Project Name:I Sanitary Sewer Rehabilitation Contract 75, Part 3 City Sec No.: 1 45012
Project No.(s): P253-609170148088&P258-709170148088 I DOE No. 7036 CityProj.No.:l 01480
Project Description: Water and sanitary sewer main replacement on Belford Avenue,Stratford Court, Stratford Drive and Meadowbrook Drive.
Contractor: William J.Schultz, Inc dba Circle C Construction Co Change Order# 0 Date: 9/29/2014
City Project Mgr. Roberto C.Sauceda City Inspector: John Crowley
Phone Number:1 817-392-2387 Phone Number: 682-432-4037
Dept. Water Sewer Totals Contract Time
(Calender days)
Original Contract Amount $228,005.00 $818,976.50 $1,046,981.50 180
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $228,005.00 $818,976.50 $1,046,981.50 180
Amount of Proposed Change Order $114,879.00 -$16,010.00 $98,869.00 120
Revised Contract Amount $342,884.00 $802,966.50 $1,145,850.50 300
Original Funds Available for Change Orders $11,400.00 $25,000.50 $36,400.50
Remaining Funds Available for this CO $11,400.00 $25,000.50 $36,400.50
Additional Funding(if necessary) $103,479.00 1 $103,479.00
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 9.44%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) [$71,3-08,-7126.88
JUSTIFICATION(REASONS) FOR CHANGE ORDER
The change order will allow for the following.
• The replacement of an 850 foot segment of an existing leaking and deteriorated 8-inch water main
that was encountered during construction
• The deletion of sanitary sewer pay items quantities that are no longer needed on the project;
Staff concurs with the contractor's request for 120 additional calendar days on the projects.
b/@ t LOFFICIAL O RECORD,� Ronald P. Gonzales,Asst. City Secretary $ CRETARY
0
�� Z O�OGUU09
It is understood and agreed that the acceptance of this Change Order by the cont�kle tt es an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
o Contractor's Company Name Contractor Name Contractor Signature Date
Circle C Construction Cc Teri Skelly
I s ec Date Proj Date
a it c ater t) Date, onstructign Su ervisor TPW Dept Datp
5 f f
i tto Da(e City Manager Date
44CLeUR4;�� V5 i (z _y-I z i
Council Action If Required
M&C Number N/A M&C Date Approved NIA
FORT WORTH City of Fort Worth
Change Order Additions
Project Name Sanitary Sewer Rehabilitation Contract 75, Part 3 City Sec No.: 45012
Project No.(s): P253-609170148088&P258-709170148088 DOE No. 7036 City Proj. No.: 01480
Project Water and sanitary sewer main replacement on Belford Avenue, Stratford Court,Stratford Drive and Meadowbrook
Description Drive.
Contractor William J.Schultz, Inc dba Circle C Construction Cc Change Order:= Date: 9/29/2014
City Project Mgr. I Roberto C.Sauceda City Inspector John Crowley
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
1 8-inch Water Pipe Water 850.00 LF $38.50 $32,725.00
3 1 -inch Water Service Water 12.00 EA $700.00 $8,400.00
11 4 Foot. Wide Asphalt Replacement Water 1069.00 LF $33.00 $35,277.00
18 Temporary Water Service Water 1.00 LS $6,000.00 $6,000.00
19 Trench Safety Water 949.00 EA $3.00 $2,847.00
20 DI Fittings Water 1.50 TN $6,000.00 $9,000.00
22 Connect to existing 6-12" Water Line Water 4.00 EA $2,000.00 $8,000.00
23: -inch Water Service Relocation Water 12.00 EA $250.00 $3,000.00
25 8-inch Gate Valve Water 3.00 EA $950.00 $2,850.00
26 Traffic Control Water 1.00 LS $2,500.00 $2,500.00
27 8-inch DI Pipe Water 80.00 EA $48.50 $3,880.00
28 Concrete Valley Gutter Water 50.00 SF $8.00 $400.00
Water $114,879.00
Sewer
Page 2 of 4 Additions Sub Total 1$114,879.00
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name Sanitary Sewer Rehabilitation Contract 75, Part 3 City Sec No.: 45012
Project No.(s): P253-609170148088&P258-709170148088 DOE No. 7036 City Proj. No.: 01480
Project Description Water and sanitary sewer main replacement on Belford Avenue,Stratford Court, Stratford Drive and Meadowbrook
Drive.
Contractor William J. Schultz, Inc dba Circle C Construction Co Change Order: E:1 Date 9/29/2014
City Project Mgr. Roberto C. Sauceda City Inspector: John Crowley
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
10 4-inch Sewer Service Sewer 1.00 EA $400.00 $400.00
11 4-inch Sewer Service, 2-Way Cleanout sewer 11.00 EA $200.00 1$2,200.00
13 4-inch Sewer Service, Private Relocation Sewer 245.00 LF J$52.00 $12,740.00
33 Trench Safety Sewer 670.00 LF $1.00 $670.00
Water
Sewer 1$16,010.00
Page 3 of 4 Deletions Sub Total
MMBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
Page 4 of 4
CITY OF FORT WORTH
AMENDMENT, CHANGE ORDER or EXTRA WORK
CONTRACT COMPLIANCE MEMORANDUM
THIS FORM MUST BE ATTACHED TO THE ROUTING "M$ C"BEFORE LEGAL AND
CITY MANAGER APPROVAL.
To: Robert Sauceda
(underline appropriate one) Project Manager Buyer Department Director
From: Adrian Zavala 212-2679
M/WBE Office Staff Extension
Date: September 26, 2014 Al
In the Amount of$ 98,869.00 Water-01480, 7036
DOE/Project/Bid Nos .
Project/Bid: Change Order No. 1-Sanitary Sewer Rehabilitation,
Contract 75, Part 3
1. Compliance with the City's Business Diversity Enterprise(BDE)Ordinance has been achieved by one
of the following MBE methods:
a) is in compliance with the City's BIDE Ordinance by committing
to an additional_% MBE participation on this Amendment/Change Order No._
b) William J. Schultz. Inc. dba Circle "C" Construction Company is in compliance with the
City's BDE Ordinance by committing to an additional 7%MBE participation on this
Amendment/Change Order No.1. The City's goal on this Amendment/Change Order or extra work
is 7%.
C) is in compliance with the City's BDE Ordinance by documenting
good faith effort. The City's goal on this Amendment/Change Order or extra work is 0%.
d) is in compliance with the City's BDE Ordinance by approval of a
waiver request of the MBE requirement. The City's goal on this Amend men t/Change Order or extra
work is 0%.
2. The apparent low dollar bidder(s)did not comply with the City's BDE Ordinance because: