HomeMy WebLinkAboutContract 31440 03-02-05An9 : 01 RCVD COMMUNITY FACILITIES AGREEMENT THE STATE OF TEXAS § City Secretary COUNTY OF TARRANT § Contract No. 31 �-6 WHEREAS, Centex Homes, a Nevada General Partnership, hereinafter called "Developer", desires to make certain improvements to Deer Valley, D.O.E. #4694 an addition to the City of Fort Worth, Texas; and WHEREAS, the said Developer has requested the City of Fort Worth, a municipal corporation of Tarrant and Denton Counties, Texas, hereinafter called "City", to do certain work in connection with said improvements. NOW, THEREFORE, KNOW ALL BY THESE PRESENTS: That said Developer, acting herein by and through Centex Homes Real Estate Corporation, A Nevada Corporation its duly authorized Managing Partner, and acting through Bred Pedigo, its duly authorized Vice President, and the City, acting herein by and through Marc Ott, its duly authorized Assistant City Manager, for and in consideration of the covenants and conditions contained herein, do hereby agree as follows: I. General Requirements A. The Policy for the Installation of Community Facilities ("Policy") dated March 2001, approved by the City Council of the City of Fort Worth, is hereby incorporated into this Community Facilities Contract as if copy herein verbatim. Developer agrees to comply with all provisions of said Policy in the performance of its duties and obligations hereunder. B. The requirements of the Policy shall govern this Community Facilities Agreement, provided, however, that any conflict between the terms of this Community Facilities Agreement and the Policy shall be resolved in favor of this Agreement. C. Developer shall provide financial security in conformance with paragraph 6, Section II, of the Policy. New CFA 4% and Utilities 02 02 05.htm 1 � D. The Developer shall award all contracts for the construction of community facilities in accordance with Section II, paragraph 7 of the Policy. E. The contracts for the construction of the public infrastructure shall be administered in conformance with paragraph 8, Section II, of the Policy. F. The Developer further covenants and agrees to, and by these presents does hereby, fully indemnify, hold harmless and defend the City, its officers, agents and employees from all suits, actions or claims of any character, whether real or asserted, brought for or on account of any injuries or damages sustained by any persons (including death) or to any property, resulting from or in connection with the construction, design, performance or completion of any work to be performed by said Developer, his contractors, subcontractors, officers, agents or employees, or in consequence of any failure to properly safeguard the work, or on account of any act, intentional or otherwise, neglect or misconduct of said DEVELOPER, his contractors, sub-contractors, officers, agents or employees, whether or not such injuries, death or damages are caused, in whole or in part, by the alle'aed neglizence of the City of Fort Worth, its officers, servants, or employees. G. Developer shall install or adjust all of the required utilities to serve the development or to construct the improvements required herein. H. In the event that City participation exceeds $25,000, Developer agrees that no street construction or storm drainage will begin prior to City Council approval of this Community Facilities Agreement. (Article 104.100, Ordinance 7234). I. Developer agrees that no lot shall be occupied under a certificate of occupancy until the improvements required herein have been constructed (Article 104.100, Ordinance 7234). New CFA 4% and Utilities 02 02 05.htm 2 = 131 7.1'� vS, J. Developer