HomeMy WebLinkAboutContract 44782-CO3 CITY SECRETAW
FORT WORTH_ City of Fort Worth CONTRACT NO. 4��82. �
Change Order Request
Project Name:1 WL I Sewer Replacement Contract 2010 STM-E and Ashland Drainage City Sec No.: 1 44782
Project No.(s): P253-605170144583&P258-705170144583 I DOE No. 6561 CityProj.No.:l 01494
Project Description: Replacement of water and sanitary sewer mains on Hillside Avenue,Pate Drive,Putnam Road and Stark Street.
Contractor: Woody Contractors, Inc. Change Order# 0 Date: 9/17/2014
City Project Mgr. Roberto C.Sauceda City Inspector: I Donald Watson
Phone Number:1 817-392-2387 Phone Number:1 817-205-8911
Dept. Water Sewer TPW Totals Contract Time
(Calender days)
Original Contract Amount $1,034,235.00 $628,236.00 $1,334,413.55 $2,996,884.55 290
Extras to Date $58,500.00 $15,150.00 $73,650.00 045
Credits to Date $27,600.00 $27,600.00
Pending Change Orders(in M&C Process)
Contract Cost to Date $1,092,735.00 $643,386.00 $1,306,813.55 $3,042,934.55 335
Amount of Proposed Change Order $143,200.00 $112,840.00 $5,000.00 $261,040.00 045
Revised Contract Amount $1,235,935.00 $756,226.00 $1,311,813.55 $3,303,974.55 380
Original Funds Available for Change Orders $40,649.00 $25,000.00 $40,032.00 $105,681.00
Remaining Funds Available for this CO $9,850.00 $67,632.00 $77,482.00
Additional Funding(if necessary) $143,200.00 $102,990.00 $246,190.00
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 10.25%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $3,746,105.69
Change Order No. 3 will provide for permanent asphalt repairs on El Campo Avenue and Birchman Avenu
in lieu of temporary asphalt pavement repair as originally specified. The existence of reinforced concrete
base that was encountered during construction necessitates permanent asphalt pavement repair. In addition,
the change order will allow for the installation of additional gate values on the project and repairs to an
existing arch storm drain line that was encountered during construction.
Staff concurs with the contractor's request to al calendar days for this change order. ® �-
� Ia— ~
y (�F FO'Q
A V 8
*o pp
a y °3
O __. o� @•
O �C
o
Mary J r, C Secretary %S oo���►
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
M 0X4r8*r Name ftAii
rn
m oody Contractors, Inc. Troy Woody A — ^l
L -
m
° l /7/'r z
Dam
tstjftA*�ff my OW)
m
-o
o Assam#
M&C Number C-26981 M&C Date Approved 1
FORT WORTH City of Fort Worth
Change Order Additions
Project Name WL/Sewer Replacement Contract 2010 STM-E and Ashland Drainage City Sec No.: 44782
Project No.(s): P253-605170144583&P258-705170144583 DOE No. 6561 City Proj.No.: 01494
Project
Description Replacement of water and sanitary sewer mains on Hillside Avenue,Pate Drive,Putnam Road and Stark Street.
Contractor Woody Contractors, Inc. I Change Order:0 Date: 9117/2014
City Project Mgr. Roberto C.Sauceda City Inspector I Donald Watson
ADDITIONS
DEPT ft Unit Unlit Cost Total
18 8 inch GV Water 11.00 EA $1,100.00 $12,100.00
40 Permanent HMAC Repair Water 1000.00 LF $60.00 $60,000.00
41 Extra Width Permanent Repair Water 100.00 SY $37.00 $3,700.00
42 2:27 Concrete Only Repair Water 1550.00 LF $40.00 $62,000.00
43 2 inch Water Service Water 2.00 EA $2,200.00 $4,400.00
44 2 inch Water Service, Meter Relocation Water 2.00 EA $500.00 $1,000.00
32 Permanent HMAC Repair Sewer 1336.00 LF $65.00 $86,840.00
33 Extra Width Permanent Repair Sewer 500.00 SY $37.00 $18,500.00
34 Import Acceptable Backfill Sewer 500.00 CY $15.00 $7,500.00
35 Repair to arch Storm Drain Line TPW 1.00 LS $5,000.00 $5,000.00
Water $143,200.00
Sewer $112,840.00
TPW $5,000.00
Page 2 of 4 JAdditions Sub Total $261,040.00
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name WL/Sewer Replacement Contract 2010 STM-E and Ashland Drainage City Sec No.: 44782
Project No.(s): P253-605170144583&P258-705170144583 DOE No. 6561 City Proj. No.: 01494
Project Description Replacement of water and sanitary sewer mains on Hillside Avenue,Pate Drive, Putnam Road and Stark Street.
