEER shall manage the PROJECT in accordance with the schedule
developed per Attachment D to this AGREEMENT.
Article V
Obligations of the City
Amendments to Article V, if any, are included in Attachment C.
A. City-Furnished Data
ENGINEER may rely upon the accuracy, timeliness, and completeness of
the information provided by the CITY.
B. Access to Facilities and Property
The CITY will make its facilities accessible to the ENGINEER as required for
the ENGINEER's performance of its services. The CITY will perform, at no
cost to the ENGINEER, such tests of equipment, machinery, pipelines, and
other components of the CITY's facilities as may be required in connection
with the ENGINEER's services. The CITY will be responsible for all acts of
the CITY's personnel.
C. Advertisements, Permits, and Access
Unless otherwise agreed to in the Scope of Services, the CITY will obtain,
arrange, and pay for all advertisements for bids; permits and licenses
required by local, state, or federal authorities; and land, easements, rights-
of-way, and access necessary for the ENGINEER's services or PROJECT
construction.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date:1/28/2013
Page 10 of 16
D. Timely Review
The CITY will examine the ENGINEER's studies, reports, sketches,
drawings, specifications, proposals, and other documents; obtain advice of
an attorney, insurance counselor, accountant, auditor, bond and financial
advisors, and other consultants as the CITY deems appropriate; and render
in writing decisions required by the CITY in a timely manner in accordance
with the project schedule prepared in accordance with Attachment D.
E. Prompt Notice
The CITY will give prompt written notice to the ENGINEER whenever CITY
observes or becomes aware of any development that affects the scope or
timing of the ENGINEER's services or of any defect in the work of the
ENGINEER or construction contractors.
F. Asbestos or Hazardous Substances Release.
(1) CITY acknowledges ENGINEER will perform part of the work at CITY's
facilities that may contain hazardous materials, including asbestos
containing materials, or conditions, and that ENGINEER had no prior
role in the generation, treatment, storage, or disposition of such
materials. In consideration of the associated risks that may give rise to
claims by third parties or employees of City, City hereby releases
ENGINEER from any damage or liability related to the presence of
such materials.
(2) The release required above shall not apply in the event the discharge,
release or escape of hazardous substances, contaminants, or asbestos
is a result of ENGINEER's negligence or if ENGINEER brings such
hazardous substance, contaminant or asbestos onto the project.
G. Contractor Indemnification and Claims
The CITY agrees to include in all construction contracts the provisions of
Article IV.E. regarding the ENGINEER's Personnel at Construction Site, and
provisions providing contractor indemnification of the CITY and the
ENGINEER for contractor's negligence.
H. Contractor Claims and Third-Party Beneficiaries
(1) The CITY agrees to include the following clause in all contracts with
construction contractors and equipment or materials suppliers:
"Contractors, subcontractors and equipment and materials
suppliers on the PROJECT, or their sureties, shall maintain
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date:1/28/2013
Page 11 of 16
no direct action against the ENGINEER, its officers,
employees, and subcontractors, for any claim arising out of,
in connection with, or resulting from the engineering
services performed. Only the CITY will be the beneficiary
of any undertaking by the ENGINEER."
(2) This AGREEMENT gives no rights or benefits to anyone other than the CITY
and the ENGINEER and there are no third-party beneficiaries.
(3) The CITY will include in each agreement it enters into with any other entity
or person regarding the PROJECT a provision that such entity or person
shall have no third-party beneficiary rights under this Agreement.
(4) Nothing contained in this section V.H. shall be construed as a waiver of any
right the CITY has to bring a claim against ENGINEER.
I. CITY's Insurance
(1) The CITY may maintain property insurance on certain pre-existing structures
associated with the PROJECT.
(2) The CITY will ensure that Builders Risk/Installation insurance is maintained
at the replacement cost value of the PROJECT. The CITY may provide
ENGINEER a copy of the policy or documentation of such on a certificate of
insurance.
(3) The CITY will specify that the Builders Risk/Installation insurance shall be
comprehensive in coverage appropriate to the PROJECT risks.
J. Litigation Assistance
The Scope of Services does not include costs of the ENGINEER for required
or requested assistance to support, prepare, document, bring, defend, or
assist in litigation undertaken or defended by the CITY. In the event CITY
requests such services of the ENGINEER, this AGREEMENT shall be
amended or a separate agreement will be negotiated between the parties.
K. Changes
The CITY may make or approve changes within the general Scope of
Services in this AGREEMENT. If such changes affect the ENGINEER's cost
of or time required for performance of the services, an equitable adjustment
will be made through an amendment to this AGREEMENT with appropriate
CITY approval.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date:1/28/2013
Page 12 of 16
Article VI
General Legal Provisions
Amendments to Article VI, if any, are included in Attachment C.
A. Authorization to Proceed
ENGINEER shall be authorized to proceed with this AGREEMENT upon
receipt of a written Notice to Proceed from the CITY.
B. Reuse of Project Documents
All designs, drawings, specifications, documents, and other work products of
the ENGINEER, whether in hard copy or in electronic form, are instruments
of service for this PROJECT, whether the PROJECT is completed or not.
Reuse, change, or alteration by the CITY or by others acting through or on
behalf of the CITY of any such instruments of service without the written
permission of the ENGINEER will be at the CITY's sole risk. The CITY shall
own the final designs, drawings, specifications and documents.
C. Force Majeure
The ENGINEER is not responsible for damages or delay in performance
caused by acts of God, strikes, lockouts, accidents, or other events beyond
the control of the ENGINEER that prevent ENGINEER's performance of its
obligations hereunder.
D. Termination
(1) This AGREEMENT may be terminated only by the City for convenience on
30 days' written notice. This AGREEMENT may be terminated by either the
CITY or the ENGINEER for cause if either party fails substantially to perform
through no fault of the other and does not commence correction of such
nonperformance with in 5 days of written notice and diligently complete the
correction thereafter.
(2) If this AGREEMENT is terminated for the convenience of the City, the
ENGINEER will be paid for termination expenses as follows:
a.) Cost of reproduction of partial or complete studies, plans,
specifications or other forms of ENGINEER'S work product;
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date:1/28/2013
Page 13 of 16
b.) Out-of-pocket expenses for purchasing electronic data files and other
data storage supplies or services;
C.) The time requirements for the ENGINEER'S personnel to document
the work underway at the time of the CITY'S termination for
convenience so that the work effort is suitable for long time storage.
