Loading...
HomeMy WebLinkAboutContract 45640-CO1 COTY SECT . FORTWORTH$ City of Fort Worth CONTRACT NO. ?� Change Order Request Project Namel HMAC Overlay 2014-3 City Sec# 1 45640 Client Project#(s)l DOE#7215; City Project#02258 Change Order Submittal# 0 Date 9/26/2014 Contract Time Dept. TIPW Totals CD Original Contract Amount $1,458,547.34 $1,458,547.34 180 Extras to Date Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $1;458;547.34: $1,458,547.34 180 Amount of Proposed Change Order .;$10,298'75,.;- $10,298.75 5 Revised Contract Amount $1.;468,846.09' $1,468,846,09 185 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO Additional Funding(if necessary) $101298.75 - $10,298.75 CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT ..0.71%- MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COS T+25%) x$1,823;184;18:. This Change Order is being submitted to request the inclusion of an additional bidlist pay item, retaining wall, as well as added pay item quantities. This request stems from the requested inclusion of Owasso Dr.;which is appropriated as a TIF project. of IF A7 V °60 C) °° %O MW Uo i , C Secretary oQ 00 7 �p° O ® O'A°OOOOObO°O° F OFFICIAL RECORD CITY SECRETARY FT.WORTH,TX FORT WORTH City of Fort Worth ! - Change Order Additions Project Name HMAC Overlay 2014-3 City Sec# 45640 Client Project# DOE#7215;City Project#02258 Change Order Submittal# 0 Date 9/26/2014 ADDITIONS rn jUnit s o a Remove Sidewalk Concrete Sidewalk Remove ADA Ramp P A Ramp P A Sidewalk etaining Wall TFPW- Mobilization T/PW $10,298.75 Sub ota R!= Change Order Additions Page 1 of 1 FORT WORTH City of Fort Worth Change Order Deletions Project Name HMAC Overlay 2014-3 City Sec# 45640 Client Project# DOE#7215;City Project#02258 Change Order Submittal# Date 9I26I2014 DELETIONS ITEM DESGRIPIIUN DEPT City Unit Unit Cost o a T/PW $0,00 Sub ota Deletions Change Order Deletions Page 1 of 1 M/SBE Breakdown for this Change Order "M/SBE:Sub . ' pad Service Amourit for this GO. None Total Previous Change Orders `CO DATE AMOUNT NA Total $0:00 CFW.Change Order Approval St-COApp01 Page 1 of 3 Routin Assigned To: Due Date: Assigned By: Due Time: Links 1 fortworthgov/Infrastructure Proiects/02258 - HMAC Surface Overlay (2014-3)/Contractor/Change Orders/Change Order Breakdown - col revised.xls Attachments(0) No Attachments have been added to this form. https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?Siteld=51500&Processld=525&Activ... 10/20/2014 CFW,Change Order Approval St-COApp01 Page 2 of 3 FORT WORTH, City of Fort Worth Change Order Request Approval (Change Order Breakdown Available in Links) For Change Order Submittal No.: 1 Change Order No.: St-COApp01 Date Started: 2014-10-07 City Sec. No.: 45640 Date Due: 2014-11-26 Project Name: HMAC Surface Overlay (2014-3) 02258 DOE Numbers: Project Numbers: DOE No. 7215 Project Removal and replacement of broken or nonfunctional curbs & Description: gutters, driveways and sidewalks; pulverization and stabilization of the existing pavement, then an overlay of HMAC surface course. Project Manager: ,Kristian Sugrim City Inspector: Mike Glover Contractor: JLB Contracting, LLC. COUNCIL ACTION (If Required): M&C Log Name: M&C Number: M&C Date: COST AND DAYS SUMMARY: Requested Department: Cost($) Fund Account Center: Days: Transportation & Public Work $ 10,298.75 C293-541200-209620225883 5 Total Cost: $ 10,298.75 Total Requested Days: 5 Approval Status: https://projeetpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?Site1d=51500&ProcessId=525&Activ... 10/20/2014 CFW,Change Order Approval St-COApp01 Page 3 of 3 Approved: Yes Comments: User: Tara Fishback Date: 2014-10-07 9:23 AM Approved: Yes Comments: User: Sam Davis Date: 2014-10-07 9:33 AM Approved: Yes Comments: User: Kristian Sugrim Date: 2014-10-07 9:40 AM Approved: Yes Comments: User: Najib Fares Date: 2014-10-09 11:54 AM Approved: Yes Comments: User: Andy Anderson Date: 2014-10-09 4:15 PM Approved: Yes Comments: User: Doug Wiersig Date: 2014-10-10 12:38 PM Approved: Yes Comments: User: Grant Jordan Date: 2014-10-20 11:22 AM Approved: Yes Comments: User: Fernando Costa Date: 2014-10-20 4:36 PM Action Required: https:Hprojectpoint.buzzsaw.com/ bz_web/Forms/FormPrint.aspx?Siteld=51500&Processld=525&Activ... 10/20/2014