HomeMy WebLinkAboutContract 31940 COMMUNITY FACILITIES AGREEMENT
THE STATE OF TEXAS § City Secretary
COUNTY OF TARRANT § Contract No., I�l
WHEREAS, Centex Homes, a Nevada Genral Partnership, hereinafter called
"Developer", desires to make certain improvements to Old Burleson Road, an addition
to the City of Fort Worth, Texas; and
WHEREAS, the said Developer has requested the City of Fort Worth, a municipal
corporation of Tarrant and Denton Counties, Texas, hereinafter called "City", to do
certain work in connection with said improvements.
NOW, THEREFORE, KNOW ALL BY THESE PRESENTS:
For and in consideration of the covenants and conditions contained herein, the City and
the Developer do hereby agree as follows:
1. General Requirements
A. The Policy for the Installation of Community Facilities ("Policy")
dated March 2001, approved by the City Council of the City of Fort
Worth, is hereby incorporated into this Community Facilities Contract
as if copy herein verbatim. Developer agrees to comply with all
provisions of said Policy in the performance of its duties and
obligations hereunder.
B. The requirements of the Policy shall govern this Community Facilities
Agreement, provided, however, that any conflict between the terms of
this Community Facilities Agreement and the Policy shall be resolved
in favor of this Agreement.
C. Developer shall provide financial security in conformance with
paragraph 6, Section II, of the Policy.
D. The Developer shall award all contracts for the construction of
community facilities in accordance with Section 11, paragraph 7 of the
Policy.
E. The contracts for the construction of the public infrastructure shall be
administered in conformance with paragraph 8, Section II, of the
Policy.
o rN,
4219210
COMMUNITY FACILITIES AGREEMENT
THE STATE OF TEXAS § City Secretary
COUNTY OF TARRANT § Contract No.
WHEREAS, , hereinafter called "Developer", desires to make certain
improvements to , an addition to the City of Fort Worth,Texas; and
WHEREAS, the said Developer has requested the City of Fort Worth, a municipal
corporation of Tarrant and Denton Counties, Texas, hereinafter called "City", to do
certain work in connection with said improvements.
NOW, THEREFORE, KNOW ALL BY THESE PRESENTS:
For and in consideration of the covenants and conditions contained herein, the City and
the Developer do hereby agree as follows:
1. General Requirements
A. The Policy for the Installation of Community Facilities ("Policy")
dated March 2001, approved by the City Council of the City of Fort
Worth, is hereby incorporated into this Community Facilities Contract
as if copy herein verbatim. Developer agrees to comply with all
provisions of said Policy in the performance of its duties and
obligations hereunder.
B. The requirements of the Policy shall govern this Community Facilities
Agreement, provided, however, that any conflict between the terms of
this Community Facilities Agreement and the Policy shall be resolved
in favor of this Agreement.
C. Developer shall provide financial security in conformance with
paragraph 6, Section Il, of the Policy.
D. The Developer shall award all contracts for the construction of
community facilities in accordance with Section 11, paragraph 7 of the
Policy.
E. The contracts for the construction of the public infrastructure shall be
administered in conformance with paragraph 8, Section 11, of the
Policy.
v Lk
—4975817
t5�1JJ�UU
4975817 1 vIO���CI RR( ;`�, V
F. The Developer further covenants and agrees to, and by these presents
does hereby, fully indemnify, hold harmless and defend the City, its
officers, agents and employees from all suits, actions or claims of any
character, whether real or asserted, brought for or on account of any
injuries or damages sustained by any persons (including death) or to
any property, resulting from or in connection with the construction,
design, performance or completion of any work to be performed by
said Developer, his contractors, subcontractors, officers, agents or
employees, or in consequence of any failure to properly safeguard the
work, or on account of any act, intentional or otherwise, neglect or
misconduct of said DEVELOPER, his contractors, sub-contractors,
officers, agents or employees, whether or not such injuries, death or
damages are caused, in whole or in part, by the alleged negligence of
the Cityof Fort Worth, its officers, servants, or employees
G. Developer shall install or adjust all of the required utilities to serve the
development or to construct the improvements required herein.
H. In the event that City participation exceeds $25,000, Developer agrees
that no street construction or storm drainage will begin prior to City
Council approval of this Community Facilities Agreement. (Article
104.100, Ordinance 7234).
I. Developer agrees that no lot shall be occupied under a certificate of
occupancy until the improvements required herein have been
constructed (Article 104.100, Ordinance 7234).