(3) Prior to proceeding with termination services, the ENGINEER will
submit to the CITY an itemized statement of all termination expenses., The
CITY'S approval will be obtained in writing prior to proceeding with
termination services.
E. Suspension, Delay, or Interruption to Work
The CITY may suspend, delay, or interrupt the services of the ENGINEER
for the convenience of the CITY. In the event of such suspension, delay, or
interruption, an equitable adjustment in the PROJECT's schedule,
commitment and cost of the ENGINEER's personnel and subcontractors,
and ENGINEER's compensation will be made.
F. Indemnification
In accordance with Texas Local Government Code Section 271.904, the
ENGINEER shall indemnify, hold harmless, and defend the CITY
against liability for any damage caused by or resulting from an act of
negligence, intentional tort, intellectual property infringement, or
failure to pay a subcontractor or supplier committed by the ENGINEER
or ENGINEER's agent, consultant under contract, or another entity
over which the ENGINEER exercises control.
G. Assignment
Neither party shall assign all or any part of this AGREEMENT without the
prior written consent of the other party.
H. Interpretation
Limitations on liability and indemnities in this AGREEMENT are business
understandings between the parties and shall apply to all the different
theories of recovery, including breach of contract or warranty, tort including
negligence, strict or statutory liability, or any other cause of action, except for
willful misconduct or gross negligence for limitations of liability and sole
negligence for indemnification. Parties mean the CITY and the ENGINEER,
and their officers, employees, agents, and subcontractors.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date:1/28/2013
Page 14 of 16
I. Jurisdiction
The law of the State of Texas shall govern the validity of this AGREEMENT,
its interpretation and performance, and any other claims related to it. The
venue for any litigation related to this AGREEMENT shall be Tarrant County,
Texas.
J. Severability and Survival
If any of the provisions contained in this AGREEMENT are held for any
reason to be invalid, illegal, or unenforceable in any respect, such invalidity,
illegality, or unenforceability will not affect any other provision, and this
AGREEMENT shall be construed as if such invalid, illegal, or unenforceable
provision had never been contained herein. Articles V.F., VI.B., VI.D., VI.F.,
VI.H., and VI.I. shall survive termination of this AGREEMENT for any cause.
K. Observe and Comply
ENGINEER shall at all times observe and comply with all federal and State
laws and regulations and with all City ordinances and regulations which in
any way affect this AGREEMENT and the work hereunder, and shall
observe and comply with all orders, laws ordinances and regulations which
may exist or may be enacted later by governing bodies having jurisdiction or
authority for such enactment. No plea of misunderstanding or ignorance
thereof shall be considered. ENGINEER agrees to defend, indemnify and
hold harmless CITY and all of its officers, agents and employees from and
against all claims or liability arising out of the violation of any such order, law,
ordinance, or regulation, whether it be by itself or its employees.
Article VII
Attachments, Schedules, and Signatures
This AGREEMENT, including its attachments and schedules, constitutes the entire
AGREEMENT, supersedes all prior written or oral understandings, and may only be
changed by a written amendment executed by both parties. The following attachments
and schedules are hereby made a part of this AGREEMENT:
Attachment A- Scope of Services
Attachment B — Compensation
Attachment C -Amendments to Standard Agreement for Engineering Services
Attachment D - Project Schedule
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date:1128/2013
Page 15 of 16
Attachment E - Location Map
Executed and effective this the i day , 20�y
BY: BY:
CITY OF FORT WORTH ENGINEER
Dunaway Associates, L.P.
Fernando Costa oby K. Ford, P.E.
Assistant City Manager Vice President
Date: -9i� Date: 911111�
APPROVAL RECOMMENDED:
By: I LJ.. LJ
Dougla W. Wiersig
Director
Transportation & Public Works
APPROVED AS TO FORM AND M&C No.: C Z6)q f
LEGALITY
M&C Date: q - %- 1 L/
By: 6 —
Douglas W. Black
Assistant City Attorney
ATTEST:
ORr
- �
Mary J. Kayser Ci a° a
City Secretary °°fit
°°°°moo°
SEX X
City of Fort Worth,Texas OFFIGUAL RECORD
Standard Agreement for Engineering Related Design Services
PMO Official Release Date:1/28/2013 �Y ��� � ��T
Page 16 of 16
v r0 1/voR my Tl K
ATTACHMENT "A"
Scope for Engineering Design Related Services for Street Improvements
The scope set forth herein defines the work to be performed by the ENGINEER in
completing the project. Both the CITY and ENGINEER have attempted to clearly define the
work to be performed and address the needs of the Project.
OBJECTIVE
This project consists of preparing construction documents for the construction of a 2-lane
asphalt street section (24-ft width) with bar ditches for Summer Creek Drive between
Posada Drive and Rancho Verde Parkway. This section of road shall act as a temporary
connection between Posada Drive and Rancho Verde Parkway until the ultimate section of
Summer Creek Drive is constructed.
WORK TO BE PERFORMED
Task 1. Design Management
Task 2. Conceptual Design
Task 3. Preliminary Design
Task 4. Final Design
Task 5. Bid Phase Services
Task 6. Construction Phase Services
Task 7. ROW/Easement Services
Task 8. Survey and Subsurface Utility Engineering Services
Task 9. Permitting
Task 10. Plan and Submittal Checklists
TASK 1. DESIGN MANAGEMENT.
ENGINEER will manage the work outlined in this scope to ensure efficient and effective use
of ENGINEER's and CITY's time and resources. ENGINEER will manage change,
communicate effectively, coordinate internally and externally as needed, and proactively
address issues with the CITY's Project Manager and others as necessary to make progress
on the work.
1.1. Managing the Team
• Lead, manage and direct design team activities
• Ensure quality control is practiced in performance of the work
• Communicate internally among team members
• Task and allocate team resources
1.2. Communications and Reporting
• Conduct review meetings with the CITY at the end of each design phase
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 1 of 13
• Complete Monthly M/WBE Report Form and Final Summary Payment Report Form at
the end of the project
• Prepare invoices, in accordance with Attachment B to this Standard Agreement and
submit monthly in the format requested by the CITY
• Coordinate with other agencies and entities as necessary for the design of the
proposed infrastructure, and provide and obtain information needed to prepare the
design
• With respect to coordination with permitting authorities, ENGINEER shall
communicate with permitting authorities such that their regulatory requirements are
appropriately reflected in the designs. ENGINEER shall work with regulatory
authorities to obtain approval of the designs, and make changes necessary to meet
their requirements, as part of the design scope.
