HomeMy WebLinkAboutContract 30634 CsTy ;F,-CRETgRY-
-ONTRACT NO. r
AMENDMENT NO. 2
STATE OF TEXAS § CITY SECRETARY CONTRACT NO. 27928
COUNTY OF TARRANT §
WHEREAS, the City of Fort Worth (City) and Carter & Burgess, Inc., (Engineer)
made and entered into City Secretary Contract No. 27928 (the Contract) which was
authorized by the City Council by M&C C-20280 on the 21st day of September, 2004;
and
WHEREAS, the Contract involves engineering services for the following project:
Engineering Contract for Northside II 16-inch Water Main Extension along
North Tarrant Parkway from IH35W to Park Vista Boulevard.
WHEREAS, it has become necessary to execute Amendment No. 2 to said
Contract to include an increased scope of work and revised maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through their duly
authorized representatives, enter into the following agreement, which amends the
Contract:
1.
Article I of the Contract is amended to include the additional engineering services
specified in a proposal letter dated June 23, 2004, a copy of which is attached hereto and
incorporated herein. The cost to City for the additional services to be performed by
Engineer total $29,240.
2.
Article II of the Contract is amended to provide for an increase in the maximum
fee to be paid to Engineer for all work and services performed under the Contract, as
amended, so that the total fee paid by the City for all work and services shall not exceed
the sum $164,885.
3.
All other provisions of the contract, which are not expressly amended herein, shall
remain in full force and effect.
4�a2y ORIGINAL
RTa, OX.
EXECUTED on this the day of , 2004, in Fort
Worth, Tarrant County, Texas.
APPROVAL RECOMMENDED: APPROVED:
A.Douglas Rademaker, P.E. arc Ott
Director, Department of Assistant City Manager
Engineering
ENGINEER
ATTEST:
pc\
Marty Hendrix, bity Secretary
By:
Name: Steven C. Veal, P.E. contract author' zatiOR
Principal/Vice President 1�0
Carter& Burgess, Inc.
U-tte
APPROVED AS TO FORM AND LEGALITY:
Gary Steinberge
Assistant City Attorney
OFFICIAL END
CRY sici ly
R. WITH, TO.
777 Main Street
P.O.Box 901058
Carter.-:Burgess Fort Worth,Texas 76101-2058
Phone: 817.735.6000
Fax: 817.735.6148
June 23, 2004 www.c-b.com
City of Fort Worth
Department of Engineering
1000 Throckmorton Street
Fort Worth, Texas 76102
Attn: Gopal Sahu, P.E.
Project: North Tarrant Parkway 16 inch Waterline.
Reference: Amendment No. 2 to the Engineering Services Agreement
Water Project No. P161-060161141100 — DOE No. 3748
Reduce Depth of Line, Update Plans with Retaining Wall and Pre-construction
De-hole Notes, Modify design at Culverts, Modify design at 1-35 interchange,
Prepare Manhole relocation detail
Dear Mr. Sahu:
On March 9, 2004 the city of Fort Worth requested that Carter & Burgess modify construction
plans to reduce the depth of the line to 4-5 feet of cover. Preliminary design of waterline
followed this 4-5 feet of cover, but in subsequent meetings with the City, Carter & Burgess was
instructed to remove vertical points of inflection and maintain 5 feet of clearance under storm
drains. During the March 91h meeting, Carter& Burgess was instructed to survey a new
retaining wall located at station 88+00, and to modify design to allow for construction without
disturbing retaining wall structure. These design changes allowed for the reduction in depth of
approximately 6,900 LF of pipe and an additional 20 LF of steel casing pipe. In addition to
these items, pre-construction de-hole notes were added at points where the waterline crosses
existing water and sewer lines.
At water line crossings at the box culvert at stations 87+00 and 134+00, the city of Fort Worth
requested that the previously approved construction plans be modified by changing the
alignment to help reduce construction costs. Carter & Burgess prepared a figure showing
proposed re-alignment profile. Based on this figure, the city of Fort Worth directed us on April
15, 2004 to change the alignment at station 87+00 and to investigate another possible
alignment option at station 134+00. At station 134+ 00, the design has been changed to leave
out this section to be constructed after the culvert has been constructed during the North
Tarrant Parkway expansion.