J. Developer hereby releases and agrees to indemnify and hold the City
harmless for any inadequacies in the preliminary plans, specifications
and cost estimates supplied by the Developer for this contract.
K. Developer agrees to provide, at its expense, all necessary rights of way
and easements across property owned by Developer required to
construct current and future improvements provided for in this
agreement.
4975817 2
L. Developer agrees to construct proposed improvements as shown on the
exhibits attached hereto. The following exhibits are made a part
hereof: Water (A)None; Sewer (A-1) None; Paving (B)Attached
Storm Drain (B-1)Attached; Street Lights and Signs (C)Attached.
M. City shall not be responsible for any costs that may be incurred by
Developer in the relocation of any utilities that are or may be in
conflict with any of the community facilities to be installed hereunder.
II. Street and Storm Drain Facilities
A. The Developer(s) agree to install or to cause to have installed, the street,
storm drainage, street lighting, street name sign and other community
facilities improvements shown as "current improvements" on the attached
Exhibits B, B 1, and C.
B. As shown below in the "Summary of Cost for Street and Storm Drain
Facilities", the Developer shall fund its share of "current improvements"
and shall pay to the City for its share of the cost of street, storm drainage,
street lighting, street name signs as shown on the attached Exhibits B, BI,
and C. The estimated total cost of current improvements and related
support services specified in this agreement, including design,
construction and inspection is estimated to $548,963.78.
4975817 3
SUMMARY OF
COST
Old Burleson Road
Item Developer City Cost Total Cost
Cost
A. Construction $ -
1. Streets $253,665.10 253,665.10
2. Storm Drainage $153,127.00 108,000.00 261,127.00
3. Street Lights $17,600.00 17,600.00
4. Street Name Sig
ns $300.00 300.00
B. Engineering Design $
C. Construction Engineering
and Management by DOE $ $
4% 16,271.68 16,271.68
TOTALS 440,963.78 108,000.00 548,963.78
Notes:
1. All Preliminary Plats filed after July 2000 will require sidewalks on all streets.
The developer is responsible for installation of sidewalk and a separate financial
guarantee is required in the form of a bond or check for the cost of the sidewalk.
2. Developer's column for Item C represents four percent (4%) cost for construction
inspection fees and materials testing. The City will pay additional inspection fee over
4%.
3. City not preparing plans and specifications.
4975817 4
IN TESTIMONY WHEREOF, the City of Fort Worth has caused this instrument to be
executed in quadruplicate in its name and on its behalf by its Assistant City Manager,
attested by its City Secretary, with the corporate seal of the City affixed, and said Developer
O
has executed this instrument in triplicate, at Fort Worth, Texas this the — day of
, 2005.
Approval Recommended:
Transportation and Public Works
Department
C S �-
Robert Goode, P. E.
Director
City of Fort Worth
Contract A thor�,izaLtiou �/ c
5—10
Marc Ott
Date Assistant City Manager
ATTEST:
Marty Hendri
City Secretary
Approv s to Form: CENTEX HOMES,
a Nevada general partnership
By: Centex Real Estate Corporation,
a Nevada corporation,
A start Attorney Its: managing general partner
By: Steven Magee
ATTEST: DEVELOPER
By:
Corporate Secretary V 14
4975817
5 pj� IUI T
PROPOSAL
(This Proposal must not be removed from this book of Contract Documents)
TO: CENTEX HOMES Fort Worth, Texas
DEVELOPER November 2004
c/o CARTER & BURGESS, INC.