• Personnel and Vehicle Identification: When conducting site visits to the project
location, the ENGINEER or any of its sub-consultants shall carry readily visible
information identifying the name of the company and the company representative.
ASSUMPTIONS
• 3 monthly project invoices
• 2 design review meetings with city staff.
DELIVERABLES
A. Monthly invoices
B. Monthly M/WBE Report Form and Final Summary Payment Report Form
C. Plan Submittal Checklists ( See Task 10)
TASK 2. CONCEPTUAL DESIGN (30 PERCENT).
The purpose of the conceptual design is for the ENGINEER to identify, develop,
communicate through the defined deliverables, and recommend the design concept that
successfully addresses the design problem, and to obtain the CITY's endorsement of this
concept. ENGINEER will utilize concepts and criteria contained in the current CITY iSWM
Criteria Manual for Site Development and Construction for conceptual planning and design.
ENGINEER will develop the conceptual design of the infrastructure as follows.
2.1. Data Collection
• In addition to data obtained from the CITY, ENGINEER will research and make
efforts to obtain pertinent information to aid in coordination of the proposed
improvements with any planned future improvements that may influence the
project. ENGINEER will also identify and seek to obtain data for existing
conditions that may impact the project including; utilities, agencies (TxDOT and
railroads), City Master Plans, and property ownership as available from the Tax
Assessor's office.
2.2. Subsurface Utility Engineering (N/A)
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 2 of 13
Z3. The Conceptual Design Package shall include the following:
• Conceptual plan exhibit presenting three (3) alignment alternatives.
• Estimates of probable construction cost.
ASSUMPTIONS
• 1 set of 11x17 size plans will be delivered for the 30% design.
• ENGINEER shall not proceed with Preliminary Design activities without written
approval by the CITY of the Conceptual Design Package.
DELIVERABLES
A. Conceptual Design Package
TASK 3. PRELIMINARY DESIGN (90 PERCENT).
ENGINEER will develop the preliminary design of the infrastructure as follows.
3.1. Development of Preliminary Design Drawings and Specifications shall include the
following:
• A Project Control Sheet, showing all Control Points, used or set while gathering
data. Generally on a scale of not less than 1:400. The following information shall
be indicated for each Control Point: Identified (existing City Monument#8901, PK
Nail, 5/8" Iron Rod); X, Y and Z Coordinates, in an identified coordinate system,
and a referred bearing base. Z coordinate on City Datum only; descriptive location
(i.e. set in the centerline of the inlet in the South curb line of North Side Drive at the
East end of radius at the Southeast corner of North Side Drive and North Main
Street).
• Updated existing and proposed typical section sheets.
• Updated roadway plan and profile sheets displaying station and coordinate data for
all horizontal alignment P.C.'s, P.T.'s, P.I.'s; station and elevation data of all
vertical profile P.C.'s, P.T.'s, P.I.'s, low points, and high points; lengths of vertical
curves, grades, K values, e, and vertical clearances where required.
• No less than two bench marks plan/profile sheet.
• Bearings given on all proposed centerlines, or baselines.
• Station equations relating utilities to paving, when appropriate.
• Overall project easement layout sheet(s).
• Preliminary roadway details to include pavement details.
• ENGINEER will delineate the watershed based on contour data and field
verification and document existing street, right-of-way and storm drain capacities
for the subject site. A drainage area map will be drawn at maximum 1" = 200'
scale from available 2-foot contour data with the contours labeled. Data source
and year will be provided by the CITY. Calculations regarding street and right-of-
way capacities and design discharges (5-year and 100-year frequencies) at
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 3 of 13
selected critical locations will be provided. Other frequencies as required by
iSWM criteria may be appropriate for outfalls and sensitive locations. Capacities
of existing storm drain will be calculated and shown. All calculations shall
conform to CITY criteria delineated in the CITY's current iSWM Criteria Manual
for Site Development and Construction. All locations in the project area where
100-year runoff exceeds available storm drain and right-of-way capacities shall
be clearly identified. The ENGINEER's responsibility includes recommendations
for improvements of the existing system as deemed reasonable and consistent
with CITY standards.
• Preliminary signing and pavement marking layouts.
3.2. Geotechnical Investigation/Pavement Design (NIA)
• CITY to provide desired pavement section.
3.3. Constructability Review (N/A)
3.4. Public Meeting
• After the preliminary plans have been reviewed and approved by the CITY, the
ENGINEER shall prepare project exhibits, and attend one (1) public meeting to
help explain the proposed project to residents. The CITY shall select a suitable
location, prepare and mail the invitation letters to the affected customers. The
ENGINEER shall coordinate with the CITY GIS staff to identify affected property
owners/residents and develop a spreadsheet listing addresses of those to invite
to the public meeting.
3.5. Utility Clearance
• The ENGINEER will consult with the CITY's Transportation and Public Works
Department, Water Department, and other CITY departments, public utilities,
private utilities, private utilities and government agencies to determine the
approximate location of above and underground utilities, and other facilities
(current and future) that have an impact or influence on the project. ENGINEER
will design CITY facilities to avoid or minimize conflicts with existing utilities, and
where known and possible consider potential future utilities in designs.
• The ENGINEER shall upload individual DWF files for each plan sheet of the
approved preliminary plan set to the designated project folder in Buzzsaw for
forwarding to all utility companies which have facilities within the limits of the
project. The DWF files should be created directly from the CAD files as opposed
to PDF files.
ASSUMPTIONS
• All storm water calculations and design shall conform to the current CITY iSWM
Criteria Manual for Site Development and Construction.
• 5 sets of 11x17 size plans will be delivered for the 90% design.
• 1 sets of specifications will be delivered for the 90% design.
• DWF files created from design CAD drawings will be uploaded to the designated
project folder in Buzzsaw.
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 4 of 13
• All submitted documents and checklists will be uploaded to the designated
project folder in Buzzsaw
• The CITY's front end and technical specifications will be used. The ENGINEER
shall supplement the technical specifications if needed.
• ENGINEER shall not proceed with Final Design activities without written approval
by the CITY of the Preliminary Design (90%) plans.
DELIVERABLES
A. Preliminary Design drawings and specifications
B. Utility Clearance drawings
C. Estimates of probable construction cost
D. Public Meeting exhibits
TASK 4. FINAL DESIGN AND FINAL CONSTRUCTION DOCUMENTS (100 PERCENT).