The final plans that were submitted and bid on back on July 17, 2003 required that construction
take place in phases. Phase A, North Tarrant Parkway and Interstate 35 exchange, was to be
constructed first. This phase was to be constructed before TxDOT began working on the exit
ramps and overpass. Because the 16" waterline was to be constructed before the interchange
was constructed, proposed grade was not shown since it would not effect how deep the
waterline would have to be constructed. Because the exit ramps are currently being
constructed, construction plans had to be modified to show construction by other than open cut.
Also, a new 18-20-inch sewer line/ manholes have been constructed in the last year. Our utility
research showed alignment only. Because the now existing manholes were not pre Ht
design phase for Carter& Burgess, they were not picked up during survey. In the pre " I �� b �� 2
k- O0
Carter&Burgess,Inc. Carter&Burgess Architects/Engineers,Inc. Carter&Burgess Consultants,Inc. C&B Architects/Eng eercFt� �1Vp���
C&B Architects/Engineers, P.0 C&B Nevada, Inc. Nixon&Laird Architects/Engineers,P.C. i �p�' ix,
City of Fort Worth
June 23, 2004
Page 2
construction meeting on April 21, 2004 two sewer manholes that may be in conflict with TxDOT
construction were brought to our attention, and the city of Fort Worth asked Carter & Burgess to
show these manholes on the construction plans. We received construction plans on the existing
sewer main, and based on the Northing and Easting coordinates provided on the sewer plans
we laid out the manhole locations. These coordinates do not match the roadway plans as well
as our waterline plans. It appears that during construction of the sewer line, there was a
change. The manhole on the west side of the interstate was moved outside the new TxDOT
ROW. The manhole on the east side of the interstate is located on the side slope of the
TxDOT's northbound exit ramp.
Due to the location of this manhole, the city of Fort Worth asked us to relocate this manhole so
that is not in the side slope of the exit ramp. This task required Carter & Burgess to perform a
field survey and then show proposed location of new manhole and other necessary sanitary
sewer details on the plans.
The following is a summary of the contract amendment request:
ANA Survey (MWBE) $1,100
Contract Administration (10%) $110
Design Fee (retaining wall and notes) $3,355
Design Fee (modify alignment at culverts) $2,925
Design Fee (modify depth of line) $8,405
Waterline extension 52' west of sta. 0+00 $1,655
Design changes at Interstate 35
manhole relocation and exit ramp profile) $3,885
Add Manhole relocation profile and detail $3,125
Update all sheets to reflect change in
stationing at culverts $4,680
Total $29,240
For a detailed breakdown of costs see attached spreadsheet. Please bear in mind that Carter &
Burgess can present time sheet reports to document the time spent on this work ordered by the
City. Please call me at 817-735-6202, if you have any questions or would like to discuss further.
Sincerely,
Wm. Ba Hines, P.E.
Senior Project Manager
W BH/tg
Attachment
T:Uob\011624M P\CORR\01162401.L21.doc
cc: Correspondence
Public Works-WBH WlInce7da,
Jonathan Shirk Carter& Burgess, Inc. Carter& Burgess Consultants, Inc. Nixon & Laird Architects/Engineers, P.C. Nixon & Laird Architects/EInc.