Contractor Woody Contractors, Inc. Change Order: FT] Date 9/17/2014
City Project Mgr. Roberto C. Sauceda City Inspector: Donald Watson
DELETIONS
ITEM DEPT Qty Unit Unit Cost dal
Water
Sewer
TPW
Page 3 of 4 Deletions Sub Total
MWWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
Co# DATE AMOUNT
Total $0.00
Page 4 of 4
M&C Revie«, Page 1 of 2
Official site of the City of Fort Worth,Texas
CITY COUNCIL AGENDA F0 "
COUNCIL ACTION: Approved on 9/16/2014
DATE: 911612014 REFERENCE NO.: **C-26981 LOG NAME: 6010STMECO3-
WOODY
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: Authorize Execution of Change Order No. 3 to City Secretary Contract No. 44782 with
Woody Contractors, Inc., in the Amount of$261,040.00 for a Revised Total Contract in the
Amount of$3,303,974.55 for Water Replacement Contract 2010, STM-E on Ashland
Avenue, Birchman Avenue and El Campo Avenue-Ashland Drainage Improvements
(COUNCIL DISTRICT 7)
RECOMMENDATION:
It is recommended that the City Council authorize the execution of Change Order No. 3 to City
Secretary Contract No. 44782 with Woody Contractors, Inc., in the amount of$261,040.00 for a
revised total contract in the amount of$3,303,974.55 for water replacement Contract 2010, STM-E on
Ashland Avenue, Birchman Avenue and El Campo Avenue-Ashland drainage improvements.
DISCUSSION:
On August 6, 2013, (M&C C-26383) the City Council authorized execution of a contract with Woody
Contractors, Inc., in the amount of$2,996,884.55 for Water Replacement Contract 2010, STM-E. The
contract was subsequently revised by Change Order No. 1 with a reduction amount of$22,800.00
administratively approved on January 30, 2014 and Change Order No. 2 in the amount of$68,850.00
administratively approved on June 26, 2014.
Change Order No. 3 will provide for permanent pavement asphalt repairs on El Campo Avenue and
Birchman Avenue in lieu of temporary asphalt pavement repair as originally specified. The existence
of reinforced concrete base that was encountered during construction necessitates permanent
asphalt pavement repair. In addition, the change order will allow for the installation of additional gate
valves on the project and repairs to an existing arch storm drain line that was encountered during
construction.
M/WBE Office- Woody Contractors, Inc., is in compliance with the City's BDE Ordinance by
committing to an additional 13 percent MBE participation on this Change Order No. 3. The City's goal
on this change order is five percent.
The project is located in COUNCIL DISTRICT 7, Mapsco 74R and 75G, 75H and 75N.
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies that funds are available in the current capital
budget, as appropriated, of the Water Capital Projects Fund, the Sewer Capital Projects Fund and the
Stormwater Capital Projects Bond Fund.
TO Fund/Account/Centers FROM Fund/Account/Centers
P253 541200 607170149483 $143,200.00
P258 541200 707170149483 $112,840.00
P227 541200 207280191883 $5,000.00
http://apps.cfwnet.org/council_packet/mc—review.asp?ID=2023 I&councildate=9/16/2014
M&C Review Page 2 of 2
Submitted for City Manager's Office by, Fernando Costa (6122)
Originating Department Head: S. Frank Crumb (8207)
Additional Information Contact: Roberto Saucaeda (2387)
ATTACHMENTS
6010STMEC03-WOODY MAP 01.pdf
I
I
!J
I
http://apps.cfwnet.org/council _packet/mc review.asp?ID=20231&councildate=9/16/2014 9/25/2014