hereby releases and agrees to indemnify and hold the City harmless for any inadequacies in the preliminary plans, specifications and cost estimates supplied by the Developer for this contract. K. Developer agrees to provide, at its expense, all necessary rights of way and easements across property owned by Developer required to construct current and future improvements provided for in this agreement. L. Developer agrees to construct proposed improvements as shown on the exhibits attached hereto. The following exhibits are made a part hereof. Water (A)None; Sewer (A-1) None; Paving (B)Attached Storm Drain (B-1) Attached; Street Lights and Signs (C) Attached. M. City shall not be responsible for any costs that may be incurred by Developer in the relocation of any utilities that are or may be in conflict with any of the community facilities to be installed hereunder. II. Street and Storm Drain Facilities A. The Developer(s) agree to install or to cause to have installed, the street, storm drainage, street lighting, street name sign and other community facilities improvements shown as "current improvements" on the attached Exhibits B, B 1, and C. B. As shown below in the "Summary of Cost for Street and Storm Drain Facilities", the Developer shall fund its share of "current improvements" and shall pay to the City for its share of the cost of street, storm drainage, street lighting, street name signs as shown on the attached Exhibits B, BI, and C. The estimated total cost of current improvements and related support services specified in this agreement, including design, construction and inspection is estimated to $1,083,566.42. 3 Notes: 1. All Preliminary Plats filed after July 2000 will require sidewalks on all streets. The developer is responsible for installation of sidewalk and a separate financial guarantee is required in the form of a bond or check for the cost of the sidewalk. 2. Developer's column for Item C represents four percent (4%) cost for construction inspection fees and materials testing. The City will pay additional inspection fee over 4%. 3. City not preparing plans and specifications. IN TESTIMONY WHEREOF, the City of Fort Worth has caused this instrument to be executed in quadruplicate in its name and on its behalf by its Assistant City Manager, attested by its City Secretary, with the corporate seal of the City affixed, and said Developer has executed this instrument in triplicate, at Fort Worth,Texas this the q dav of `4 L 200 5- Approval Recommended: Transportation and Public Works Department C�2 Robert Goode, P. E. Director City f Fo Wo ', Marc Ott Assistant City Manager ATTEST: VJIi 4r �5�7dJIC�,�j New CFA 4% and Utilities 02 02 05.htm 4 ffi ( DEVELOPER Marty HendAK Centex Homes City Secretary A Nevada General Partnership By: Centex Homes Real Estate Corp. Approved as to Form: A Nevada Corporation Managing Partner By: ITV"� AAssistanty Attorney BVei Pedigo ice President ATTEST: Corporate Secretary Off JK���`',if;�' New CFA 4% and Utilities 02 02 05.htm 5 FT, SUMMARY OF COST Deer Valley Item Developer City Cost Total Cost Cost A. Construction $ - 1. Streets $693,070.10 $ 693,070.10 2. Storm Drainage $287,763.00 $ 287,763.00 3. Street Lights $61,600.00 $ 61,600.00 4. street I ame Signs $1,900.00 $ 1,900.00 B. Engineering Design $ - C. Construction Engineering a.,a Ift-ago. ent by nnG (4%) $ 39,233.32 39,233.32 11G IV IGI IG GIIIGIII V VVL TOTALS $ 1,083,566.42 1 $ - $ 1,083,566.42 f y N � d 16 o � M = 3A a w � ` o � ^ O OF 4 m yy �Z�•p U w I J a I � / � Z t I - z J - � o v CL a J z � � o .r e v 0 U 0 r` ea U O N t0 O a i O I'I U N N W O to O M e W II � O V CL Z o Lu N � _ h a W CO "' Q ccc = a a mror = cn X W16 W w Q W w A Va a m 1 L 00 N 2M' •4 $ n w w 'Ri a a N - n A Q pp n •IIS N Q Q4 CL w ~ iOZ av i o x N ' r z 12- Ft O w- - - w h lzQ r '2 w - h n � h � � .e° V uoM' F" n iswv. 4 J ......... ------- ------ V __ ' . ........ ----- •__••___..__ 1 .._.....�f __..._..__. ............J ' i.___.__..__ vx I I Z � W U W 0 QW [Ocr WOJ WW co C> 0— CI CL 0. ti m Ln ko N[n oOJ Li M N� vQ Qm Q> O o Q •� O W N d 0 CL 0 _ 4.O F- 0 =O �� m[O m[O - a & LL o y m e 7 >1 O C m a z c a LU Lu o r U � m 16oc o N _ mmam z W16 im W W W W A O O I � M p ' I w N \ e Y ry . h P b h n R I h - Lda'4 Z I1flISSOlI �' h w _ I N ` O O w w p 4 a ~ h LL W n h M 0 CL W LLJ e I < w yy O w +� h !WOM Noswr& H (TIO 1 . ----'--`- . I , I Z � W `J 1 LTJ F- cp Yom. Y U L J O: J W O m� RMO RMm O 1 mir WJ WW cr mo mo �� �p p to II) In n J M Ili n N� cQ v2 tr> O i Q O W In O_O Z O F- ir C) - irp OO� D_'OO_'m O_'m — e N N o N L o C) c m r� II W c a a Z r W a m ` ? s o U V] m� Z p w W a Fx W A V S�omCL I m m N N n C7 2 C J = X C7 D ir000 = a Cq� �p N 1h m Q n N N N h N h N C ~ h N h n Q h h N N 0 h �~ cn 77nz � W � J s c d o = ZN J Z OJdV Z _ 2I oo N J = U �n h n W _ 2 Qmc J OM a ; N Z r ou Ll ------------ -------- ------- ------ ----------- ------ - ----- u w w z Z Z �W J o n Z U W Z — �- J a a U M ui 0 W J O J Q o H O �:: m C o m W 2 O O ti O J Z Q LL. LO n W H Z Q N O N — = o V] O O O O n n n n X i o c I y o M c C o 0 M i LA M l o F� U_ c Z r- W vii n -� F- w o Q ` 2g to m mt _ � W L ��� � OX A a �Ii , cn V CL N L h N�h C N w w h w W - N h _ _b0+ N m W � .F�is 1 NDI`02i o c = N a W HR `2 Ly Z W o O V w w w I n o d d w h AVON Nosxlwm CFO .......... it ujII I II II III Z Z ? i wJ J 4 (' Z t UJ Z _ c .J W a SJ D 7 S p W J p J Q S t L F- O S O_ 'c S W S D p r O J Z Q f- LL- u F- z a W V) o c V) , N N N p LD rn (!? w o < o = ,va az LD LD Q W O W � ` o�C o N w T m� Z U-1 X W ` "=o o Q w W W V) 2.Q V nF,CK � ^ a m -7-7 iiqunoo xoxvmwi f'} n Q _ N h h h LL O h IrVILaXV'l X.'AMSui 4� U Oc h n h O m O d M Q. o W W Ldnoo av0 17HA MIT z �I J oG = 0 O 4 V� h ON 0v SVmNv 3 N W U „ ^ --___...__- ______________ ------------- N I ------------= ----—----- J � ------------ ~ =L~IJ = 0LLJ �� I � JF-W J N= ~ LLJ 2 Q LL! LLJ F-H Z O z LL! —1- Z 0 H La w � L Q _ V) W i o N WN N 4J J Z 1- O W LLJ J O o H LJ Cz o J OCL— W W 4_ r J cD Z Ln w Z —J F- LL_ — N LLJ CL H N O N LLJ O N F-H N o HNV) H H N i 0 Z 0 v0 O - v N N Ln L6 o N m p o to In rn to ;LU s W = �, . m� W ` °° 69 w W w O W LI CD a ��3�., 0, � s Ir � ma N � c N Y ^ Y Mu'�` I g_ J raaals -ioDIJISSo-d h ^ _ n " A V A e n -nVM.L x1.1.7 XHVJ 'IIVN.L AM XaVC1 h - _ UVox Hosanna azo — — — — . o gal � =W C.� —M C; O JH W v J In= C F- W=Q 0 w G ui Z z = a `° W Ln — cn LL In W N N w Li.l L J J Z O F- JO0 F- W M o J 0CL— W W Cl- r- J O Z N W = Z —J Cr- F- LL. Ln W IL F- N O In W O N F-F- N F-N N F- O —z cn O — 6 CL PROPOSAL (This Proposal rust not be removed from this book of Contract Documents) TO: CENTEX HOMES Fort Worth, Texas DEVELOPER November 2004 c/o CARTER & BURGESS, INC. FOR: STREET IMPROVEMENTS FOR DEER VALLEY DEPARTMENT OF ENGINEERING No. 4694 Pursuant to the foregoing "Notice to Bidders," the undersigned bidder having thoroughly examined the Contract Documents, Plans, Special Provisions, Standard Special Provisions, the site of the project, and understanding the amount of work to be done, and the prevailing conditions hereby proposes to do all the work as provided in the Plans and Contract Documents subject to inspection and approval by the Director of Public Works of the City of Fort Worth, Texas, and binds himself upon acceptance of this Proposal to execute a contract and furnish an approved Performance Bond and Payment Bond, and such other bonds as may be required by the Contract Documents, for the performing and completing of the said work. Contractor proposes to do the work within the time stated and for the following sums: (Furnish and Install, including all appurtenant work, complete in place, the following items): SPEC PAY APPROXIMATE DESCRIPTION OF ITEMS WITH BID UNIT AMOUNT ITEM ITEM QUANTITY PRICES WRITTEN IN WORDS PRICE BID STREET IMPROVEMENTS 210 1. 32,358 S.Y. 6" Lime Stabilized Subgrade (Includes Preparation of Subgrade), complete in place for the sum of One Dollar & Five Cents per Square Yard $1.05 $33,975.90 212 2. 485 Tons Lime for Subgrade (30#/S.Y.)* complete in place for the sum of Eighty-seven Dollars & No Cents per Ton $87.00 $42,195.00 SPEC PAY APPROXIMATE DESCRIPTION OF ITEMS WITH BID UNITAMOUNT ITEM ITEM QUANTITY PRICES WRITTEN IN WORDS PRICE BID 314 3. 31,356 S.Y. 6" Reinforced Concrete Pavement (Includes Joint Sealer, and 7" STD Attached Concrete Curb), complete in place for the sum of Eighteen Dollars & Twenty Cents per Square Yard $18.20 $570,679.20 4. 26 EA. ADA Sidewalk Ramps, complete in place for the sum of Five Hundred Dollars & No Cents per Each $500.00 $13,000.00 5. 2,615 S.F. 4' Sidewalks, complete in place for the sum of Three Dollars & No Cents per Square Foot $3.00 $7,845.00 6. 3 EA. End of Road Barricade, complete in place for the sum of One Thousand Three Hundred Twenty-five Dollars & No Cents per Each $1,325.00 $3,975.00 7. 1 L.S. Payment, Performance and Maintenance Bonds Twenty-one Thousand Four Hundred Dollars & No Cents per Lump Sum $21,400.00 $21,400.00 TOTAL STREET IMPROVEMENTS --- $693,070.10 City of Fort Worth requires a minimum of 30#/S.Y. The Paving Contractor will be responsible for a lime series test as directed by the City of Fort Worth Construction Inspection Department. This contract is issued by an organization which qualifies for exemption pursuant to the provisions of Article 20.04�F) of the Texas Limited Sales, Excise and Use Tax Act. Taxes: All equipment and materials not consumed by or incorporated into the project construction, are subject to State sales taxes under House Bill 11, enacted August 15, 1991. The successful Bidder shall be required to complete the attached Statement of Materials and Other charges at the time of executing the contract. The Contractor shall comply with City Ordinance 7278, as amended by City Ordinance 7400 (Fort Worth City Code Sections 13-A-21 through 13-A-29), prohibiting discrimination in, employment practices. The undersigned agrees to complete all work covered by these Contract Documents within 30 working days from and after the date for commencing work, as set forth in the written Work Order to be issued by the Owner, and to pay not less than the "Prevailing Wage Rates for Streets, Drainage and Utility Construction," as established by the City of Fort Worth, Texas. Within ten (10) days of receipt of notice of acceptance of this bid, the undersigned will execute the formal contract, and will deliver an approved Surety Bond for the faithful performance of this contract. The attached deposit check in the sum of 5% GAB Dollars (Bid Bond) is to become the property of Centex Homes or the attached Bidder's Bond is to be forfeited in the event the contract and bond are not executed within the time set forth as liquidated damages for delay and additional work caused thereby. Respectfully bmitted, By: dale Title: President Address: GOIGO GGAtFaCtGng, 1PIC 4200 S, Hulen St., Suite 513 (S E A L) If Bidder is Corporation Date Receipt is acknowledged of the following addenda: Addendum No. 1 Addendum No. 2 Addendum No. 3 SPEC PAY APPROXIMATF- DESCRIPTION OF ITEMS WITH BID UNIT AMOUNT ITEM ITEM QUANTITY PRICES WRITTEN IN WORDS PRICE BID SECTION C - STORM DRAIN SYSTEM 1440 1. 246 L.F. 6' x 3' R.C. Box Culvert Including 402 Trench Excavation and Backfill, complete in place for the sum of Two Hundred Four Dollars & No Centsper Linear Foot $204.00 $50,184.00 440 2. 118 L.F. 48" Class III R.C. Pipe Including 402 Trench Excavation and Backfill, complete in place for the sum of One Hundred Sixteen Dollars & No Cents per Linear Foot $116.00 $13,688.00 440 3. 26 L.F. 39" Class III R.C. Pipe Including 402 Trench Excavation and Backfill, complete in place for the sum of Ninety-six Dollars & No Cents per Linear Foot $96.00 $2,496.00 440 4. 960 L.F. 36" Class III R.C. Pipe Including 402 Trench Excavation and Backfill, complete in place for the sum of Seventy-three Dollars & No Cents per Linear Foot $73.00 $70,080.00 013670.00B P-11 SPEC PAY APPROXIMATE DESCRIPTION OF ITEMS WITH BID UNIT AMOUNT ITEM ITEM QUANTITI(� PRICES WRITTEN IN WORDS PRICE BID 440 5. 40 L.F. 33" Class III R.C. Pipe Including 402 Trench Excavation and Backfill, complete in place for the sum of Sixty-four Dollars & No Cents per Linear Foot $64.00 $2,560.00 440 6. 330 L.F. 30" Class III R.C. Pipe Including 402 Trench Excavation and Backfill, complete in place for the sum of Fifty-six Dollars & No Cents per Linear Foot $56.00 $18,480.00 440 7. 101 L.F. 27" Class III R.C. Pipe Including 402 Trench Excavation and Backfill, complete in place for the sum of Fifty-one Dollars & No Cents per Linear Foot $51.00 $5,151.00 440 8. 700 L.F. 24" Class III R.C. Pipe Including 402 Trench Excavation and Backfill, complete in place for the sum of Forty-three Dollars & No Cents per Linear Foot 1 $43.00 1 $30,100.00 013670.008 P-12 SPEC PAY APPROXIMATE DESCRIPTION OF ITEMS WITH BID UNIT AMOUNT ITEM ITEM QUANTITYt PRICES WRITTEN IN WORDS PRICE BID 440 9. 83 L.F. 21" Class III R.C. Pipe, including 402 trench excavation and backfill, complete in place for the sum of Thirty-eight Dollars & No Cents per Linear Foot $38.00 $3,154.00 444 10. 14 Ea. 10' Standard Curb Inlet, complete in place for the sum of Two Thousand Dollars & No Cents per Each $2,000.00 $28,000.00 444 11. 4 Ea. 15' Standard Curb Inlet, complete in place for the sum of Two Thousand Eight Hundred Dollars & No Cents per Each $2,800.00 $11,200.00 410 12. 5 Ea. 4' Square Storm Drain Manhole, complete in place for the sum of Two Thousand Four Hundred Dollars & No Cents per Each $2,400.00 $12,000.00 410 13. 1 Ea. 5' Square Storm Drain Manhole, complete in place for the sum of Two Thousand Six Hundred Dollars & No Cents per Each $2,600.00 $2,600.00 013670.00B P-13 SPEC PAY APPROXIMATE DESCRIPTION OF ITEMS WITH BID UNIT AMOUNT ITEM ITEM QUANTITY. PRICES WRITTEN IN WORDS PRICE BID 410 14. 1 Ea. Standard Storm Drain Manhole Riser, complete in place for the sum of One Thousand Nine Hundred Forty Dollars & No Cents per Each $1,940.00 $1,940.00 410 15. 1 Ea. 6' x 3' Parallel Concrete Wingwall, includes Grade to Drain excavation, complete in place for the sum of Five Thousand Eight Hundred Dollars & No Cents per Each $5,800.00 $5,800.00 410 16. 1 Ea. 48" R.C. Pipe sloping Headwall, complete in place for the sum of Two Thousand Six Hundred Dollars & No Cents per Each $2,600.00 $2,600.00 410 17. 1 Ea. 30" R.C. Pipe sloping Headwall, complete in place for the sum of One Thousand Six Hundred Dollars & No Cents per Each $1,600.00 $1,600.00 410 18. 4 Ea. 24" R.C. Pipe sloping Headwall complete in place for the sum of One Thousand Four Hundred Dollars No Cents per Each $1,400.00 $5,600.00 013670.008 P-14 SPEC PAY APPROXIMATE DESCRIPTION OF ITEMS WITH BID UNIT AMOUNT ITEM ITEM QUANTITY, PRICES WRITTEN IN WORDS PRICE BID 410 19. 299 S.Y. Rock Rubble Rip Rap, complete in place for the sum of Fifty Dollars & No Cents per Square Yard $50.00 $14,950.00 410 20. 1 Ea. Concrete Weir, complete in place for the sum of Three Thousand Eight Hundred Dollars & No Cents per Each $3,800.00 $3,800.00 525 21. 2,601 L.F. Trench Safety No Dollar & Thirty Cents per Linear Foot $0.30 $780.00 . 22. 1 L.S. Storm Water Management One Thousand Dollars & No Cents per Lump Sum $1,000.00 $1,000.00 SECTION C -- - STORM DRAIN SYSTEM: $287,763.00 SUMMARY Section A Water System $ 435.244.40 Section B Sanitary Sewer System $ 345,886.70 Section C Storm Drain System $ 287.763.00 Total Amount of Bid $ 1.068,894.10 013670.00B P-15 PART B - PROPOSAL (cont.) Within ten (10) days after acceptance of this Proposal, the undersigned will execute the formal contract and will deliver an approved Surety Bond and such other bonds as required by the Contract Documents, for the faithful performance of the Contract. The attached bid security in the amount of 5% is to become the property of the Developer, in the event the contract and bond or bonds are not executed and delivered within the time above set forth, as liquidated damages for delay and additional work caused thereby. The undersigned bidder certifies that he has been furnished at least one set of the General Contract Documents and General Specifications for Water Department Projects dated January 1, 1978, and that he has read and thoroughly understands all the requirements and conditions of those General Documents and these specific Contract Documents and appurtenant plans. The undersigned assures that its employees and applicants for employment and those of any labor organization, subcontractors or employment agency in either furnishing or referring employee applicants to the undersigned are not discriminated against as prohibited by the terms of City Ordinance No. 7278 as amended by City Ordinance No. 7400. The Bidder agrees to begin construction within 10 calendar days after issue of the work order by the Owner, and to complete the contract within 70 working days after beginning construction as set forth in the written work order to be furnished by the Owner. (Complete A or B below, as applicable:) [ ] A. The principal place of business of our company is in the State of [] Nonresident bidders in the State of , our principal place of business are required to be_ percent lower than resident bidders by state law. A copy of the statute is attached. [j Nonresident bidders in the State of , our principal place of business, are not required to underbid resident bidders. DI B. The principal place of business of our company or our parent company or majority owner is in the State of Texas. 013670.008 P-16 Receipt is acknowledged of the following addenda: Addendum No. 1 Addendum No. 2 Addendum No. 3 Respectfully submitted, u o Construction Inc. ( SEAL ) BY: If Bidder is Corporation. TITLE: }�tzrc�i�E�vT ADDRESS: gZoo -5 au►eN ST. 513 -Few,- Wm+z-r►a. Tx 7 e..1 Dpi 013670.00B P-17 I. STREET LIGHT COST ESTIMATE QUANTITY UNIT COST TOTAL COST INTERSECTIONS 15 EA $ 2, 000 $30, 000 . 00 MID-BLOCK RESIDENTIAL 6 EA $ 2, 000 $12, 000 . 00 CHANGE OF DIRECTION RESIDENTIAL 8 EA $ 2, 000 $16, 000 . 00 MID-BLOCK COLLECTOR 0 EA $ 2, 000 $0, 000 . 00 MID-BLOCK ARTERIAL PARKWAY 0 EA $ 2, 500 $0, 000 . 00 MID-BLOCK ARTERIAL MEDIAN 0 EA $ 2, 500 $0, 000 . 00 RELOCATE EXISTING LIGHT 0 EA $ 11500 $0, 000 . 00 Subtotal $58,000.00 City's Cost $00,000.00 Developer's Subtotal $58 ,000.00 10% Contingencies $5,800.00 Project Total $63,800.00 Adjacent Developer's Cost $00,000 .00 Developer's Cost $61, 600.00 2% Inspection Fee $00,000 .00 CFA CODE #2004172 DEVELOPER' S COST: $63,800. 