WHEREAS, the City of Fort Worth (City) and HNTB Corporation (Engineer)
made and entered into City Secretary Contract No. 29323 (the Contract) which was
authorized by the City Council by M&C C-19818 on the 21st day of October, 2003; and
WHEREAS, the Contract involves engineering services for the following project:
Engineering Service for Pavement Reconstruction and water and sanitary
sewer reconstruction on Malcom Street (Craig Street to Lancaster Avenue) and
Haynie Street (Craig Street to Lancaster Avenue)
WHEREAS, it has become necessary to execute Amendment No. 1 to said
Contract to include an increased scope of work and revised maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through their duly
authorized representatives, enter into the following agreement, which amends the
Contract:
1.
Article I of the Contract is amended to include the additional engineering services
specified in a proposal letter dated August 20, 2004, a copy of which is attached hereto
and incorporated herein. The cost to City for the additional services to be performed by
Engineer total $12,684.00
2.
Article II of the Contract is amended to provide for an increase in the maximum
fee to be paid to Engineer for all work and services performed under the Contract, as
amended, so that the total fee paid by the City for all work and services shall not exceed
the sum of$127,547.77
3.
All other provisions of the contract, which are not expressly amended herein, shall
remain in full force and effect.
ORIGINAL
EXECUTED on this the QCyh day of , 2004, in Fort
Worth, Tarrant County, Texas
APPROVAL RECOMMENDED: APPROVED:
A. Douglas Rademaker, P.E. Marc Ott
Director, Department of Assistant City Manager
Engineering
HNTB Corporation, Inc.
ENGINEER
ATTEST:
Marty Hendrix, ity Secretary
By:
kl,010L
Name: Benjamin J B4ter, P.E. contract authorization
Vice-President
Date
APPROVED AS TO FORM AND LEGALITY:
ary Steinberger
Assistant City Attorney
ARCHITECTS ENGINEERS PLANNERS 0I Cournle""•S7ree!
,,,,<<.-00
Dallas,Texas
7520_'
(219)-98-8900
Fax(214)-41-4681
August 20, 2004
Mr. Gopal Sahu, P.E.
Project Manager
Engineering Department
City of Fort Worth
1000 Throckmorton
Fort Worth, TX 76102
Reference: Malcolm Street and Haynie Street Improvement
Contract Amendment No. 1
Dear Gopal
I am pleased to submit to you our attached proposal for Contract Amendment No. 1, which will
accommodate the following additional design services for the referenced project:
1. Extend the proposed 8" water line under Haynie Street from Church Street to Kerr Street, a
distance of approximately 450 feet. Assessment taps are to be installed at each lot within the limits.
The cost for this service is $4,512.
2. Prepare plans and bid documents so that the City can receive bids for three separate construction
options. The options are described in the attached document emitted "Malcolm Street and Haynie
Street Bid Options". The cost this service is $8, 172.
Therefore, the total cost for Contract Amendment No. 1 is $12,684. The attached proposal shows
the cost breakdown between Water Department and TPW. Since you had stated that you wanted to
bid the project quickly, we ask that you expedite the approval of this contract amendment. If you
need additional information or have questions, please let me know.
Sincerely,
Ctv�) F.I-:.
Bo V. Cung, P.E.
Senior Project Manager
C: Jerry Holder, HNTB
Anthony Kalinski, HNTB
1
�iui . . , . .. •..,i i i.�. il ... v ,.-i ,. i.�i, i ,. ., nua �m �� � rtpcy�"4/�4�\""ti`='Fk�IC('EVa..
• n i �, ,in. „ � i i,11�c.v"VL1'1 11 WC- u.
AI .Il 1 .ill r ��I u,\i ,. ,ii M �4�tiVl���n'n r�:�tl?��kl��� '�Yo
M1f Ill
r� e i.,niai 1AH ic, tiiYria�F�rn'.i�'.
.. 1• 1 1 W, ... .i ., _ _ IIS . [. ! i. ', " .I O11•1PV�1•,,. UC
Malcolm Street and Haynie Street Bidding Options
1. Option 1:
• Unit 1:
o Water Line Replacement on Haynie
o Sewer Line Replacement on Malcolm and Haynie
o Temporary pavement repair on Malcolm and Haynie.
• Unit 2: Paving on Malcolm and Haynie
2. Option 2:
• Unit 1:
o Water Line Replacement on Haynie
o Sewer Line Replacement on Malcolm and Haynie
o Temporary pavement repair on Malcolm
o Permanent pavement repair on Haynie.
