Project Namel Construction of Pennsylvania Ave from Tenth St to West Cannon St City Sec# 1 44209
Client Project#(s)l City Project#01742
Change Order Submittal# Date 9/19/2014
Dept. TPW Water Sewer Contract Time
Totals CD
Original Contract Amount $653,432.10 $20,950.00 $50,710.00 $725,092.10 150
Extras to Date $26,355.00 $4,060.00 $30,415.00 80
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $653,432.10 $47,305,00 $54,770.00 $755,507.10 230
Go to ADD&DEL Tabs to Enter CO Backup $0.00 $34,595.00 $0.00 $34,595.00 30
Revised Contract Amount $653,432.10 $81,900.00 $54,770.00 $790,102.10 260
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO $0.00 $0.00 $0.00
Additional Funding(if necessary) $34,595.00 $34,595.00
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 8.970/(
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $906,365,13
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Replace existing water line discovered under Cannon Street
A
77 " by:
A%0i 0
8 0
us 070
Mary,. r, rkybeewtary $
00000A°o
r�
z
0
ND
(0111-IM10 1 RNIMMI
90 WV SEC Nk"' AVAK
pq"I M00 RVC , ti%K
FORT WORTH City of Fort Worth
Change Order Additions
Project Name Construction of Pennsylvania Ave from Tenth St to West Cannon St City Sec# 44209
Client Project# City Project#01742
Change Order Submittal# Date 9/19/2014
ADDITIONS
ITEM DESCRIPTION DEPT City Unit Unit Cost Total
ater tems
I-21 Rework 36"Plug&Weld Water 1.00 LS 3,325.00 =, 5.
I-22 Concrete 36"Plug Water 10.00 CY 220.00
1-23 8"PVC Water Water 210.00 LF 56.00 ,7
1-24 8"Gate Valve Water 2.00 Ea T1,350.00---777=
1-25 Connect to Existing Water Water 2.00 Ea $2,230.00
I-26 Re-Mobilization Water 1.00 LS 5,000.00 5,
1-27 De-Hole Existing Services Water 3.00 Ea 700.00
Existign Contract Items
1-6 6"DI Fitting Water 0.20 TN 7,000.00
1-15 1"Water Service Water 1.00 Ea 1,650.00 , 5 .
TPW $0.00
Water $34,595.00
Sewer $0.00
Sub Total Additions
Change Order Additions Pagel of 1
FORT WowrH City of Fort Worth
Change Order Deletions
Project Name Construction of Pennsylvania Ave from Tenth St to West Cannon St City Sec# 44209
Client Project# City Project#01742
Change Order Submittal# Date 9/19/2014
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
TPW $0.00
Water $0.00
Sewer $0.00
Sub Total Deletions
Change Order Deletions Page 1 of 1
M/SBE Breakdown for this Change Order
M/SBE Sub Type of Service Amount for,this CO
N/A
Total $0,00
Previous Change Orders
Co# DATE AMOUNT
Total $0."00
CFW Change Order Approval Wa-COApp08 Page 2 of 3
City of Fort Worth
- ° Change Order Request Approval
(Change Order Breakdown Available in Links)
For Change Order Submittal No.: ';2
Change Order No.: 'Wa-COApp08 Date Started: '11/3/2014
City Sec. No.: 44209 Date Due: 12/23/2014
Project Name: Pennsylvania-10th Ave tol2th Ave
01742 DOE Numbers:
Project Numbers:
Project 'Construction of Pennsylvania Avenue from Tenth Street to West Cannon
Description: 'Street
City Project Mgr.: Leon Wilson City Inspector: Mike Collier
Contractor: McClendon Construction Co.
COUNCIL ACTION (If Required):
M&C Log Name:
M&C Number: M&C Date: A
COST AND DAYS SUMMARY:
Department: Cost($) Fund Account Center: Requested Days:
Water $ 34,595.00 P253 541200 609170174283 30
Total: $ 34,595.00 Total Requested Days: 30
Approval Status:
https://projeetpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?Site1d=51500&Proces... 11/20/2014
CFW Change Order Approval Wa-COApp08 Page 3 of 3
Approved: Yes
Comments:
User: Justin Blair
Date: 2014-11-03 3:06 PM
Approved: Yes
Comments:
User: Leon Wilson
Date: 2014-11-03 3:16 PM
Approved: Yes
Comments:
User: Tony Sholola
Date: 2014-11-05 3:41 PM
Approved: Yes
Comments:
User: Andy Cronberg
Date: 2014-11-13 7:08 PM
Approved: Yes
Comments:
User: Doug Black
Date: 2014-11-20 1:14 PM
Approved: Yes
Comments:
User: Fernando Costa
Date: 2014-11-20 7:27 PM
Action Required: Please review,approve,and submit