WHEREAS, the City of Fort Worth (CITY) and GHD, Inc . (formerly
Ourston Roundabout Engineering) , (ENGINEER) made and entered into City
Secretary Contract No. 45118, (the CONTRACT) which was authorized by M&C
C-26524 on the 22nd day of October, 2014 in the amount of $ 200, 000 . 00;
and
WHEREAS, the CONTRACT involves engineering design and review
services for the following project:
ON-CALL ROUNDABOUT DESIGN SERVICES; and
WHEREAS, it has become necessary to execute Amendment No. 1 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement,
which amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional
engineering services for on-call design and review of roundabouts as
agreed upon in task orders to be defined at a later date within the
remainder of the 24-month time period specified in the initial contract
in the amount of $300, 000 . 00 .
2 .
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $500, 000 . 00 .
3 .
All other provisions of the Contract, which are not expressly
amended herein, shall remain in full force and effect.
EXECUTED and EFFECTIVE as of the date last written by a signatory,
below.
City of Fort Worth
Professional Services Agreement Amendment Template
PMO Official Release 8/1/2012 �t• j�-r �-
Page 1 of 2 4 CORD
RECEIVED OCT 2 O 2
APPROVED:
City of Fort Worth ENGINEER
GHD, Inc.
Fernando Costa Mark Len_ 1�s, P.E.
Assistant City Manager Service Group Manager
DATE: _ /O 14 .-...__. DATE: zf
i
APPR AL RECOMMENDED:
� 6" 4 , \
Douglas Wiersig, P.E.
Director, Department of Transportation
and Public Works
APPROVED AS TO FORM AND LEGALITY: M&C: C _ 2-6-S s y
Date:
Douglas W. Black
Assistant City Attorney
�+S
000
ATTEST:
0
o°O j0
-,t®r—' pg�y
° 00 �i
J
Mary Mary . err
City Secretary '
City of Fort Worth
Professional Services Agreement Amendment Template OFFICIAL
PMO Official Release 8/1/2012
Page 2 of 2
M&C Review Page 1 of 2
Official site of the Gtv of Fort Worth,Texas
FORTRTN
CITY COUNCIL AGENDA i
COUNCIL ACTION: Approved on 8/5/2014
DATE: 8/5/2014 REFERENCE ,.0-26898 LOG 20ROUNDABOUTS/INTERSECTIONS
NO.: NAME: ON-CALL DESIGN CONTRACT-2 GHD
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: Authorize Execution of Amendment No. 1 to City Secretary Contract No. 45118, an
Engineering Services Agreement with GHD Inc., Formerly Ourston Roundabout
Engineering, in the Amount of$300,000.00 for On-Call Roundabout and Intersection
Design Services, Thereby Increasing the Total Contract Amount to $500,000.00 (ALL
COUNCIL DISTRICTS)
RECOMMENDATION:
It is recommended that the City Council authorize execution of Amendment No. 1 to City Secretary
Contract No. 45118, an Engineering Services Agreement with GHD Inc., formerly Ourston
Roundabout Engineering, in the amount of$300,000.00 for On-Call Roundabout and Intersection
Design Services, thereby increasing the total contract amount to $500,000.00.
DISCUSSION:
The Department of Transportation and Public Works (TPW), Infrastructure Design and Construction
Division is responsible for coordinating and managing the design and construction of arterial
roadways, neighborhood streets, and intersection improvements. As part of the intersection
improvements program, the construction of modern roundabouts (and other alternative intersection
technologies) are being considered at intersections planned for improvements. A review of the
viability of a roundabout in comparison with other intersection technologies requires a level of
experience that few engineering consultants in Texas possess. Based on their qualifications,
extensive knowledge of roundabouts, past design experience and competence, GHD Inc., was
retained for a two-year period beginning October of last year. The proposed engineering services will
be utilized over that period to provide conceptual design services, feasibility analyses and quality
assurance/quality control assistance as needed.
GHD Inc., has completed conceptual design, review and feasibility studies for multiple roundabouts
over the last five months as outlined in the table below. GHD Inc., is currently providing preliminary
design for two roundabouts along Harmon Road, at its intersection with State Highway
287, Amendment No. 1 will increase the contract limit from the initial $200,000.00 to a total of
$500,000.00 enabling GHD Inc., to complete the previously defined projects and help in the delivery
of the 2014 Bond Program on a project-by-project basis.
The following table summarizes previous contract action and amendments:
http://apps.cfwnet.org/council_packet/mc_review.asp?ID=19767&councildate=8/5/2014 9/17/2014
M&C Review Page 2 of 2
Funding Committed Available Description
Funds
Initial Contract $200,000.00 - $200,000.00 On-Call Roundabout
City Secretary Contract
No. 45118 M&C C-26524
Approved 10/22/2013
Task Order No. - $102,811.00 $97,189.00 Design review for 12
1, 4 and 7 thru roundabouts.
9
Task Order No. - $53,740.00 $43,449.00 Conceptual Design
2, 5 and 6 and Design Review
(Including feasibility
study) for
three roundabouts.
Task Order No. - $12,880.00 $30,569.00 Feasibility review for
3 six intersections
proposed as
roundabouts.
Proposed $300,000.00 - $330,569.00
Amendment
otals 1 $500,000.00 $169,431.001 1 $330,569.00 -
M/WBE Office -A waiver of the goal for MBE/SBE subcontracting requirements was requested by the
Department and approved by the MNVBE Office for the contract with GHD Inc., in accordance with
the BDE Ordinance, because the purchase of goods and services from source(s) where
subcontracting or supplier opportunities are negligible.
Some expenses under this Agreement will be associated with the 2014 Bond Program. Available
resources within the General Fund will be used to provide interim financing for these expenses until
debt is issued. Once debt associated with this project is sold, bond proceeds will reimburse the
General Fund in accordance with the statement expressing official intent to reimburse that was
adopted as part of the ordinance canvassing the bond election -Ordinance No. 21241-05-2014.
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies that funds are available in the General Fund to
pay expenses which will be incurred on this contract until reimbursement can occur from the issuance
of public securities.
TO Fund/Account/Centers FROM Fund/Account/Centers
Submitted for City Manager's Office by: Fernando Costa (6122)
Originating Department Head: Douglas W. Wiersig (7801)
Additional Information Contact: Todd Estes (5448)
ATTACHMENTS
http://apps.cfwnet.org/council_packet/mc_review.asp?ID=19767&councildate=8/5/2014 9/17/2014