FOR: OFF-SITE STREET IMPROVEMENTS FOR
OLD BURLESON ROAD
DEPARTMENT OF ENGINEERING No. 4714
Pursuant to the foregoing "Notice to Bidders," the undersigned bidder having thoroughly
examined the Contract Documents, Plans, Special Provisions, Standard Special Provisions, the
site of the project, and understanding the amount of work to be done, and.the prevailing
conditions hereby proposes to do all the work as provided in the Plans and Contract Documents
subject to inspection and approval by the Director of Public Works of the City of Fort Worth,
Texas, and binds himself upon acceptance of this Proposal to execute a contract and furnish an
approved Performance Bond and Payment Bond, and such other bonds as may be required by
the Contract Documents, for the performing and completing of the said work. Contractor
proposes to do the work within the time stated and for the following sums:
(Furnish and Install, including all appurtenant work, complete in place, the following items):
SPEC PAY APPROXIMATE DESCRIPTION OF ITEMS WITH BID UNIT AMOUNT
ITEM ITEM QUANTITY PRICES WRITTEN IN WORDS PRICE BID
OFF-SITE STREET IMPROVEMENTS (OLD BURLESON ROAD)
210 1. 8,126 S.Y. 6" Lime Stabilized Subgrade (Includes
Preparation of Subgrade), complete in
place for the sum of
One Dollar&
Five Cents per Square Yard $1.05 $8,532.30
212 2. 122 Tons Lime for Subgrade (30#/S.Y.)*
complete in place for the sum of
Eighty-seven Dollars &
No Cents per Ton $87.00 $10,614.00
SPEC PAY APPROXIMATE DESCRIPTION OF ITEMS WITH BID UNIT AMOUNT
ITEM ITEM QUANTITY PRICES WRITTEN IN WORDS PRICE BID
314 3. 7,829 S.Y. 6" Reinforced Concrete Pavement
(Includes Joint Sealer, and 7" STD
Attached Concrete Curb), complete in
place for the sum of
Eighteen Dollafs &
Twenty Cents per Square Yard $18.20 $142,487.80
4. 6,244 S.Y. Sawcut, Remove & Dispose of
Existing Pavement, complete in place
for the sum of
Four Dollars &
No Cents per Each $4.00 $24,976.00
5. 6 EA. ADA Sidewalk Ramps, complete in
place for the sum of
Five Hundred Dollars &
No Cents per Square Foot $500.00 $3,000.00
6. 520 a S.Y. Asphalt Transition, complete in place
for the sum of
Twenty-four Dollars &
Fifty Cents per Each $24.50 $12,740.00
7. 725 S.Y. Concrete Driveway Pavement with
Subgrade, complete in place for the
sum of
Thirty Dollars &
No Cents per Each $30.00 $21,750.00
SPEC PAY APPROXIMATE DESCRIPTION OF ITEMS WITH BID UNIT AMOUNT
ITEM ITEM QUANTITY, PRICES WRITTEN IN WORDS PRICE BID
8. 9,105 S.F. 4' Sidewalks, complete in place for the
sum of
Three Dollars &
No Cents per Each $3.00 $27,315.00
9. 1 L.S. Pavement Markings, complete in
place for the sum of
One Thousand
Five Hundred Dollars &
No Cents per Each $1,500.00 $1,500.00
10. 3 EA. Adjust Sewer Manhole Rims to Grade,
complete in place for the sum of
Two Hundred Fifty Dollars &
No Cents per Lump Sum $250.00 $750.00
TOTAL STREET IMPROVEMENTS --- $253,655.10 �...
City of Fort Worth requires a minimum of 30#/S.Y. The Paving Contractor will be responsible for a lime series test as directed by the City
of Fort Worth Construction Inspection Department.
This contract is issued by an organization which qualifies for exemption pursuant to the
provisions of Article 20.04(F) of the Texas Limited Sales, Excise and Use Tax Act.
Taxes: All equipment and materials not consumed by or incorporated into the project
construction, are subject to State sales taxes under House Bill 11, enacted August 15, 1991.
The successful Bidder shall be required to complete the attached Statement of Materials and
Other charges at the time of executing the contract.
The Contractor shall comply with City Ordinance 7278, as amended by City Ordinance 7400
(Fort Worth City Code Sections 13-A-21 through 13-A-29), prohibiting discrimination in,
employment practices.
The undersigned agrees to complete all work covered by these Contract Documents within 10
working days from and after the date for commencing work, as set forth in the written Work
Order to be issued by the Owner, and to pay not less than the "Prevailing-Nage Rates for
Streets, Drainage and Utility Construction," as established by the City of Fort Worth, Texas.
,Jif,
Within ten (10) days of receipt of notice of acceptance of this bid, the undersigned will execute
the formal contract, and will deliver an approved Surety Bond for the faithful performance of this
contract. The attached deposit check in the sum of 5% GAB Dollars Bid Bond) is to become
the property of Centex Homes or the attached Bidder's Bond is to be forfeited in the event the
contract and bond are not executed within the time set forth as liquidated damages for delay
and additional work caused thereby.
