Loading...
HomeMy WebLinkAboutContract 44049-CO5 CITY SECRETARY FORTWORT City of Fort Worth CONTRACT NO. 'C Change Order Request Breakdown Project Namel Henderson Street(SH. 199)Detour City Sec# 44049 Client Project#(s)l 00144 Change Order Submittal# L _J Date 3/4/2014 Dept. TPW Contract Time Totals CD Original Contract Amount $1,929,961.63 $1,929,961.63 Extras to Date $344,152.34 $344,152.34 Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $2,274,113.97 $2,274,113.97 Amount of Proposed Change Order $29,708.75 $29,708.75 Revised Contract Amount $2,303,822.72 $2,303,822.72 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 Additional Funding(if necessary) $29,708.75 $29,708.75 CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 19.37% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $2,412,452.04 JUSTMATION TREASONS) FOR CHANGE ORDER Change order is required to add street lighting to detour,and add additional 4"white edge line striping to the project. ° Mary J. Kayser, City Secretary Good/ SAS OFFICIAL RECORD CITY SECRETARY FT. WORTH,TX RECEIVED DEC 2 2 P.M. ., FoRr Wo3TH City of Fort Worth T Change Order Additions Project Name Henderson Street SH.19g Detour City Sec# 44049 Client Project# 00144 Change Order Submittal# Date 31412014 ADDITIONS ITEM DLS(;RIPI IUN DEPT Unit n Cost Total ee rg n9 de Edge Line Striping TPW 29, 08.75 u ota rhons Change Order Additions Page 2 of 4 Fo r Wo rN City of Fort Worth Change Order Deletions Project Name Henderson Street SH.199 Detour pb,Sac# CFent Project# 00144 Change Order Submittal# f- 55 Date 3!4!2014 DELETIONS Unif Una Total TPW $0.00 Sub ota ebons Change Order Deletions Page 3 of 4 MISBE Breakdown for this Change Order M/SBE Sub Type of Service Amount for this CO none Total $0.00 Previous Change Orders CO# DATE AMOUNT 1 9/19/2013 $289,139.75 2 3/27/2014 $26,617.00 3 7/16/2014 $9,545.59 4 9125/2014 $18,850.00 Total $344,152.34 t-r w Change Order Approval St-COApp07 Page 2 of 3 FORT WORTH, city of Fort Worth Change Order Request Approval (Change Order Breakdown Available in Links) For Change Order Submittal No.: 5 Change Order No.: St-COApp07 Date Started: 2014-12-15 City Sec. No.: 44049 Date Due: 2014-12-17 Project Name: Henderson Street Detour 00144 DOE Numbers: Project Numbers: DOE 6124 Project Henderson Street Detour adding pavemnt markings and street Description: lights for the project. - TRV to provide Funds to CFW for this C05. Project Manager: Patrick Buckley City Inspector: Mike Collier Contractor: JLB Contracting, LLC COUNCIL ACTION (If Required): M&C Log Name: M&C Number: M&C Date: COST AND DAYS SUMMARY: Requested Department: Cost($) Fund Account Center: Days: TPW $ 29,708.75 C204 541200 209260014480 Total Cost: $ 29,708.75 Total Requested Days: 0 Approval Status: https://projeetpoint.buzzsaw.com/ bz web/Forms/Fom,Print.aspx?SiteId=51500&Pro... 12/22/2014 CFW Change Order Approval St-COApp07 Page 3 of 3 Approved: Yes Comments: User: Tara Fishback Date: 2014-12-15 4:31 PM Approved: Yes Comments: User: Sam Davis Date: 2014-12-15 5:01 PM Approved: Yes Comments: User: Patrick Buckley Date: 2014-12-15 6:00 PM Approved: Yes Comments: User: Doug Rademaker Date: 2014-12-16 9:32 AM Approved: Yes Comments: User: Andy Anderson Date: 2014-12-16 12:57 PM Approved: Yes Comments: User: Doug Wiersig Date: 2014-12-16 3:54 PM Approved: Yes Comments: User: Doug Black Date: 2014-12-22 10:47 AM Approved: Yes Comments: User: Fernando Costa Date: 2014-12-22 4:55 PM Action Required: Approve C05 https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?Site1d=51500&Pro... 12/22/2014 CF`11 Change Order Approval St-COApp07 Pagel of 3 Routh! Assigned To: Due Date: Assigned By: Due Time: Links 1 fortworthgov/Infrastructure Proiects/00144 - Hederson Street Detour/Contractor/Change Orders/Change Order Breakdown co-5.xls Attachments(0) No Attachments have been added to this form. https://projectpoint.buzzsaw.com/_bz web/Forms/FomiPrint.aspx?Siteld=51500&Pro... 12/22/2014