• Unit 2: Paving on Malcolm only
3. Option 3:
• Unit 1:
o Water Line Replacement on Haynie
o Sewer Line Replacement on Malcolm and Haynie
o Temporary pavement repair on Malcolm and Haynie.
• Unit 2: Paving on Malcolm only
• Unit 3:
o Replace curb and gutter, driveways, sidewalks on Haynie
o Pavement pulverization on Haynie (3" asphalt overlay over 8" lime
pulverization.)
HNTB Proposal
Malcolm & Haynie From Craig Street to Lancaster Avenue
Contract Amendment# 1
Prepared for:The Citv of Fort Worth DATE:08-19-2004
Contract Summary
Original Supplemental Agreement No.1 Amount New
Contract Amount Prepare
Extend Water Line Documents for 3
on Haynie Bid Options Subtotal Contract Amount
1 Depart ment of Engineering
21 Pavement Design Services $75,636.83 $4,086.00fl$4,086.00
$79,722.133
3
4 Subtotal Department of Engineering $75,636.83 $4,086.00 $79 722.83
5
6 Water Utilities
7 Water Desi n Services $21,433.70 $4,512.00 $2,043.00 $27,988.70
8 S ecial Services $17,793.24 $2,043.00 $19,836.24
910 Subtotal Water Utilities $39 226.94 $4,512.00 $4,086.00 $47,824.94
11
12 Total Contract $114,863.771 $4,512.00, $8,172.00 $12,684.001 $127,547J7
Consultant Participation Summary
Original Orig%of New New%of
Contract Amount Contract Contract Amount Contract
1 HNTB Corporation $87,301.68 76.0°% $99,985.68 78.4%
2
3 Gorrondona&Associates MBE Sub $24,782.09 21.6% $24,782.09 19.4%
4
5 Hu o C.Trevino&Associates BE Sub $2,780.00 2.4%1 $2,780.00 2.2%
6
7 Total Contract $114,863.771 100.0%1 $127,547.771 100.0%
Page 1
row
HNTB Design Fee
r�r�
Malcolm & Haynie From Craig Street to Lancaster Avenue
Contract Amendment# 1
Prepared for:The Citv of Fort Worth DATE:08-19-2004
Scope Revision:Extend Water Line on Haynie to Kerr Street.Approx.Construction Cost:$33,125
Prepare plans,specifications and estimates to extend the proposed water Principal Manager Engrf Arch Cadd Tech Clerk TOTAL
line on Haynie from Church Street to Kerr Street. Hours Hours Hours Hours Hours IF
1 Final Design 100°!°
2 Collect data 0 2 2 12 0 16
3 Developtans bid quantities sheets andspecial specifications 2 4 8 10 0 24
4 Finalize Opinion of Probable Cost. 2 4 4 0 10
5 Qualityassurance/control review 0 2 0 0 0 2
6 Submit plans to Cit 0 0 0 0 0 0
7 Sub-total 2 8 12 14 0 36
8
9 Total Man-hours 2 8 12 14 0 36
10 Contract HourlyRates $195 $164 $135 $60 $37
11 Labor Cost $390 $1,312 $1,620 $840 $0 $4,162
12
13 Expenses $350
14
15 Total Cost for Department of Enaineerinq $4,512
Page 2
(Z--�
HNTB Design Fee
Malcolm & Haynie From Craig Street to Lancaster Avenue
Contract Amendment# 1
Prepared for:The City of Fort Worth DATE:08-19-2004 F1
Scope Revision:Develop Three(3)Bid Options
Prepare plans,specifications and estimates for three separate bidding Principal Manager EngiTarch Cadd Tech Clerk TOTAL
options for the Project Hours Hours Hours I Hours I Hours
Final Design(100%)
2 DeveloD Dians,bid quantities sheets ands ecial specifications 2 8 16 24 0 so
3 Finalize Opinion of Probable Cost. 2 2 4 4 0 12
4 Quality assurance/control review 2 4 4 0 10
5 Submit plans to City 0 2 2 0 0 4
6 Sub-total 6 8 26 28 0 76
7
8 Total Man-hours 6 8 26 28 0 76
9 Contract Hourly Rates $195 $164 $135 $60 $37
10 Labor Cost $1,170 $1,312 $3,510 $1,680 $0 $7,672
11
12 Expenses $500
13
14 Total Cost for Department of Engineering $8,172