Respectfully submitted,
By:
tR. 6iL 1zTit
Address: 4 Zoo 5T- ti X513
F:iirz r tVO 2rµ ; 'FOX 42 76 (Oct
(S E A L) If Bidder is Corporation
Date
Receipt is acknowledged of the following addenda:
,Addendum No. 1
Addendum No. 2
Addendum No. 3
PART B - PROPOSAL
r
(This Proposal must not be removed from this book of Contract Documents)
TO: CENTEX HOMES Fort Worth, Texas
DEVELOPER NOVEMBER 2004
c/o CARTER & BURGESS, INC.
FOR: STORM DRAIN FACILITIES FOR
OLD BURLESON ROAD
DEPARTMENT OF ENGINEERING NO. 4714
Includes the furnishing of all materials (except as specified to be furnished by the City),
equipment and labor for the installation of a storm drain system, all necessary appurtenances
and incidental work to provide a complete and serviceable project.
Pursuant to the foregoing "Notice to Bidders," including plans, special contract documents, and
the General Contract Documents and General Specifications for Water Department Projects,
the site of the project and understanding the amount of work to be done, and the prevailing
conditions, hereby proposes to do all the work, furnish all labor, equipment and material except
as specified to be furnished by the City, which is necessary to fully complete the inspection and
approval of the Director of the City Water Department of the City of Fort Worth, Texas; and
binds himself upon acceptance of this proposal to execute a contract and furnish an approved
Performance Bond, Payment Bond, Maintenance Bond, and such other bonds, if any, as may
be required by the Contract Documents for the performing and completing of the said work.
Contractor proposes to do the work within the time stated and for the following sums (Furnish
and install, including all appurtenant work, complete in place, the following items):
SPEC PAY APPROXIMATE DESCRIPTION OF ITEMS WITH BID UNIT AMOUNT
ITEM ITEM QUANTITY PRICES WRITTEN IN WORDS PRICE BID
STORM DRAIN SYSTEM
440 1. 60 L.F. 3-10' x 6' Multi-Box culverts, including
Trench Excavation and backfill,
complete in place for the sum of
Nine Hundred Eighty Dollars &
No Cents per Linear Foot $980.00 $58,800.00
V'f��V�Gti� A��1�1�J7U
'vMi 61E1121�ll�� A111 2dy
013670.00C P-4
SPEC PAY APPROXIMATE DESCRIPTION OF ITEMS WITH BID UNIT AMOUNT
ITEM ITEM QUANTITYi PRICES WRITTEN IN WORDS PRICE BID
440 2. 57 L.F. 8'x 5', single box culvert, including
Trench Excavation and Backfill,
complete in place for the sum of
Three Hundred Seventy Dollars &
No Cents per Linear Foot $370.00 $21,090.00
440 3. 68 LF. 24" Class III R.C. Pipe, Including
Trench Excavation and Backfill,
complete in place for the sum of
Forty Three Dollars &
No Cents.per Linear Foot $43.00 $2,924.00
440 4. 8 L.F. 21" Class III R.C. Pipe, Including
Trench Excavation and Backfill,
complete in place for the sum of
Forty Dollars &
No Cents per Linear Foot $40.00 $320.00
444 5. 1 Ea. 10' Standard Curb Inlet, complete in
place for the sum of
Two Thousand Dollars &
No Cents Each $2,000.00 $2,000.00
410 6. 491 S.Y. Rock Rubble Rip Rap, complete in
place for the sum of
Fifty Dollars &
No Cents per Square Yard $50.00 $24,550.00-
013670.00C P-6
SPEC PAY APPROXIMATE DESCRIPTION OF ITEMS WITH BID UNIT AMOUNT
ITEM ITEM QUANTITYi PRICES WRITTEN IN WORDS PRICE BID
410 7. 1 L.S. Parallel Wings for 3-10'x 6' MBC and
1-8' x 5' Box per plans, complete in
place for the sum of
Twenty-four Thousand
Nine Hundred Dollars &
No Cents Lump Sum $24,900.00 $24,900.00
525 8. 193 L.F. Trench Safety
Two Dollars &
No Cents per Linear Foot $2.00 $386.00
525 9. 152 L•.F. Pedestrian Handrail, complete in
place for the sum of
One Hundred Five Dollars &
No Cents per Linear Foot $105.00 $15,960.00
525 10. 2 Ea. 2-24" Headwall per TxDOT Detail
CH-FW-O, complete in place for the
sum of
Two Thousand
Two Hundred Dollars &
No Cents Each $2,200.00 $4,400.00
525 11. 1 L.S. Remove and Dispose of existing 18"
RCP, complete in place for the sum
of
Five Hundred Dollars &
Mn Cents per Lump Sum $500.00 $500.00
013670.00C P_7
SPEC PAY APPROXIMATE DESCRIPTION OF ITEMS WITH BID UNIT AMOUNT
ITEM l ITEM QUANTITYi PRICES WRITTEN IN WORDS PRICE BID
525 12. 1 L.S. Storm Water Management*
Five Hundred Dollars &
No Cents per Lump Sum $500.00 $500.00
STORM DRAIN SYSTEM $156,330.00
013670.00C P_$ v
Ue 'a'v J.�'td P u LG:o
PART B - PROPOSAL (cont.)