Upon approval of the Preliminary (90%) plans, ENGINEER will prepare construction plans
as follows:
• Following a 90% construction plan review meeting with the CITY, the ENGINEER shall
submit Final Plans (100%) to the CITY per the approved Project Schedule. Each plan
sheet shall be stamped, dated, and signed by the ENGINEER registered in State of
Texas.
• The ENGINEER shall submit a final design estimate of probable construction cost with
the 100% design package. This estimate shall use ONLY standard CITY bid items.
ASSUMPTIONS
• 1 set of 11x17 size drawings and 1 specifications will be delivered
for the 100% Design package.
• A DWF file for the 100 % Design will be created from design CAD drawings and
will be uploaded to the project folder in Buzzsaw.
• Estimate final sheet list:
• Cover/index, general notes, project layout sheet including easement layouts and
control point location, typical section sheet, removal plan sheet, approx. 2
roadway plan/profile sheets, pavement detail sheet, drainage area map and
hydrologic data sheet, signing/pavement marking plan sheet, etc.)
DELIVERABLES
A. 100% construction plans and specifications.
B. Detailed estimates of probable construction costs including summaries of bid
items and quantities using the CITY's standard bid items and format.
C. Original cover mylar for the signatures of authorized CITY officials.
TASK 5. BID PHASE SERVICES.
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 5 of 13
ENGINEER will support the bid phase of the project as follows.
5.1. Bid Support
• The ENGINEER shall upload all plans and contract documents onto Buzzsaw for
access to potential bidders.
• Contract documents shall be uploaded in a .xls file.
• Unit Price Proposal documents are to be created utilizing CFW Bidtools only
and combined in a specified spreadsheet workbook, Bid Proposal Worksheet
Template, and will be populated and configured so that all pages are
complete and the Summary Worksheet(s) in the workbook detail and
automatically summarize the totals from the inserted Unit Price Proposal
document worksheets.
• Plan Sets are to be uploaded to Buzzsaw in two formats, .pdf and Awf files.
The .pdf will consist of one file of the entire plan set. The .dwf will consist of
individual files, one for each plan sheet, and will be numbered and named in
a manner similar to that of the plan set index.
• The ENGINEER shall sell contract documents and maintain a plan holders list on
Buzzsaw from documents sold and from Contractor's uploaded Plan Holder
Registrations in Buzzsaw.
• The ENGINEER will develop and implement procedures for receiving and
answering bidders' questions and requests for additional information. The
procedures shall include a log of all significant bidders questions and requests
and the response thereto. The log shall be housed and maintained in the
project's Buzzsaw folder titled Request for Information. The ENGINEER will
provide technical interpretation of the contract bid documents and will prepare
proposed responses to all bidders questions and requests, in the form of
addenda. The ENGINEER shall upload all approved addenda onto Buzzsaw and
mail addenda to all plan holders.
• Attend the prebid conference in support of the CITY.
• Assist the CITY in determining the qualifications and acceptability of prospective
contractors, subcontractors, and suppliers.
• Attend the bid opening in support of the CITY.
• Tabulate and review all bids received for the construction project, assist the CITY
in evaluating bids, and recommend award of the contract. A copy of the Bid
Tabulation and the CFW Data Spreadsheet created utilizing CFW Bidtools only
are to be uploaded into the project's Bid Results folder on Buzzsaw.
5.2 Final Design Drawings
• Final Design Drawings shall be submitted as an Adobe Acrobat PDF format
(version 6.0 or higher) file and DWF format. There shall be one (1) PDF file
and one (1) DWF file (created from CAD application of drawing) for the TPW
plan set and a separate PDF and DWF file for the Water plan set. Each PDF and
DWF file shall be created from the original CAD drawing filess and shall contain
all associated sheets of the particular plan set. Singular PDF and DWF files for
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 6 of 13
each sheet of a plan set will not be accepted. PDF and DWF files shall
conform to naming conventions as follows:
1. TPW file name example — "W-1956—org47.pdf' where "W-1956" is the
assigned file number obtained from the CITY, "_org" designating the file is
of an original plan set, "47" shall be the total number of sheets in this file.
Example: W-0053_org3.pdf and K-0320_org5.pdf
II. Water and Sewer file name example — "X-35667_org36.pdf' where "X-
35667" is the assigned file number obtained from the CITY, "_org"
designating the file is of an original plan set, "36" shall be the total number
of sheets in this file.
Example: X-12755_org18.pdf
Both PDF and DWF files shall be uploaded to the project's Record Drawing folder
in Buzzsaw.
• In addition to the PDF and DWF files, the ENGINEER shall submit each plan sheet
as an individual DWG file with all reference files integrated into the sheet. If the
plans were prepared in DGN format, they shall be converted to DWG prior to
uploading. The naming convention to be used for the DWG files shall be as
follows:
I. TPW files shall use the W number as for PDF and DWF files, but shall
include the sheet number in the name —"W-1966_SHT01.dwg", "W-
1956_SHT02.dwg", etc.
II. Water and Sewer file names shall use the X number as for PDF and DWF
files, but shall include the sheet number in the name — "X-
12155_SHT01.dwg", "X-12755_SHT02.dwg", etc.
For information on the proper manner to submit files and to obtain a file number for
the project, contact the Department of Transportation and Public Works Vault at
telephone number(817) 392-8426. File numbers will not be issued to a project
unless the appropriate project numbers and fund codes have been assigned and
are in the Department of Transportation and Public Works database.
ASSUMPTIONS
• The project will be bid only once and awarded to one contractor.
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 7 of 13
• Construction documents will be made available on Buzzsaw for plan holders
and/or given to plan viewing rooms.
• 3 sets of construction documents will be printed and made available for
purchase by planholders and/or given to plan viewing rooms.
• 2 sets of 22x34 size plans and specifications (conformed, if applicable)
will be delivered to the CITY.
• PDF, DWF and DWG files will be uploaded to Buzzsaw.
DELIVERABLES
A. Addenda
B. Bid tabulations
C. Recommendation of award
D. Construction documents (conformed, if applicable)
E. CFW Data Spreadsheet
TASK 6. CONSTRUCTION PHASE SERVICES.
ENGINEER will support the construction phase of the project as follows.
6.1 Construction Support
• The ENGINEER shall attend the preconstruction conference.
• The ENGINEER shall attend the "Final" project walk through and assist with
preparation of final punch list.
6.2 Record Drawings (N/A)
ASSUMPTIONS
• 1 site visit is assumed for"Final" project walk through.
• One copy of full size (22"x34") mylars will be delivered to the CITY
DELIVERABLES
A. NONE
TASK 7. ROW/EASEMENT SERVICES.