00 DEER VALLEY January 31, 2005 Fort Worth, Texas January 31 , 2005 PAGE I OF Exhibit C II. STREET LIGHTS WORK DESCRIPTION: 1 . The Developer shall provide for the installation of streetlights at the approximate locations shown in Exhibit "C", immediately after final acceptance of the street construction, in accordance with engineering plans and specifications approved by the Transportation and Public Works Department. 2 . Streetlights on residential and /or collector streets can be installed using overhead or underground conductors with the approval of the Director of Transportation and Public Works . 3 . The City will install all the streetlights that use overhead or underground conductors on residential, and collector streets. the developer agrees to pay the city the amount shown below prior to the City starting it' s design efforts. 4 . Streetlights on arterial streets shall be installed with underground conduit and conductors . 5 . The Developer agrees to dedicate all easements required for the installation and maintenance of the street lights and to provide for the installation of any electrical transformers required for the proper operation of the street lights 6. The estimated cost of this street light installation is detailed on page 1 of exhibit C and is summarized below, the street lights will remain the property of, and will be maintained by the City of Fort Worth. DEVELOPER'S COST: $63,800.00 DEER VALLEY January 31, 2005 FORT WORTH, TEXAS CFA CODE #2004172 Page II of Exhibit C III. "STREETLIGHTS" INTERSECTIONS CRESCENT RIDGE DR & PARK CITY TRI, 1 CHALK MOUNTAIN DR & PARK CITY TRI, 1 WOLF MOUNTAIN LN & PARK CITY TRL 1 DEER MEADOWS LN & CHALK MOUNTAIN DR 1 DEER MEADOWS LN & WEBER RIVER TRL 1 DEER MEADOWS LN & WOLF MOUNTAIN LN 1 WEBER RIVER TRL & MCPHERSON RD 1 WEBER RIVER TRL & PARK CITY TRL 1 WOLF MOUNTAIN LN & ROSSIGNOL ST 1 CHALK MOUNTAIN DR & OLD BURLESON RD 1 WOLF MOUNTAIN LN & OLD BURLESON RD 1 SILVER LAKE TRL & TAMARON CT 1 ROOSEVELT GAP CT & DEER RUN 1 OLD BURLESON RD & DEER RUN 1 ANIMAS CT & DEER RUN 1 MID-BLOCK DEER MEADOWS LN 2 WOLF MOUNTAIN LN 1 CHALK MOUNTAIN LN 1 CRESCENT RIDGE DR 1 TAMARRON CT 1 CHANGE OF DIRECTIONS ROSEVELT GAP CT 1 SILVER LAKE TRL 2 ROSSIGNOL ST 1 FLAGSTAFF RUN 2 TAMARRON CT 1 ANIMAS CT 1 DEER VALLEY Page III of Exhibit C IV STREET NAME SIGNS 1. The City of Fort Worth will install the street name signs upon final approval of the street construction. The street name signs will remain the property of, and will be maintained by, the City of Fort Worth. 2. The Developer will pay for the street name sign installations required for this development to the extent of $100.00 per intersection. This unit cost will be revised annually by the Department of Transportation and Public Works to reflect prevailing costs of materials and labor. 3. This development creates the following nineteen (19) intersections at a cost to the Developer of $1,900.00: Old Burleson Rd & Deer Run Animas Ct & Deer Run Roosevelt Gap Ct & Deer Run Silver Lake Tr & Deer Run Tammaron Ct & Silver Lake Tr Old Burleson Rd & Wolf Mountain Lane Old Burleson Rd & Chalk Mountain Dr Park City Tr & Wolf Mountain Lane Park City Tr & Crescent Ridge Dr Park City Tr & Chalk Mountain Dr Park City Tr & Weber River Tr Park City Tr & Flagstaff Run Rossignol St & Wolf Mountain Lane Rossignol St & Crescent Ridge Dr Deer Meadows Lane & Wolf Mountain Lane Deer Meadows Lane & Chalk Mountain Dr Deer Meadows Lane & Weber River Tr Deer Meadows Lane & Flagstaff Run McPherson Rd & Weber River Tr Deer Valley CFA code: 2004172 January 7, 2005