HomeMy WebLinkAboutContract 32224 AMENDMENT NO. 2
STATE OF TEXAS S CITY SECRETARY CONTRACT NO. ✓ d o�`�
(No M&C Needed)
COUNTY OF TARRANT S
WHEREAS, the City of Fort Worth (City) and Parsons Water and
Infrastructure, Inc. (Engineer) made and entered into City
Secretary Contract No. 31257, (the Contract) which was authorized
by the City Council by M&C C-20470 on the 4th day of January,
2005; and subsequently revised by one previous amendment;
WHEREAS, the Contract involves engineering services for the
following project:
Water and Sanitary Sewer Main Replacements on Throckmorton
Street and 14th Street
WHEREAS, it has become necessary to execute Amendment No. 2
to said Contract to include an increased scope of work and revised
maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and
through their duly authorized representatives, enter into the
following agreement which amends the Contract:
1.
Article I of the Contract is amended to include the
additional engineering services specified in a proposal letter
dated August 5, 2005, a copy of which is attached hereto and
incorporated herein. The cost to City for the additional design
services to be performed by Engineer total $10, 132 . 98 .
2 .
Article II of the Contract is amended to provide for an
increase in the maximum fee to be paid to Engineer for all work
and services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall not
exceed the sum of $94 , 657 . 96.
ORIGINAL
3.
All other provisions of the Contract which are not expressly amended
herein shall remain in full force and effect.
EXECUTED on this the day of 6 2005, in Fort
Worth, Tarrant County, Texas.
ATTEST:
�\-\t�) �A�b"&L��L7
Marty Hendrix
City SecretaryNO M&C REQU[RED
APPROVAL RECOMMENDED: RO
A. Douglas Rademaker, P.E. Marc tt
Director, Department of Assi tant City Manager
Engineering
PARSONS WATER AND INFRASTRUCTURE, INC.
ENGINEER
By: % 4
Name: Marvin Williams
Vice President
4500 Mercantile Plaza Dr. , STE 235
Fort Worth, TX 76137
APPROVED AS w FORM AND LEGALITY:
Assistan Cit tt,orney
ar.,�� ❑r �,at
PARSONS
4500 Mercantile Plaza Drive,Ste 228•Fort Worth,TX 76137.(817)759-4820•Fax(817)834-2165•www.parsons.com
August 5, 2005
Mr. Rakesh Chaubey, P.E.
Engineering Services
City of Fort Worth
1000 Throckmorton Street
Fort Worth, Texas 76102-6311
Re: Request for Amendment No. 2
Water and Sanitary Sewer Replacement -Throckmorton St. and 14`h St.
Project No. 00136
Dear Mr. Chaubey:
The original scope of work for this project included topographic and subsurface
utility surveys along Throckmorton St. from 14`h St. to 11`h St., along 11`h St. from
Throckmorton St. to Houston St., and along 14`h St. from Throckmorton St. to Houston
St.
Parsons submitted a Conceptual Design Report to the City of Fort Worth on April
8, 2005. This report included five alternate alignments for relocation of the gravity
sanitary sewer. Three of the alternatives were eliminated during the Conceptual Design
review meeting on May 6, 2005. Alternative 4 provided for a portion of the line to be
routed along the new 12`h St. from Throckmorton St. to Houston St. and north along
Houston St. to tie into an existing manhole at the intersection of 11`h St. and Houston St.
Parsons did not provide survey information for this alignment because construction in the
new 12`h St. and Houston St. was not in the original scope of work. Parsons was asked to
do additional due diligence work to locate other subsurface utilities along this alignment.
Parsons completed the additional due diligence work and submitted a revised
Conceptual Design Report on June 7, 2005 which showed the subsurface utilities based
on the best information available from the utility companies. Parsons strongly
recommends that a topographic and subsurface utility survey be completed along the new
12`h St. from Throckmorton St. to Houston St., along 13`h St. from Throckmorton St. to
Houston St., and along Houston St. from 11`h St. to 13`h St. to make certain that all of the
subsurface utilities have been correctly located in the project area so that there are no
delays during the construction phase of the project because of unknown utility
interferences.
The cost for the additional topographic and subsurface utility survey is
$10,132.98 which includes a 10% mark-up allowed by our contract. A breakdown of the
costs is attached. Therefore, we request an amendment in this amount to cover the costs _
of the additional survey work.
Original Contract Amount $ 81,319.98
Amendment No. 1 $ 3,205.00
Amendment No. 2 $ 10,132.98
Total Contract Amount $ 94,657.96
Please do not hesitate to contact me via e-mail at jack.thibodeaualDarsons.com or
on my cell phone at (972) 898-3462 if you have any questions or need additional
information.
Sincerely,
J ._ Thibodeau, P.E.
Senior Project Manager
Attachment
Amendment No. 2
Cost Estimate
Project No. 00136
SUE
PM $ 123.78 3 $371.34
PE $ 110.74 8 $885.92
SUE Mgr $ 83.62 24 $2,006.88
SUE Tech $ 44.72 48 $2,146.56
CADD $ 67.76 12 $813.12
Tech Support $ 41.33 6 $247.98
$6,471.80
Vac Truck $ 80.00 0 $ -
Des Truck $ 15.00 48 $ 720.00
$ 720.00
$ 7,191.80
Surveying
RPLS 75 2 $150.00
Survey Tech 65 4 $260.00
3-Man Crew 115 14 $1,610.00
$2,020.00
Subtotal $ 9,211.80
10% Mark-Up $ 921.18
TOTAL SUE & Survey $10,132.98