ENGINEER will support and perform activities related to ROW and land as outlined below,
per scoping direction and guidance from the CITY's Project Manager.
7.1. Right-of-Way Research
• The ENGINEER shall determine rights-of-way, easements needs for construction
of the project. Required temporary and permanent easements will be identified
based on available information and recommendations will be made for approval
by the CITY.
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 8 of 13
ASSUMPTIONS
• Right-of-Way research includes review of property/right-of-way records based on
current internet based Tarrant Appraisal District (TAD) information available at
the start of the project and available on-ground property information (i.e. iron
rods, fences, stakes, etc.). It does not include effort for chain of title research,
parent track research, additional research for easements not included in the
TAD, right-of-way takings, easement vacations and abandonments, right-of-way
vacations, and street closures.
DELIVERABLES
A. NONE.
TASK 8. SURVEY AND SUBSURFACE UTILITY ENGINEERING SERVICES.
ENGINEER will provide survey support as follows.
8.1. Design Survey
• ENGINEER will perform field surveys to collect horizontal and vertical elevations
and other information needed by ENGINEER in design and preparation of plans
for the project. Information gathered during the survey shall include topographic
data, elevations of all sanitary and adjacent storm sewers, rim/invert elevations,
location of buried utilities, structures, trees (measure caliper, identify overall
canopy, and have qualified arborist identify species of trees), and other features
relevant to the final plan sheets. Existing drainage at intersections will be verified
by field surveys. Spot elevations will be shown on intersection layouts with cross
slope to fit intersecting grade lines.
• The minimum survey information to be provided on the plans shall include the
following:
— A Project Control Sheet, showing ALL Control Points, used or set while
gathering data. Generally on a scale of not less than 1:400:
— The following information about each Control Point;
a. Identified (Existing. CITY Monument#8901, PK Nail, 5/8" Iron Rod)
b. X, Y and Z Coordinates, in an identified coordinate system, and a
referred bearing base. Z coordinate on CITY Datum only.
c. Descriptive Location (Ex. Set in the centerline of the inlet in the South
curb line of North Side Drive at the East end of radius at the Southeast
corner of North Side Drive and North Main Street).
— Coordinates on all P.C.'s, P.T.'s, P.I.'s, Manholes, Valves, etc., in the
same coordinate system, as the Control.
— No less than two horizontal bench marks, per line or location.
— Bearings given on all proposed centerlines, or baselines.
— Station equations relating utilities to paving, when appropriate.
8.2. Temporary Right of Entry Preparation and Submittal (N/A)
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 9 of 13
8.3. Subsurface Utility Engineering (NIA)
8.4. Construction Survey
• Be available to the CITY on matters concerning the layout of the project during its
construction
• ENGINEER will set control points (i.e. tie survey to permanent monument such as
TPW monuments and/or property corners, one location each at beginning and
end of project) for the project, these points must be indivisible. Streets over 500 ft
in length or streets on curves may require a greater density of control points to
maintain intervisibility between each point. ENGINEER shall establish a minimum
of two bench marks per plan sheet (bench marks shall be located adjacent to
project) and shall provide the following construction staking services:
— ROADWAY EXCAVATION STAKING: Provide 10' or property line offset
at 50' intervals and at all points of curve, points of tangent, and at all
horizontal or vertical angle points with a cut/fill to the top of proposed
curb. The right-of-way shall also be flagged during this process along with
line and grade stakes for excavation purposes. Stake all vertical and
horizontal curves at 50' intervals. Line and grade shall be set to a
tolerance of+/- 0.1 ft.
— FINAL ROADWAY STAKING: Provide 4' or 5' offset stakes at 50'
intervals and at all points of curve, points of tangent, and at all horizontal
or vertical angle points with a cut/fill to the top of proposed curb. Staking
for curb grade and intersecting streets, if required, shall be performed
under final pavement staking. Inlets shall be staked if needed. Set tacks
in offset hubs for street alignment. Stake all vertical and horizontal curves
at 50' intervals and provide intermediate stakes between curve points, if
the radius is less than 300'. Line and grade shall be set to a tolerance of
+/- 0.01 ft.
— "AS STAKED" RECORD OF THE CONSTRUCTION: Throughout the
process of all construction, locate and record anything that does not
conform with the construction plans. A drawing of the project layout with
dimensions and a coordinate list must be submitted.
A copy of sample field notes that must be provided is attached. The field
notes must include the following information:
a. For roadways;
Field notes signed and sealed by a licensed surveyor must be
submitted to the CITY Inspector prior to the beginning of construction.
• COORDINATION WITH CITY INSPECTOR/CONTRACTOR: ENGINEER's
surveyor is expected to work with the CITY inspector and contractor to provide
any special requests contractor may have providing the scope of work described
above is not exceeded. It is expected that a few stakes will be knocked out
during dirt work. Providing that the number of disturbed stakes is minor (less than
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 10 of 13
10% of the stakes for any phase of the project), the ENGINEER's surveyor shall
replace these stakes at no extra cost. If additional major restaking is required, the
ENGINEER's surveyor, shall provide the additional work at an hourly rate of
$ per hour for a field crew. Major restaking may be required if a substantial
number of the initial stakes are knocked down as a result of the contractor's
activity and there are not enough stakes left to complete the project. The
contractor shall be responsible for paying the ENGINEER for this additional work.
• INCIDENTAL PRE-CONSTRUCTION STAKING: Right-of-way flagging, back of
curb location, driveways, walks and retaining walls as requested by the CITY
Inspector, curb radii (to determine construction location) for utility clearance.
• SPECIAL CONDITIONS:
a. The CITY Inspector assigned to the project shall oversee all construction
staking activity and shall be responsible for all field coordination. All
documentation including field notes, cut and/or fill notes, grades, "as staked"
information etc., shall be provided to the CITY inspector and shall be sealed
and signed by a surveyor licensed in the State of Texas.
b. The ENGINEER's Surveyor shall attend the pre-construction conference.
c. The ENGINEER's Surveyor shall meet with CITY Inspector and Contractor to
coordinate surveying schedule and needs prior to beginning work.
d. The ENGINEER's Surveyor shall provide enough construction staking
information so that the projects can be constructed as designed.
e. A member of ENGINEER's firm familiar with project shall be available at all
times to immediately respond to questions from the field.
ASSUMPTIONS
DELIVERABLES
A. Copies of field survey data and notes signed and sealed by a licensed surveyor.
B. Drawing of the project layout with dimensions and coordinate list.
TASK 9. PERMITTING.
