Change Order Request Breakdown
Project Namel Spinks Stone Road Alsbury Improvements City Sec# 1 44659
Client Project#(s)l #1273
Change Order Submittal# 0 Date 8/19/2014
Contract Time
Dept. TPW Totals (CD)
Original Contract Amount $1,380,164.00 $1,380,164.00 240
Extras to Date $15,930.00 $15,930.00 5
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $1,396,094.00 $1,396,094.00 245
Amount of Proposed Change Order $71,616.25 $71,616.25 158
Revised Contract Amount $1,467,710.25 $1,467,710.25 403
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO $0.00
Additional Funding(if necessary) $71,616.25 $71,616.25
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 6.34%
MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $1,725,205.00
JUSTIFICATION(REASONS)FOR CHANGE ORE)ER
Add/Delete items to complete a 10'sidewalk/trail on the south side of Alsbury Blvd. Contract time requested will coverall known delays and
shutdowns due to franchise utility conflicts to date,demobilization for south side sidewalk redesign,delay in receiving the McDonalds
temporarly construction easment,pricing and approval for sidewalk redisign,and finally scheduling and remobilization to complete the chagnes.
b 00
'Y L qty 3ecrtctaury $ °�
° °
°°°°0-C
SAS �
m
C-)
m
m
0
v
M
C—)
0
G'
M RECORD RETARY TH, TX
City of Fort Worth
T Change Order Additions
Project Name Spinks Stone Road Alsbury Improvements City Sec# 44659
Client Project# #1273
Change Order Submittal# 0 Date 8/1912014
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit m Cost Total
Remove and Replace Crape Myrtle
1- Remove Concrete Drive TPW F 5
II- Retaining Wall Drop Inlet TPW EA 5
II- Widening of idewalk Bridge TPW EA
11-22 Additional V Concrete Sidewalk
II- 5"Concrete Sidewalk TPW 3,570.00 $5.75
II- Concrete Ret Wall with Sidewalk,Face PW 5. F
11717--Additional oncrete Ret Wall with Sidewalk,Sidewalk
II- Concrete Ret Wall with Sidewalk,Sidewalk 5"Thickness TPW
11-26 Curb Ramp ) at Stone Road Intersection TPW EA 5 .
11- 7 Curb Ramp Additional Width at IH-35 NBFR Intersection W
11-28 Barrier Free Ramp,Type P- Additional Width TPW 3.00 EA
II- Concrete Driveway PW F
II- REFL PAV M K TY I MIL TPW L
II- tone Fagade TPW 5. F
11- Irrigation Adjustments W L 7
TPW 74,406.25
Sub Total Additions 7 ,
Change Order Additions Pagel of 1
City of Fort Worth
Change Order Deletions
Project Name I S inks Stone Road Alsbury Improvements City Sec# 44659
Client Project# 1 #1273
Change Order Submittal# 0 Date 8/19/2014
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
'Concrete Klprap
Concrete Flume 9Pw 5. L
Barer Free amp,Type - EA 5
Barrier Free Ramp,Type M-3 EA 5
TPW 2,790.00
Sub Total Deletions
Change Order Deletions Page 1 of 1
M/SBE Breakdown for this Change Order
M/SBE Sub Type of Service Amount for this CO
N/A
Total $0.00
Previous Change Orders
Co# DATE AMOUNT
Total $0.00
CFW Change Order Approval St-COApp06 Page 1 of 3
Routina
Assigned To: Due Date:
Assigned By: Due Time:
Links 1
ffortworthcov/Aviation Proiects/01273 - Spinks Stone Road Alsbury Improvements/Contractor/Chance Orders/Chance
Order Breakdown Recuest 2.xls
Attachments 10)
No Attachments have been added to this form.
https://projectpoint.buzzsaw.com/ bz web/Forms/FonnPrint.aspx?Site1d=51500&ProcessI... 12/1/2014
CFW Change Order Approval St-COApp06 Page 2 of 3
FORT WORTH® City of Fort Worth
Change Order Request Approval
(Change Order Breakdown Available in Links)
For Change Order Submittal No.: 2
Change Order No.: St-COApp06 Date Started: 2014-10-08
City Sec. No.: 44659 Date Due: 2014-11-27
Project Name: Alsbury Blvd Improvements
Project Numbers: 01273 DOE Numbers:
DOE 7004
Project Construction of Alsbury Blvd from 135W to Stone Road
Description:
Project Manager: Mike Bennett City Inspector: Michael Collier
Contractor: McClendon Construction Co.
COUNCIL ACTION (If Required):
M&C Log Name: NA
M&C Number: NA M&C Date:
COST AND DAYS SUMMARY:
Requested
Department: Cost($) Fund Account Center: Days:
TPW $ 71,616.25 C206-541200-208230127383 158
Total Cost: $ 71,616.25 Total Requested Days: 158
Approval Status:
https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?Siteld=51500&ProcessI... 12/1/2014
CFW Change Order Approval St-COApp06 Page 3 of 3
Approved: Yes
Comments:
User: Tara Fishback
Date: 2014-10-09 8:31 AM
Approved: Yes
Comments:
User: Justin Blair
Date: 2014-10-09 10:40 AM
Approved: Yes
Comments: No M&C required
User: Mike Bennett
Date: 2014-10-09 2:43 PM
Approved: Yes
Comments: Why do they need 158 Days?
User: Todd Estes
Date: 2014-11-04 9:00 AM
Approved: Yes
Comments:
User: Andy Anderson
Date: 2014-11-04 1:03 PM
Approved: Yes
Comments:
User: Doug Wiersig
Date: 2014-11-06 12:35 PM
Approved: Yes
Comments:
User: Doug Black
Date: 2014-11-07 1:33 PM
Approved: Yes
Comments:
User: Fernando Costa
Date: 2014-11-07 10:52 PM
Action Required:
https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?Siteld=51500&ProcessI... 12/1/2014