HomeMy WebLinkAboutContract 31943 AMENDMENT NO. 1
STATE OF TEXAS $ CITY SECRETARY CONTRACT NO.
n IqLB
(No M&C Needed)
COUNTY OF TARRANT $
WHEREAS, the City of Fort Worth (City) and Parsons Water and
Infrastructure, Inc . made and entered into City Secretary Contract
No. 31257, (the Contract) which was authorized by the City Council
by M&C C-20470 on the 4th day of January, 2005 .
WHEREAS, the Contract involves engineering services for the
following project:
Water and Sanitary Sewer Main Replacements on Throckmorton
Street and 14th Street
WHEREAS, it has become necessary to execute Amendment No. 1
to said Contract to include an increased scope of work and revised
maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and
through their duly authorized representatives, enter into the
following agreement which 'amends the Contract:
1 .
Article I of the Contract is amended to include the
additional engineering services specified in a proposal letter
dated May 19, 2005 a copy of which is attached hereto and
incorporated herein. The cost to City for the additional design
services to be performed by Engineer total $3,205 . 00
2 .
Article II of the Contract is amended to provide for an
increase in the maximum fee to be paid to Engineer for all work
and services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall not
exceed the sum of $84, 524 . 98
3 .
All other provisions of the Contract which are not expressly amended
herein shall remain in full force and effect.
/Wh EXECUTED on this the day of L.Y u► ,
2005, in Fort Worth, Tarrant County, Texas .
ATTEST:
1 l
Marty Hendri , City Secretary NO M&C REQUIRED
APPROVAL RECOMMENDED: APPROVED:
A. Douglas Rademaker, P.E. Marc Ott
Director, Department of Assistant City Manager
Engineering
Parsons Water and Infrastructure, Inc.
ENGINEER M&,�
& LaL,
Name: Marvin Williams _
Vice President
4500 Mercantile Plaza Dr. ; STE 235_
Fort Worth, TX 76137
APPROVE ; AS TO FO LEGALITY:
Ga Ste' rger
ssistan City Attorne
ENGl.FRM(NO M&C)
-2-
PARSONS
4500 Mercantile Plaza Drive, Suite 235 • Fort Worth, Texas 75137• (817) 759-0215 • Fax: (817) 759-1819•www.parsons.com
May 19, 2005
Mr. Rakesh Chaubey, P.E.
Engineering Services
City of Fort Worth
1000 Throckmorton Street
Fort Worth, Texas 76102-6311
Re: Request for Amendment No. 1
Water and Sanitary Sewer Replacement-Throckmorton St. and 14th St.
Project No. 00136
Dear Mr. Sholola:
The original scope of work for this project included topographic and subsurface
utility surveys along Throckmorton St. from 14th St. to 11th St., along 11th St. from
Throckmorton St. to Houston St., and along 14th St. from Throckmorton St. to Houston
St.
During the kick-off meeting Parsons identified a potential route for the sewer line
that would involve construction in Houston St. between 14th St. and 13 St. It was our
understanding that we were to investigate this alternate route further and to complete
additional survey work.
The cost for the additional topographic and subsurface utility survey is $3205.00
which includes a 10% mark-up allowed by our contract. A breakdown of the costs is
attached. Therefore, we request an amendment in this amount to cover the costs of the
additional survey work.
Please do not hesitate to contact me via e-mail at jack.thibodeau(a-,parsons.com or
on my cell phone at (972) 898-3462 if you have any questions or need additional
information.
Sincerely,
Jc Thibodeau, P.E.
Senior Project Manager
Attachment
Request for Amendment No. 1
Cost Breakdown
Project No. 00136
SUE
PM $ 123.78 1 $123.78
PE $ 110.74 2 $221.48
SUE Mgr $ 83.62 8 $668.96
SUE Tech $ 44.72 8 $357.76
CADD $ 67.76 4 $271.04
Tech Support $ 41.33 2 $82.66
$1,725.68
Vac Truck $ 80.00 0 $ -
Des Truck $ 15.00 8 $ 120.00
$ 120.00
$ 1,845.68
Surveying
RPLS $ 75.00 1 $75.00
Survey Tech $ 65.00 2 $130.00
3-Man Crew $ 115.00 7.5 $862.50
$1,067.50
SUE& Survey $2,913.18
Parsons Mark-Up (10%) $292.19
Total Amendment No. 1 Request $3,205.00