ENGINEER will provide permitting support for the CITY to obtain any and all agreements
and/or permits normally required for a project of this size and type, as follows.
9.1. Storm Water Pollution Prevention Plan
• For this project, the Contractor will be responsible for preparing and submitting
the Storm Water Pollution Prevention Plan (SWPPP) according to the current
CITY iSWM Criteria Manual for Site Development and Construction with the
appropriate regulatory agencies.
9.2. Environmental Services (N/A)
9.3. Floodplain Services (N/A)
9.4 Oncor Encroachment Agreement
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 11 of 13
• This project will require an approved permit for crossing an existing Oncor utility
easement.
• Meet, negotiate and coordinate to obtain approval of the agency issuing the
agreement and/or permits.
• Completing all forms/applications necessary.
• Submitting forms/applications for CITY review
• Submitting revised forms for agency review
• Responding to agency comments and requests
ASSUMPTIONS
• Permit preparation will begin after approval of the Conceptual Design.
• 1 meeting is assumed with Oncor for the Encroachment Agreement
permit.
DELIVERABLES
A. Approved permit.
TASK 10. PLAN SUBMITTAL CHECKLISTS
Engineer shall complete and submit Plan Submittal Checklists in accordance with the
following table:
PLAN SUBMITTAL CHECKLIST REQUIREMENTS
Street Water Traffic Traffic Traffic
Traffic Storm Storm Lights /Sewer Traffic Control Control Control
Attachment"A" Signal Engineering 30% 60% 90%
Water Water (Submit (Submit
Type (Submit All (Submit All
@ 30%) 30% 60% All All @ @ 60%) Required for all work in City
30%% 60%) ROW
Street X X X X X. X X X X
Storm Water X X X X X
Water/Sewer X X X X
*If included in street project
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 12 of 13
ADDITIONAL SERVICES NOT INCLUDED IN THE EXISTING SCOPE OF SERVICES
Additional Services not included in the existing Scope of Services — CITY and
ENGINEER agree that the following services are beyond the Scope of Services
described in the tasks above. However, ENGINEER can provide these services, if
needed, upon the CITY's written request. Any additional amounts paid to the
ENGINEER as a result of any material change to the Scope of the Project shall be
agreed upon in writing by both parties before the services are performed. These
additional services include the following:
• Negotiation of easements or property acquisition.
• Services related to development of the CITY's project financing and/or budget.
• Services related to disputes over pre-qualification, bid protests, bid rejection
and re-bidding of the contract for construction.
• Construction management and inspection services
• Performance of materials testing or specialty testing services.
• Services necessary due to the default of the Contractor.
• Services related to damages caused by fire, flood, earthquake or other acts of
God.
• Services related to warranty claims, enforcement and inspection after final
completion.
• Services to support, prepare, document, bring, defend, or assist in litigation
undertaken or defended by the CITY.
• Performance of miscellaneous and supplemental services related to the project
as requested by the CITY.
• Environmental Permitting
• Geotechnical Investigation/Pavement Design
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 13 of 13
ATTACHMENT B
COMPENSATION
Design Services for
Posada Drive Connection
City Project No. 00997
Lump Sum Project
I. Compensation
A. The ENGINEER shall be compensated a total lump sum fee of $68,850.00 as
summarized in Exhibit B-1 — Engineer Invoice and Section IV— Summary of Total
Project Fees. The total lump sum fee shall be considered full compensation for
the services described in Attachment A, including all labor materials, supplies,
and equipment necessary to deliver the services.
B. The ENGINEER shall be paid monthly payments as described in Section II -
Method of Payment.
II. Method of Payment
A. Partial payment shall be made to the ENGINEER monthly upon City's approval of
an invoice prepared and submitted by the ENGINEER in the format and including
content as presented in Exhibit B-1, Progress Reports as required in item III. of
this Attachment B, and Schedule as required in Attachment D to this Agreement.
B. The estimated current physical percent complete as required on the invoice shall
be calculated from the progress schedule as required in Attachment D to this
Standard Agreement and according to the current version of the City of Fort
Worth's Schedule Guidance Document.
C. The cumulative sum of such monthly partial fee payments shall not exceed the
total current project budget including all approved Amendments.
D. Each invoice shall be verified as to its accuracy and compliance with the terms of
this Agreement by an officer of the ENGINEER.
III. Progress Reports
A. The ENGINEER shall prepare and submit to the designated representative of the
Transportation and Public Works Department monthly progress reports and
schedules in the format required by the City.
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 1 of 3
B-1
ATTACHMENT B
COMPENSATION
IV. Summary of Total Project Fees
Firm Primary Responsibility Fee Amount %
Prime Consultant
Dunaway Associates, Engineering & Project $57,750.00 84
L.P. Management
Proposed MBE/SBE Sub-Consultants
Gorrondona & Survey & Construction Staking $11,100.00 16
Associates, Inc.
Non-MBE/SBE Consultants
TOTAL $68,850.00 100%
Project Number& Name Total Fee MBE/SBE Fee MBE/SBE
00997— Posada Drive Connection $68,850.00 $11,100.00 16
City MBE/SBE Goal = 16 % Consultant Committed Goal = 16 %
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 2 of 3
B-2
EXHIBIT "B-1"
ENGINEER INVOICE
(Supplement to Attachment B)
Insert required invoice format following this page, including negotiated total budget and
allocations of budgets across work types and work phases.
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 3 of 3
B-3
\ ) \ \
� 2
J
L)
) -
� § J {
cn
>
77 22
\ \ \\
{ / a- \
� _ «
cu ) ) t
E
§ 3 o
m °
E V ;
\ § 3A {
) o « < u
&
- _ [ § \ . § t m
_ \ \ \ \
uj
� k \ \ / \
ST
/ j \ / 0 { 1 { �«
cn
"0
&J J %
U) \ E I
2 0 \
eU = a.