i
Within ten (10) days after acceptance of this Proposal, the undersigned will execute the formal
contract and will deliver an approved Surety Bond and such other bonds as required by the
Contract Documents, for the faithful performance of the Contract. The attached bid security in
the amount of 5% is to become the property of the Developer, in the event the contract and
bond or bonds are not executed and delivered within the time above set forth, as liquidated
damages for delay and additional work caused thereby.
The undersigned bidder certifies that he has been furnished at least one set of the General
Contract Documents and General Specifications for Water Department Projects dated January
1, 1978, and that he has read and thoroughly understands all the requirements and conditions
of those General Documents and these specific Contract Documents and appurtenant plans.
The undersigned assures that its employees and applicants for employment and those of any
labor organization, subcontractors or employment agency in either furnishing or referring
employee applicants to the undersigned are not discriminated against as prohibited by the terms
of City Ordinance No. 7278 as amended by City Ordinance No. 7400.
The Bidder agrees to begin construction within 10 calendar days after issue of the work order
by the Owner, and to complete the contract within 20 working days after beginning
construction as set forth in the written work order to be furnished by the Owner.
(Complete A or B below, as applicable:)
[ ] A. The principal place of business of our company is in the State of
[] Nonresident bidders in the State of , our principal place of business
are required to be_percent lower than resident bidders by state law. A copy
of the statute is attached.
[] Nonresident bidders in the State of , our principal place of business,
are not required to underbid resident bidders.
Ix B. The principal place of business of our company or our parent company or
majority owner is in the State of Texas.
013670.000 P_8
Receipt is acknowledged of the following addenda:
Addendum No. 1 {
Addendum No. 2
Addendum No. 3
Respectfully submitted,
ur co Construction Inc.
( SEAL )
BY:
If Bidder is Corporation.
TITLE: Piz E-.--s I D E NT
ADDRESS: _gZoO S. 1 gLEN -�>?'. 4 513
Fczr Wozrij ,Tx 7&1019
a
013670.00C
.7 MA ��'�EE'� ' �b1�7....tZf�TN .TEXAS ..7,11 ................................................
.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.
.
....... .....7...:104 :. ..........Mttr.........7. 42 -# .71 ...............................................................
OLD BURLESON ROAD
MARCH 24, 2005
STORM DRAINAGE
ITEM# DESCRIPTION QTY UNIT PRICE AMOUNT
1 6-10'x 6' MBC 40 L.F. 980.00 39,200.00
2 8' x 5' SBC 29 L.F. 370.00 10,730.00
3 24" RCP 69 L.F. 43.00 2,967.00
4121" RCP 8 L.F. 1 40.00 320.00
5 STD 10' CURB INLET 1 EA. 2,000.00 2,000.00
6 6-10'x 6' & 1-8'x 5' MBC PARALLEL WINGWALL 1 L.S. 24,900.00 24,900.00
7 2-24" HEADWALL 2 EA. 2,200.00 4,400.00
8 PEDESTRIAN HANDRAILS 280 L.F. 105.00 29,400.00
9 ROCK RUBBLE RIPRAP 12"-15" 760 SY. 50.00 38,000.00
10 REMOVE & DISPOSE OF EX. 18" RCP 1 L.S. 500.00 500.00
11 TRENCH SAFETY 105 L.F. 2.00 210.00
12 STORMWATER MANAGEMENT 1 L.S. 500.00 500.00
T TAL -STORM DRAINAGE 153,127.00
GAJ08\013670\ESTI0Id Burleson\tmp.XLS 5/13/2005
...................
U0.
.. .........
..........
........... ... .......
