STATE OF TEXAS S CITY SECRETARY CONTRACT NO. I
(No M&C Needed)
COUNTY OF TARRANT S
WHEREAS, the City of Fort Worth (City) and Camp, Dresser &
McKee, Inc. , (Engineer) made and entered into City Secretary
Contract No. 27761, (the Contract) which was authorized by the
City Council by M&C C-19103 on the 28th day of May 2002, and
subsequently revised by one previous amendment; and
WHEREAS, the Contract involves engineering services for the
following project:
Engineering contract for the design of Northside II 48-inch
Water Main Extension Contract 2, Sections A and B.
WHEREAS, it has become necessary to execute Amendment No. 2
to said Contract to include an increased scope of work and revised
maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and
through their duly authorized representatives, enter into the
following agreement, which amends the Contract:
1.
Article I of the Contract is amended to include the
additional engineering services specified in a proposal letter
dated September 14, 2004, a copy of which is attached hereto and
incorporated herein. The cost to City for the additional design
services to be performed by Engineer total $13, 040 .00 .
2 .
Article II of the Contract is amended to provide for an
increase in the maximum fee to be paid to Engineer for all work
and services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall not
exceed the sum of $1,322, 957 .52 .
3 .
All other provisions of the Contract which are not expressly amended
herein shall remain in full force and effect.
EXECUTED on this the day of 2004, in Fort
Worth, Tarrant County, Texas.
ATTEST: - L.� �) 6(4
- Contract Authorization
Marty Hendr , City Secretary Date
APPROVAL RECOMMENDED: APPROVED:
A. Douglas Rademaker, P.E. Marc A. 6tt
Director, Department of Assistant City Manager
Engineering
Camp. Dreso-e-r-1 McKee Inc.
ENGINE
By:
Name: Richard W. Sawev, P.E. , D.E.E.
0
Vice-President
777 Taylor Street, Suite 1050
Fort Worth, TX 76102
APPROVED AS TO FORM AND LEGALITY:
Gary Steinberger
Assistant City Attorney
-2-
®FFIC� 111"Co
onymcmSm
CDM
777 Taylor Street,Suite 1050
Fort Worth,Texas 76102
tel: 817 332-8727
fax: 817 332-6870
September 14,2004
Mr. Tony Sholola,P.E.
City of Fort Worth Department of Engineering
1000 Throckmorton Avenue
Fort Worth,Texas 76102
Subject: Holly/Northside II Water Main Extension,Contract 2,Sections A&B,from
Northside Pump Station to Harmon Road,Engineering Amendment Two
Dear Mr.Sholola:
The City of Fort Worth has requested additional engineering services of CDM on the subject
project. CDM's engineering services contract for this project was executed on May 28,2002,
under City Secretary Contract Number 27761. The lump sum amount of the contract is
currently$1,309,917.52, including Amendment number 1 of$44,586.22,approved on
August 14,2003. The design contracts included 64,100 linear feet of 54-inch and 48-inch
waterline, associated waterline appurtenances,miscellaneous water and sewer line
replacements, and railroad/highway crossing. The waterline will transport water from the
Northside Pump Station to Heritage Trace Parkway.
We are pleased to provide these services to you,and have provided a listing of the out of
scope items and the associated fees on the attached tables. The total for this amendment
number 2 is$13,040.00 resulting in a revised total contact amount of$1,322,957.52.
If you need additional information or have questions please advise.
Very truly yours,
�YL2r.�� .`LV cXs=LcLtr�
tchen N. Williams,P.E.
Senior Project Manager
Camp Dresser &McKee Inc.
cc: Miguel Domenech,P.E.,City of Fort Worth,DOE
Rodney Chapin,P.E.,CDM
Richard Sawey,P.E.,CDM
File:0515-34655 AD1.1
consulting-engineering•construction•operations
Contract
NSII -Section A Amount Spent to date
Site Visits/Meetings $14,400 $11,800
Shop Drawing Review $6,300 $14,000
Responding to Contractors RFI's $8,000
Preparing revised drawings $7,060
Record Drawings $11,550
Final Completion $2,370 $600
Redesign of Butterfly Valve Vaults $6,200
$34,620 $47,660 $13,040
Notes
1 A total of 34 Shop Drawings were submitted by the Contractor to the Engineer and
Reviewed. 9 resumittals of shop drawings were reviewed and 3 shop drawings were
reviewed for the 3rd time.
2 Six Requests for Information were addressed by the Engineer
3 A total of 15 proposed contract modification requests were logged, reviewed and
comment on by the Engineer.
4 Attached is a listing of the plan sheets that were changed during construction of the
project.
5 Butterfly Valve Vaults were redesigned as requested by the City.
The following is a revised Project Fee Summary to include Amendment Number
Original Contract(Total) $1,265,331.00
Amendment Number 1 $44,586.52
Subtotal $1,309,917.52
Amendment Number 2 $?3,040.00
Subtotal $?,322,957.52
R. WITH, TEX.
a
List of Plans changed during the Construction Phase
F
Sheet
umber Description
7 Sansom Park -Trees
C1-8 Sansom Park -Trees
CZ1-1 Butterfly Vault Change
CZ1-2 Butterfly Vault Change
Connection at Cromwell-Marine Creek Rd and
CZ-24 Marine Creek Parkway
CZ2-1 Butterfly Vault Change
CZ2-2 Butterfly Vault Change
C3-5 Concrete embedment on Railhead
C3-6 Railhead Change in Easement
C3-7 Railhead Change in Easement
C3-8 Railhead Change in Easement
C3-9 Railhead Change in Easement
C3-17 Connection at Cantrell Sansom Road
C3-18 Connection at Cantrell Sansom Road
C3-19 TXU alignment change
CZ3-1 Butterfly Vault Change
CZ3-2 Butterfly Vault Change
E
ICUT HY