E ¢ _ ; « /
La
a ( I
@ n ) LL P 2
/ \ E ( ~ # /
( 0k
& &k2
§ ® E z CL ;
> {\()
� \ \
\
J » � G CL « \/ƒpp/
2 /« f § ( (2f\ ) tt # # tt
aG o 0 o}(�w= mk ; kkk �
\)\\�� j
J £
E
J /
\�
} §
L)
o o\
kk �
#
#§ k { a \\�� \
! § « « o
Em f
- ) � £ §
- k ` I
k )
o
\k u\ ) ) /
- )ƒ( _ | 2
� § _ ` ! ! «
k j (k
t, B-5 K !// §f
! [[! )/\\ { 2!E
}kk /\�\ `
�k
7 = k()) )
� 0
k
/
n
CO)� _
E / § \1.
aO J -16 ®
n
D {/
:
0 m w -
(1) 1 «
® { ° ■
7 § L: 2
2 �k§ m0 f ()ƒ� ) § -
c a a
@ �ƒƒ, ¥ ;
0 �/`a}0 § )2 (§22 !ƒ/�
(L (L a. o G;IL LEA/ � 1;;l&Q
O
(P m CA M r r(p M M
F. O M M M M M Oi (O N (b N M N r O M M M M n M M m h N r r eA
M M M M wMM M M M w w� M M MM eD N M O
a w win ww w M M e»i» M
Y
N
A
H
d O
00 0 0 0
N M MM MMMM MenMM r MMM N M M MMMM M M m MM O O O
c U ww MM M M oV o cl tN o E d �o m `n O
U
CL 00 y x w W° 2 ! m m c U w O�o o u N
Q
° 'o F-
(0(D w
F M W W m
O M M N N M M a V M M H m m w 0
(n m p W F-
0 O O O N N N
d
7
d �
C F'
d
x
w m
c �
0
c Z
0 0 0 0 0 0 0 0 0 0 0 0 0 0
m W M M M M M M M o 0 0 0 0 0
N f0 00
U) m O WO MM
� w w
N N N O O e0 O M O N O N 0 0 0 N O O O O O N T O N O N O O 0 0 0 O O O
W �` V s{M 00 t0 N
a M N N O CO CO N eD p r 0 °e N N O CO h 0(D °e m N N V N N N N Ce
M M M N N N
MM M MwMM M M M ww ww MMN
«v w ww win M
Z C �
��w.O� o, �o mm o NV av a v o 0 0 o m
t0.Q a., C O in
O,W�? 00 'c
(nom �UZ a
oW nz y
=
W �Q
`•O ❑ � o N N oa oV ov ov o 0 0 0 ooc
M
O= vi v r r
N
DU O N N O V CO N r V V N mom O O a0 m N tD N N N
� w
0
t
LN N W V W m N O a0 N N V O O O O O N
J 0 C M
a` c
w
V M M 1 CON N N'd'M r to V N a r N N N m N N V V OD 00 N
U d w
d N
O C
a` 10
r
° °w
d[?
.O d
a`o
d N
A N
K c C -O 1°
f0 N
yta C O G 3 U N
4 0 E E
raw E 2.
o
e°n c CE m m c M d en m d ar/'i E d K to
.°_ c m c o` m 10 m v.. c° °c 0 2 ° y d m N
U E N o J D d d 1 O C L C d J E
R d d O O ❑ O G W ❑ d C c W C a W U I I o."NO C(n O F d fn N a N
c d 'o ° o 3 c o. m e N d d-O m o c m x E °� c o °ai
m o d o o c0_ r g o d 2 0 o
uU d cU .°o. 0' cc rrA
c mU c c o omt' c c� v
v ea aEi cy E.- .o d u U c 2 'E.E 0 U 2 2 a to U m aci aci n N 2 C o y c 2 `o w aj
aka�¢ o p :L3 QQI� O OL aNi o x`o❑
o o ()000 o aa�o IL LU co Fn vU a� vioo ao H y
O r N r N M V
PP Z 'N r r N M r N M 7 r N r �� r t0 N r r s{ � j � K
O r O N CV N O m m m CM O V V O N O(O O r O to M O m m N
tG r W OI 0.
E'O
0
O U
T N
ci¢a
ATTACHMENT "C"
CHANGES AND AMENDMENTS TO STANDARD AGREEMENT
Design Services for
Posada Drive Connection
City Project No. 00997
NONE
City of Fort Worth,Texas
Attachment C
PMO Release Date:05.19.2010
Page 1 of 1
Consulting Contract Schedule Specifications FORT WORT H
City of Fort Worth Capital Improvement Program
Attachment D e Project Schedule
This PROIECT requires a Tier << 1 >> schedtiJe as defined herein and in the Cittl's Schedule
Guidance Document.
D1. CONSULTING SERVICES SCHEDULE DEVELOPMENT: The CONSULTANT shall
prepare schedules for consulting services that meet the requirements described in this
specification, showing by Critical Path Method (CPM) the planned sequence and timing of
the Work associated with the Agreement. All submittals shall be submitted in PDF format,
and schedule files shall also be submitted in native file format (i.e. file formats associated
with the scheduling software). The approved scheduling software systems for creating the
schedule files are:
— Primavera (Version 6.1 or later or approved by CITY)
— Primavera Contractor (Version 6.1 or later or approved by CITY)
— Microsoft Project(Version 2003/2007 or later or approved by CITY)(PHASING OUT)
D2. BASELINE CONSULTING SERVICES SCHEDULE: Following notice-to-proceed, the
CONSULTANT shall develop, submit and review the draft detailed baseline consulting
services schedule with the CITY to demonstrate the CONSULTANT's understanding of the
Agreement requirements and approach for performing the work. The CONSULTANT will
prepare the final detailed baseline consulting services schedule based on CITY comments,if
any,and submit to the CITY no later than the submittal of the first project invoice.
The following guidelines shall be adhered to in preparing the baseline schedule, and as
described in further detail in the CITY's Schedule Guidance Document.
a. The scope shall be subdivided by work breakdown structure (WBS) representing the
tasks,subtasks,and activities associated with delivering the work.
b. The schedule shall accurately describe the major work activities,key milestones, and
dependencies/relationships as appropriate to the work.
c. The schedule should include appropriate meetings, review periods, critical decision
points,including third party utility dependencies and reviewing agencies.
D3. PROGRESS CONSULTING SERVICES SCHEDULE: The CONSULTANT shall prepare
and submit monthly to the CITY for approval the updated schedule in accordance with D1
and D2 and the CITY's Schedule Guidance Document inclusive. As the Work progresses,
the CONSULTANT shall enter into the schedule and record actual progress as described in
the CITY's Schedule Guidance Document.
The updated schedule submittal shall also include a concise schedule narrative that
highlights the following,if appropriate and applicable:
• Changes in the critical path,
• Expected schedule changes,
• Potential delays,
• Opportunities to expedite the schedule,
• Coordination issues the CITY should be aware of or can assist with,
City of Fort Worth,Texas
Attachment D
PMO Release Date:02.15.2011
Page 1 of 2
• Other schedule-related issues that the CONSULTANT wishes to communicate to the
CITY.