OLD BURLESON ROAD
MARCH 24, 2005
PAVING
ITEM# DESCRIPTION QTY UNIT PRICE AMOUNT
1 SAWCUT EXIST. PAVEMENT AND REMOVE 6,244 S.Y. 4.00 24,976.00
2 6" LIME STABALIZED SUBGRADE 8,126 S.Y. 1.05 8,532.30
3 HYDRATED LIME (30#/SY) 122 TON 87.00 10,614.00
416" R.C. STREET PVMT W/7" CURB 7,829 S.Y. 18.20 142,487.80
5 6" HMAC ASPHALT TRANSITION PAVEMENT 520 S.Y. 24.50 12,740.00
6 CONCRETE DRIVEWAY PAVEMENT 725 S.Y. 30.00 21,750-00
7 SIDEWALK RAMPS 6 EA. 500.00 3,000.00
8 4' SIDEWALK 9,105 S.F. 3.00 27,315.00
9 ADJUST SANITARY SEWER MANHOLE RIMS 3 EA. 250.00 750.00
10 PAVEMENT MARKINGS 1 L.S. 1,500.00 1,500.00
11TOTAL - PAVING $253,665.1011
G:W0B\013670\EST\0Id Burleson\33105 CFA FINAL REVISED.XLS
TEX.
. ..... ..:::
.....:.:.. ................... ..
......
...........:. ............................................::....:...........................................................::.::..:.:....:................::::::::::....:..........................................:..:...........:.:...::...::... .......::.:::..
:...:......:......:................ .........................................................................PaE ............
....«:::::<::' 7 I ... TR PERT 7fiI
:.:.::.:.....................:.:..:..:..... .................:::::::::: :::.:. ..... .. ............... .........................................................................
:::::........................:..:::::::::::::: .. .:::....:. .....................:.. .. .....a.::::::::::::::::......................
---
.G .. lrc.. 174............
..... .......................................:..:....::..:::.:::::::::::::.::::::::::::::::.:::::::::
OLD BURLESON ROAD
MARCH 24, 2005
STREET LIGHTS
ITEM# DESCRIPTION QTY UNIT PRICE AMOUNT
1 STREET LIGHTS 8 EA. 2,200.00 17,600.00
TOTAL -STREET LIGHTS $17,600.00
SIGNAGE
ITEM# DESCRIPTION QTY UNIT PRICE AMOUNT
1 SIGNS 3 EA 100.00 300.00
TOTAL - SIGNAGE $300.00
G:\JOB\013670\EST\Old Burleson\33105 CFA FINAL REVISEDALS 3/31/2005
I. STREET LIGHT COST ESTIMATE
QUANTITY UNIT COST TOTAL COST
INTERSECTIONS 0 EA $ 2, 000 $0, 000. 00
MID-BLOCK RESIDENTIAL 0 EA $ 2, 000 $0, 000 . 00
CHANGE OF DIRECTION RESIDENTIAL 0 EA $ 2, 000 $0, 000 .00
MID-BLOCK COLLECTOR 8 EA $ 2, 000 $16, 000 .00
MID-BLOCK ARTERIAL PARKWAY 0 EA $ 2, 500 $0, 000 .00
MID-BLOCK ARTERIAL MEDIAN 0 EA $ 2, 500 $0, 000 . 00
RELOCATE EXISTING LIGHT 0 EA $ 1, 500 $0, 000. 00
Subtotal $16,000.00
City's Cost $00,000.00
Developer's Subtotal $16,000.00
10% Contingencies $1, 600.00
Project Total $17, 600. 00
Adjacent Developer's Cost $00,000.00
Developer's Cost $17, 600.00
2% Inspection Fee $00,000.00
CFA CODE #2005001
DEVELOPER' S COST: $17, 600. 00
OLD BURLESON RD
February 2, 2005
Fort Worth, Texas
May 18, 2005
PAGE I OF Exhibit C
NAV,P
q �
Y7
S U rri'i�C �Ry
JUp
II. STREET LIGHTS WORK DESCRIPTION:
1 . The Developer shall provide for the installation of streetlights at
the approximate locations shown in Exhibit "C" , immediately after
final acceptance of the street construction, in accordance with
engineering plans and specifications approved by the Transportation
and Public Works Department.
2 . Streetlights on residential and /or collector streets can be
installed using overhead or underground conductors with the approval
of the Director of Transportation and Public Works.
3 . The City will install all the streetlights that use overhead or
underground conductors on residential, and collector streets. the
developer agrees to pay the city the amount shown below prior to the
City starting it' s design efforts.
4 . Streetlights on arterial streets shall be installed with underground
conduit and conductors .