CARTER & BURGESS JOB COST ESTIMATE
PROJ MGR: W. Bart Hines, P.E. 06/23/04
16" Waterline Along N. Tarrant Parkway, Job#011624.010 04:03 PM
TOTALTASK
TASK Project Manager I Project Engineer Technican/CADD COST
Parti ADDITIONAL DESIGN SURVEY MWBE
Survey of Retaining Wall ANA Lump Sum Fee for Surveying $1,100
Verify existing rade
Contract Administration(10%) $110
SUBTOTALS 0 0 0 $1,210
Part2 ADDITIONAL DESIGN
Modify drawings(Retaining wall construction notes 4 6 20 $3,100
Modify Design at Culverts 3 8 18 $2,925
Client meeting 1 1 $255
SUBTOTALS 8 15 38 $6,280
Modify drawings Reduce depth of line 8 15 55 $7,895
Client meeting 2 2 $510
SUBTOTALS 10 17 55 $8,405
Extend waterline 52'west of station 0+00 1 4 4 $905
Additional Easement Lopez Garcia $750
SUBTOTALS 1 4 4 $1,655
Modify drawings at Interstate 35 1 16 24 $3,885
Field visit to take measurements of manhole locations 3 3 $555
Add sewer manhole relocation details to plans 2 8 16 $2,570
Update all sheets due to change in stationing around culverts 8 12 24 $4,680
and add 8"waterline ring connection
SUBTOTALS 3 39 67 $11,690
GRAND TOTAL 22 75 164 $29,240.00
TOTAL MAN-HOURS PER DISCIPLINE 22 75 164
AVERAGE HOURLY SALARY RATE PER DISCIPLINE $165.00 $90.00 $95.00
TOTAL JOB COST PER DISCIPLINE $3,630.00 $6,750.00 $15,580.00
PERCENT OF TOTAL JOB HOURS PER DISCIPLINE 8% 29% 63%
PERCENT OF TOTAL JOB COST PER DISCIPLINE 12% 23% 53%
TOTAL SALARY.COST $29,240.00
TaTAt JOB tiOIJRS 261 �" 'jwr gcoaa
M1NBE P:gRTiCtPAT1ON . 4% MY
I�i V01101 fiYr
M&C'Request Review Pagel of 2
Rome I Council Agenda I M&C I Employee Directory Departments
Print M&C
........... . .........
COUNCIL ACTION: Approved on 9/21/2004
DATE: 9/21/2004 REFERENCE NO.: **C-20280 LOG NAME: 30CARTERBURG A2
CODE: C TYPE: CONSENT PUBLIC HEARING: NO
SUBJECT: Amendment No. 2 with Carter& Burgess, Inc. for the Northside II 16-Inch Water Main Extension
along North Tarrant County Parkway from IH-35 W to Park Vista Boulevard
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute Amendment No. 2 to City
Secretary Contract No. 27928 with Carter& Burgess, Inc. in the amount of$29,240, thereby increasing the
original contract amount to $164,885.
DISCUSSION:
On August 23, 2002 (M&C C-19160), the City Council approved an engineering agreement with Carter&
Burgess, Inc. in the amount of$114,595 for the Northside II 16-inch Water Main extension along North
Tarrant County Parkway from IH-35 W to Park Vista Boulevard.
This contract was previously revised on November 19, 2003 by Amendment No. 1 for$21,050 for additional
services pertaining to the Texas Department of Transportation's (TxDOT) North Tarrant County Parkway
Project.
Amendment No. 2 will allow Carter& Burgess, Inc. to design a retaining wall, modify alignments at two
culverts, extend the waterline 52 feet west of station 0+00, modify design at IH-35 W and add a sanitary
sewer manhole. These modifications are required to avoid conflicts with the aforementioned TxDOT project.
Carter& Burgess, Inc. proposes to perform the design work for a lump sum fee of$29,240. City staff
considers this fee to be fair and reasonable for the scope of services proposed.
This project is located in COUNCIL DISTRICT 4, Mapsco 35G, H; and 36E, F, and G. Carter& Burgess, Inc.,
is in compliance with the City's M/WBE Ordinance by committing to an additional 6% M/WBE participation on
this Amendment No. 2.
FISCAL INFORMATION/CERTIFICATION:
The Finance Director certifies that funds are available in the current capital budget, as appropriated, of the
Water Capital Projects Fund.
YOFFI�C"^IAL RVARD
b+111yWRE fp RY
umavuhttp://www.cfwnet.org/council_packet/mc review.asp?ID=2664&councildate=9/21/2004 9/24/2004
MSC Request Review Page 2 of 2
TO Fund/Account/Centers FROM Fund/Account/Centers
P163 531200 060163014106 $29,240.00
Submitted for City Manager's Office by Marc Ott (8476)
Originating Department Head: A. Douglas Rademaker (6157)
Additional Information Contact: A. Douglas Rademaker (6157)