D4. PERFORMANCE AND CONSULTING SERVICES SCHEDULE: If the work
accomplished falls behind that scheduled due to factors within the CONSULTANT's
control, the CONSULTANT shall take such action as necessary to improve the progress of
the Work. In addition, the CITY may require the CONSULTANT to submit a revised
schedule demonstrating the proposed plan to make up the delay in schedule progress and
to ensure completion of the Work within the allotted Agreement time.
D5. SCHEDULE TIERS SPECIAL INSTRUCTIONS:
The requirements for the schedule are determined based on the nature and needs of the
project. The schedule tier for this project is stated at the top of this document.
CONSULTANT shall submit each schedule relying on the CITY's current Schedule
Guidance Document.
D6. SCHEDULE SUBMITTAL AND PAYMENT:
As stated in III.A.(1). of the Agreement, CONSULTANT shall provide the information
required by Attachment D. CONSULTANT's monthly invoices will not be accepted and
processed for payment without monthly schedule updates that are submitted in the time
and manner required by Attachment D and the CITY's current Schedule Guidance
Document.
City of Fort Worth,Texas
Attachment D
PMO Release Date:02.15.2011
Page 2 of 2
PROPOSED POSADA DRIVE CONNECTION WO��
FROM THE EAST END OF EXISTING
POSADA DR TO RANCHO VERDE PKWY Q9
CITY PROJECT NO. 00997
MAPSCO 116 D ��
COUNCIL DISTRICT 6 Awr DUNAWAY
f000 o f000
550 Bailey Avenue •Suite 400•Fat Worth,Texas 76107
Tel:81 7M5.1 121•Fax:817.33S.7437
SCALE:T.1000' VX REG.F-1114)
— — McPhars h
N
S
U
^mi^ll
^W W^`
•�
F:7
� I
E a)
0 E
Ln
N E
D
U N
FUTURE
EXTENSION
PROJECT N�d -R-ajnlolVlerldel
arkway
LOCATION
> Po a a ri e �
> a�
c
0 �
c �
c
0
U 0
0
U
FTF71 M
5=
U
COPYRIGHT 2014 CITY OF FORT WORTH. Unauthorized reproduction is a violation of applicable laws. This product is for informational purposes and may not
have been prepared for or be suitable for legal, engineering, or surveying purposes. It does not represent an on—the—ground survey and represents only
approximate relative location of property boundaries. The City of Fort Worth assumes no responsibility for the accuracy of the said data.
M&C - Council Agenda Page 1 of 2
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 919/2014 -Ordinance Nos. 21415-09-2014 & 21416-09-
2014
DATE: Tuesday, September 09, 2014 REFERENCE NO.: **C-26949
LOG NAME: 20SUMMER CREEK POSADA DESIGN DUNAWAY
SUBJECT:
Authorize Execution of an Engineering Services Agreement with Dunaway Associates, L.P., in an Amount
Not to Exceed $68,856.23 for the Design of Summer Creek Drive from Posada Drive to Rancho Verde
Parkway and Adopt Appropriation Ordinances (COUNCIL DISTRICT 6)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached appropriation ordinance increasing the estimated receipts and appropriations in the
Special Assessments Fund in the amount of$68,856.23 from available funds;
2. Authorize transfer of$68,856.23 from the Special Assessments Fund to the Street Improvements 2008
Fund;
3. Adopt the attached appropriation ordinance increasing the estimated receipts and appropriations in the
Street Improvements 2008 Fund in the amount of$68,856.23 from available funds; and
4.Authorize execution of an Engineering Services Agreement with Dunaway Associates, L.P., in an
amount not to exceed $68,856.23 for the design of Summer Creek Drive from Posada Drive to Rancho
Verde Parkway.
DISCUSSION:
This project consists of preparing design and construction documents for the construction of a temporary
two-lane asphalt street section (24-feet width) of future Summer Creek Drive between Posada Drive and
Rancho Verde Parkway. This section of road is necessary to provide better access to McPherson
Boulevard and Hulen Street for residents. The Chisholm Trail Parkway eliminated access via Stewart Feltz
Road for residences along Posada Drive and the surrounding area including Old Granbury Road.
Funds for this Agreement are Special Assessments Funds which were received from the Developer for
future improvements to Summer Creek Drive under Community Facilities Agreement No. 99025 in the
amount of$68,856.23.
Staff considers the proposed fee to be fair and reasonable for the scope of services that will be performed.
M/WBE Office- Dunaway Associates, L.P., is in compliance with the City's BDE Ordinance by committing
to 16 percent SBE participation. The City's SBE goal on this project is 16 percent.
This project is located in COUNCIL DISTRICT 6, Mapsco 116D.
FISCAL INFORMATION/CERTIFICATION:
http://apps.cfwnet.org/ecouncil/printrnc.asp?id=19610&print=true&DocType=Print 9/10/2014
M&C - Council Agenda Page 2 of 2
and adoption of the appropriations ordinances, funds will be available in the current budget, as
appropriated, in the Street Improvements 2008 Fund.
FUND CENTERS:
TO Fund/Account/Centers FROM Fund/AccounVCenters
1)GS94 488100 020941369010 $68,856.23 2)GS94 538040 020941369010 $68,856.23
1) GS94 538040 020941369010 $68,856.23 4)C204 531200 206760099730 $68,856.23
2&3)C204 476094 206760099730 $68,856.23
3) C204 531200 206760099730 $68,856.23
CERTIFICATIONS:
Submitted for City Manager's Office by: Fernando Costa (8476)
Originating Department Head: Doug Wiersig (7801)
Additional Information Contact: Patrick Buckley (2443)
ATTACHMENTS
1. 00997 -Posada Dr- Contract.pd (CFW Internal)
2. 20SUMMER CREEK POSADA DESIGN DUNAWAY C204 A014.doc (Public)
3. 20SUMMER CREEK POSADA DESIGN DUNAWAY dev deposit.docx (CFW Internal)
4. 20SUMMER CREEK POSADA DESIGN DUNAWAY GS94 AO14.doc (Public)
5. GS94 5zzzzz 136901.doc (CFW Internal)
6. Location Map Summer Creek Posada.pdf (Public)
7. MSBE Summer Creek.pd (CFW Internal)
http://apps.cfwnet.org/ecouncil/printinc.asp?id=19610&print=true&DoeType=Print 9/10/2014