5 . The Developer agrees to dedicate all easements required for the
installation and maintenance of the street lights and to provide for
the installation of any electrical transformers required for the
proper operation of the street lights
6. The estimated cost of this street light installation is detailed on
page 1 of exhibit C and is summarized below, the street lights will
remain the property of, and will be maintained by the City of Fort
Worth.
DEVELOPER' S COST: $17,600.00
OLD BURLESON RD
February 2, 2005
FORT WORTH, TEXAS
CFA CODE #2005001
Page II of Exhibit C
" ;JGti i � i
III.
"STREETLIGHTS"
MID-BLOCK
OLD BURELESON RD 8
OLD BURLESON RD
Page III of Exhibit C
J c ilk
o ts�J1: Jl�o LGa
Iv
STREET NAME SIGNS
1. The City of Fort Worth will install the street name signs upon final
approval of the street construction. The street name signs will remain
the property of, and will be maintained by, the City of Fort Worth.
2. The Developer will pay for the street name sign installations required
for this development to the extent of $100.00 per intersection. This
unit cost will be revised annually by the Department of Transportation
and Public Works to reflect prevailing costs of materials and labor.
3. This development creates the following three (3) intersections at a cost
to the Developer of $300.00:
Old Burleson Rd & Deer Run
Old Burleson Rd & Wolf Mountain Lane
Old Burleson Rd & Chalk Mountain Dr
Old Burleson Road
CFA code: 2004176 January 18, 2005
i
EVERMAN
QlI RMAN
I np s,fn
? ..3pppV.iiiii I I
C-
�II
RISINGER
1
111 PRO ECT
' '� N ° LOCATION
CLAW MCPHERSON
COAD
11
II
I \
GARDEN A _
�I 1 OAK GROVE
I'
\ i QII
I
CROWLEY I am N
h►4f7f � I
I
o� II NOT TO SCALE
LOCATION MAP
OLD BURLESON ROAD
Carfer z-Burgess
GARTER & BURGESS,INC.
777 MAIN mar
roa Worm,rx
18171 735.e0=00 .
PROJECT I .;0f,38?6:,of0;1.`0630 T,^I
OCH=df\lob\ 013670\cfv\old bur leeon\6701c-fa don - Q
r. PAGE 1 Ic'4,y
U
�/q
°''
17
/
WN
DEER RUN
...... Cp SCALE11" = 300'
COLN STREET O'"
FUTURE
it B'x5'SBC
?�♦♦� STD.10'CURB I NLET
♦
II 21"RCP °` 9
Vie'xS•see—]II
1 6-10'x6'IBC
r
4
COAD STREET
O�7J
v°
2-24' ,RCP
_ I
--. WOLF MOL'TMIN LX'E
.......le I
Ol 41
P4 .
1r A� I i`O
0
h
♦ c♦ y1p CHALK MOUNTIUN DRIVE
cf}'9Q♦♦�4.
. ,♦♦� II ,i`o2
off}-�qo y♦ _ _ �0�,y
i♦Q.i�°6� at"g4�
I STORM D RAI N
i
LEGEND ,�,,ry."'ev I it EXHIBIT 'A'
PROP. STORM DRAIN LINE I I OLD BURLESON ROAD
PROP. INLET ` o�RDe� ACRES DRIVE
FUTURE STORM DRAIN LINE ___ __• Ca~v Burgess
LIMITS OF PROJECT CARTER& BURGESS,INC.
777 MAIN SnUffT
FORT W097H.T%76102
(8I7)73+6000
PROJECT NO. 013670.010.1.0630
DCN=9-\Job\ 013670\civ\old burleeon\6701cfd.dgn PAGE 2 OF 4
,♦:rte.. .,
� OJN
IDEER AUN
-,--- ♦ SCALE1 1" = 300'
Jryt�}
COIN STREET
4♦e,
41
tea' �' � �y♦~
tii.
cQ� „a-♦a
COAD SrRZT
I 1 rygp+�y
I yO GT
WOLF MOUNTAN [.'.,♦-E
41
3 c♦
m
p.
o-
oti
,♦♦�y��' CHALK MOUN"f'AiN DRIVE
���♦�� is
0"�r
............ ._.._
'b
LEGEND
PROP. 26' B/B Qv ' -_---
ROADWAY/ 1/2 60' ROW I
PROP. 29' B/B
ROADWAY/ 50' ROW `�"�"""}
PROP. HMAC ' STREETS
TRANSITION ROADWAY I
EXHIBIT 'A-1'
PROP. DRIVEWAY '�♦� I
I
B N
OLD
REPLACEMENT
URLE O
S ROAD
PROP. 4' S I DEWALK �► GARDEN ACRES DR VE
....................
