AMENDMENT NO. 1
STATE OF TEXAS § CITY SECRETARY CONTRACT NO.3-11 �133
(No M&C Needed)
COUNTY OF TARRANT §
WHEREAS, the City of Fort Worth (City) and Baird, Hampton & Brown Inc.
(Engineer) made and entered into City Secretary Contract No. 30001 (the Contract)
which was authorized by the City Council by M&C C-20081 on the 18th day of May,
2004; and
WHEREAS,the Contract involves engineering services for the following project:
Birchman Street Reconstruction (Ashland to Camp Bowie)
- Paving,Drainage, Water& Sanitary Sewer-
WHEREAS, it has become necessary to execute Amendment No. 1 to said
Contract to include an increased scope of work and revised maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through their duly
authorized representatives, enter into the following agreement, which amends the
Contract:
1.
Article I of the Contract is amended to include the additional engineering services
and provide additional contract time as specified in a proposal letter, dated February 8'h
2005, a copy of which is attached hereto and incorporated herein. The cost to City for the
additional services to be performed by Engineer total $16,204.90. The additional contract
time for these services is 30 working days.
2.
Article II of the Contract is amended to provide for an increase in the maximum
fee to be paid to Engineer for all work and services performed under the Contract, as
amended, so that the total fee paid by the City for all work and services shall not exceed
the sum of$139,319.90.
3.
All other provisions of the contract, which are not expressly amended herein shall
remain in full force and effect.
ORIGINAL
EXECUTED on this the day of , 20045 in
Fort Worth, Tarrant County, Texas.
APPROVAL RECOMMENDED: APPROVED:
A.Douglas Rademaker, P.E. Marc
Director,Department of Assistant City Manager
Engineering
Baird,Hampton&Brown Engineering&Surve3ng
ENGINEER
ATTEST:
Marty He x, City Secretary
Name: Konstantine Bakintas, P.E.
Vice-President
APP ED AS TO AND LEGALITY:
S*mb rger
Ass7
istant City Attorney
i0i
U,1 lS 14�ty:'1 ,I
n
D � D
I
Baird, ton& Brown, Ina 0 En ineering & SurveV_ ng
February 8,2005
Mr.Gopal Sahu, PE, Project Manager
Department of Engineering
City of Fort Worth
1000 Throckmorton Street
Fort Worth,TX 76102
Tel(817)392-7949,Fax 392-7854
RE: CONTRACT MODIFICATION
BIRCHMAN STREET(ASHLAND TO CAMP BOWIE)RECONSTRUCTION
Weber,Sanitary Sewer, Paving A Drainage
DOE No 3913,
Weber No P264 541200 60917 00063 80,
Sewer No P274 541200 70917 00063 8o
BHB No 03.115.00
Mr.Sahu:
We are pleased to have been selected to assist the City of Fort Worth with the above referenced project;
submitted herewith is a revised proposal to our previously submitted request for a contract modification
dated January 18°i, 2005. This revised request provides for additional compensation to perform sewer
service line re-route surveys.
Our original contract was for the reconstruction of sanitary sewer lateral 2576,which Is in the right of way
of Birchman Ave, and services between five and ten homes. Upon review of this lateral by the city, we
were asked to review the feasibility of abandoning Lateral 2576 and rerouting the services to the sewer
laterals within the alley behind the homes, L-2361 and L-991 which Is under design by IGmely Horn and
associates. We were then supplied with videos of sanitary sewer lateral 2361 and 2576 for our review.
Based on our review of sanitary sewer lateral 2576, we feel that abandoning this lateral and rerouting the
services to lateral 2361 in,the alley behind the homes would be feasible. Based on our review of sanitary
sewer lateral 2361 we have determined that the general condition of the line is poor. The existing pipe
from Sta:13+00 to the end Sta:24+68 Is VCP with multiple cracks, significant surface wear and varying
degrees of root growth at most joints. Also in this reach of the lateral the existing manholes are general
old with brick tops that are cracked. Between Sta:9+00 and Sta:13+00 the pipe Is PVC that Is noticeably
newer and in good condition. Also,the manholes at Sta:9+00 and Sta:15+00 are in noticeably newer with
concrete tops and concrete pads. So our recommendation to the city is to reconstruct sanitary sewer
lateral 2361 from Sta:13+00 to Sta:24+68,which is within the limits of our project.
The estimated construction cost for this additional scope of work has been estimated at $151,800; we
propose an engineering fee, which Includes basic and additional services, of $18,204.90. Additional
services consist of topographic(design)surveys.
6300 Flidglea Place,Suite 700 • Fort Worth,Taxes 76116 • Tel:(817)338-1277 Fax:[817)338-9245 • www.bhbinc.com
Mr.Gopal Sahu, P.E., Project Manager
February 8,2005
Page 2
We propose to continue to utilize the services of an M/WBE surveying and reproduction firm to assist us
with this project,and thus provide 38%M/WBE participation, on this contract modification.
Sincerely,
BHB Engineering dr Surveying BHB Engineering dr Surveying
t
L '
Austin Baird, EIT Icons 'ne , E.
Vice President
Enclosure: Fee&Schedule Summary
Construction Cost Estimate
e.12003.000.00012003.113.00d1documentslcontracNrevised proposal additlonel improvemeMs.doc
• r
BIRCHMAN STREET(ASHLAND TO CAMP BOWIE)RECONSTRUCTION
Water,Sanitary Sewer,Paving&Drainage
DOE No 3913
Water No P264 541200 60917 00063 80
Sewer No P274 541200 70917 00063 80
Fee Summary for Contract Modifications
Basic Services:
Water Department: (Construction Cost X ASCE Curve°A"X 85%)
Water Improvements 36,300 X 7.300/6 X 85% _$ 2,252
Sanitary Sewer Improvements 115,500 X 7.30%X 85% -=$ 7.167
Water:Basic Services Total $ 9,419
Additional Services:
Water Department:
Topographic Surveying Services(by M/WBE)
'Survey for Service Line Re-route(Lots 1-11 Block 100) _$ 1,800.00
Topographic Survey 1,175LF X$3.25 =$ 3,819.00
Right-of-Entry Agreements 22 Ea X$25/Ea =$ 550.00
Administrative (10%) Fee on M/WBE Firms =$ 619.90
Water Department:Additional Services Total =$ 6,785.90
Water Department:Total Additional Compensation =$ 16,204.90
Project Schedule for Contract Modifications
Topographic Surveying 20 Working Days
Engineering 10 Working Days
Total Additional Time 30 Working Days
Note: Revised Proposal Provides for Additional Compensation for S.S. Service Line Re-Route Surveys