( BY HOMEBU I LDER) Carter«Burgess
PROP. 4' S I DEWALK
( BY DEVELOPER) CARTER & BURGESS,INC.
LIMITS OF PROJECT ---- n»M 6102
PROJECT NO. 013670.010.1.0630
OGN=qe\Job\ 013670\olv\old bur I eson\670 Iola.dgn PAGE 3 OF 4
DEER RUN
...... . --- SCALES i" = 300'
� y
COIN SCRE6r - ...
e
r 4
COADII16
SLRg�
L [.�
y1'
0
•.-- - R'OIF MOUWAIN LONE
P
ti 1r
CRALY.MOUNTALY DRIVE
v
�Q;r,~etiom� I yp��t
---------- -N
STREET LIGHTS
LEGEND ¢° I it EXHIBIT 'C'
PROP. SINGLE STREET LIGHT y8; I 01-DBURLESON ROAD
EXIST. SINGLE STREET LIGHT
(ON STEEL POLE WITH STREET 1 GARDEN ACRES DRIVE
AND STOP SIGNS ATTACHED) //����
PROP. STREET SIGN AL `rs�!"tw-" BurgmS
EXIST. STREET SIGN Q CARTER& BURGESS,INC.
M JlWN STREET
LIMITS OF PROJECT tORf WORTH,TX 76102
1917173S-6000
PROJECT NO. 013670.010.1.0630
OGN=cl\lob\ 013670\clv\old t>rIeeon\6701cFc.dan PAGE 4 OF 4
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 5/10/2005
DATE: Tuesday, May 10, 2005
LOG NAME: 20OLDBURLESON REFERENCE NO.: C-20726
SUBJECT:
Authorize Execution of a Community Facilities Agreement with Centex Homes for the Installation of
Community Facilities to Serve Deer Valley and Neighboring Developments
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute a Community Facilities
Agreement (CFA) with Centex Homes for the installation of community facilities to serve Deer Valley and
neighboring developments.
DISCUSSION:
Centex Homes, developer of Deer Valley, has executed a proposed CFA for construction of Old Burleson
Road to serve its single family (259-lots) development, as well as neighboring developments, in south Fort
Worth. The proposed project is bounded on the south by Garden Acres Drive and on the north by the Deer
Valley plat boundary, (See attached map).
The existing bridge structure on the subject portion of Old Burleson Road was closed to traffic, due to
disrepair. City funds were identified for reconstruction of the bridge to its original condition, but the
reconstruction was deferred to allow coordination with the development of Deer Valley. The pending
development of Deer Valley requires that Centex Homes construct the adjacent portion of Old Burleson
road, including one half of the ultimate, expanded bridge structure. According to the proposed agreement,
the City funds previously identified for reconstruction of the failed bridge will be added to those of Centex
Homes, allowing the ultimate bridge structure to be constructed concurrent with the construction of Old
Burleson Road. Centex Homes will fund 100% of all other community facilities associated with this portion
of Old Burleson Road.
The estimated costs of all community facilities for Old Burleson Road are as follows:
Estimated Cost Developer City Total
Paving $253,665.10 $0.00 $253,665.10
Storm Drain $153,127.00 $108,000.00 $261,127.00
Street Lights $17,600.00 $0.00 $17,600.00
Street Name Signs $300.00 $0.00 $300.00
Inspection $16,271.68 0.00 $16.271.68
TOTAL $440,963.78 $108,000.00 $548,963.78
Execution of this CFA would entail the allocation of City funds in the amount of $108,000 from the
Department of Transportation and Public Works Contract Street Maintenance Funds.
This project is located in COUNCIL DISTRICT 8.
Logname: 20OLDBURLESON Pave 1 of 7
FISCAL INFORMATION/CERTIFICATION:
The Finance Director certifies that funds are available in the current capital budget, as appropriated, of the
Contract Street Maintenance Fund.
TO Fund/Account/Centers FROM Fund/Account/Centers
GS93 541200 020930260690 $108,000.00
Submitted for City Manager's Office by: Marc Ott (8476)
Originating Department Head: Robert Goode (7804)
Additional Information Contact: Kate Mehl (7918)
Logname: 20OLDBURLESON